Q A.docx
DOCX document 15 KB Posted
- Solicitation number
- DOL-ETA-15-R-00030
About this file
Q A
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_DOL-ETA-15-R-00030.pdf | ||
| Revise_RFP_Amd6.pdf | ||
| J-12(b)_utilites_PY_2015.xlsx | XLSX spreadsheet | |
| AMS_amendment_005DOL-ETA-15-R-00030_(1).pdf | ||
| Attachment J-3.xlsx | XLSX spreadsheet | |
| Attachment J-1.xlsx | XLSX spreadsheet | |
| Revised Attachment J-7.docx | DOCX document | |
| amendment 003 sf30.pdf | ||
| J 11 Brunswick Vehicle Listing.pdf | ||
| J 12(a) Utilities PY 13.xlsx | XLSX spreadsheet | |
| Attachment J-4.xlsx | XLSX spreadsheet | |
| Cont SF30 sow revised.pdf | ||
| Sol_DOL-ETA-15-R-00030_Amd_000002.pdf | ||
| Amendment_0001.pdf | ||
| DOL-ETA-15-R-00030.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and answers Brunswick DOL-ETA-R-00030
1. Q. Please provide an updated and more recent utility usage estimate for (2014-2015).
A. Please see revised attachment J-12 document titled RFP 2016 Calendar year 2015 Utilities Information.
2. Q. Is electricity the only utility cost at the Center?
A. The center uses Electric, Gas, City/County Water, and Cable
3. Q. Please provide all utility utilization estimates for years 2013-2014.
A. Please see Listing located under attachment J 12 attached document titled RFP 2016 PY13 Utilities Information.
4. Q. Please provide a vehicle listing.
A. Please see Listing located under attachment J 11 document titled Brunswick Vehicle Listing.
5. Q. Please clarify the technical performance fee and the cost incentive fee offerors should propose. Section G and Section L are contradicting.
A. Section L Pricing schedule and Cost Detail : the maximum cost incentive Fee shall now change from 3.6% to now Read 4%.
6. Q. Page 11 Section C.1.C: Please clarify the Exception and Additional Considerations sections. They seem to apply to the WIOA option renewal information in section F.3 instead of the Center Design. Is that correct?
A. Yes, This is correct. Note: This information is taken directly from the Module RFP.
7. Q. page 47 Section H.30: Review and Approval of Staff Development and Incentives – Will the government consider revising this submission requirement to within 90 days of contract award to be consistent with the standard due date for other SOP’s?
A. Section H: 30 is hereby changed from 15 days to 90 Days
8. Q. Section I: Please clarify if offerors’ proposals should consider the Executive Order 13658, Establishing a Minimum Wage for Contractors. There is no reference to this requirement in the RFP.
A. Yes Clause 52.222.55 Minimum Wage Under Executive Order 13658 ( Dec 2014) shall be added to section I
9. Q. page 56 & 57 Attachment J-17 & 18 The Davis-Bacon and Service Contract Act Wage Determination schedules seem outdated. Will revised schedules be provided?
A: Yes revised decisions: Building GA139 dated 01/02/2015, Residential GA64 dated 01/02/2015 and Highway GA11 dated 01/02/215 shall all be included.
10. Q. page 76 L.6.H.A.5.c. Please confirm the maximum cost incentive fee should be 4.0%, instead of 3.6%, consistent with the charts in Section G. The instructions in Section L reference a maximum cost incentive fee of 3.6%.
A. Section L Pricing schedule and Cost Detail : the maximum cost incentive Fee shall now change from 3.6% to now Read 4%.