About this file

This is a submittal document for starting block equipment being procured by the City of Doral, Florida for the Doral Central Park Aquatics Center. The submittal (PH4A - 131100-030 Revision 2) details specifications for seventeen starting blocks with the following key features: standard black powder coat finish on frames, black backplate and side grips, and FINA bars included to match design renderings. The manufacturer clarifies that fifteen blocks require a left step configuration while two require a right step configuration to accommodate grab rail placement. Additionally, FINA backstroke bars are required per the 131100 specification. For starting blocks equipped with a backplate, the specified safety cover (model 23969) must be provided. The submittal includes technical notes confirming that the client must approve color selections and that the equipment configuration follows the dual 25-meter course layout detailed in drawing 2/AQ203.

The document serves as a product specification and design confirmation for the starting block and backstroke flagpole anchor installation project at the Doral Aquatic Center. The broader contract opportunity requires installation of twenty-one starting block anchors and two backstroke flagpole anchors, including concrete coring, anchor bonding to the existing equipotential bonding grid in compliance with NEC 680, deck restoration, and testing. The City is seeking qualified contractors with demonstrated expertise in commercial aquatic facility construction and competitive swimming equipment installation to complete this work while maintaining code compliance and minimizing operational disruption.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

tbeason Image tbeason Text Box Submittal #PH4A - 131100-030 Revision 2:

PH4A -Starting Block tbeason Stamp tbeason Text Box #PH4A - 131100-030 Revision 2 tbeason Text Box x tbeason Text Box 9/13/2024 tbeason Text Box 1.The frame will come with a standard black powder coat unless otherwise specified.

2.The backplate and side grips are listed as black to match the rendering.

3.Fina Bars – they were added to match the renderings. Please let us know if you need the Fina Backstroke Bars.

4.Can you specify if you need right vs left step? If so, how many of each and what number should they be. The manufacturer states that you may need some with a right step to fit around the grab rails. The submittal lists all 17 as left step currently.

5.Please note for platforms with a backplate the safety cover you need is 23969.

JJN

Stamp

JJN

Text Box CH Notes:

#!: Client to confirm color #2: Client to confirm color #3: FINA backstroke bars required per 131100 specification.

#4: Refer to dual 25M course layout 2/AQ203. Quantity to be 15 with a left step and 2 with a right step.

#5: Provide safety cover that matches specified starting block tbeason Image