DRAFT Attachment 1- Deliverables Schedule.pdf

PDF 166 KB Posted

Attached to
Complete Trip- ITS4US Deployment Program Federal contract opportunity
Solicitation number
693JJ3-20-BAA-0004
Issued by
Department of Transportation Federal Highway Administration

About this file

This document outlines a draft deliverables schedule for a Broad Agency Announcement seeking proposals for a Complete Trip-ITS4US Deployment Program Phase 1. The schedule lays out 14 tasks and associated deliverables due on a monthly or bi-weekly basis over a 12-52 week period following award. Key deliverables include a program management plan, user needs identification, concept of operations, data management plan, safety management plan, performance measurement plan, deployment system requirements, technology readiness assessment, human use approval, training and stakeholder education plan, institutional and financial plan, outreach plan, systems engineering management plan, and an integrated deployment plan. The Department of Transportation Federal Highway Administration seeks these plans and assessments to inform deployment of a trip planning and mobility program.

View the file

Other files for this federal contract opportunity

Other files attached to Complete Trip- ITS4US Deployment Program, newest first.
File Type Posted
Summary of BAA.pdf PDF
DRAFT Attachment 2-Deployment Summary Template 1.pdf PDF
DRAFT Attachment 3- BAA Pricing Schedule.pdf PDF
DRAFT Complete Trip-ITS4US BAA.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT 693JJ3-20-BAA-0004

Attachment 1- Complete Trip-ITS4US Deployment Program

Phase 1 BAA Deliverable Matrix

Note: This is intended as an initial roadmap to completing the deliverables within 12 months. Proposed variations to this schedule will be considered. However, all Phase 1 activity must conclude within 12 months from award.

ID BAA

Section Task Name and Deliverable Due Date Format

Compliant

Deliverables

Task 1: Project Management

P1T01D1 5.1 Kickoff Briefing award + 3 weeks PP

P1T01D2 5.1 Program Management Plan (Draft) award + 3 weeks Word

P1T01D3 5.1 User Needs Identification and Requirements Planning Document (Draft) award + 4 weeks

Word

P1T01D4 5.1 Program Management Plan (Final) award + 6 weeks Word

P1T01D5 5.1 User Needs Identification and Requirements Planning Document (Final) award + 7 weeks

Word X

P1T01D6 5.1 Monthly Reports Monthly Word

Task 2: Concept of Operations (ConOps)

P1T02D1 5.2 Stakeholder ConOps Review Panel Roster (Draft) award + 8 weeks Word

P1T02D2 5.2 Needs Summary (Draft) award + 8 weeks Word

P1T02D3 5.2 Stakeholder ConOps Review Panel Roster (Final) award + 10 weeks Word

P1T02D4 5.2 Needs Summary (Final) award + 10 weeks Word

P1T02D5 5.2 ConOps (Draft) award + 13 weeks Word

P1T02D6 5.2 ConOps Walkthrough Briefing Deck award + 13 weeks PP

P1T02D7 5.2 ConOps Comment Resolution Report (Draft) award + 15 Word

P1T02D8 5.2 ConOps (Final) award + 18 weeks

Word X

P1T02D9 5.2 ConOps Comment Resolution Report (Final) award + 18 weeks Word

P1T02D10 5.2 ConOps Webinar (Public) award + 21 weeks PP

Task 3: Data Management Plan

P1T03D1 5.3 Data Management Plan (Draft) award + 22 weeks Word

P1T03D2 5.3 Data Management Plan (Final) award + 26 weeks Word X

Task 4: Safety Management Plan

P1T04D1 5.4 Safety Management Plan (Draft) award + 22 weeks Word

P1T04D2 5.4 Safety Management Plan (Final) award + 26 weeks Word X

Task 5: Performance Measurement and Evaluation Support Plan

P1T05D1 5.5 Performance Measurement Plan (Draft) award + 26 weeks Word

P1T05D2 5.5 Performance Measurement Plan (Final) award + 35 weeks Word X

P1T05D3 5.5 Performance Measurement Plan Webinar (Public) award + 38 weeks PP

Task 6: Deployment System Requirements (SyRS)

P1T06D1 5.6 Stakeholder SyRS Review Panel Roster (Draft) award + 25 weeks Word

P1T06D2 5.6 Stakeholder SyRS Review Panel Roster (Final) award + 27 weeks Word

P1T06D3 5.6 SyRS Document (Draft) award + 30 weeks Word

P1T06D4 5.6 SyRS Walkthrough Workbook award + 30 weeks PP

P1T06D5 5.6 SyRS Walkthrough Comment Resolution Report (Draft) award + 32 weeks Word

P1T06D6 5.6 SyRS Document (Final) award + 35 weeks Word X

P1T06D7 5.6 SyRS Walkthrough Comment Resolution Report (Final) award + 35 weeks Word

Task 7: Enabling Technology Readiness Assessment

P1T07D1 5.7 Enabling Technology Readiness Assessment (Draft) award + 27 weeks Word

P1T07D2 5.7 Enabling Technology Readiness Assessment (Final) award + 38 weeks Word X

Task 8: Human Use Approval

P1T08D1 5.8 Human Use Approval Summary (Draft) award + 40 weeks Word

P1T08D2 5.8 Human Use Approval Summary (Final) award + 44 weeks Word X

Task 9: Participant Training and Stakeholder Education Plan

P1T09D1 5.9 Participant Training and Stakeholder Education Plan (Draft) award + 41 weeks Word

P1T09D2 5.9 Participant Training and Stakeholder Education Plan (Final) award + 45 weeks Word X

Task 10: Institutional, Partnership, and Financial Plan

P1T10D1 5.10 Institutional, Partnership, and Financial Plan (Draft) award + 42 weeks Word

P1T10D2 5.10 Institutional, Partnership, and Financial Plan (Final) award + 46

Task 11: Outreach Plan

P1T11D1 5.11 Outreach Plan (Draft) award + 40 weeks Word

P1T11D2 5.11 Outreach Plan (Final) award + 44 weeks Word X

Task 12: Systems Engineering Management Plan

P1T12D1 5.12 Systems Engineering Management Plan (Draft) award + 40 weeks Word

P1T12D2 5.12 Systems Engineering Management Plan (Final) award + 44 weeks Word X

Task 13: Integrated Complete Trip Deployment Plan

P1T13D1 5.13 Integrated Complete Trip Deployment Plan (Draft) award + 42 weeks Word

P1T13D2 5.13 Integrated Complete Trip Deployment Plan (Final) award + 46 weeks Word

P1T13D3 5.13 Deployment Plan Webinar (Public) award + 49 weeks PP X

Task 14: Deployment Readiness Summary Briefing

P1T14D1 5.14 Deployment Readiness Summary Briefing award + 49 weeks PP

P1T14D2 5.14 Deployment Readiness Summary (Draft) award + 49 weeks Word

P1T14D3 5.14 Deployment Readiness Summary (Final) award + 52

File details come from the government source that posted it. Updated .