FACIILTY_SURVEY_(PART_II).pdf
PDF 13 MB Posted
- Attached to
- Operation of the Long Beach Job Corps Center
- Solicitation number
- DOLJ14SA00008
About this file
FACIILTY SURVEY (PART II)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fleet_Tracking_Management_System.pdf | ||
| Amendment_5.pdf | ||
| Amendment_4.pdf | ||
| Pre-proposal_Conference_Sign-in_Sheet.pdf | ||
| Amendment_3.pdf | ||
| Amendment_2.pdf | ||
| Amendment_1.pdf | ||
| Site_Map.pdf | ||
| Utilities_and_Fuel_Usage.pdf | ||
| Square_Foot_Facility_Utilization_Table.pdf | ||
| FACILITY_SURVEY_(PART_I).pdf | ||
| National_Staff_Compensation_Table.pdf | ||
| Computer_Property_Management_(EPMS_Non-reportables).pdf | ||
| Solicitation.docx | DOCX document | |
| Regional_Career_Pathways_Plan.doc | DOC document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LONG BEACH
Job Corps Center Long Beach, CA
Facility Planning Report Volume II
Supporting Data
Final September 2014
Department of Labor/ Office of Job Corps
LONG BEACH
Job Corps Center Long Beach, CA
Facility Planning Report Volume II
Supporting Data
Final September 2014
Cafeteria Building 3
VOLUME I - PLANNING STRATEGY
Acronyms and Abbreviations Defi nition of Terms Executive Summary Exsting Site Plan Center Statistics Facility Survey Assement Results and Recommentdations
1.0 INTRODUCTIONS
• Objective and Scope
• Report Contents
2.0 EXISTING CONDITIONS
• Background
• Ownership
• General Site Conditions
• General Building Conditions
• Preventive Maintenance
• Facility Assessment by Function
• Environmental Management
• Resource Use/Conservation
• Sustainability
• Accessibility Standards
• Completed and Current Projects
• Health and Life Safety Issues
• Defi ciency Summary
3.0 PLANNING ANALYSIS
• Space Utilization Analysis
• Federal Real Property Assest Management
• Defi ciency Analysis
• Facility Condition Summary
• Building Condition by Function
• Planning Analysis Results and Conculsions
3.0 RECOMMENDATIONS
• Status of Previous Plan
• Signifi cant Issues
• Proposed Plan
• Funded Not Corrected (FNC) Defi ciencies
• Summary of Proposed Plan
• Proposed Site Plan
• Implementation Plan
• Summary List of National Projects
• Project Data Sheets
Appendix A. Energy and Water Evaluation Report
VOLUME II - SUPPORTING DATA
Acronyms and Abbreviations Defi nition of Terms Executive Summary
1.0 SITE LAYOUT AND PLANS
• Location Map
• Exisiting Site Plan
2.0 DESCRIPTIONS
• Buildings and Structures
• Space Utilization By Function
• NSF by Building
• Environmental Management Report
• Asbestos Report
• Radon Report
• Site Descriptions
• Building Descriptions
3.0 DEFICIENCIES
APPENDICES - CORRESPONDENCE AND REPORTS
Appendix A.
• Center Review Meeting Minutes
• Survey Brief
• Student Questionnaire
Appendix B.
• Life Safety Defi ciencies and List
Appendix C.
• O&M Defi ciencies List
Appendix D.
• Active Warranty List
Appendix E.
• FRPC Performance Measures Matrix
Acronyms and Abbreviations
ACRONYMS AND ABBREVIATIONS
A Amperage ABAAS Architectural Barriers Act Accessibility Standard ACM Asbestos-Containing Materials AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ANSI American National Standards Institute ARRA American Recovery and Reinvestment Act of 2009 BTU British Thermal Units\ CAA Clean Air Act CCF Hundred Cubic Feet CCTV Closed Circuit Television CDC Child Development Center CDC Centers for Disease Control and Prevention CDP Career Development Period CDSS Career Development Service System CFL Compact Fluorescent Light Bulbs CFM Cubic Feet per Minute CIS Center Information System CMA Certified Medical Assistant CMMS Computerized Maintenance Management System CMU Concrete Masonry Unit CAN Certified Nursing Assistant CO Carbon Monoxide CO Contracting Officer COR Contracting Officer’s Representative CPP Career Preparation Period CRA Construction, Rehabilitation, and Acquisition CTP Career Transition Period CTS Career Transition Services
CTST Career Technical Skills Training (formerly Vocational Skills Training [VST])
CW Cold Water CWA Clean Water Act DDC Direct Digital Controls DFAM Division of Facilities and Asset Management DOL Department of Labor EISA Energy Independence and Security Act of 2007 EMT Emergency Medical Technician
EMT Electrical Metal Tubing (Conduit) EO Executive Order EPA U.S. Environmental Protection Agency EPCRA Emergency Planning and Community Right-to-Know Act (1986) EPMD Ethylene Propylene Diene Terpolymer ESC Engineering Support Contractor ESCIS Engineering Support Contractor Information System ESL English as a Second Language oF Degrees Fahrenheit FACP Fire Alarm Control/Annunciator Panel fc Foot Candle FNC Funded Not Corrected FOP Financial Operating Plan FRPC Federal Real Property Council FY Fiscal Year GAO General Accounting Office GED General Educational Development GFCI Ground Fault Circuit Interrupter gph Gallons per Hour GSA General Services Administration GSF Gross Square Feet HID High Intensity Discharge HP Horsepower HSD High School Diploma HTW Hazard and Toxic Waste HVAC Heating, Ventilating, and Air Conditioning HW Hot Water IBC International Building Code IMC International Mechanical Code ION Inventory of Needs IPC International Plumbing code KBTU Thousand British Thermal Unit/Gross Square Foot/Year kV Kilovolt kVA Kilovolt-Amps kw Kilowatt JCC Job Corps Center JCDC Job Corps Data Center JCH Job Corps Handbook kWh Kilowatt Hours LAN Local Area Network LED Light Emitting Diode LF Linear Feet MBH Thousand BTUs per Hour MBTU Thousand British Thermal Unit MWH Megawatt Hour MC Mission Critical MCF Million Cubic Feet MDNC Mission Dependent, Not Critical MDP Main Distribution Panel MLO Main Lug Only m/s Meters/Second MTS Manual Transfer Switch NEC National Electric Code NEMA National Electrical Manufacturers Association NEPA National Environmental Protection Act NFPA National Fire Protection Association NMD Not Mission Dependent NSF Net Square Feet OA Outreach and Admissions OBS On Board Strength OCM Office of Contract Management OIG Office of Inspector General O&M Operations and Maintenance OSHA Occupational Safety and Health Administration PA Public Address pCi Picocurie PV Photovoltaic PVC Polyvinyl Chloride RCRA Resource Conservation and Recovery Act RTU Rooftop Unit SGA Student Government Association SHPO State Historic Preservation Office SF Square Feet SPCC Spill Prevention, Control and Countermeasure SST Social Skills Training T5 Fluorescent Lighting Designation (High Efficiency)
T8 Fluorescent Lighting Designation T12 Fluorescent Lighting Designation (Low Efficiency TSCA Toxic Substances Control Act of 1976 TV Television TVSS Transient Voltage Surge Suppression UEV Unevaluated UFAS Uniform Federal Accessibility Standards UL Underwriters Laboratories USDA U. S. Department of Agriculture V Volt VCR Video Cassette Recorder VST Vocational Skills Training W Watt WAN Wide Area Network WBL Work-Based Learning WIA Workforce Investment Act WIB Workforce Investment Board
Defi nition of Terms
DEFINITION OF TERMS
Accessibility: The degree to which a product, device, service, or environment is available to as many people as possible. Accessibility can be viewed as the "ability to access" and benefit from some system or entity. The Federal Government is required to comply with published law (Architectural Barriers Act (ABA) of 1968 , American Disabilities Act of 1990), regulations and related standards. Accessibility laws and standards have evolved over the past 12 years. DOL now follows ABA Accessibility Standards for Federal Facilities (ABAAS) adopted by the General Services Administration.
Annual Operating Cost: This FRPC performance measure reflects the cost to operate each used asset and consists of lease costs as well as costs related to recurring maintenance, utilities, janitorial, and roads and grounds expenses (Source: FRPC 2012).
Building: In accordance with the FRPC 2012 Guidance for Real Property Inventory Reporting, a building includes an enclosure for human occupancy that serves a variety of functions (food service, education, recreation, medical/dental, storage, administration) and is likely to have full utility services (heating, cooling, etc.). A building typically is over 400 square feet.
Building Condition Rating by Function: Each building is assigned a building condition based on the physical condition of the building and the impact on the functional use of the facility. Three ratings are possible:
Good: The facility condition is not impacting the facility function. A facility can have deficiencies and still be considered good.
Fair: The facility condition is impacting the facility function and deficiencies are limited to less than 30% of the replacement value. Correction of the deficiencies would allow the facility to return to a good status.
Poor: The facility condition is significantly impacting the facility function and/or deficiencies are more than 30% of the replacement value. Generally a poor rating indicates a “gut renovation or total replacement/demolition would be required.
Building/Structure Ratings: Each building is rated according to three ratings (good, fair, and poor) based on evaluations of the structure, exterior, interior, mechanical, and electrical elements. Three ratings are possible:
Good: The facility condition is not impacting the facility function. A facility can have deficiencies and still be considered good.
Fair: The facility condition is impacting the facility function and deficiencies are limited to less than 30% of the replacement value. Correction of the deficiencies would allow the facility to return to a good status.
Poor: The facility condition is significantly impacting the facility function and/or deficiencies are more than 30% of the replacement value. Generally a poor rating indicates a “gut renovation or total replacement/demolition would be required
Construction Type: The International Building Code (IBC) construction classifications include the following:
Type I and II. Those types of construction in which building elements are of noncombustible materials, except as permitted in Section 603 and elsewhere in the code.
Type II and III. Any type of construction where the exterior walls are of noncombustible material and the interior building elements are of any material permitted by the code.
Type IV. This type (heavy timber, HT) is where the exterior walls are of noncombustible material and the interior building elements are of solid or laminated wood without concealed spaces.
Type V. That type of construction where structural elements, exterior walls, and interior walls are of any materials permitted by the code.
Contract Strength: The authorized number of students at a Center in accordance with the contract between the Region and Center Operator.
Deficiency: A deficiency at a Center represents the spectrum of conditions related to the Center’s mission and/or its physical, functional, or operational features do not meet related goals, standards, codes, or other measures of acceptability. Each deficiency at a JCC or CCC initially is categorized as one of the following three deficiencies: Program, Site, or Building:
Program: Program deficiencies address issues such as square footage shortages or the omission of amenities required or standard for the proper operation of a particular Job Corps function.
Site: Site deficiencies indicate adverse site and infrastructure conditions which negatively impact operations and environment (e.g., site lighting, sidewalks, roads, etc.)
Building: Building deficiencies indicate adverse conditions at the building level.
This element includes the substructure, shell, interior, services (plumbing, HVAC, fire protection, and electrical), and equipment and furnishings.
Deficiency Classifications (I to IV): Deficiency classifications are defined as follows:
Class IA - Deficiencies which address imminent life safety and health hazards.
Class II - Deficiencies which address code violations, however, do not represent imminent life safety and health hazards.
A - Deficiencies which violate code (Federal, State or Local) and may result in an interruption of center operations if not corrected.
B - Deficiencies which violate code (Federal, State or Local) and have no immediate impact on center operations if not corrected.
C- Deficiencies which are not in compliance for accessibility in accordance with the Architectural Barriers Act (ABA), Americans with Disabilities Act (ADA), Uniform Federal Accessibility Standards (UFAS), or other applicable standards.
Class III - Deficiencies which address facility repair, replacement or maintenance.
A - Deficiencies which if not corrected may result in an interruption of center operations.
B - Deficiencies which if not corrected will have minimal impact on center operations or can be mitigated through temporary measures until the deficiency is corrected.
Class IV – Deficiencies which address programmatic needs.
A - Deficiencies which if corrected produce substantial improvements in the quality of the learning and living environment.
B - Deficiencies which if corrected are desirable enhancements.
Deficiency Funding Status: The status of the deficiency included the following categories:
Funded deficiencies report indicates the funding year for funded Regional projects, which have dollar amounts shown, or deficiencies assigned to funded National and Regional projects without dollar amounts. Major Regional projects are equivalent to National projects but assigned to the Federal agency (e.g., U.S.
Department of Agriculture) that acts as the Center operator. All operations and maintenance (O&M) deficiencies are treated as funded through the Center Operators O&M contract within the Region.
Proposed deficiencies have been assigned to a proposed future National project.
Unfunded deficiencies are Regional projects unless or until they are assigned to a National project.
Deficiency Status: The deficiency status is tracked and updated during the three-year facility survey cycle, or as such deficiencies are corrected and reported. The status includes:
Uncorrected: Once a deficiency is identified, documented, reported, and assigned for correction, the deficiency remains uncorrected until such time that the deficiency is corrected, reported, and verified.
Corrected: A corrected deficiency is one that has been assigned, funded, corrected, reported, and verified. Typically, the ESC verifies completion of the deficiency through the facility survey or site visit. The Center also may report completion and provide verifiable evidence of the correction, subject to review by the ESC.
Funded Not Corrected: A deficiency that has been approved and authorized as a regional project through the CRA budget, emergency or supplemental funding, or the Life Safety Memo. Note: the funding may not have reached the Center yet as the first steps are a FOP allocation by the National Office and a contract modification by the Region.
No Longer Needed: A no longer needed deficiency is one that has been approved and funded as a Regional project, but due to subsequent circumstances, has been reported by the Center as no longer being required to be accomplished. This type of deficiency is verified and confirmed by the ESC and removed from the Funded Not Corrected deficiency category. The Center should take action with its Region to return the funds.
Facility Condition Index: This performance measure reflects the condition of each asset by comparing the current repair needs to the replacement value of the asset. The index is expressed as a percentage, with 100% being a facility with no repair needs.
Gross Square Foot: The sum of all areas on all floors of a building included within the outside faces of its exterior walls, including all vertical penetration areas, for circulation and shaft areas that connect one floor to another. Gross Area is computed by physically measuring or scaling measurements from the outside faces of exterior walls, disregarding cornices, pilasters, buttresses, etc., that extend beyond the wall faces. Exclude areas having less than a 3-foot clear ceiling height unless the criteria of a separate structure are met. Measured in terms of Gross Square Feet (GSF): GSF = Net Usable Area + Structural Space (Source: http://nces.ed.gov/pubs2006/ficm/).
Mission Dependency: The value an asset brings to the performance of the mission as determined by the governing agency. Specific elements of this category include (FRPC 2012):
Mission Critical - – Without constructed asset or parcel of land, mission is compromised.
Mission Dependent, Not critical (MDNC) - Does not fit into Mission Critical or Not Mission Dependent categories.
Not Mission Dependent (NMD) – Mission unaffected
Ownership (Owned vs Leased): If the property is owned, the Federal Government has fee simple interest for the real property asset. If the property is leased, the rights to use the asset are assigned to the Federal Government by a private entity or a non-Federal Government entity for a defined period of time in return for rental payments (FRPC 2012).
National Project: Generally large and complex projects that require professionally prepared drawings and specifications that are time phased (design and construction) and contracted by the DOL National Office.
Net Square Foot: The sum of all areas on all floors of a building assigned to, or available for assignment to, an occupant or specific use. This value is computed by physically measuring or scaling measurements from the inside faces of surfaces that form the boundaries of the designated areas. Exclude areas having less than a 3-foot clear ceiling height unless the criteria of a separate structure are met. Included should be major space use categories for assignable space (e.g., dormitories, education, recreation, etc.) that are used to accomplish the institution’s mission. Net Square foot: NASF = Sum of Areas Designated by the Major Space Use Categories (Source: http://nces.ed.gov/pubs2006/ficm/).
On Board Strength (OBS): The actual number of students on Center on a day to day basis.
Preventive Maintenance: The care and servicing by personnel for the purpose of maintaining equipment and facilities in satisfactory operating condition by providing for systematic inspection, detection, and correction of incipient failures either before they occur or before they develop into major defects (Source: Dictionary of Military and Associated Terms, US DOD 2005).
Property Type: Indicates the asset as one of the following categories of real property:
land, building, structure.
Property Use: Since the elements defined by the FRPC do not match the space use codes employed in ESCIS, a mapping procedure will be created to align the definitions.
In the report, the Federal Real Property Council (FRPC) classifications will be printed for display. The information is available through the property registration field of Engineering Support Contractor Information System (ESCIS), and the current ESCIS designations will be correlated to the FRPC designations as follows:
ESCIS FRPC
Dormitory Dormitories/Barracks Food Service Other Institutional Uses Education School Recreation Other Institutional Uses Medical/Dental Other Institutional Uses Storage Warehouse Administration Office Structure * Storage, Service, Utility
Systems, or Other Land Institutional
* Each structure will be entered manually from the ESCIS database into one of four FRPC categories listed opposite the term “structure”.
Replacement Value: The cost of replacing the existing constructed asset at today’s building standards. It is the amount required to construct an asset of similar size and in the same location at today’s construction standards. The replacement value reported must be greater than zero (FRPC 2012).
Regional Office Project: Generally smaller projects where the funds will be transferred to the region for center execution.
Structure: In accordance with the FRPC 2012 Guidance for Real Property Inventory Reporting, a structure serves to provide storage, service, utility systems and is not likely to have full utilities (heating, cooling, etc.). A structure typically is less than 400 square feet.
Sustainability: Formally known as the World Commission on Environment and Development, the Brundtland Commission's mission in the 1980s was to unite countries to pursue sustainable development. The Commission defined sustainability as the “development which meets the needs of current generations without compromising the ability of future generations to meet their own needs".
Sustainability also is defined as the creation or enhancement of environmental, economic, and social-cultural balance, as realized through business activities, individual actions, and community engagement. Sustainability addresses approaches, methods and practices that optimize the use of energy, water, and materials while reducing greenhouse gas emissions.”
Utilization: This performance measure assesses the degree to which each asset is utilized and is expressed as a percentage. It is calculated on a square footage basis, comparing the square footage used to the “design square footage” based on contract strength (Source: FRPC 2012).
Executive Summary
EXECUTIVE SUMMARY
The facility survey for the Phoenix Job Corps Center (JCC was completed the week of February 10, 2014. The information presented in Volume II, Supporting Data, represents the current status of the campus.
The information includes the following:
Existing site layout Overall status of existing building and structures Space utilization by building and function compared to recommended standards Status of environmental elements of the Center’s operations Details on the site and buildings and structures based on architectural, electrical, and mechanical survey and supporting documentation Presentation of the status of historical deficiencies and compilation of deficiencies documented through this survey Supporting documentation, as presented in the appendices of the center review meeting; survey brief and student questionnaire; life safety IA/IIA transmittal;
active warranties; and Federal Real Property Council (FRPC) Measures Matrix
Section 1.0 of this volume addresses site layout and plans while Section 2.0 presents details on the buildings and structures. Section 3.0 presents historic deficiencies and their status as well as new ones identified in this survey. The appendices provide additional information as noted below:
Appendix A. Survey Brief Questionnaire Appendix B. Life Safety Deficiencies and List Appendix C. O&M Deficiencies List Appendix D. Active Warranty Report Appendix E. FRPC Performance Measures Matrix
1.0 - Site Layout and Plans
LONG BEACH
JOB CORPS CENTER
LONG BEACH, CALIFORNIA
LONG BEACH
JCC
10 MI5 0
2.0 - Descriptions
2.0 DESCRIPTIONS
In this section, the following information on the Center and its buildings and structures is presented in tabular format:
Building and Structures – This table indicates the building type, asset number, name, use group, gross square footage (GSF), construction year, number of floors, number of sleeping room and number of beds, construction type (noted as numerical values instead of code-specified Roman numerals), status (active or closed), and overall condition. The possible International Building Code (IBC) construction classifications include the following:
Type I and II. Those types of construction in which building elements are of noncombustible materials, except as permitted in Section 603 and elsewhere in the code.
Type III. This type of construction is where the exterior walls are of noncombustible material and the interior building elements are of any material permitted by the code.
Type IV. This type (heavy timber, HT) is where the exterior walls are of noncombustible material and the interior building elements are of solid or laminated wood without concealed spaces. Fire-retardant-treated wood framing complying with IBC section 2303.2 shall be permitted within exterior wall construction with a 2-hour rating or less.
Type V. That type of construction where structural elements, exterior walls, and interior walls are of any materials permitted by the code.
The overall building/structure condition is rated in one of three categories: good, fair, or poor.
Space Utilization by Function - This table compares the DOL recommended net square footage per enrollee and for the total function (e.g., housing, education, food service, recreation, medical/dental, administration, storage/support) to the actual values.
Net Square Footage by Building - This table compares the DOL recommended net square footage for the buildings with the function (e.g., housing, education, food service, recreation, medical/dental, storage/support) to the actual values and presents a percentage difference in the two values. In some instances, a recommended value is not available for sub-elements of a function; therefore, the recommended value is shown as “0”.
Environmental Management Report – This table summarizes regulatory related solid and hazardous waste information in accordance with the Resource Conservation and Recovery Act (RCRA) and the presence or absence of hazardous material storage facilities in accordance with Emergency Planning and Community Right-to-Know Act of
1986 (EPCRA). An inventory of petroleum storage tanks is noted as well as asbestos and polychlorinated biphenyls (PCBs) in accordance with the Clean Water Act (CWA) and Toxic Substance Control Act (TSCA), respectively. In addition, this report statuses air quality as required under the Clean Air Act (CAA).Any radon testing of buildings also is documented.
Site Descriptions – Tabular information is documented for the site. Among the data presented are the topography; total number of buildings and structures; roads, parking and sidewalks; fencing; site utilities; storage tanks; accessibility; historic preservation;
natural hazards; and sustainability. The overall condition of the site is rated in one of three categories: good, fair, or poor.
Building Descriptions – Tabular information, as well as photographs and floor plan drawings, are provided for each building or structure, as appropriate, in the following categories: real estate; accessibility; building envelope; interior finishes; vertical circulation; heating, ventilation and air conditioning (HVAC); plumbing; fire protection;
electrical services; fire alarms; carbon monoxide detection; communication; and building metering. The overall condition of the building and its five key subsystems (structure, exterior, interior, mechanical, and electrical) are rated in one of three categories: good, fair, or poor. If applicable, recommendations for renovation or demolition are provided.
BUILDINGS AND STRUCTURES
00913 LONG BEACH 09/03/2014
1Page: of Date:
0001 - WELLNESS CENTER
0002 - BASIC EDUCATION
0003 - CAFETERIA
0004 - CHILD DEVELOPMENT CENTER
0005 - DORMITORY EAST
0006 - GYMNASIUM
0007 - MAINTENANCE/WAREHOUSE
0008 - VOCATION/EDUCATION
0010 - ADMINISTRATION
0012 - CAREER CENTER
0013 - VOCATION/EDUCATION
0014 - DORMITORY WEST
0003A - PERGOLA (10Ft x10Ft) 0008A - SHELTER (28Ft x 17Ft) 0009 - GATEHOUSE (8Ft x 10Ft) 0011 - GREENHOUSE (22Ft x 45Ft) 0013A - HBI STORAGE (23Ft x 23Ft) 0013B - PERGOLA (10Ft x10Ft) 0014B - GAZEBO (8Ft x 8Ft)
Name GSF 4,580
21,055 15,100
6,506 24,430 19,480 14,470 11,250
7,500 2,786
17,510 24,430
1,000
Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active
StatusType Building Building Building Building Building Building Building Building Building Building Building Building Structure Structure Structure Structure Structure Structure Structure
Use Group Built Flrs Const Business Business Assembly Business Residential Assembly Storage Business Business Business Business Residential Assembly Assembly Business Business Storage Assembly Assembly
Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good
ConditionAsset Number
0091300002 0091300003 0091300004 0091300014 0091300006 0091300007 0091300008 0091300009 0091300011 0091300015 0091300010 0091300005 0091308013 0091308010 0091300012 0091300013 0091308011 0091308015 0091308014
12 169,097
7 2,380
19 171,477
Buildings
Structures
Total
GSF
GSF
GSF
Summary
09/03/2014
Space Utilization By Function 00913 Long Beach Page: 1 of Date:
HOUSING
EDUCATION
FOOD SERVICE
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
Resident Men Resident Women Total Residents
Residents 213 Non Residents 28
241Total Students
(213)
(254)
(241)
DIFFERENCE
23,004
17,670
4,338
39,186
43,478
8,588
Lounge Other Shower/Toilet Sleeping excl. SPD(72 rooms; 272 beds) Storage
Academic (254) Non-Academic
20 -- Auto Repair Tech/Helper + 20 -- Cement Masonry + 24 -- Facilities Maint. and Const. + 20 -- Glazing + 60 -- Medical Assistant 30 -- Medical Office Support 20 -- Painting + 30 -- Pharmacy Tech +
Vocational Theory (134)
Dining (2 Servings) Food Preparation Food Storage
8,600 3,691 4,334
21,825
6,363 9,126
5,213 4,299 5,492 4,211 1,717
3,762
1,580
4,816 2,433 1,339
2,130 1,704 2,556
15,336 1,278
2,540 2,540
1,500 1,500 1,800
1,800
1,500 1,350
1,340
1,928 1,446
6,470 1,987 1,778 6,489
-542
3,823 6,586
3,713 2,799 3,692 3,311
-83 -35
2,262 -500
2,888
Vocations
16,182
25,808
4,250
09/03/2014
Space Utilization By Function 00913 Long Beach Page: 2 of Date:
RECREATION
MEDICAL/DENTAL
ADMINISTRATION
STORAGE/SUPPORT
VACANT
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
TOTAL 295.96 71,327 133,409
(241)
(241)
(241)
(241)
(0)
DIFFERENCE
169,097
0.79
TOTAL GSF
NET TO GROSS RATIO
11,070
1,445
8,980
4,820
14,861
2,947
10,251
12,729
1,369
Arts & Crafts Computer Lab Concession Stand/Restroom Gymnasium Men's Exercise Room Miscellaneous Recreation Multipurpose Room Recreation Office Recreation Storage Student Store Women's Exercise Room
Medical/Dental
Administration Child Development Center (52)
Operations & Maintenance Warehouse
Vacant
6.00
6,890
2,168 2,634
2,947
4,776 5,475
6,163 6,566
1,369
1,445
4,820 4,160
1,928 2,892
6,890
2,168 2,634
1,502
-44 1,315
4,235 3,674
1,369
RESIDENT
NON-RESIDENT
(213)
(28) 15
50 10,650
3,791
1,502
1,271
7,909
1,369
62,082
Net Square Footage By Building Date: 09/03/2014 Page: 1
Center: LONG BEACH (00913) of 4
HOUSING
Sleeping excl. SPD
Lounge
Storage
Shower/Toilet
Other
Function Suggested
NSF
10,915 10,910
4,631 3,969
2,154 2,180
2,015 1,676
0014 - DORMITORY WEST
0005 - DORMITORY EAST
0014 - DORMITORY WEST
0005 - DORMITORY EAST
0005 - DORMITORY EAST
0014 - DORMITORY WEST
0014 - DORMITORY WEST
0005 - DORMITORY EAST
0005 - DORMITORY EAST
0014 - DORMITORY WEST
Bldg Name Actual NSF Difference
21,825
8,600
4,334
3,691
Sub Total: 39,186
15,336
2,130
1,278
2,556
1,704
23,004
6,489
6,470
-542
1,778
1,987
( 213
16,182
36 rooms; 136 beds 36 rooms; 136 beds
Page: 2
Center: LONG BEACH (00913) of 4
EDUCATION
Academic
Vocational Theory (134)
Cement Masonry
Painting
Facilities Maint. and Const.
Medical Assistant
Non-Academic
Pharmacy Tech
Medical Office Support
Auto Repair Tech/Helper
Glazing
Function Suggested
NSF
2,230
1,175
4,299
3,762
5,492
1,717
2,242
1,419
1,356
5,213
4,211
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0008 - VOCATION/EDUCATION
0013 - VOCATION/EDUCATION
0008 - VOCATION/EDUCATION
0008 - VOCATION/EDUCATION
0013 - VOCATION/EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0010 - ADMINISTRATION
0003 - CAFETERIA
0002 - BASIC EDUCATION
0007 - MAINTENANCE/WAREHOUSE
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0006 - GYMNASIUM
0014 - DORMITORY WEST
0012 - CAREER CENTER
0003 - CAFETERIA
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0002 - BASIC EDUCATION
0013 - VOCATION/EDUCATION
0013 - VOCATION/EDUCATION
Bldg Name Actual NSF Difference
6,363
1,580
4,299
3,762
5,492
1,717
9,126
5,213
4,211
Sub Total: 43,478
2,540
1,340
1,500
1,500
1,800
1,800
2,540
1,350
1,500
17,670
3,823
2,799
2,262
3,692
-83
6,586
-500
-35
3,713
3,311
( 254
25,808
Page: 3
Center: LONG BEACH (00913) of 4
FOOD SERVICE
RECREATION
MEDICAL/DENTAL
Dining (2 Servings)
Food Preparation
Food Storage
Multipurpose Room
Arts & Crafts
Gymnasium
Student Store
Miscellaneous Recreation
Concession Stand/Restroom
Men's Exercise Room
Women's Exercise Room
Computer Lab
Recreation Storage
Recreation Office
Medical/Dental
Function Suggested
NSF
4,816
2,433
1,339
2,634
6,890
2,168
2,947
0003 - CAFETERIA
0003 - CAFETERIA
0003 - CAFETERIA
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0006 - GYMNASIUM
0001 - WELLNESS CENTER
Bldg Name Actual NSF Difference
4,816
2,433
1,339
2,634
6,890
2,168
2,947
Sub Total:
Sub Total:
Sub Total:
8,588
14,861
2,947
1,928
1,446
1,445
4,338
11,070
1,445
2,888
1,502
4,250
3,791
1,502
Page: 4
Center: LONG BEACH (00913) of 4
ADMINISTRATION
STORAGE/SUPPORT
VACANT
Administration
Child Development Center
Warehouse
Operations & Maintenance
Vacant
Function Suggested
NSF
4,264
5,475
6,566
6,163
1,076
0012 - CAREER CENTER
0010 - ADMINISTRATION
0004 - CHILD DEVELOPMENT CENTER
0007 - MAINTENANCE/WAREHOUSE
0007 - MAINTENANCE/WAREHOUSE
0003 - CAFETERIA
0010 - ADMINISTRATION
Bldg Name Actual NSF Difference
4,776
5,475
6,566
6,163
1,369
Sub Total:
Sub Total:
Sub Total:
10,251
12,729
1,369
4,820
4,160
2,892
1,928
8,980
4,820
-44
1,315
3,674
4,235
1,369
1,271
7,909
1,369
Environmental Management Report Center: LONG BEACH (00913)
Page: 1 Date: 09/03/2014 of 1
SOLID & HAZARDOUS WASTE MANAGEMENT (RCRA)
Commercial Waste Service
HAZARDOUS MATERIALS STORAGE (EPCRA)
Yes Locker located in Wellness Center
Lawn Chemicals - 500 lbs, Misc. Solvents - 25 gal Yes
PETROLEUM UNDERGROUND STORAGE TANKS (RCRA)
N/A0
PETROLEUM ABOVEGROUND STORAGE TANKS (CWA)
ASBESTOS AND PCB MANAGEMENT (TSCA)
AIR POLLUTION CONTROL (CAA)
None
Non-Attainment
Solid Waste Disposal :
Hazardous Waste Generator :
Hazardous Waste ID :
Generator Classification :
Hazadous Materials Storage :
Hazardous Materials ID :
HazMat Storage Area :
HazMat Spill Response Plan :
Number of Regulated USTs :
Number of Un-regulated USTs :
Local Hazardous Use Permit :
LEPC Notification :
EPA Generator ID Number :
Hazardous Waste Disposal :
RCRA Compliance
ID LocationFuel Type Capacity
Number of ASTs :
Asbestos Survey Date :
Asbestos Type :
Asbestos Coordinator :
Coordinator Training Date:
Custodial/Maintenance Training :
AHERA Regulated :
Management Plan Approval :
PCB Transformer Testing :
PCB Transformers :
PCB-Contaminated Transformers :
Transformers Labelled :
Regional Air Quality :
Permitted Air Pollution Source :
Source Description :
Consolidated Sevices Yes Lawn chemicals, Solvents
Small Quantity Generator N/A Commercial Hazardous Waste Disposal Service
Stericycle
No Yes
Overfill Leak Corrosion
SPCC Plan Required : SPCC Plan Completed :
N/A N/A
No Survey Performed None
N/A No N/A No Yes
CO, Ozone, PM-10
ID Fuel Type Capacity Location Overfill
Prevention Secondary ContainmentTank Status
Tank Status Prevention/Detection
Site Description
Aerial view of campus
Page: 1 Date: 09/03/2014 of 4
Paving Type for Roads & Parking Paving Type for Sidewalks
Asphalt Concrete
Comments:
Topography Buildings and Structures
Center is fully enclosed by fencing.
ROADS, PARKING & SIDEWALKS
Water Source Water Authority Service Meter On-Site Treatment Plant
1. Water System
Treatment Type Storage Type Storage Capacity(Gallons)
NoIndividualLong Beach Water and GasPublic Water Authority
None 0None
All water softeners have been removed or taken offline at Center.Comments:
Comments:
Fire Hydrants On-Site Water Supply Storage Capacity
(Gallons) Pressure Source FD Response Time (Minutes)
Yes 0 5None Municipal
Long Beach Fire Department Station 13 is approximately 1 mile away.
Sewage Treatment Flow
Center
Publicly Owned Treatment Works
Center
Gravity
Maintenance ResponsibilityOwnership
Number of Deficiencies = 1
SITE FEATURES
UTILITIES
3. Sanitary Sewer System/ Sewage Treatment Plant
2. Fire Protection System
Buildings Structures12 7Flat
Surrounding
Outdoor Recreation
Light Commercial, Residential, Urban
Basketball, Field None
Entire Site
Entrance
Chain Link
Automatic Gate
Location Type
Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Separate Loop
No
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Utility Utility Yes Good
System Capacity Adequate System Condition
Yes Good
Ownership
Roads & Parking Adequate Roads & Parking Condition Sidewalks Adequate Sidewalk Condition Yes Good Yes Good
Fencing
Other Features
Page: 2 Date: 09/03/2014 of 4
Long Beach Water & Gas
Comments:
Electric Company PCB Trans.
Transformer Mounting Transformer Ownership
Systems Ownership Maintenance Responsibility
Southern California Edison Co.
The primary 12.47kV underground service is delivered to the center from a utility pole at the corner of 19th Street West and Santa Fe Avenue to the pad-mounted utility-owned transformer located between Cafeteria Building 3 and Female Dormitory Building 5. The secondary 480/277V system is distributed throughout the center via a 3,000A, 480/277V, 3-section switchboard which is located in the cafeteria main electrical room. This is where utility metering and web-based owner metering occur. The 3000A switchboard serves Buildings 1, 2, 5, 6, 13 and 14.
Vocation/Education Building 13 subfed Vocation/Education Building 8. Gymnasium Building 6 subfed Maintenance/Warehouse Building 7. Administration Buildings 10 subfed Child Development Center Buildings 4 and Career Center 12. The owner's meter is located in each building electrical room. The 120/208V system is provided via an indoor transformer located in each building.
Pad Utility
Utility Utility
No
12.47 kV
480/277V, 3-Ph and 120/208V 3-PhUnderground
UndergroundPrimary Service
Secondary Service
Distribution Characteristics
5. Fuel Distribution System
Number of Deficiencies = 1
4. Storm Water System
Drain Type On-Site Storm Water Management
Underground N/A
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Yes GoodCenter
Gas Company Metering
Individual
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
7. Electrical (Service)
Transformer Maint Resp
Utility
System Capacity Adequate System Condition
Yes Good
Generator
None
8. Electrical (Site Lighting)
Roadways Parking Walkways Building Outdoor Sports
Mounting
Control
Pole Pole None Pole, Building Sport Light
Photocell, Time Clock Photocell, Time Clock N/A Photocell, Time Clock Switch
System Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Comments: The site lighting system, consisting of pole-mounted and building-mounted exterior fixtures, is owned and maintained by the center.
ATS MTS
No No
Number of Deficiencies = 1
6. Central Plant: None
Metering Master
Page: 3 Date: 09/03/2014 of 4
Comments:
Telephone Company
On-site Line Owner
The main telephone communications closet (MC) is located in Administration Building 10. Local telephone service is provided by Verizon and long distance is provided by Job Corps Data Center (JCDC) via nine T1 lines, three provided for Sai-Tech and six for the center (DOL) system. The telephone system has 110 digital and 2 analog lines and a fax lines which are all connected through VoIP system. Data transmission is routed from each building over fiber optic cabling to the MC and connected to a Cisco 6500 switch. The six T1 lines are for handling telephone communication, data network and video conferencing. Each piece of the equipment in the MC is connected to an three UPSs, which buffers the power surges and drops in the line voltage and will maintain the power needs of the system up to 35 minutes before an automated shutdown is enacted. The fire alarm system is centrally-connected to the fire alarm control panel located in the Female Dormitory Building 5 electrical room. A remote annunciator panel in Gatehouse Structure 9 monitors the fire alarm system center wide. The center security system includes a gate operator, remotely controlled from the gatehouse, door alarms for monitoring the door status at each exterior egress door in all dormitories, and motion detectors in Buildings 1, 2, 6, 7 and 10.
Closet circuit TV located on exterior and interior is monitored and recorded in Buildings: 1, 3, 5, and 14. Several strategically located exterior and interior cameras are monitored from the color monitor at Gatehouse Structure 9.
Cable TV is provided in Wellness Center Building 1, Education Building 2, dormitory lounges of Buildings 5 and 14, Administration Building 10, cafeteria and gymnasium.
Verizon
Maint. Responsibility
Center Center
Gate Operator, Door Alarms, CCTV, Motion Sensors
9. Electrical (Communication/Alarm/Security)
Yes
Central
VOIP
System Capacity Adequate System Condition
GoodYes
Number of Deficiencies = 2
STORAGE TANKS: None
Fire Alarm Security
Page: 4 Date: 09/03/2014 of 4
ACCESSIBILITY
Yes
NoNoNoNo
Nationally Registered Site
Site Eligible for National Register
Located in Historic District
Archaeological Significance
Earthquake Risk High Low MediumLow MediumIBC Medium
LightningEarthquake Def. Authority Flooding Tornado Hurricane Forest
Fire
Accessible Parking: Accessible Slope:
Yes
Curb Cuts:
Yes
Ramps:
YesYes
Site Accessible Route:
GENERAL SITE CONDITION
Rating X Good Fair Poor
HISTORIC PRESERVATION
NATURAL HAZARDS
The site condition is not impacting the functional use of the facilities.
The site condition IS impacting the functional use of the facilities.
The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.
Active Energy Use Reduction Program
Active Water Use Reduction Program
Approximate or Measured Waste Recycled
Use of School Dude or CMMS for Preventative Maintenance
Green Purchasing Policy Practiced
Site Stormwater Absorption Measures in Place
Center has Onsite Renewable Energy (PV or Wind)
Center has a Chartered Green Committee & Roster
Center Uses Green Cleaning Practices
SUSTAINABILITY
NO
NO
NO
NO
Yes
Yes
Yes
Yes
Building Descriptions and Structures
BUILDING 1 - WELLNESS CENTER
Building Descriptions Date: 09/03/2014Center : Long Beach (00913) Page: 1 of 62
Building: 0001 - WELLNESS CENTER
BUILDING ENVELOPE
Foundation RoofBuilding Concrete Loadbearing Masonry Steel
CMU Masonry Corrugated Metal Siding
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors Business 4,580 2,947 1 Owned 1998 Not Evaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Material
Because the roof material is thin corrugated metal, its life expectancy was reduced to 20 years.
Drainage Year Life
Remaining Type Area Served
Modified Bitumen
Asphalt Shingles
Corrugated Metal
Sealed Concrete Deck
Roof Drains and Scuppers
Gutters and Downspouts
Surface Run-off
Roof Drains and Scuppers
Flat
Gable
Shed
Flat
Building Perimeter
Mechanical Penthouse
Vestibule
Mechanical Penthouse
Comments:
3. Roof
Entire Building
Area Served
Page: 2 of 62
Building: 0001 - WELLNESS CENTER
Wall Roof Rigid Batt
INTERIOR FINISH
Carpet Ceramic Tile Concrete Vinyl Tile
CMU Ceramic Tile Drywall Wall Covering
Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Metal Frame
Awning Units - Aluminum Frame; Single Glazing; Fixed - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Insulation4.
Exterior Doors5.
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
The packaged gas heat/DX-cool rooftop unit is a Trane model YCD151C4H0AA manufactured in 3/1997.
Comments:
HVAC
Heat1.
Gas-Fired Packaged
Variable Air Volume
None Direct Digital Control (DDC)
Mechanical Economizer Entire Building
Ceilings
Page: 3 of 62
Building: 0001 - WELLNESS CENTER
Mechanical Toilet/Shower
The water heater is a G.E. 40 gallon residential type.Comments:
Cast Iron None None
Electric Water Cooler Fixed Emergency Eyewash Hose Bibb Lavatory Portable Bottled Water Cooler Shower/Bathtub Sink Urinal Water Closet (Flush Valve)
Gas (Natural)
None None ABC Type Fire Extinguisher
Ventilation Area Served
Copper Copper Gas-Fired None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Split Direct Expansion (Air
Source)
Variable Air Volume
None Direct Digital Control (DDC)
Mechanical Economizer Entire Building
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Exhaust Ventilation
The packaged gas heat/DX-cool rooftop unit is a Trane model YCD151C4H0AA manufactured in 3/1997.
Comments:
Ventilation2.
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 1
Fuel Distribution4.
FIRE PROTECTION
3. Air Conditioning
Page: 4 of 62
Building: 0001 - WELLNESS CENTER
Comments: Service to the building is subfed from the 400A switchboard in the Administration Building 10 electrical room. Service enters to a 400A main distribution panel (MDP) with a 400A main circuit breaker and a Westinghouse IQ Data Plus digital multi-function meter. A 45 kVA transformer provides 120/208V system for the building, to a 150A MCB and 100A MLO panels. A 100A MLO, 277/480V panel served from the MDP provides for exterior and interior lighting.
FIRE ALARM
Comments: The building fire alarm devices are connected to the Center's main fire alarm control panel located in the Female Dormitory Building 5 electrical room and monitored by a remote annunciator panel in Gatehouse Structure 9.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Audible Alarm Manual Pull Station Smoke Detector Visual Alarm
Comments: Recorded footcandle levels include natural light contribution. Pendant-mounted 175W HID fixtures are used in the waiting/reception area. Several offices are equipped with occupancy sensors. Interior lighting is served by 277V power.
Comments: Tritium gas exit signs expire January 2018.
High Intensity Discharge (HID)
Comments: The building exterior lighting includes pole-mounted and building-mounted fixtures. The exterior lights are controlled by photocells mounted on the roof and a time clock with the lighting contactor in the electrical room. Exterior lighting is served by 277V power.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
High Intensity Discharge (HID)
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Offices
Equipment Rooms (Elec/Mech)
Mail Room
Reception
Toilets
Storage Rooms
Medical/Dental
Wards (Patient)
Area Recommended Level
Recorded Level Light Type
Battery Backup Tritium Gas
Main Distribution Panel 277/480V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Emergency Exit
ELECTRICAL SERVICES Number of Deficiencies = 1
Exterior Lighting1.
Interior Lighting2. Number of Deficiencies = 1
Emergency /Exit Lighting3. Number of Deficiencies = 1
Type Location None None
There are no CO devices in this building.
CARBON MONOXIDE DETECTION
LIGHTING
Detection Required
Number of Deficiencies = 1
Page: 5 of 62
Building: 0001 - WELLNESS CENTER
Comments: The building is connected to the Center's LAN system. Four bullet cameras utilized on the building exterior are monitored by color monitor and recorded by DVR, both located in the electrical room. The building also has motion detectors in the corridor and waiting/reception area.
Connected to Main System Closed Circuit TV None Local Cable Company
Telephone Security Public Address Television
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas Yes YesYes
BUILDING UTILITY METERING
Structure: Good Exterior: Good Interior: Good Mechanical: Good Electrical: Good
BUILDING 2 - BASIC EDUCATION
Page: 6 of 62
Building: 0002 - BASIC EDUCATION
BUILDING ENVELOPE
Foundation RoofBuilding Concrete Loadbearing Masonry Steel
CMU Masonry Corrugated Metal Siding
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors Business 21,055 14,001 1 Owned 1998 Not Evaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Material
The life expectancy of the modified bitumen roof was reduced due to its fair condition. The roof has a history of standing water and leaks inside the building and the south roof membrane shows signs of deterioration
The mechanical penthouse has a gable roof with a large square opening in the middle, leaving the concrete deck exposed to the elements. The penthouse has a 16 inch concrete curb with scuppers which conduct the storm water to the interior drains located on the flat roof.
Drainage Year Life
Remaining Type Area Served
Modified Bitumen
Asphalt Shingles
Sealed Concrete Deck
Roof Drains and Scuppers
Surface Run-off
Roof Drains and Scuppers
Flat
Gable
Flat
Building Middle Section
Main Building
Mechanical Penthouse
Number of Deficiencies = 1
Comments:
Comments:
3. Roof
Page: 7 of 62
Building: 0002 - BASIC EDUCATION
Wall Roof Rigid Batt
INTERIOR FINISH
Carpet Ceramic Tile Concrete Vinyl Tile
CMU Ceramic Tile Drywall Wall Covering
Metal Unit - Metal Frame Storefront - Metal Frame
Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Wood Unit - Metal Frame
Awning Units - Aluminum Frame; Single Glazing; Double Hung - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Insulation4.
Exterior Doors5. Number of Deficiencies = 2
Windows6.
Floors1.
Interior Walls2.
3. Number of Deficiencies = 1
Interior Doors4.
Page: 8 of 62
Building: 0002 - BASIC EDUCATION
Mechanical Toilet/Shower
Ventilation Area Served
Direct Expansion Refrigerant
Chiller Units
Split Direct Expansion (Air
Source)
Variable Air Volume
Fan Coil
Fan Coil
None
Four-Pipe
Refrigerant
Direct Digital Control (DDC)
Direct Digital Control (DDC)
Electric
Mechanical
Mechanical
Natural
Economizer
Economizer
None
Offices
Classrooms
Electronic Equipment
Room
Exhaust Ventilation
Common areas and offices are served by a packaged rooftop unit supplying a VAV distribution system.
The unit is a Trane model YCD181C4L0AA.
Classrooms are served by independent fancoils with hot water and chilled water coils. Chilled water is provided by a Trane model CGAEC604ACA1ACGRVH chiller. Hot water is provided by a Teledyne Laars model HHO400CN12KBACX boiler.
This is a Rheem model RAKA-018JAZ split/ductless system.
Comments:
Comments:
Comments:
Number of Deficiencies = 1
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Classrooms are served by independent fancoils with hot water and chilled water coils. Chilled water is provided by a Trane model CGAEC604ACA1ACGRVH chiller. Hot water is provided by a Teledyne Laars model HHO400CN12KBACX boiler.
Common areas and offices are served by a packaged rooftop unit supplying a VAV distribution system.
The unit is a Trane model YCD181C4L0AA.
Comments:
Comments:
HVAC
Heat1.
Gas-Fired Hot Water Boiler
Gas-Fired…
This is the start of the file's text. The full file is on GovTribe.