DRAFT Appendix A CDRL.docx

DOCX document 37 KB Posted

Attached to
Hill AFB Base Integrated Environmental Support Tasks (BIEST) Federal contract opportunity
Solicitation number
W9123822R0011(1)
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

This document contains a Contract Data Requirements List (CDRL) and details for a solicitation to provide Base Integrated Environmental Support Tasks at Hill Air Force Base in Utah. The CDRL outlines over 100 deliverables required under the contract across areas including air quality evaluation, hazardous material management, water quality evaluation, and environmental compliance reporting. Deliverables include plans, permits, inspections, analyses, training materials, and compliance and audit reports. Due dates range from monthly to annually with draft and final submittals required for most deliverables. The related solicitation will be a Firm Fixed Price single award contract issued by the U.S. Army Corps of Engineers for $42 million. The solicitation is anticipated to issue on December 6, 2021 with proposals due on January 6, 2022 and contract award shortly thereafter. The work will be performed at Hill Air Force Base over a five year period.

View the file

Other files for this federal contract opportunity

Other files attached to Hill AFB Base Integrated Environmental Support Tasks (BIEST), newest first.
File Type Posted
Hill BIEST Site Visit 12-6-2021.mp4 MP4 file
DRAFT Appendix B Property.docx DOCX document
DRAFT Appendix C Building Layout.docx DOCX document
DRAFT PWS.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix A Contract Data Requirements List

Section
CDRL
Deliverable
Daft Copies
Final Copies
Due Date
3.1.1
A0001
Evaluate and Assess Base Operations HAFB
1
1
Monthly
3.1.1
A0002
Evaluate and Assess Base Operations UTTR
1
1
Monthly
3.1.1
A0003
Emissions Testing
1
1
Draft – January 5

Final -January 31st

3.1.1
A0004
General Conformity
1
1
As Completed
3.1.2
A0005
Main Base AEI
1
1
Draft February 1st

Final March 1st

3.1.2
A0006
UTTR AEI
1
1
Draft February 1st

Final March 1st

3.1.2
A0007
AEI Follow-up w/ State of Utah
1
1
As needed
3.1.2
A0008
Main Base GHG Report
1
1
Draft February 15th

Final March 1st

3.1.2
A0009
Burn Schedule
1
1
Draft February 1st

Final March 1st

3.1.2
A0010
Refrigerant Reporting
1
1
As completed
3.1.3
A0011
Annual/Semi Annual Compliance Report -HAFB
1
1
Draft January 15th & July 15th

Final January 15th & July 15th

3.1.3.
A0012
Annul/Semi Annual Compliance Report - UTTR
1
1
Draft January 15th & July 15th
3.1.3
A0013
Deviation Reports
2
2
As Needed
3.1.3
A0014
Initial Notification Reports
2
2
As Needed
3.1.4
A0015
New Source Review Permit Application
2
2
As Needed
3.1.4
A0016
Flexibility Notices
2
2
As Needed
3.1.4
A0017
Notices of Intent / TVOP Administration Amendments
2
2
As Needed
3.1.4
A0018
Notice of Intent Exemption Requests
2
2
As Needed
3.1.4
A0019
TVOP Update Applications
2
2
As Needed
3.1.6
A0020
Emergency Episode Plans
2
2
As Needed
3.1.6
A0021
Asbestos and Lead Base Paint Plans
4
4
Draft December 1st

Final December 31st

3.1.7
A0021
Environmental Compliance Administration and Communications
2
2
As Needed
3.1.8
A0022
Site Specific Documentation
2
2
As Needed
3.1.8
A0023
Non-Compliance Documentation
2
2
As Needed
3.1.8
A0024
Specific Activities
2
2
As Needed
3.1.9
A0025
Aerospace NESHAP Semiannual Compliance Reports
4
4
Draft January 15th & July 15th
3.1.9
A0026
Various Other Semiannual NESHAP Reports
4
4
Draft January 15th & July 15th

Final January 15th & July 15th

3.1.9
A0027
Semi-Annaul NSPS Boiler Report
2
2
Draft December 15th & January 1st

Final June 15th & July 1st

3.1.9
A0028
Annual OB/OD Report
2
2
Draft December 15th

Final January 1st

3.2.2
B0001
HAFB Tier II Report
1
1
Draft January 25th

Final February 13th

3.2.3
B0002
UTTR Tier II Report
1
1
Draft January 25th

Final February 13th

3.2.4
B0003
HAFB TRI Form R
1
1
1st Draft February 01

2nd Draft March 01 Final March 31

3.2.4
B0004
Letter Report Justifying Exclusions of LMTF from TRI Report
1
1
1st Draft February 01

2nd Draft March 01 Final March 31

3.2.5
B0005
UTTR TRI Form R
1
1
1st Draft February 01

2nd Draft March 01 Final March 31

3.3.1.1
C0001
Work Plan
1
1
Annual, Prior to Beginning IWCS Study
3.3.2.1
C0002
Database for GIS Mapping
1
1
Draft Mar 1

Final Mar 15

3.3.2.1
C0003
Quantity and Quality of Industrial Waste Collection System Discharges Annual Group and Yearly Group Study
1
1
Draft Feb 15

Final Mar 15

3.3.2.1
C0004
NDSD Hill Wastewater evaluation
0
1
Mar 15
3.3.2.2
C0005
Test Results
0
1
Monthly 1st of each month
3.3.2.2
C0006
Hill AFB Industrial Waste Treatment Plant Monthly Compliance Report
0
1
Monthly 1st of each month
3.3.3.1
C0007
Summary Report Industrial Monitoring and Sampling Analysis Results
1
1
Draft January 22

Final February 28

3.3.3.1
C0008
Stormwater Discharge Monitoring Reports
1
1
Draft January 22

Final February 28

3.3.3.2
C0009
Deicing agendas and minutes
0
1
Bi – Annually
3.3.3.2
C0010
Annual Site Compliance Evaluation Audit Report
1
1
Draft February 15

Final March 15

3.3.3.3
C0011
Workplace Posters
50 Copties
November 5
3.3.3.4
C0012
Workplace Fact Sheets (MSGP)
1
1
Draft August 1

Final September 1

3.3.3.4
C0013
Priority Area Fact Sheets (MS4)
1
1
Draft January 28

Final February 25

3.3.3.4
C0014
Training (Briefing)
1
1
Draft 30 Calendar Days before Briefing

Final 2 business days before Briefing

3.3.3.5
C0015
Illicit Discharge Investigation Report
1
1
Draft 15 Calendar days after investigation

Final 15 Calendar days from Comments

3.3.3.5
C0016
Dry Weather Screening Report
1
1
Draft December 23

Final February 2

3.3.3.5
C0017
Construction Site Inspections
0
1
2 Business Days after each inspection
3.3.3.5
C0018
Pre-Construction Site Plan Review
0
1
1 Business Day after each review
3.3.3.5
C0019
MS4/SWMP Annual Report with supporting documentation
1
1
Draft August 15

Final September 3

3.3.3.5
C0020
High Priority Area Report
1
1
Draft January 28 2023

Draft February 28 2023

3.3.3.5
C0021
Updated Base Wide Drainage Map
1
December 24
3.3.3.5
C0022
Program Successes and Failures Analysis Report
1
1
Draft December 31

Final 14 Calendar days of receipt of comments

3.3.3.5
C0023
Stormwater Brochures
1
1
Draft October 29

Final December 03

3.3.3.5
C0024
Stormwater Inlet Marking Technical Memorandum
1
December 24
3.3.3.5
C0025
Design Criteria Document
1
1
Draft January 05

Final February 15

3.3.3.5
C0026
Pollution Prevention and Good Housekeeping – Municipal Facility Inventory
1
1
Draft February 15

Final March 15

3.3.3.5
C0027
Annual Long-Term BMP Inspection Report
1
March 15
3.3.4.7
C0028
Stormwater Management Plan (HILL SWMP)
1
1
Draft October 15 2025

Final January 15 2026

3.3.5.1
C0029
Stormwater Pollution Prevention Plan (HILL SWPPP, MSGP)
1
1
Draft January 15 2024

Final February 2024

3.4.3.7
D0001
Response Action Documentation
1
1
Draft 14 days of completion of clean up

Final 14 days after comments received

3.5.7
E0001
Oil Water Separator Inspection Report
0
1
Due Quarterly

Due by the 10th of each month following December, March, June, September

3.5.1
E0002
Hill AFB Annual Waste Stream Certification
1
1
Due to State and Air Force Annually

Draft January 15 Final 14 days after comments

3.5.1
E0003
Hill AFB Biennial Report
1
1
Due to State annually by 1 March of each even-numbered year for odd-numbered year data. Draft due to Hill AFB by January 15, Final report due 14 days after comments received.
3.5.1.1
E0004
Analysis of Waste Volumes and Disposal
0
1
Monthly

Due 5th of every month

3.5.1.1
E0005
Monthly Waste Reports
1
1
Monthly. Drafts due by the 10th of each month for the previous month. Final reports due for distribution to tenants/organizations within 5 working days of receipt of comments.
3.5.1.1
E0006
Review of Interfund Reports
0
1
Due to 75 CEG/CEIE within 1 working day of receipt.
3.5.2.1
E0007
Part B Permit Renewal Application
1
1
Draft December 31 2022

Final March 31 2023

Base Year & Option Year 1 Only

3.5.2.4
E0008
UTTR Biennial Report
1
1
Due to State annually by 1 March of each even-numbered year for odd-numbered year data. Draft due to Hill AFB by January 15, Final report due 14 days after comments received.
3.5.2.6
E0009
Soil Sampling Report
1
1
Field Work Completed by Mid November

Draft 120 days after Field Work is complete.

Final Report Due 14 Days after Field Work Final Due 14 days after comments

Option Year 1 & Option Year 3 Only

3.5.2.7
E0010
Land Use Assessment Letter Report
1
1
Due Annually

Draft Due March 01 Final Due 14 days after comments

3.5.2.8
E0011
Report of Wastes Treated at the TTU
1
1
Due Annually

Draft Due January 15 Final Due 14 days after comments

3.5.2.8
E0012
UTTR Annual Waste Stream Certification
1
1
Due to the State and Air Force Annually

Draft March 1 Final Due 14 Days after comments

3.5.2.9
E0013
Waste Minimization Statement
1
1
Due to State and Air Force

Annually Draft February15 Final 14 days after comments

3.5.2.10
E0014
Report Evaluating Alternatives to OB/OD

Treatment Technology

1
1
Due to the State and Air Force

Annually Draft February 15 Final March 31

3.5.2.11
E0015
Risk Assessment Evaluation
1
1
Draft Due August 31

Final Due 30 Days after comments

Base Year Only

3.6.2
F0001
HAZMAT Inventory Audit Analysis Report
0
1
Quarterly by the 30th of each month following the end of a quarter
3.6.2
F0002
Compliance Assessment Checklist Updates
0
1
As needed
3.6.3
F0003
Updated EESOH-MIS HM Training Materials and EESOH-MIS HM user Guides for Hill AFB
0
1
Twice yearly within 30 days of release of request, a new EESOH-MIS HM version, or updated local procedures.
3.6.4
F0004
HMMP Team Meeting Presentations, Agendas and Meeting Minutes
1
1
At least biannually, but no more than quarterly. Agendas - Drafts due 15 working days prior to meeting and finals due 5 working days prior to meeting. Presentations - Drafts due 5 working days prior to meeting and finals due 1 working day prior to meeting. Meeting minutes - Drafts due 5 working days following meeting and final due within 5 working days of receipt of comments.
3.6.5
F0005
Custom Reports
0
1
As needed within 5 working days of customer requests.
3.6.12
F0006
Submittal of BCRs/DIREPs to EESOH-MIS Help Desk
0
1
As needed within 5 working days of identification of problem.
3.6.15
F0007
Monthly Progress Reports
0
1
Monthly by the 10th of each month.
3.7.1
G0001
ICP and Spill Management Plan Technical Amendments
0
1
Annually for years that a full plan update is not required. Due by 1 November.
3.7.2.5
G0002
Five Year Integrated Contingency Plan Update
0
1
Draft report due on 30 August 2025. Final report due by 1 November 2025 or ten (10) business days after comments received, whichever comes first.
3.8.2
H0001
EMS Training Updates
1
1
As required to maintain EMS conformance. Draft due within 30 days of request from Hill AFB EMS Coordinator. Final due within 14 days of receipt of comments.
3.8.3
H0002
Environmental Action Plans
1
1
As needed. Draft due within 30 days of request from Hill AFB EMS Coordinator. Final due within 14 days of receipt of comments.
3.8.3
H0003
EMS Audit and Gap Analysis Results
0
1
As required to maintain EMS conformance. Due within 14 days of the completion of each audit.
3.8.4
H0004
EMS CFT and ESOHC Meeting Presentations, Agendas and Meeting Minutes
1
1
Quarterly for the EMS CFT; at least biannually but no more than quarterly for the ESOHC. Agendas - Drafts due 15 working days prior to meeting and finals due 5 working days prior to meeting. Presentations - Drafts due 5 working days prior to meeting and finals due 1 working day prior to meeting. Meeting minutes - Drafts due 5 working days following meeting and final due within 5 working days of receipt of comments.
3.8.5
H0005
Monthly Progress Reports
0
1
Monthly by the 10th of each month.
3.9.1
I0001
Monthly Metric Progress Report for Converting Hard-Copy Documentation to Electronic Format
0
1
Due by the 5th of each month.
3.10.1.1
J0001
Quarterly Solid Waste Reports
1
1
Draft due 30 days following the end of each quarter. Final report due 7 days after comments received.
3.10.1.1
J0002
Quarterly Landfill Fee Reports
1
1
Due by April 10, July 10, October 10, and January 10 to meet the submission deadline to UDEQ of the 15th of the first month of each quarter.
3.10.1.2
J0003
Annual Landfill Reports
1
2
Due to State annually by 1 March. Draft due to Hill AFB by January 15, Final report due 14 days after comments received.
3.10.1.3
J0004
Integrated Solid Waste Management Plan Review
1
1
Review and draft proposed changes, if any, submitted by 31 October (to be approved in 4th quarter CFT meeting). Final report due 14 days after comments received.
3.10.1.4
J0005
Qualified Recycling Plan Business Plan Review
1
1
Review and draft proposed changes, if any, submitted by 31 October (to be approved in 4th quarter CFT meeting). Final report due 14 days after comments received.
3.10.2.1
J0006
QRP Committee Briefing Slides
1
1
Draft due 10 days prior to meeting. Final due 4 days prior to meeting.
3.10.2.1
J0007
QRP Committee Meeting Minutes
1
1
Draft due 2 days following meeting. Final due 10 days following meeting.
3.10.2.1
J0008
Recyclable Material Processing Business Case Analysis
1
1
As needed and prior to initiating processing of a recyclable material stream.