DRAFT_Barrington Victory Field ADD3.pdf

PDF 642 KB Posted

Attached to
Victory Field Athletic Complex Renovation at BHS
Solicitation number
Bid #25010
Issued by
Bristol County, Rhode Island

About this file

This is Addendum #3 for the Barrington Public Schools Victory Field Project (RFP Reference Number: 25010), issued on February 27, 2025, which modifies the original Request for Proposals dated February 5, 2025. The addendum provides additional design details, clarifications, and responses to bidder questions for the athletic facility renovation at Barrington High School. Key modifications include changes to the construction sequence, deletion of specific notes on lighting fixtures, and clarification on electrical and drainage requirements. The document specifies that two new light poles with new foundations and LED lights are needed for the Baseball/Softball side, with existing poles by the bleachers to be retrofitted with new LED fixtures.

The addendum includes a $20,000 allowance for permitting expenses, to be refunded to the owner if unexpended, and confirms a 5% bid bond requirement. For the turf alternate (Alternate 2), the document approves the Sprinturf Predator 60 system contingent on meeting specification requirements and specifies a minimum infill of 4.5 lbs of sand and 1.2 lbs of organic fill per square foot. The bid form indicates that the project will be completed in accordance with contract documents prepared by Nesra Engineering, with provisions for multiple alternates and a base bid that includes the permitting cost allowance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Barrington Public Schools

Request for Proposals

Victory Field Project

RFP Reference Number: 25010

Addendum #3 Issue Date: February 27, 2025

This Addendum provides additional design and details to the original plans and specs and also requests additional pricing for owner review which modifies the original Request for Proposals dated February 5, 2025 as noted below.

Please refer to the following pages for:

• Question Responses

• Additional Lighting Information

• Bid Form

Items for Addendum #3

Plan Notes:

• Sheet C2 Construction Sequence: Delete Item #30 in reference to the Grandstands, Press box, and Lift.

• Sheet C5 Layout and Materials Plan: Delete note “(Consider Alternate for Double

Fixtures)”

Permitting:

• The design is currently under permitting. The Contractor shall include an allowance of

$20,000 for permitting expenses. Should the actual permitting costs be less than the allotted amount, any unexpended funds shall be refunded to the Owner.

General:

Q: Is a Bid Bond Required? We Don’t see any Requirements for a Bid Bond and want to make sure there is enough time to acquire one, in the event it is needed.

A. A 5% bid bond is required with the bid.

Q: Bid Forms – We do not see any bid forms in the Bid Package. I’m assuming this is due to the fact that the bids will be submitted via BidNet. Please confirm.

A: Please see the Bid Form attached to this addendum.

Drainage:

Q: Is the Intent to Provide Fabric Wrapped Flat Panel Drain? If so, please clarify.

A: Yes, provide perforated flat panel HDPE pipe with geotextile sock. J-Drain type systems will not be accepted.

Electrical:

Q: We Don’t See any Product Specific Info for the Musco Lighting. Please provide product info, foundation design and bill of material.

A: Foundation design for lighting has been provided. See attached documentation.

Q: There also appears to be a discrepancy between electrical drawings and layout and materials drawing. On the Electrical Plan, it appears we are removing (2) existing sports poles and replacing with (4) new poles heads and bases. On the Layout and Materials it talks about (2) new poles and (2) retrofitted poles. Please clarify.

A: Two new poles with New foundations and LED lights are needed for the Baseball/Softball Side. The existing two by the bleachers to remain and be retrofitted with new LED fixtures. See attached control summary for more information.

Bleachers:

Q: Are all the planks to be replaced on the bleachers?

A: Only the planks with a plastic cover. They shall be replaced for metal seats similar to what has already been replaced.

Q: On the bleachers, should the missing nuts be added to the bolts?

A: Yes, add nuts to all the bolts that are missing them.

Turf:

Q: I would like to submit for approval our Sprinturf Predator 60 system. This is specifically for deduct alternate #2.

A. The Predator 60 system is approved for Alternate 2 contingent on it meeting all other requirements in the specifications.

Q: For Alternate 2, how much sand and infill shall we carry?

A: Sand/Infill mix shall be in accordance with turf manufacturer requirements to meet and pass GMAX and HIC test requirements. At the minimum, the contractor shall carry 4.5 lbs of sand and 1.2 lbs of organic fill per square foot. If more infill is needed to meet testing parameters, the contractor will provide it at no extra cost to the Owner.

LIGHT/POWER CONTROL SYSTEM

System Requirements: Control System Summary

Pre lim in ary

P la ns:

Confirm all d eta ils se e N ote

Project Name: Barrington High School Football Track Retrofit | Project #: 170921

Control System ID: 1 of 1

Distribution Panel Location/ID: Service #1

Project Information

Control System Control System ID: 1 of 1

Control System Type: Control-Link ® Control and Monitoring

System

Communication Type: PowerLine-ST

Power Requirements

Control cabinet(s):

Control voltage (phase to neutral) 120/60

VA loading - Inrush 3023.0

VA loading - Sealed 336.0

Lighting Circuits:

Voltage/Hertz/Phase 480/60/1

Project Notes:

Equipment Listing

Description Qty Size (in)

Control and monitoring cabinet -primary

1 24 X 72

Contactors, 30 amperes 10 -

Off/On/Auto switches 4 -

Important Notes:

1. Please confirm that the lighting circuit voltage listed above is accurate for this facility. This is the voltage/phase being connected and utilized at each lighting pole's electrical components enclosure disconnect. Inaccurate voltage/phase can result in additional costs and delays. Contact your Musco sales representative to confirm this item.

2. In a 3 phase design, all 3 phases are to be run to each pole location. Musco's single phase luminaires come pre-wired to utilize all 3 phases across the entire facility.

3. One contactor is required for each circuit at each pole location. Contactors are 3 pole and 100% rated for the published continuous load.

4. If the lighting system will be fed from more than one distribution location, additional equipment may be required. Contact your Musco sales representative.

5. Size overcurrent devices using the full load amps column of the Circuit Summary by Switch chart (Minimum power factor is

0.9). Size conduit per code unless otherwise specified as larger to allow for harness connectors.

6. Avoid use of in-ground junction/pull boxes when possible. If used, all wire connectors must be UL listed for Wet Locations to prevent leakage current.

7. Control power wiring must be in separate conduit from line or load power wiring. Communication cables must be in separate conduit from any power wiring.

8. Refer to Installation Instructions for more details on equipment information and the installation requirements.

Sales Representative: Alan Grady | Project Engineer: Tanner Lanphier | Scan: 170921C | Document ID: 170921P1V2C2-0130163147 www.musco.com | lighting@musco.com

Page 1 of 3 -- 30-January-2025

Project Name: Barrington High School Football Track Retrofit | Project #: 170921

Control System ID: 1 of 1

Distribution Panel Location/ID: Service #1

Equipment Layout and Connection Details

Connection Details

ID Description

1a Line power to contactors, and equipment grounding conductor. Requires one circuit per contactor, size wiring per load and voltage drop.

1b Load power from contactors, and equipment grounding conductor. Requires one circuit per contactor, size wiring per load and voltage drop.

2a Control power with equipment ground to control cabinet. Requires dedicated

20 A circuit. Provide transformer if control voltage not present.

Equipment

ID Description

1 Control and monitoring cabinet -primary

Sales Representative: Alan Grady | Project Engineer: Tanner Lanphier | Scan: 170921C | Document ID: 170921P1V2C2-0130163147

Page 2 of 3 -- 30-January-2025

Project Name: Barrington High School Football Track Retrofit | Project #: 170921

Control System ID: 1 of 1

Distribution Panel Location/ID: Service #1

Circuit Summary

Switching Schedule

Field/Switch Description Switches

Football 1,2

Football 1

Track 2

Track 2

Security 3

Bleacher 4

Control Module ID: 1 Lighting Circuit Voltage: 480/60/1

Circuit Summary by Switch

Switch Zone Description Pole ID Qty of

Fixtures

Full load amperes

Contactor

Size (Amps)

Cabinet # Contactor

ID

1 Football F1 10 26.9 30 1 C1

Football F2 10 26.9 30 1 C2

Football F3 10 26.9 30 1 C3

Football F4 10 26.9 30 1 C4

2 Track F1 2 6 30 1 C5

Track F2 2 6 30 1 C6

Track F3 2 6 30 1 C7

Track F4 2 6 30 1 C8

3 Security F1, F2 2 2.78 30 1 C9

4 Bleacher F1, F2 2 2.78 30 1 C10

Sales Representative: Alan Grady | Project Engineer: Tanner Lanphier | Scan: 170921C | Document ID: 170921P1V2C2-0130163147

Page 3 of 3 -- 30-January-2025

FOUNDATION FOOTINGS

BID FORM

TO THE AWARDING AUTHORITY

A. The undersigned proposes to furnish all labor and materials required for Barrington High School Athletic

Facility Renovation Project Project Description for the Barrington School District in Barrington, RI in accordance with Contract Documents prepared by Nesra Engineering

Name of Architect/Engineer

For the contract price specified below, subject additions and deductions according to the terms of the specifications.

B. This bid includes addenda numbered

C. The proposed contract price is:

Dollars $

Bid Amount in Words Bid Amount in Numbers

Allowance #1

A $20,000 twenty-thousand-dollar allowance shall be provided as part of the base bid for this project to cover permitting costs for any/all conditions under the jurisdiction of the Rhode Island Department of Environmental Management

Confirmed: ___________________________________________ Signature

For Alternate(s) No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________

No. ___ Add $ _________________ Subtract $ _________________ Each Alternate shall be listed separately

Name of General Bidder

Signature BY:

Signature & Title of person signing bid

Date:

Business Address

Email & Phone Number

File details come from the government source that posted it. Updated .