System Development Life Cycle Management (SDLCM) Manual
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Semi-Agile Procedure Document.doc | DOC document | |
| Question 272 Update 26 Mar 2012.doc | DOC document | |
| Section B Updated 23 Mar 2012.doc | DOC document | |
| Section B Updated 21 Mar 2012.doc | DOC document | |
| Updated Vendor Q and A 21 Mar 2012.doc | DOC document | |
| Section B Final 15 Mar 2012.doc | DOC document | |
| Offeror Questions 20 Mar 2012.docx | DOCX document | |
| 15 Feb 2012 Updated SOW page 25.doc | DOC document | |
| SOW 21 Jan 2011 Final.docx | DOCX document | |
| OPA WEB SERVICES RFP 14 Feb 2012.rtf | RTF text file | |
| Key Personnel and Supporting Document.doc | DOC document | |
| Past Performance Questionnaire.doc | DOC document | |
| Attachment D Contract Administration Data.doc | DOC document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. DEPARTMENT OF LABOR
Office of the Chief Information Officer
System Development Life Cycle Management (SDLCM)
Manual
Version 2.2
November 2006
U.S. Department of Labor SDLCM Version 2.2 Preface
November 2006 i
PREFACE
The following is Version 2.2 of the Department of Labor’s (DOL) System Development Life Cycle Management (SDLCM) Manual. The SDLCM Manual was last updated in December 2002. This version (i.e., Version 2.2) provides an Administrative Update to the document, and includes the following changes:
• Replaced/updated I-TIPS references and information with eCPIC information throughout the entire document since I-TIPS is no longer used by the Department.
• Added section “1.14 Document Revision History”.
• Updated the FAQ section to clarify answers to previous questions and to add several new questions and answers.
• Combined the Figure 3 and 4 Large and Medium System Work Patterns
• Updated the deliverables in the Large/Medium and small work patterns (and the associated text in Chapters 2 through 8 supporting these Figures),
• Eliminated the Threshold 3i investment category in Section 1.4.1 and removed Figure 5 the Maintenance and Enhancement Effort Work Pattern
• Updated the Threshold 1, 2, and 3 descriptions to be consistent with the OCIO Capital
Planning Guide and increased the minimum annual investment cost from $100K to $250K for Threshold 1 and 2 investments. Also, added the text “with annual investment costs of $500K or above” to the financial management system bullet in the Threshold 3 section and language clarifying whether the threshold level was considered an Major or Non-Major investment as defined by Circular A-11.
• Deleted References to OMB Director’s Policy Memorandum M-97-02 (Raines Rules)
• Replaced the word “project” with “investment” accept when referencing the Project
Manager or Project Management Plan (PMP).
• Updated Figure 1 the DOL IT Investment Management Framework
• Deleted References to the following six deliverables:
Data Sensitivity Assessment Acceptance Test Approval Delivered System System Fielding Authorization Trained Personnel Implemented System
• Added six new deliverables including a description of each in Figure 7 Investment Target Architecture Investment Transition Strategy FIPS 199 System Categorization Contingency Plan Test Report Security Controls Testing/ Continuous Monitoring Re-certification and Accreditation
• The following changes were made to the list of existing deliverables in the Figure 3 work pattern:
“Security “Security Test & Evaluation” was changed to “Security Control Assessment Aid (SCAA) / Security Test & Evaluation (ST&E)”
November 2006 ii
“Acceptance Test Report” was combined with “Acceptance Test Approval” to form “Acceptance Test Report and Approval”
“Implementation Certification Statement” was changed to “System Acceptance Letter”
“Archived System” is now integrated into the “Disposition Plan” Updates to the CBA are now indicated for Phase 4 and 5, and 6. Updates in Phase
6 are driven by the results of the Operational Analysis.
The PMP and RMP are required to be updated in Phase 6 The WBS is a core requirement in Phase 1 and is updated for each of the remaining phases.
The Acquisition Plan is a core requirement in Phase 2 Deleted Implemented System, Acceptance Test Approval, Delivered System, System Fielding Authorization, and Trained Personnel A Records Management Plan has been added to the Project Management Plan
(PMP) – a description of what is expected by implementing a Records Management is also described in the document.
• Deleted Section 1.8 entitled “Certificate Based Services” which described the
Departments intention to create a PKI certificate based service since the Department is know longer pursuing this service.
• Added text throughout the document describing EVM and Operational Analysis requirements including for example an FAQ question/answer and Section 1.12 Performance Management
• Added text to Section 2.1, Step 1 indicating an Agency should use its EA to identify the need for new or modified IT investments as well as consolidation, business optimization, and collaboration opportunities.
• Replaced text in Section 2.1, Step 2, in the EA section of the table that states “the Departments enterprise target architecture and standards” with “the Departments enterprise architecture and IT standards.”
• Added a “Note” to Figure 5 in Section 1.9 to the definition of the Investment Target Architecture and Investment Transition Strategy to clarify that these EA deliverables are required to be incorporated into the Agency Target Architecture and Transition Strategy, respectively. Otherwise, an IT Investment PM may choose to create and maintain an IT Investment Target Architecture and Transition Strategy document that is separate from the Agency Target Architecture document.
• The Cost Benefit Analysis (CBA) outline in Appendix VII has been updated and well as the CBA text in Chapter 2 and 3.
• A description of the OCIO Cost Model has been incorporated in the CBA sections.
• The Project Management Plan (PMP) text has been updated to clarify the WBS and several other existing requirements.
• The Risk Management sections have been updated to reflect the new OCIO Risk
Management Plan template and associated Risk Register.
• The References section has been updated including the URLs.
• The Acronyms List has been updated to reflect current acronyms.
November 2006 iii
Please refer to the “Document Revision History” in Section 1.3 for a complete list of changes that have been made to this document since its inception. This document is considered a living document and as such is subject to change. This document will be updated in time, as necessary, to reflect any changes or new information that becomes known or available.
The Office of the Chief Information Officer (OCIO) believes that Version 2.2 of the SDLCM Manual is an important administrative update and DOL Project Managers should find it beneficial. If you have any questions, please contact the OCIO, Room N1301, 200 Constitution Avenue, NW, Washington, DC 20210 or via email at OCIO@dol.gov.
Executive Summary
November 2006 iv
EXECUTIVE SUMMARY
Annually, the U.S. Department of Labor (DOL) invests millions of dollars on information technology (IT) systems. These IT systems are vital to DOL mission programs and administrative functions. DOL’s goal is to rely on systems and technology for a safe, secure, and a dependable method to provide services, develop products, administer daily activities, and perform short- and long-term management functions. DOL must ensure data privacy and security when developing and implementing information systems as well as establish uniform privacy and protection practices.
To effectively manage the Department’s IT development and maintenance efforts within the framework provided by the "DOL Guide to IT Capital Investment Management (Version 2.0, May 2000)," DOL developed the System Development Life Cycle Management (SDLCM) Manual. The SDLCM serves as the mechanism to assure that developing, modifying, or enhancing systems meet established customer requirements and support DOL critical success factors. It sets forth a standard and logical process for managing IT system development activities and acquisition approvals that are controlled, measured, documented, and ultimately improved while responding to the following current legislation mandating the use of industry standards:
• National Technology Transfer and Advancement Act of 1995
• Information Technology Management Reform Act of 1996 – ITMRA (Clinger-Cohen
Act)
• OMB Circulars (i.e. A-11, A-130, A-94, A-109)
DOL uses an IT Investment Management Framework (IMF) to help Agencies manage investments and integrate several different functional areas. The main components are IT Capital Planning and Investment Management, the SDLCM, and Security Compliance. Other related functional areas within the Office of the Chief Information Officer (OCIO) include Enterprise Architecture, Information Quality, Quality Assurance, Performance Measurement, E- Government and Records Management. The Framework is described in greater detail in later sections of the document, including an integrated business process section. The Department’s PMF identifies the SDLCM phases and maps them to corresponding IT Capital Planning and Security phases, thereby ensuring a comprehensive, integrated approach to investment management.
The SDLCM represents many years of systems development and engineering experience by information systems professionals, including the incorporation of lessons learned from prior implementation versions. The purpose of this manual is to disseminate proven practices for use throughout DOL. The specific benefits expected include the following:
• Reduced risk of IT system investment failure
• Improved consideration of DOL program environments and associated system and data requirements throughout the entire life of the system (lessons learned)
• Early identification of technical and management issues to avoid investments in features
Executive Summary
November 2006 v or functions not benefiting the business community
• Formalization of the IT system acquisition approval process
• Disclosure of all life cycle costs to guide business decisions
• Fostering realistic expectations of what the system will and will not provide, through active user involvement
• Information to enable consideration of all aspects -- programmatic, technical, management, and cost -- of a proposed system development or modification effort
• Periodic evaluations to identify systems that are no longer effective
• Measurements of progress and status to enable effective corrective action before proceeding to the next phase
• Information that supports effective resource management and budget planning.
The Department’s SDLCM divides an IT system's life cycle into seven phases starting with Conceptual Planning and ending with the Disposition Phase. It describes the inputs, activities and deliverables associated with each phase. Further, it presents guidance on how the approach can be tailored to suit the various types of systems development and maintenance projects that exist within DOL today.
The use of the SDLCM applies to all DOL and contractor personnel who are developing, acquiring (i.e. Commercial Off-The-Shelf (COTS)), or managing new systems, including making modifications or enhancements to existing systems. Adherence to the SDLCM by program officials, system developers, employees, contractors performing systems work for the Department, and all levels of DOL management across functional areas is crucial to delivering cost effective information systems. DOL Agencies are responsible for ensuring that the systems development and management approach described in the SDLCM is practiced on a day-to-day basis. The Chief Information Officer/Office of the Chief Information Officer (CIO/OCIO) is the authority for the SDLCM.
On September 27, 2004, the DOL Office of the Assistant Secretary for Administration and Management (OASAM) issued a memorandum titled “Guidance for the DOL Earned Value Management System (EVMS) Methodology” which established the requirements and timeline for submission of earned value data by specific Information Technology (IT) initiatives within the Department of Labor (DOL), pursuant to directives from the Office of Management and Budget (OMB) and applicable legislation. As a result of this memorandum, Earned Value Management (EVM) has become a mandatory requirement for major DOL IT investments. As such, EVM information and guidance has been added to this SDLCM manual to assist and support IT Project Manager’s in understanding what the EVM requirements are in the context of the SDLCM. A more detailed explanation of EVM and of the DOL EVM requirements can be found in the DOL EVM Guide which can be found in the DOL OCIO Resource Library on LaborNet at http://labornet.dol.gov/OCIO/resource-lib.htm In addition, the DOL OCIO has prepared an EVM FAQ which can also be found in the DOL OCIO FAQ web page at http://labornet.dol.gov/OCIO/EVM-EVMS-FAQ.htm .
November 2006 vi
TABLE OF CONTENTS
PREFACE .................................................................................................................................................................... I
EXECUTIVE SUMMARY ...................................................................................................................................... IV
1 INTRODUCTION
1.1 PURPOSE
1.2 DOCUMENT OVERVIEW
1.3 DOCUMENT REVISION HISTORY
1.4 FREQUENTLY ASKED QUESTIONS (FAQ) ABOUT THE SDLCM
1.5 DOL IT INVESTMENT MANAGEMENT FRAMEWORK
1.6 INVESTMENT MANAGEMENT ROLES AND RESPONSIBILITIES
1.7 IT CAPITAL PLANNING AND INVESTMENT MANAGEMENT REVIEW AUTHORITIES
1.8 IT INVESTMENT MANAGEMENT WORK PATTERNS
1.9 DELIVERABLE DESCRIPTION MATRIX
1.10 SECURITY COMPLIANCE
1.11 ENTERPRISE ARCHITECTURE
1.12 PERFORMANCE MANAGEMENT
1.13 QUALITY ASSURANCE
1.14 INFORMATION QUALITY GUIDELINES
1.15 SOFTWARE LIFE CYCLE MODELS
1.16 WAIVER/EXCEPTION PROCESS
2 SDLCM INTEGRATED BUSINESS PROCESS
2.1 INTEGRATED BUSINESS PROCESS DESCRIPTIONS OF SDLCM PHASES AND STEPS
3 CONCEPTUAL PLANNING PHASE
3.1 PHASE OVERVIEW
3.2 PHASE INPUTS
3.3 PHASE ACTIVITIES AND DELIVERABLES
3.4 PHASE CONSIDERATIONS
4 PLANNING & REQUIREMENTS DEFINITION PHASE
4.1 PHASE OVERVIEW
4.2 PHASE INPUTS
4.3 PHASE ACTIVITIES AND DELIVERABLES
4.4 PHASE CONSIDERATIONS
5 DESIGN PHASE
5.1 PHASE OVERVIEW
5.2 PHASE INPUTS
5.3 PHASE ACTIVITIES AND DELIVERABLES
5.4 PHASE CONSIDERATIONS
6 DEVELOPMENT AND TEST PHASE
6.1 PHASE OVERVIEW
6.2 PHASE INPUTS
6.3 PHASE ACTIVITIES AND DELIVERABLES
6.4 PHASE CONSIDERATIONS
7 IMPLEMENTATION PHASE
7.1 PHASE OVERVIEW
7.2 PHASE INPUTS
7.3 PHASE ACTIVITIES AND DELIVERABLES
November 2006 vii
7.4 PHASE CONSIDERATIONS
8 OPERATIONS AND MAINTENANCE PHASE
8.1 PHASE OVERVIEW
8.2 PHASE INPUTS
8.3 PHASE ACTIVITIES AND DELIVERABLES
8.4 PHASE CONSIDERATIONS
9 DISPOSITION PHASE
9.1 PHASE OVERVIEW
9.2 PHASE INPUTS
9.3 PHASE ACTIVITIES AND DELIVERABLES
9.4 PHASE CONSIDERATIONS
APPENDIX I - ENTERPRISE ARCHITECTURE
ENTERPRISE ARCHITECTURE LAYERS
FEDERAL ENTERPRISE ARCHITECTURE (FEA)
DOL ENTERPRISE ARCHITECTURE MANAGEMENT SYSTEM (DEAMS)
THE FEDERATED MODEL
INITIATIVE ALIGNMENT
UPDATES
APPENDIX II - SECURITY ROLES, ACTIVITIES AND DELIVERABLES
SECURITY ROLES
SECURITY ACTIVITIES AND DELIVERABLES
APPENDIX III – SOFTWARE LIFE CYCLE MODELS
APPENDIX IV – INFORMATION REFERENCES
APPENDIX V – SLDCM DELIVERABLE SUPPORTING DOCUMENTATION
APPENDIX VI – EXCEPTION REQUEST FORM
APPENDIX VII – SDLCM DELIVERABLE TEMPLATES
REQUEST FOR INFORMATION TECHNOLOGY SERVICES (RITS)
FEASIBILITY STUDY (FS)
COST BENEFIT ANALYSIS (CBA)
PROJECT MANAGEMENT PLAN (PMP)
WORK BREAKDOWN STRUCTURE (WBS)
RISK MANAGEMENT PLAN (RMP)
INVESTMENT TARGET ARCHITECTURE
INVESTMENT TRANSITION STRATEGY
FIPS 199 SYSTEM CATEGORIZATION REPORT
PRIVACY IMPACT ASSESSMENT
ACQUISITION PLAN (AP)
STATEMENT OF WORK (SOW)
FUNCTIONAL REQUIREMENTS DOCUMENT (FRD)
SECURITY RISK ASSESSMENT
SYSTEM SECURITY PLAN
SECURITY PLAN OF ACTION & MILESTONES (POA&M)
TEST PLAN (TP)
CONFIGURATION MANAGEMENT PLAN (CMP)
LEGACY DATA PLAN
DETAILED DESIGN DOCUMENT (DDD)
November 2006 viii
CONTINGENCY PLAN
IMPLEMENTATION PLAN (IP)
ACCEPTANCE TEST PLAN
SECURITY CONTROL ASSESSMENT AID (SCAA) / SECURITY TEST & EVALUATION (ST&E) REPORT
ACCEPTANCE TEST REPORT (ATR) AND APPROVAL
TRAINING PLAN (TP)
SYSTEMS ADMINISTRATION MANUAL (SAM)
USER MANUAL (UM)
SECURITY CERTIFICATION AND ACCREDITATION PACKAGE
CONTINGENCY PLAN TEST REPORT
SECURITY ACCREDITATION LETTER
SYSTEM ACCEPTANCE LETTER
SECURITY CONTROLS TEST REPORT / CONTINUOUS MONITORING ANNUAL REPORT
SECURITY RECERTIFICATION AND ACCREDITATION PACKAGE
SECURITY SELF-ASSESSMENT (ANNUAL)
DISPOSITION PLAN (DP)
ADDITIONAL DELIVERABLES
APPENDIX VIII – STRATEGIC PLANNING DISCUSSION
STRATEGIC MANAGEMENT PROCESS
BUSINESS PROCESS REENGINEERING
PERFORMANCE MEASUREMENT
APPENDIX IX – LIST OF ACRONYMS
LIST OF FIGURES
Figure 1: DOL IT Investment Management Framework Figure 2: DOL IT Investment Review Board Structure Figure 3: Large and Medium Investment Work Pattern Figure 4: Small Investment Work Pattern Figure 5: SDLCM Deliverable Matrix Figure 6: Types of Questions Answered by Earned Value Management (EVM) Figure 7: SDLCM Integrated Business Process Figure 8: Capital Planning and Investment Control Process – Control Phase Figure 9: Conceptual Planning Phase Activities Figure 10: Planning & Requirements Phase Activities Figure 11: Design Phase Activities Figure 12: Development and Test Phase Activities Figure 13: Implementation Phase Activities Figure 14: Operations and Maintenance Phase Activities Figure 15: Disposition Phase Activities Figure 16: Enterprise Architecture Layers Figure 17: Federal Enterprise Architecture (FEA) Models Figure 18: Iterative/Incremental SW Development Model Integrated with DOL SDLCM and CPIC Framework...100
LIST OF EXHIBITS
Exhibit 1: Sample Feasibility Study Outline Exhibit 2: Cost Benefit Analysis (CBA) Outline Exhibit 3: Sample Project Management Plan Outline Exhibit 4: Sample Acquisition Plan Outline Exhibit 5: Sample Functional Requirements Document Outline Exhibit 6: Sample Test Plan Outline
November 2006 ix
Exhibit 7: Sample Configuration Management Plan Outline Exhibit 8: Sample Detailed Design Document Outline Exhibit 9: Sample Implementation Plan Outline Exhibit 10: Sample Acceptance Test Report and Approval Outline Exhibit 11: Sample Training Plan Outline Exhibit 12: Sample Systems Administration Manual Outline Exhibit 13: Sample User Manual Outline Exhibit 14: Sample System Acceptance Letter Exhibit 15: Sample Disposition Plan Outline Exhibit 16: Sample Requirements Traceability Matrix Exhibit 17: Sample Preliminary Design Document Outline Exhibit 18: Sample Test Problem Report Outline Exhibit 19: Sample Maintenance Manual Outline Exhibit 20: Sample Operations Manual Outline
November 2006 1
1 INTRODUCTION
1.1 Purpose
This manual describes the U.S. Department of Labor’s (DOL’s) System Development Life Cycle Management (SDLCM) methodology including the procedures, practices, and guidelines for governing the conceptual planning, requirements definition, design, development & test, implementation, operations & maintenance, and disposition of an IT investment (e.g., an IT project, system, service, program, or initiative) within the DOL . This SDLCM Manual has been created to assist and support DOL Agencies in successfully managing their IT investments throughout the entire life cycle of the investment. This manual applies to all IT investments including for example custom software development, COTS integration, infrastructure changes, as well as IT services, programs, or initiatives. The SDLCM manual provides a proven, structured, and standardized life cycle management approach to all DOL IT investments. The concepts presented in this manual are the foundation for the life cycle management approach adopted by DOL to improve the quality of Departmental information technology (IT) investments.
1.2 Document Overview
This introductory chapter provides an overview of some general concepts that are relevant to the SDLCM, including the Departmental IT investment management framework, project management roles and responsibilities, the capital planning and investment control (CPIC) process, security, enterprise architecture and quality assurance. The second chapter includes an integrated business process for the SDLCM. Subsequent chapters address particulars regarding the Department’s seven defined phases of the SDLCM. Finally, the appendices provide additional information on several of the areas highlighted in the main document as well as detailed descriptions and templates for the SDLCM deliverables. Appendix IV contains hyperlinks and relevant references for Departmental, Federal and legislative guidance that impacts SDLCM activities.
1.3 Document Revision History
The following table describes the revision history of this document including the version number, the version date, the person who made the modification(s), and a description of the changes.
Version
No.
Version
Date Modified
By Description of Changes
1.0 01/2000 • Initial draft developed
2.0 06/2000 •
2.1 12/2002 DOL OCIO Administrative update including the following changes:
• Addition of Frequently Asked Questions
(FAQs)
• Addition of a business process, integrating
November 2006 2 the SDLCM with Capital Planning, Security and Privacy, and other functional areas under CIO oversight
• Update of security requirements
• Addition of enterprise architecture material
• Addition of quality assurance material
• Addition of information quality material
• Addition of software life cycle models
• Addition of a Waiver/Exception process
• Legislative update for the E-Government Act of 2002, Public Law 107-347
2.2 08/2006 DOL OCIO • See the “Preface” of this document for a complete list of changes made to this document.
1.4 Frequently Asked Questions (FAQ) about the SDLCM
What is the SDLCM Manual?
The DOL System Development Life Cycle Management (SDLCM) Manual establishes and describes the standard methodology including procedures, practices, and guidelines for governing the conceptual planning, requirements definition, design, development & test, implementation, operations & maintenance, and disposition of IT investments (e.g., an IT project, system, service, program, or initiative) within the DOL . The SDLCM Manual has be created to assist and support DOL Agencies in successfully managing their IT investments throughout the entire life cycle of the investment. It applies to all IT investments including for example custom software development, COTS integration, infrastructure changes, as well as IT services, programs, or initiatives. The SDLCM manual provides a proven, structured, and standardized life cycle management approach to all DOL IT investments.
Why do I have to use the SDLCM methodology?
The DOL SDLCM methodology is based on standard SDLC principles and practices that are time-tested and have been proven successful for managing IT investments in the private sector as well as in the Federal Government including other civilian Agencies and the Department of Defense. The SDLCM methodology serves as the structured mechanism to ensure that DOL IT investments are developed, modified, enhanced, as well as operated and maintained efficiently and effectively. It also assists and supports IT investment managers in achieving the intended or planned investment mission, goals, financial benefits as well as applicable DOL IT strategic goals and critical success factors. It sets forth a standard, repeatable, reliable, and logical process for managing IT investment development , acquisition, implementation, and operating activities to assure that they are controlled, measured, documented, and ultimately improved while complying with applicable legislation. The SDLCM adds value to IT investments by establishing a uniform and standardized approach to IT investment management and leading as well as guiding IT investment staff to think about and address many required activities and challenging issues throughout the investment life cycle.
November 2006 3
When do I use the SDLCM?
Agencies will need to follow the SDLCM for all IT investments (e.g., an IT projects, systems, services, programs, or initiatives) throughout the entire life cycle of the investment from conceptual planning to disposition. A key point of understanding is that the SDLCM should be utilized as a reference and guide throughout the life cycle of an IT investment. The SDLCM should be used in conjunction with other existing DOL IT investment management framework processes including the Capital Planning and Investment Control (CPIC), Security, and Enterprise Architecture life cycle processes. (See the DOL IT Investment Management Framework below for further details.)
What is a work pattern and how do I know which one to use?
A “work pattern” refers to the activities and products associated with a systems development investment that are tailored to the investment’s size and scope. There are four work patterns:
small, medium, large, and maintenance. Criteria used to determine the appropriate work pattern include cost, timelines, technical complexity, and security risk. In general, the more costly, technically complex, or risky an investment is, the more likely it is that the large work pattern will be appropriate. All major systems must follow the large work pattern. Please refer to the work pattern and threshold approval sections of this manual for specific details. They can be found in Section 1.8 of this document.
How do I know what the security requirements for my system will be?
Security requirements should be discussed with Departmental security staff during the beginning of the conceptual planning phase. Sponsoring Agency security authorities should, if possible, review the requirements referenced in the Computer Security Handbook prior to these discussions. This version of the SDLCM addresses security requirements in each phase of the life cycle. In addition, Appendix II focuses on Security roles, activities, and deliverables.
Where do I go to get help when I have questions?
The OCIO IT capital planning and system development personnel are the primary resources for providing SDLCM assistance. If you have questions about the SDLCM, please contact Peter Sullivan in the OCIO at 202/693-4211 or sullivan-peter@dol.gov. Additional SDLCM information can be found in the OCIO Resource Library on the DOL LaborNet under the System Development Life Cycle Management (SDLCM) topic area.
What if the SDLCM process does not suit the needs of my software development project?
If an investment team proposes to use an alternate system development approach or non-standard SDLCM templates (deliverables) in conjunction with an initiative, this exception needs to be approved by Departmental IT system development and capital planning staff. Project managers must coordinate with OCIO staff to discuss the exception process during the conceptual planning phase. Exception requests will be handled on a case-by-case basis, taking into consideration the complexity of the investment and the applicability/reason for the specific request. Please refer to the Waiver/Exception Process section of this manual, and direct exception requests to the OCIO’s IT System Development Staff. In addition, please refer to Appendix III for more information on Software Life Cycle Models.
November 2006 4
How does the SDLCM relate to other OCIO requirements for IT investments?
The SDLCM is one component of DOL’s IT Investment Management Framework. This Framework is described as the activities necessary to ensure that an IT investment progresses toward the achievement of its objectives in accordance with planned or revised cost, schedule and technical baselines, as well as performance outcomes. The other components of the framework include theCapital Planning and Investment Control (CPIC) process, the Security Life Cycle phases, and the Enterprise Architecture phases. Other related functional areas within the OCIO include Information Quality, Quality Assurance, Performance Measurement, E- Government and Records Management. All of these components must work together in an integrated manner to ensure compliance with statutory and regulatory requirements and to lead to successful investment outcomes. In formulating a lifecycle development process, it is essential that requirements documentation, work efforts and system specifications reflect the Department’s guidance on these topics. Reference materials on these topics are listed in the appendices.
What is Earned Value Management (EVM) and do I have to implement it for my IT investment?
EVM is a Department of Labor and OMB mandated IT investment performance based management process that integrates cost, schedule, and technical performance, to provide decision makers timely and accurate information on the overall performance or health of an IT investment. The EVM process measures the cost and schedule performance of an IT investment by comparing planned, budgeted, and scheduled work activities (which are laid-out in a time-phased manner) against actual work accomplished. As work is accomplished on an IT investment, IT investment value is “earned.” The EVM process is also used as a predictive tool that, when used effectively, can highlight investment risks, identify opportunities to manage or control the performance of the IT investment, and estimate the future (near-term) cost and schedule performance of the investment.
EVM is applicable to all Capital Planning and Investment Control (CPIC) Threshold 3 initiatives that are in the Select or Control phases of the CPIC process. EVM will also be applicable to Threshold 3 Mixed Lifecycle investments when the annual cost of Development, Modernization, and Enhancement (DME) exceeds $1,000,000. These exemptions are not applicable to an investment that warrants special attention because of other factors as delineated in OMB Circular A-11, such as significant importance to an agency’s mission, high management visibility, or high risk. The $1,000,000 per year threshold will be reconsidered before the end of FY 2007.
Investments in the Operational and Maintenance (O&M) or “steady state” phase are not required by OMB to perform EVM. These investments will conduct an Operational Analysis to determine how they are performing relative to operational cost, schedule, and performance goals.
For more information on EVM and the DOL Earned Value Management System (EVMS) please see the DOL EVM Guide which can be found in the DOL OCIO Resource Library on LaborNet at http://labornet.dol.gov/OCIO/resource-lib.htm and the DOL EVM FAQ which can be found
November 2006 5 in the DOL OCIO Resource Library on LaborNet at http://labornet.dol.gov/OCIO/EVM-EVMS- FAQ.htm .
What is an Operational Analysis and do I have to perform an Operational Analysis for my IT investment?
An Operational Analysis (OA) is an OMB Circular A-11, Part 7 required IT investment performance based management process that is to be conducted at least annually by all DOL Threshold 2 and 3 IT investments that are in the operations and maintenance (O&M) phase (i.e., Steady State). An operational analysis is also required by the O&M elements of “mixed life cycle” IT investments. That is IT investments that have Development, Modernization, and Enhancement (DME) activities and O&M elements occurring at the same time. The operational components of the mixed life cycle investment are required to conduct an Operational Analysis.
An operational analysis provides decision makers timely and accurate information on the performance and any performance gaps of an IT investment. It helps determine whether an IT initiative or asset is continuing to meet its planned objectives as well as the current needs of its users, customers, owners, stakeholders, and/or sponsors. The result or output of an Operational Analysis is a recommendation regarding the future operational status of an IT investment. For example, it may be determined that an operational IT investment should be:
• Maintained “as is” without any changes,
• Modified (i.e., requiring operational changes that do not result in any new DME activities),
• Enhanced (i.e., requiring new DME activities),
• Replaced (i.e., decommissioned in a planned manner and replaced with a new capital asset), or
• Terminated (i.e., decommissioned in a planned manner with no replacement)
Depending on the results of the Operational Analysis, an updated or new investment CBA may need to be completed in the O&M Phase to justify for example, an enhancement or even a replacement investment.
The Operational Analysis process implemented by an IT initiative or asset (including any associated documentation) should be commensurate with the size and scope of the initiative and associated documentation should be as detailed as necessary to support (i.e., justify and substantiate) the conclusion and/or recommendations regarding the future operational status of the IT initiative or asset.
The DOL OCIO has developed an OA template within the eCPIC tool as well as a standalone OA Worksheet Guide to support IT investments in the development of their OA.
A copy of the OA Worksheet Guide can be found in the OCIO Resource Library at http://labornet.dol.gov/OCIO/resource-lib.htm In addition, the OCIO has also developed an Operational Analysis FAQ to support IT investment PMs and associated team members. The OA FAQ can be found at http://labornet.dol.gov/OCIO/faqs.htm .
Where can I find more information about the DOL’s IT Investment Management
November 2006 6
Framework, specifically, the Capital Planning and Investment Control (CPIC) process, the Security life cycle phases, and the Enterprise Architecture (EA) phases.
A high level overview of the DOL IT Investment Management Framework can be found in the DOL IT Investment Management Quick Reference Guide, which can be found in the OCIO Resource Library on the DOL LaborNet (http://labornet.dol.gov/OCIO/resource-lib.htm) under the Project Management topic area. A detailed description of the DOL IT Investment Management Framework can be found in the DOL Governance Framework for IT Investments Reference Guide for Capital Planning, Security, and Enterprise Architecture, which also can be found in the OCIO Resource Library on the DOL LaborNet under the Project Management topic area.
A detailed description of the DOL Capital Planning and Investment Control (CPIC) process can be found in the DOL Capital Planning and Investment Control (CPIC) Guide, which can be found in the OCIO Resource Library on the DOL LaborNet under the Capital Planning and Investment Control (CPIC) topic area.
A detailed description of the DOL IT Security Life Cycle phases can be found in the DOL Computer Security Handbook, which can be found in the OCIO Resource Library on the DOL LaborNet under the Security topic area.
A detailed description of the DOL Enterprise Architecture process can be found in the DOL Enterprise Architecture Resources, which can be found in the OCIO Resource Library on the DOL LaborNet under Enterprise Architecture topic area.
November 2006 7
1.5 DOL IT Investment Management Framework
The Department’s Investment Management Framework (IMF) identifies the SDLCM phases and maps them to corresponding IT Capital Planning and Security phases, thereby ensuring a comprehensive, integrated approach to investment management. Process reviews by Agency, OCIO, Management Review Board (MRB), and the Technical Review Board (TRB) are conducted and recommendations/approvals are given addressing risk, complexity, cost and budget coverage. The figure also maps the SDLCM to the major milestones of the Department's Security process. Other related functional areas within the OCIO include Enterprise Architecture, Information Quality, Quality Assurance, Performance Measurement, E- Government and Records Management. These components are described in greater detail in later sections, including an integration overview in the business process section. The products of these components, and more importantly, the integration of them, help facilitate investment success.
Figure 1: DOL IT Investment Management Framework
During the Conceptual Planning Phase, the Project Manager and appropriate investment team members are identified. An individual, team, or reviewing authority such as the sponsoring Agency, OCIO, TRB or MRB, as appropriate, is designated as having review and approval responsibility for investment milestones and products prior to the investment continuing to the next phase. Other organizations and individuals become actively involved in the life cycle as the IT system matures. These organizations include user organizations or individuals responsible for database management, data administration, configuration management (CM), acquisition (procurement) support, and system security.
Conceptual Planning
Systems Development Life Cycle Management (SDLCM) Phases Planning &
Reqts Definition Design Development & Test Implement Operations &
Maintenance Disposition
Select
Capital Planning and Investment Control (CPIC) Phases Control Evaluate
Initiation
Security Life Cycle Phases Development or Acquisition Implement Operations &
Maintenance Disposition
Business Alignment
Enterprise Architecture Phases Technical Alignment Compliance
Assessment
November 2006 8
1.6 Investment Management Roles and Responsibilities
1.6.1 Project Manager
The Project Manager has overall responsibility for coordinating the management and technical aspects of the life cycle of a system, including activities related to the development of a system.
Responsibilities of a Project Manager may include (but are not limited to) the following:
developing a Project Management Plan, developing a cost and schedule baseline, and completing a investment within schedule and budget constraints while meeting the customer’s needs. In addition, a Project Manager is responsible for coordinating the development, implementation, and operation and maintenance of a system with appropriate units within an Agency (including centralized IT staff such as network operations staff, security personnel, database management staff, the IRM manager, etc.) as well as reporting the results of investments to the System Owner and other appropriate Agency staff. When appropriate, a Project Manager should present the progress of critical investments to the OCIO, the Technical Review Board (TRB), or another entity within the capital planning and investment management program. The Project Manager performs the following functions:
• Determine investment team organization based on user and information systems organization recommendations.
• Provide detailed work assignments, making sure there are written tasks for all work.
• Develop measurement criteria that define acceptable performance of each task.
• Manage investment development risks in accordance with SDLCM guidance, providing prioritized risk lists, probability of risk occurrence, impact to the investment, and mitigating activities for all identified investment risks. Risk management planning should include the contingency costs of mitigation.
• Coordinate and/or perform system planning, design, and implementation. Report on the progress of these efforts at quarterly capital planning control reviews.
• Coordinate user involvement, ensuring adequate involvement for all phases of the investment is maintained. Particular emphasis in the requirements and testing phases is critical. It is the Project Manager’s responsibility to ensure the System Owner is involved in authorizing the completeness of the requirements.
• Schedule and direct SDLCM documentation and milestone reviews and participate in reviews conducted by independent staff or a review committee.
• Lead the resolution of problems during all phases.
• Ensure delivery of base lined and fully documented deliverables required to initiate system implementation.
• Oversee preparation of required documentation and maintenance (QA) of an investment file.
November 2006 9
• Serve as the overall Quality Assurance (QA) manager for all required document sets and deliverables. When required, report on the QA status of all required investment documents and deliverables as part of an OCIO generated Quality Assurance Audit.
• Follow SDLCM guidance as outlined in this manual.
• Coordinate with the Computer Security Officer (CSO) to ensure all security activities are completed. The DOL Computer Security Handbook contains more in-depth information on this subject.
1.6.2 System Owner
The System Owner is located within the DOL organization benefiting from or requesting the work on an IT investment and is frequently thought of as the “customer” for that investment.
The System Owner performs the following functions:
• Maintains active senior-level involvement throughout the development of the system.
• Initiates the need identification process to generate a request for a new information system or modification to an existing system.
• Participates in investment review activities and reviews investment deliverables.
• Coordinates activities with the Agency Senior IT Executive.
• Obtains and manages the budget throughout the investment's life cycle against a Project Manger’s delivered locked baseline.
• Identifies high-level business functions and the need for new development.
• Defines the scope and context of the new development.
• Selects functional organization representatives as the essential participants on the investment team with responsibility for defining functional and user needs.
• Holds review and approval authority for ensuring that developed products meet user requirements.
• Conducts a review of Privacy Act issues to determine applicability. If determined to be appropriate, the System Owner will prepare or oversee preparation of the Privacy Act Notice and coordinate with the Records Management representative on the Privacy Act System Notice.
• Conducts review of Section 508 compliance issues to determine applicability.
• Provides baseline assessment performance measures to evaluate the delivered IT initiative against.
1.6.3 Users
Active user participation is essential at all levels in the definition, design, and development of an IT system. Users are responsible for initiating and expeditiously resolving issues relating to both
November 2006 10 system development efforts and identification and documentation of requirements. Specifically, user objectives are as follows:
• Provide a quick and consistent review of the requirements.
• Provide statistical information relative to the work processes.
• Develop performance standards.
• Review and refine the functional requirements and their documentation.
• Approve and prioritize requirements.
• Perform user acceptance testing.
1.6.4 Integrated Project Team
Integrated project team (IPT) members bring technical and functional expertise to the investment with each member planning and performing tasks in that individual’s area of expertise. Team members may not necessarily serve on the investment team for the duration of the investment;
however, all essential investment team members must be identified in the Conceptual Planning Phase of the investment.
The investment team may include individuals fulfilling the roles of: system developer; system tester; data administrator; database administrator; quality assurance (QA) representative; risk representative; Computer Security Officer (CSO); Configuration Management (CM) representative; telecommunications representative; Acquisitions Management representative;
Systems Operations representative; Freedom of Information Act/Privacy Act (FOIA/PA) representative; and other representatives required by the investment. Not every investment will have full-time staff assigned to every role, and some investments may not need all roles fulfilled.
However, consider all roles during investment planning.
1.7 IT Capital Planning and Investment Management Review Authorities
DOL has developed an approach to identify, fund, and manage IT investments. Specifically, the process described herein applies to the selection, control, and evaluation of the Department's IT initiatives. The three phases are described as follows:
• Select – The process used to identify all new, ongoing, and operational investments for inclusion into the Department's IT portfolio. Within this phase, Department personnel screen, score, rank, and select IT investments with input provided by functional and technical staff. The final approval of large "above threshold" initiatives (thresholds are defined below) will be made by the Department's Management Review Board with the support of the Technical Review Board and Chief Information Officer. Other IT investment selection decisions will be made by the Department's Agencies and the CIO, as designated by the Department's IT investment threshold policy. Select is broken down into two sub-phases: “Pre-Select” and “Final Select.” Pre-Select begins with the initial agency budget submission and continues until DOL sends their final budget request to OMB (after
November 2006 11 passback). Final Select occurs after DOL is informed of the final budget following the Congressional appropriations process.
• Control – The process used to monitor ongoing IT initiatives through their development or acquisition life cycle up to deployment and operation. The objective of the control phase is to ensure, through timely oversight that IT initiatives are performing within acceptable cost, schedule, and technical performance parameters and that potential risks and returns are continually being addressed.
• Evaluate – The process used when an IT investment becomes operational to determine whether the investment met performance, cost, and schedule objectives. The process is also used to determine the extent to which the Capital Planning process improved the outcome of the investment (lessons learned). These two steps are accomplished by conducting a Post Implementation Review (PIR) that focuses on each category.
1.7.1 IT Investment Approval Thresholds and Review Responsibilities
All IT initiatives are not the same – they vary according to cost, size, technical complexity, and duration. To help distinguish between different IT initiatives, DOL uses three thresholds in governing approval authority of IT systems. They are defined as follows:
• Threshold 1 (Small IT Investments): Investments with expected costs up to $250K annually. Threshold 1 investments are considered Non-Major IT Investments as defined by OMB Circular A-11 and are required to include the investment in the Agency Exhibit 53 template within the DOL OCIO Electronic Capital Planning and Investment Control (eCPIC) system, as part of the annual budget preparation process.
eCPIC is a web-based IT investment and portfolio management system designed to help Agencies and the OCIO manage and control Agency and Department-wide IT initiatives and portfolios, as well as, prepare budget documentation (i.e., OMB Exhibit 300 and 53).
eCPIC replaces the legacy Information Technology Investment Portfolio System (I-TIPS) application that DOL Agencies used in the past. eCPIC brings consistency to IT planning, budget formulation, and management processes and provides ready access to the information that is required to prioritize, select, monitor, and evaluate IT investments. All major IT investments must be entered into eCPIC before they can be approved. Additional information about eCPIC can be found at (http:\\ecpic.dol.gov).
Investments meeting Threshold 1 criteria are self-certified and governed at the Agency-level and are not required to complete and submit an OMB Exhibit 300. However, the OCIO is responsible for providing oversight of these investments as well as Agencies’ IT management principles and practices. In particular, the OCIO is required to ensure that the Agency complies with the guidance provided in this SDLCM Manual. This oversight is achieved through the OCIO Quarterly Control Review process.
• Threshold 2 (Medium IT Investments): Investments with expected costs between $250K and $5M annually. Threshold 2 investments are considered Non-Major IT Investments as defined by OMB Circular A-11 and are required to include the investment in the Agency Exhibit 53 template within the OCIO eCPIC systems, as part of the annual budget
November 2006 12 preparation process. Threshold 2 investments are not required to complete an OMB Exhibit 300, however, investment information such as SDLCM deliverables are required to be entered into the OCIO eCPIC system as required by the DOL Capital Planning Guide.
The OCIO will review Threshold 2 investments to ensure compliance with the guidance provided in the DOL SDLCM and CPIC guides.
• Threshold 3 (Large IT Investments): Any investment with annual costs at or above $5M or regardless of annual costs meets at least one of the following criteria:
• Is designated as having high management visibility, significant program or policy implications, or high development, operating, or maintenance costs.
• Is mission critical
• Is a financial management system with annual investment costs of $500K or above
• Is interoperable - having an interface with one or more Threshold 2 or 3 investments.
• Is cross-cutting - to be implemented in or used by two or more Agencies internal or external to the DOL.
• Interfaces with or is interoperable with a financial management system
• Is a Presidential Priority Initiative
Threshold 3 investments are considered Major IT Investments as defined by OMB Circular A-11 and as such are required to complete an Exhibit 53 and 300 templates within the OCIO eCPIC system, as part of the annual budget preparation process, for the life of the investment. In addition, Threshold 3 investment information is required to be entered into eCPIC. Threshold 3 investments will also need to be reviewed by the OCIO with corresponding referrals to the DOL TRB and Management Review Board (MRB) per the procedures found in the DOL Capital Planning Guide. The OCIO will assist the TRB/MRB by reviewing the investment to ensure compliance with the guidance provided in the SDLCM. This includes ensuring that any additional requirements of the TRB/MRB have been followed by the initiating investment. If in compliance, the OCIO recommends support of a compliant initiative to the TRB/MRB.
As part of the capital investment management process, DOL has established an investment review board structure to review and approve IT investments. This investment review board structure is depicted in Figure 2 below. Within the capital planning process, there are different types of IT initiatives that are defined using criteria (primarily related to the amount of funding required) and four levels or thresholds (referenced above). The approving authority within the investment review board structure will depend on what threshold an IT initiative falls under.
Process reviews by Agency, OCIO, Management Review Board (MRB), and the Technical Review Board (TRB) are conducted and recommendations/approvals are…