Semi-Agile Procedure Document.doc
DOC document 71 KB Posted
- Attached to
- Web and Mobile Application Development
- Solicitation number
- DOL121RP21395
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SDLCM-v2-2 Manual.pdf | ||
| Question 272 Update 26 Mar 2012.doc | DOC document | |
| Section B Updated 23 Mar 2012.doc | DOC document | |
| Section B Updated 21 Mar 2012.doc | DOC document | |
| Updated Vendor Q and A 21 Mar 2012.doc | DOC document | |
| Section B Final 15 Mar 2012.doc | DOC document | |
| Offeror Questions 20 Mar 2012.docx | DOCX document | |
| 15 Feb 2012 Updated SOW page 25.doc | DOC document | |
| SOW 21 Jan 2011 Final.docx | DOCX document | |
| OPA WEB SERVICES RFP 14 Feb 2012.rtf | RTF text file | |
| Key Personnel and Supporting Document.doc | DOC document | |
| Past Performance Questionnaire.doc | DOC document | |
| Attachment D Contract Administration Data.doc | DOC document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPA Semi – Agile Procedure Document
Task Activities Work Products Project Kick-off Determine all the team members who will be working on the project and conduct a project kick-off.
Briefly elaborate the Semi-Agile process that will be followed during the project lifecycle and the deliverables that will produced through the lifecycle of the project Kick-off meeting agenda and MOM Tailoring Request & Worksheet Determine if the project iteration will follow CMMI Process or if tailoring will be required Project Waiver form needs to be approved by the team lead if CMMI processes will not be followed.
Tailoring Request and Worksheet needs to be approved by the team lead if any of the processes are modified or followed as-is to suit the project Define Scope Discuss the objectives, benefits and the business needs for the project Document the Scope for the project and send it for review to the peer , team and the team lead Scope Statement Project Planning Plan for project planning document is completed Define any training requirements for the team members Collect the high level estimates Define the project schedule Create the Project Management Plan PPP, Project schedule, Estimation sheet, Project Management Plan Elicit Requirements Engage relevant stakeholders using a requirements questionnaire for eliciting high level business requirements Develop user stories Requirements Log with the high level business requirements Prioritize requirements From the elicited high level business requirements, the requirements are prioritized and selected for implementation in the 1st iteration taking any hard timelines for delivery into consideration. The prioritized requirements are reviewed by the team.
Iteration 1 requirements tab in the Requirements backlog sheet containing the prioritized requirements as agreed with the customer Develop Prototype Follow the Admin interface and Public interface standards to develop the prototype for the prioritized requirements in the iteration (Axure, White board, paper and PPT are used to develop prototypes). The prototype is reviewed by the team.
Prototypes for the iteration Refine Project Estimates Collect detailed estimates from the team based on the prioritized requirements and prototypes Update the project schedule according to the new estimates Updated project schedule reflecting the timeline for the Iteration.
Develop high level Test Plan With the requirements backlog and prototypes, the quality assurance analyst develops the high level test plan for the project and the first iteration High level test plan Requirements Inconsistencies audit and CM/DM audit Business analyst conducts the requirements inconsistencies audit after every iteration. Similarly the CM/DM audit is conducted after every iteration Audit report Product Development/DDD Using the prototypes, the prioritized requirements from the requirements backlog , the technical team documents the Detailed design for the iteration Detailed Design document for the iteration Product Modules Updated Prioritized requirements log for traceability
Product Testing by the Quality Management Team In the Semi-Agile process, the quality assurance analyst and the developer work closely with each other. Every module developed is immediately tested by the quality assurance analyst. The final product is as well tested when development is complete.
Bug report and Test report Security deliverables and Security Scan The Security team starts working on security deliverables as soon as the prioritized requirements are shared with them. To complete some of their deliverables, they also require inputs from the DDD. The security scan conducted when the product development is complete to ensure that the product complies with OCIO security controls.
Security deliverables Scan report, POAMS User Acceptance Testing When the product is ready for implementation, we conduct the User acceptance testing with the client. The quality assurance analyst demonstrates the product to the client. If the client has any feedback on the functionalities, the project manager will decide whether the feedback can be addressed as part of this iteration or further iterations. If there are any bugs identified at this stage, the developer will fix them and the quality assurance analyst will retest the application. If the client is satisfied with the iteration output, he will sign off on the developed product.
User acceptance test report Product Test Report User acceptance sign off Submit RFC The Request for change is submitted by the Change manager to ITC for the implementation of the application. It takes a minimum of 2 weeks for the implementation of the product in the ITC environment.
Request for Change Implementation and Testing on Production The product is implemented in the ITC environment and the quality assurance analyst runs a quick test in the Production environment Production testing report Post Implementation Review The project manager facilitates the post implementation review with the client. If any defects are found at this stage, a helpdesk ticket will be submitted and the technical team will then work on the issue since the project is handed over to O&M when the project is implemented at ITC.
Iteration Close out form Lessons Learned For every iteration, the lessons learned will be conducted to discuss what went well, what could be done better and recommendations for further iterations Lessons Learned document
This above procedure presents the Semi-Agile process we follow here at OPA during the 1st iteration. After the 1st iteration in closed, for further iterations the Project Scope document, Project Management Plan document, Plan for Project Planning document, Tailoring request and Worksheet will be updated only if any of the details included in these documents need to be changed. From the Elicit requirements task until Post Implementation review task, all of them have to be repeated for every iteration but the existing high level documents created during 1st iteration will be updated. There will be new tabs created for the prioritized requirements for every iteration in the Requirements backlog document. Similarly, the DDD will be updated for every iteration.
When the last iteration of the project is completed, the following are the tasks that will need to be pursued.
Task Activities Work Products Final Functional Requirements document (FRD) The FRD is completed including details of all the iterations for the entire project
FRD
FRD sign-off Final Detailed Design Document The final version of the DDD is completed including the details for all the iterations for the entire project
DDD
Final Test Plan Document The final version of the Test plan document is completed including the details for all the iterations for the entire project Test Plan document Test cases Document The consolidated test cases document with the test cases for all the iterations for the project is completed Test cases document Security Deliverables The consolidated security deliverables are presented for the entire project Security Deliverables Demonstration The application as a whole is demonstrated at the end of the project to the stakeholders Product Demonstration
Project Management activities Task Activities Work Products Schedule Management Daily stand up meetings with the team are conducted to keep everyone in the team is informed on the current activities. The status reports are shared with all the stakeholders on a weekly basis Status reports, Project Journal Project Planning and Risk management audits The Quality Assurance analyst conducts the PP and RSKM audits as the first iteration begins Audit findings report Requirements Inconsistencies audit and CM/DM audit Business analyst conducts the requirements inconsistencies audit after every iteration. Similarly the CM/DM audit is conducted after every iteration Audit report PMC, M&A, CM and PPQA Audits The PMC, M&A, CM and PPQA audits are conducted by the quality assurance analyst after the final iteration of the project is completed Audit report