Dobbin and Quadriga - JA - 2026-LGR-0059 - Redacted.pdf
PDF 240 KB Posted
- Attached to
- Cube-Tec Dobbin and Quadriga Support - J&A
- Solicitation number
- 2026-LGR-0059
- Issued by
-
Library of Congress
About this file
This is a Justification and Approval for Other than Full and Open Competition document issued by the Library of Congress for contract requisition LGR-2026-0059. The Library of Congress, specifically the Audio Preservation Laboratory within the LCSG, RCS, NAVCC, and PSS divisions, is seeking contract support for maintenance, upgrades, and technical support of existing Cube-Tec Dobbin/CWF System and Cube-Tec Quadriga Digital Audio Workstation (DAW) equipment installed at the Culpeper facility. The contract is sole-source with Cube-Tec, the only company certified to maintain the proprietary Dobbin/CWF/Quadriga software code. The period of performance extends from May 31, 2026, through May 30, 2031, with an estimated value not specified in the visible document sections.
The justification for limiting competition is based on the fact that Cube-Tec's systems are proprietary software products with customized implementations that enable compliance with Federal Agency Digital Guidelines Initiative (FADGI) requirements. The Audio Preservation Lab has previously customized these systems for specific workflows, and no other commercially available Digital Audio Workstation software can replicate these capabilities. Modifying the source code would be unlawful and void the warranty. The Contracting Officer, James R. Robinson, certified on February 10, 2026, that the action represents best value and that prices are fair and reasonable based on historical pricing, the Independent Government Estimate, and market research. No advance notice will be published, and no competing sources expressed interest in the award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Statement of Work (SOW).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval For Other than Full and Open Competition
LGR-2026-0059
Form Updated 7/2/2020
Justification & Approval
As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.
This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.
This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.
Part 1 – Identification
1. Contracting Agency and Activity: Library of Congress, LCSG, RCS, NAVCC, PSS, Audio Preservation Laboratory
2. Nature of Action Being Approved
Contract LoC or Leg Branch Order GSA Schedule or GWAC Other
Requisition Number: LGR-2026-0059 Contractor (or Brand Name): Cube-Tec Estimated Value (Base and all options):
Period of Performance: 5/31/2026 – 5/30/2031
3. Description of Supplies or Services Required to Meet Library Needs
Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.
The Library requires the following supplies or services: The Library of Congress (Library) requires contract support to provide maintenance, upgrades and support for the existing custom Cube-Tec Dobbin/CWF System and Cube-Tec Quadriga DAW system equipment installed in the Culpeper facility for the LOC/NAVCC/Audio Lab.
Part 2 – Program Office Justification & Approval
4. Authority for Contracting Without Competition Over $350,000 For this requirement over $250,000, under FAR part 6, the basis for contracting without providing for full and open competition is:
There is only one responsible source and no other supplies or services will satisfy Library requirements.
41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.
Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).
Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302-
1(b)(2).
Other exception identified in FAR 6.302-1: Identify the exception
There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.
41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.
Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5: Identify the authority
Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302: Identify the exception Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
Up to and including $350,000 For this requirement up to $250,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:
Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.
Product or service is reasonably available from only one source.
Source controls copyrights, patents or other exclusive licensing arrangements.
Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.
Source is expressly authorized or required by statute: Identify the authority Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:
An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.
FAR 8.405-6(a)(1)(i)(A).
Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).
In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).
Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:
The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).
The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR
16.505(b)(2)(i)(B).
A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(C).
To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).
Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).
The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41
U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
5. Rationale for Contracting Without Competition
In supporting an action not providing for full and open competition, it is not sufficient to demonstrate that the contractor is exceptionally well qualified or even the best qualified, or that the required brand name product is well suited to the Library’s needs. The rationale must demonstrate that no one else, or no other competing product, can satisfactorily fulfill the Library’s requirement. Do not focus on the importance of the requirement; the issue is the rationale for not competing.
In supporting urgency, address the following: What are the unexpected facts or the unpredictable events that led to this situation? When is the required delivery or performance start date? Why this date? What specific harm to the Government will occur if the delivery is not made or performance not begun as scheduled? (Note that expiration of funds is not sufficient harm to justify not competing.) Demonstrate that the contract is only for items and quantities urgently needed until a competitive procurement action can be developed, or that a separate competitive follow-on is not practical.
In supporting a brand name justification, the brand name or feature must be essential to the Library’s requirements, and market research indicates that other company’s similar products or products with similar features cannot meet or be modified to meet the Library’s needs.
We are authorized to limit competition on the basis of the citation in section 4 because: Dobbin/CWF/Quadriga are proprietary software products of Cube-Tec. The audio preservation lab has previously purchased these products, worked with Cube-Tec to customize them to our needs and have based our current preservation and production workflows on them. Cube-Tec is the only company certified to maintain Dobbin/CWF/Quadriga software code. A separate competitive follow-on will not be practical because MBRS is utilizing customized instances of Cube-Tec CWF/Dobbin software to enable compliance with Federal Agency Digital Guidelines Initiative (FADGI) requirements, customized QC software and customized derivative creation software for digitized and born digital, historical, archival and cultural content. The capabilities of the customized Cube-Tec implementation are not replicable using other commercially available Digital Audio Workstation software and no other company would have access to the source code. Modifying the source code would be unlawful and void the warranty.
6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required
State what actions, if any, the program office can take to overcome barriers to competition before a contracting for this requirement again, such as:
using action to provide time to develop specifications for a competitive procurement by a certain date; licensing copyrights or patents so other contractors may use the works; or breaking the requirement into parts that may be purchased competitively. If this is a one-time requirement, explain that action to increase future competition is not needed. If the source is expressly required by statute, state “Source is statutory.”
To increase competition, we will: Cube-Tec CWF/Dobbin is a proprietary software product of Cube-Tec. Cube-Tec is the only company certified to maintain CWF/Dobbin software code. A separate competitive follow-on will not be practical.
7. Program Office Certification
I certify that the description of the Government’s minimum needs, schedule requirements, and technical information that provide the basis for this justification are accurate and complete.
Part 3 – Contracting Officer Determinations & Certification
8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on beta.sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.
Advance notice will be published in beta.sam.gov for 15 days before a contract is awarded. FAR 5.203(a).
Advance or concurrent notice will be published in beta.sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).
Advance notice will not be published because the action meets the following FAR exception:
Notice would compromise national security. FAR 5.202(a)(1).
Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).
Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).
Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).
Order will be placed against GSA schedule or other competitively-awarded contract. FAR 5.202(a)(11).
Other:
Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.
We made the following efforts to interest potential sources in this award: None
9. Listing of Sources That Expressed Interest in Writing
The following sources expressed interest in this award: None
10. Additional Information
The following additional information is relevant to this justification and approval: N/A
11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):
Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other: Prices obtained through competitive proposals
The following analysis (based on attached pricing information) supports my determination: Fair and reasonable pricing shall be determined before an award is made.
12. Contracting Officer Determination of Responsibility Checked System for Award Management (or will check in the case of competitive proposals for a brand name product)
13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because: No other company is able to provide upgrades and maintenance for the Library s existing Cube-Tec CWF/Dobbin QC/Derivative creation system. Prices are fair and reasonable based on historical prices paid, information from the IGCE, and information obtained through market research.
14. Contracting Officer Certification I certify that, to the best of my knowledge and belief, this justification is accurate and complete. For those actions up to $700,000, I approve contracting without competition for this requirement.
James R. Robinson James R. Robinson 02/10/2026
Name
Signature
Date
File details come from the government source that posted it. Updated .