Division 1 Revised.pdf
PDF 4 MB Posted
- Attached to
- W9128F21R0031 - RFP $254M 8(a) RDI MATOC
- Solicitation number
- W9128F21R0031
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9128F21R0031 - AM0002 254M RDI 2 MATOC.pdf | ||
| W9128F21R0031 - AM0001 254M RDI 2 MATOC.pdf | ||
| Attch3_Cost_Spreadsheet_RDI2__Reg8a.xlsx | XLSX spreadsheet | |
| W9128F21R0031_RFP- 254M 8(a) RDI MATOC Final.pdf | ||
| Attch1_PPQ.pdf | ||
| Attch2_R123 Sample Project SOW 28June2021.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01 30 00.24
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
03/19
PART 1 GENERAL
Attachments:
-Appendix A - Contract Document Distribution List -AF Form 103 - Base Civil Engineering Work Clearance Request (for Air Force task orders only) -Project Sign Details(to be provided with task order if required) -General Wage Decision No(s). (applicable wage rates will be provided with each task order)
NOTE: Individual task orders may have additional attachments to this section.
1.1 (UAI 5152.231-9000) EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(MAR 1995)
Note: Copies of each regional schedule may be obtained through the following Internet site:
http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.a spx.Currently the "Construction Equipment Ownership and Operating Expense Schedule" can be accessed on page 11 of 14 of the afore indicated URL.
Standard Form 1411 is no longer a current form. The Contracting Officer may require submission of cost or pricing data in the format indicated in Table 15-2 of FAR 15.408, specify an alternative format, or permit submission in the contractor’s format. Information other than cost or pricing data may be submitted in the contractor’s own format unless the use of a specific format is prescribed elsewhere in this contract.
(a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for settlement of proposals and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series of equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region (see task order). Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be developed using the formula provided in the schedule. For forward pricing, the Schedule in effect at the time of negotiations shall apply. For retrospective pricing, the Schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx.
http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx.
organization under common control, lease-purchase arrangements, and sale-leaseback arrangements will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
1.2 (UAI 5152.232-9000) PAYMENT FOR MATERIALS DELIVERED OFF-SITE (MAR
2009)
(a) Pursuant to FAR clause 52.232-5, Payments Under Fixed Priced Construction Contracts, materials delivered to the contractor at locations other than the site of the work may be taken into consideration in making payments if included in payment estimates and if all the conditions of the General Provisions are fulfilled. Payment for items delivered to locations other than the work site will be limited to:
(1) materials required by the technical provisions; or
(2) materials that have been fabricated to the point where they are identifiable to an item of work required under this contract; or.
(3) Items specifically listed below.
(b) Payment for materials delivered off-site shall be made only after receipt of paid invoices listing the value of material and labor incorporated in the items along with a canceled check showing the prime contractor's title to the time delivered off site. Payment for materials delivered off-site shall be limited to the following items:
(List specific material items to be considered for payment when off-site delivery is made.)
1.3 (UAI 5152.222-9000) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE
FOR PROCESSING CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR
PAYROLLS (APRIL 2011)
(a) The Contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
(b) If the Contractor elects to use an electronic payroll processing system, then the Contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Wage Rate Requirements statute. When the Contractor uses an electronic payroll system, the electronic payroll service shall be used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the Contractor chooses to use an electronic payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
(c) The Contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the FAR;
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;
(4) capable of producing electronic output of weekly payroll records that are capable of being uploaded into the Resident Management System (RMS);
(5) demonstrated security of data and data entry rights;
(6) ability to produce Contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Construction Wage Rate payroll processing system shall be provided to the Government during contract closeout.
(d) All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service shall be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.
1.4 (UAI 5115.504) AWARD TO SUCCESSFUL OFFEROR
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer. Proceeding with any work not authorized by the Contracting Officer will be at the Contractor’s own risk.
1.5 (UAI 5122.1302-100) VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS
OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
U.S. Department of Labor Veterans employment: https://www.vets.gov/
Federal Veteran employment information at https://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heros Act http://benefits.va.gov/vow/
Army Wounded Warrior Program-http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heros https://www.uschamberfoundation.org/hiring-our-heroes
Guide to Hiring Veterans - Reference Material https://www.whitehouse.gov/sites/default/files/docs/white_house_business_ council_-_guide_to_hiring_veterans_0.pdf
1.6 UAI 5152.249-9000 BASIS FOR SETTLEMENT OF PROPOSALS (MAR 2009)
Actual costs will be used to determine equipment cost for a settlement proposal submitted on the total cost basis under FAR 49.206-2(b). In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(c) Recorded job costs adjusted for unallowable and unallocable expenses will be used to determine equipment operating expenses.
(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of FAR 31.205 11).
(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.
1.7 COMPLETION OF WORK
See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT
REQUIREMENTS), FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984).
1.8 CONTRACTOR PERFORMANCE EVALUATIONS
Federal Acquisition Regulation (FAR) Subpart 36.201(Evaluation of Contractor Performance) requires evaluation of the construction contractor's performance throughout the contract period of performance. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering and Construction Bulletin 2014-13 to fulfill this FAR requirement. For construction contracts valued at or above $700,000.00, including all modifications, the USACE will evaluate Contractor's performance using the web-based Contractors Performance Assessment Reporting System (CPARS). After the USACE drafts an evaluation (interim or final), the Contractor will have the opportunity to access, review, comment and either concur or non-concur with the evaluation in the CPARS system for a period of 60 days. Access to the CPARS system requires either specific software called PKI certification (recommended method) or a username and password. The PKI certification is a Department of Defense recommendation and to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and may be purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and contacting vendors can be found on the web site: https://www.cpars.gov.
1.9 MANPOWER REPORTING
Contractors may direct technical questions to the "Send an Email" link at website or email contractormanpower@hqda.army.mil for current information on CMRA. Information regarding changes to the reporting process, when data should be entered, general policy information, how data is protected, and how to enter certain data can be found under the Frequently Asked Questions (FAQ) section at the CMRA website. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013.
The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report ALL contractor manpower (including subcontractor manpower) required for performance of this contract. The contractor is required to completely fill in all the information in the format using the following web address: https://ecmra.mil (https://cmra.army.mil). The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer's Technical Representative; (2) Contract number, including task and delivery order number; (3) Beginning and end dates covered by reporting period; (4) Contractor name, address, phone number, e-mail address, identity of contractor employee entering data; (5) Estimated direct labor hours (including sub-contractor); (6) Estimated direct labor https://www.cpars.gov/ dollars paid this reporting period (including sub-contractor); (7) Total payments (including subcontractor); (8) Predominant Federal Service Code(FSC) reflecting services provided by contractor (and separate predominant FSC for each sub-contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information; (11) Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest City, Country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and, (13) Number of contractor and sub-contractor employees deployed in theater this reporting period (by country). As part of its submission, the contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. "*
*Note: Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data. For internal Army analysis, the reports and queries from the database shall not contain proprietary data.
1.10 LIQUIDATED DAMAGES-CONSTRUCTION
See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT
REQUIREMENTS), FAR 52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION (SEPT 2000).
1.11 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS (FOR ARMY
TASK ORDERS ONLY, SAMPLE - SEE TASK ORDER FOR SPECIFIC REQUIREMENTS)
1. AT Level I Training
Not Applicable.
2. AT Awareness training for US based contractor personnel traveling overseas
Not Applicable.
3. Access and General Protection/Security Policy and Procedures
All contractor employees, including subcontractor employees, requiring access to an Army or USSOCOM controlled installation, facility, or area shall comply with applicable security policies and procedures (provided by the government representative). This includes policies pertaining to the use or prohibition of electronic recorders, devices, cameras, etc. If the Contractor is required to take photographs or videos on a government installation, the Contractor must obtain written permission from the Senior Commander. The Contractor shall also provide all information required for background checks to meet installation and facility access requirements to be completed by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, USSOCOM, USASOC and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should Force Protection Condition (FPCON) at any individual facility or installation change, the government may require changes in contractor security matters or processes.
4. For contractors requiring Common Access Card (CAC)
Not Applicable.
5. For contractors to maintain and recover a CAC
Not Applicable.
6. for Contractors Who Do Not Require CAC, But Require Access To A Dod Facility Or Installation
Not Applicable.
7. iWATCH Training
The Contractor and all associated sub contractors shall brief all employees on the local iWATCH program (training standards provided by the government requiring activity Antiterrorism Officer (ATO)). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the designated security office. Training shall be completed within 60 calendar days of contract award and within 30 calendar days of new employees' commencing performance with the results reported to the COR no later than 90 days after contract award and new employees' commencing performance.
8. Contractor Employees Who Require Access to Government Information Systems
Not Applicable.
9. OPSEC Standing Operating Procedure/Plan
Not Applicable.
10. OPSEC Training
All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites:
https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
11. Information Assurance (IA)/Information Technology (IT) Training
Not Applicable.
12. Information Assurance (IA)/Information Technology (IT) Certification
13. Not Used
14. Not Used
15. Handling or Access to Classified Information
Not Applicable.
16. Will be Escorted in Areas Where They May be Exposed to Classified and/or Sensitive Materials and/or Sensitive or Restricted Areas
All contractor employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. The Contractor will coordinate with the COR and/or facility security office for access when required.
17. NCIC and terrorist threat data base screening required
All contractor employees, including subcontractor employees, who are not in possession of a current Common Access Card (CAC) will be vetted by the local security office to determine fitness and eligibility for access IAW DTM 09- 012, paragraph 2.b(4) to include but not limited to an NCIC III and Terrorist Database screening. The Contractor will ensure that the government has sufficient biographical information to conduct said screening including, but not limited to the person's name, date of birth, and social security number.
18. Contractor Company to Obtain a Facility Clearance and Individual Clearances at the Appropriate Level
Not Applicable.
19. Pre-Screen Candidates using E-Verify Program
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Contractor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
20. For contracts that require delivery of food or water
Not Applicable.
21. Contractor responsible for ensuring security documentation is completed by applicants
22. Contractor must provide completed packets at least 70 days prior to start
Not Applicable.
23. COR notification to the Contractor
1.12 EXCEPTION TO COMPLETION TIME AND LIQUIDATED DAMAGES
In case the Contracting Officer determines that seeding, sodding, and/or planting and/or the specified maintenance thereof is not feasible during the construction period, such work will be exempt from the completion time and liquidated damages. This work shall be accomplished during the first seeding, sodding, and/or planting period and the specified maintenance period following the completion date.
1.13 COMPUTING COMPLETION DATES FOR NON-WORK PERIOD
No work will be required at the construction site during the period (see task order) inclusive. The days in this period have been included in computing the calendar days for completion of the work. The Contractor may perform work at the site during all or any part of this period upon giving prior written notice to the Contracting Officer. Working during this non-work period shall require approval by the Contracting Officer. No time extensions will be granted for delays during this period.
1.14 ORDER OF WORK
Any specific order of work requirements will be provided in each task order.
1.15 OFFUTT AIR SHOW/OPEN HOUSE (FOR TASK ORDERS AT OFFUTT AFB ONLY)
Work shall be scheduled so that there will be no construction during the 3 days (Friday, Saturday, and Sunday) of the annual air show and open house at Offutt AFB. Construction sites shall be in safe and orderly condition with no open holes, materials neatly and safely stored, equipment properly secured, and all debris removed. The open house usually occurs during the month of August.
1.16 GENERAL REQUIREMENTS (FOR TASK ORDERS AT FORT CARSON ONLY)
Not applicable.
1.17 MISSION DELAY DAYS
The Contractor shall anticipate a work delay of up to (see task order) days during the contract period due to Using Service operations. The Contractor will be notified one week in advance of these interruptions. This time is included in the overall completion time stated.
1.18 CONTRACT DRAWINGS AND SPECIFICATIONS
1.18.1 SETS FURNISHED
Make copies of conformed specifications with amendments or changes incorporated. Use the bid drawings and specifications as amended in the performance of the work until reciept of the conformed specifications and contract drawings (i.e., bid drawings that have been posted with all amendment changes). The Government will mail a CD/DVD or send the conformed specifications and drawings electronically to the Contractor. See Appendix A for Document Distribution list. See paragraph below for contract drawing reproduction and distribution requirements. The work shall conform to the contract drawings, set out in the drawing index, all of which form a part of these specifications. The work shall also conform to the standard details bound or referenced herein.
1.18.2 REPRODUCTION AND DISTRIBUTION
The Contractor shall reproduce multiple legible hard copy sets (half-size English unless directed otherwise) of contract drawings from Government provided CD-ROM or DVD-ROM or sent electronically containing read-only Adobe.pdf file drawings. Within 14 calendar days after receipt of CD-ROM or DVD-ROM or electronically sent conformed specifications and drawings containing read-only Adobe.pdf drawing files, the Contractor shall provide legible hard copy drawing and conformed specification sets to the addressees contained in the Contract Document Distribution List for Project in Appendix A to this specification. The Government will process no progress payments prior to receipt of the legible contract drawings and conformed specification sets. After receipt and distribution of the legible hard copy drawing and conformed specification sets, the Government will provide the Contractor with a CD-ROM or DVD-ROM or sent electronically containing editable CAD file drawings (format defined in Section 01 78 39.00 24 AS- BUILT DRAWINGS)). The Contractor shall prepare as-built drawings as defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS.
1.18.3 NOTIFICATION OF DISCREPANCIES
The Contractor shall check all CD-ROM or DVD-ROM or electronically sent drawing files furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Dimensions marked on drawings shall be followed in lieu of scale measurements.
Enlarged plans and details shall govern where the same work is shown at smaller scales. All scales shown are based on a standard drawing size of 22" x 34" (for military task orders) or 28" x 40" (for civil work task orders). If any other size drawings are furnished or plotted the contractor shall adjust the scales accordingly. The Contractor shall also advise his sub-contractors of the above. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
1.18.4 OMISSIONS
Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.
1.19 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Equipment Room Drawings; G-[RO][AO][PO].
Plant Layout Drawings; G-[AO][PO]. (for civil works task orders only)
1.20 CONCURRENT CONSTRUCTION
Construction work closely related to and/or located at the site of the work under a concurrent contract, including (see task order) may be in progress simultaneously with work under this contract. The location(s) of this concurrent work is shown on the drawings or described in these specifications. The Contractor shall cooperate with others as necessary in the interest of timely completion of all work. In the event of interference, the Contracting Officer shall be notified immediately for resolution and his decision shall be final.
1.21 PAYMENT
1.21.1 PROMPT PAYMENT ACT
Pay requests authorized in GENERAL CONDITIONS (CONTRACT CLAUSES) clause:
"Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Pay requests will be submitted on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses will be submitted with the ENG Form 93, and the required certification will be included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed. The designated billing office is the Office of the Area Engineer (unless noted otherwise in task order).
1.21.2 PAYMENT FOR MATERIALS DELIVERED OFFSITE
See UAI 5152.232-9000 PAYMENT FOR MATERIALS DELIVERED OFF-SITE
1.21.3 CONTRACTOR PAYROLL RECORD (for task orders in Rocky Mountain Area
Contractor shall be required to log payrolls for all their own employees and subcontractors utilizing ENG Form 3180. Each subcontractor requires a separate ENG 3180 for their payrolls. The Contractor shall maintain the ENG 3180, along with the payrolls, on site and available for review by the Contracting Officer's Representative. The ENG 3180's shall be updated weekly as payrolls are submitted. After making copies for their files, the Contractor is required to submit the originals of each week’s payrolls to the Resident Office. Before final payment, the Contractor shall provide the completed ENG 3180’s to the Contracting Officer's Representatives. If the Contractor has elected to use an electronic payroll system, as described in
(UAI 5152.222-9000) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR
PROCESSING CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR
PAYROLLS (APRIL 2011), the payroll inventory produced by the electronic payroll system will satisfy the requirements in this paragraph and FAR 52.222-8, Payrolls and Basic Records.
1.22 PLANT LAYOUT DRAWINGS (FOR CIVIL WORKS TASK ORDERS WITH CONCRETE BATCH
PLANT ONLY)
In accordance with paragraph: SUBMITTALS, drawings showing the layout of the plant the Contractor proposes to use on the work shall be submitted by the Contractor for review by the Contracting Officer. The drawings shall show the locations of the principal components of the construction plant;
offices; shop and storage buildings; housing facilities, if any; and storage areas and yards which the Contractor proposes to construct at the site of the work and elsewhere. The Contractor shall also furnish for review by the Contracting Officer drawings showing the general features of his aggregate processing plant; aggregate transporting, storage and reclaiming facilities;
aggregate rinsing and dewatering plant, if required; coarse aggregate rescreening plant, if required; concrete batching and mixing plant; concrete conveying and placing plant; and when precooling of concrete is required, the cooling plant. The drawing shall appropriately show the capacity of each major feature of the plant including the rated capacity of the aggregate production plant in tons per hour of fine and coarse aggregates;
rated capacity of the aggregate transporting, storage and reclaiming facilities; volume of aggregate storage; capacity of cement and pozzolan storage; rated capacity of the concrete batching and mixing plant in cubic yards per hour; rated capacity of the concrete transporting and placing plant in cubic yards per hour; and when used rated capacity of plant for precooling of concrete. Drawings showing any changes in plant made during design and erection or after the plant is in operation shall be submitted to the Contracting Officer for review.
1.23 DAMAGE TO WORK (FOR CIVIL WORKS TASK ORDERS ONLY)
The responsibility for damage to any part of the permanent work shall be as set forth in the GENERAL CONDITIONS (CONTRACT CLAUSES) clause: "Permits and Responsibilities." However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to GENERAL CONDITIONS (CONTRACT CLAUSES) clause: "Changes," of the contract will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
1.24 AVAILABILITY AND USE OF UTILITY SERVICES (FOR CIVIL WORKS TASK ORDERS
ONLY)
Use of public and private utilities will be as found available. The Contractor shall make his own arrangements for use of public and private utilities.
1.25 AVAILABILITY OF UTILITY SERVICES (FOR MILITARY TASK ORDERS NOT IN
DENVER AREA ONLY)
All reasonably required amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies. The Contractor shall, at his own expense, make all temporary connections and install distribution lines. The Contractor shall furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. The Contractor shall make arrangements with the Using Service, through the Contracting Officer, as to the method of determining the amount of water and electricity to be used by him and the method of payment therefore. All temporary lines shall be maintained by the Contractor in a workmanlike manner satisfactory to the Contracting Officer and shall be removed by the Contractor in like manner prior to final acceptance of the construction. Normal quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government.
1.26 AVAILABILITY OF UTILITY SERVICES (FOR TASK ORDERS IN DENVER AREA ONLY)
The Contractor shall arrange with the local utility company for electricity required by him for construction under this project and shall pay all costs in connection therewith. Reasonable amounts of domestic water will be made available to the Contractor by the Government from existing system outlets and supplies. The Contractor shall meter the amount of water used by him, and such amount of water will be paid for by or charged to the Contractor.
The Contractor shall, at his own expense, make all temporary connections and install distribution lines. The Contractor shall furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. All temporary lines shall be maintained by the Contractor in a workmanlike manner satisfactory to the Contracting Officer and shall be removed by the Contractor in like manner prior to final acceptance of the construction.
Normal quantities of electricity and water used to make final tests of completely installed systems shall be furnished by the Government.
1.27 UTILITY SERVICE INTERRUPTIONS (FOR MILITARY TASK ORDERS NOT AT FORT
CARSON ONLY)
Not applicable.
1.28 DIGGING PERMITS AND ROAD CLOSINGS (FOR MILITARY TASK ORDERS ONLY)
The Contractor shall allow 14 calendar days from date of written application to receive permission to dig and to close roads. Roads shall only be closed one lane at a time and vehicular traffic shall be allowed to pass through the construction area. Work on or near roadways shall be flagged in accordance with the safety requirements in Safety and Health Requirements Manual EM 385-1-1, which forms a part of these specifications. Work located along the alert force route shall not cause blockage and the Contractor shall maintain unobstructed access for alert force traffic at all times.
1.29 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (FIRM – FIXED PRICE TASK
ORDERS ONLY)
a. This clause specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default: (Fixed-Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
(see task order for schedule of monthly anticipated adverse weather days)
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the RMS daily CQC report, any occurrence of adverse weather and resultant impact to normally scheduled work, within 24 hours of the event. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. Describe in the RMS daily CQC reports the critical path item that is being affected and provide the critical path activity number(s) from the current schedule. The COR must acknowledge and accept the agreed upon occurrence of each adverse weather delay in RMS for the delays to be considered as adverse weather delays.
At the end of each month, identify the number of actual adverse weather delay days that includes days impacted by actual adverse weather (even if adverse weather occurred in previous month), calculated chronologically from the first to the last day of each month, and recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default (Fixed Price Construction)". (ER 415-1-15)
1.30 IOWA SALES AND USE TAX (FOR TASK ORDERS IN IOWA ONLY)
a. In the event goods, wares or merchandise on which the Contractor has paid Iowa sales or use tax become an integral part of the project, the Contractor shall obtain appropriate forms from the Iowa State Tax Commission for recording the amount of purchases of such goods, wares, or merchandise, and shall complete, execute, and deliver them to the Contracting Officer prior to final settlement of the contract. The Contractor shall provide and report all data and information which may be necessary or required to enable the Contracting Officer to obtain all refunds from the Iowa Tax Commission to which the Federal Government may be entitled.
b. The Contractor shall insert a clause containing the substance of the foregoing paragraph a. in every first tier subcontractor or vendor to include such a clause in any subcontract or purchase order which he places.
The Contractor shall obtain completed forms from his subcontractor and suppliers for submission to the Contracting Officer before final settlement of the contract.
1.31 INSURANCE REQUIRED
In accordance with GENERAL CONDITIONS (CONTRACT CLAUSES) clause: "Insurance Work on a Government Installation," the Contractor shall procure the following minimum insurance:
Type Amount
Workmen's Compensation and Employer's Liability Insurance $100,000
General Liability Insurance $500,000 per occurrence
Automobile Liability Insurance Bodily injury $200,000 per person and $500,000 per occurrence Property damage $ 20,000 per occurrence
(Coverages per FAR 28.307-2)
1.32 SECURITY REQUIREMENTS
1.32.1 Contractor's Employee Identification
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer, for cancellation upon release of any employees. When the contract involves work in restricted security areas, only employees who are U.S. citizens will be permitted to enter. Proof of U.S. citizenship is required prior to entry. When required by the Contracting Officer, the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project. (Based on FAR 52.204-2)
1.32.2 Entry Requirements
(See individual task order for requirements.)
1.32.3 F.E. Warren AFB Entry Requirements (for F.E. Warren AFB task orders
Not applicable.
1.33 CONTRACTOR PERSONNEL (FOR MINOT AFB TASK ORDERS ONLY)
Once a contract has been formalized, the contractor must furnish the 5 CONS or the Army Corps of Engineers with a full list of personnel and vehicles requiring access to the installation. The list must include full name, SSAN, address, and the inclusive dates/times of each employee requiring entry; and the make, model, year, color, and license plate number of all vehicles to be operated on the installation. This list will be verified and authenticated by the escorting agency and forwarded to 5 SFS Pass and Registration for further processing. After reviewing the form for accuracy and verification, 5 SFS Pass and Registration will maintain the form until the contractor arrives on the installation to begin work. The contractor must report to Pass and Registration to obtain the passes between 0800 and 1600 on the duty day the work is to begin. The escorting agency, in coordination with the contractor, will be responsible for monitoring the expiration dates of passes, and will ensure all personnel and vehicle passes are returned for destruction no later than the duty day following expiration, or the employees termination of employment. As the sponsoring agency for all contracts let on this installation, the escorting agency will be the point of contact for contracted employees.
1.34 CONTRACTOR QUALITY CONTROL (CQC)
See Section 01 45 00.00 10 QUALITY CONTROL.
1.35 NONDOMESTIC CONSTRUCTION MATERIALS
The list of excepted nondomestic construction materials or their components referenced in the Buy American Construction Material Contract Clauses includes the list set forth in paragraph 25.104 of the Federal Acquisition Regulation.
1.36 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
In order to closely coordinate work under this contract, the Contractor shall prepare a written agenda/meeting minutes and attend a weekly coordination meeting with the Contracting Officer and Using Service at which time the Contractor shall submit for coordination and approval, his proposed daily work schedule for the next two week period. The Contractor shall provide a copy of modifications (MODs), Serial Letters, Requests for Information (RFIs)and any other information that is needed in the minutes of the meeting. Required temporary utility services, time and duration of interruptions, and protection of adjoining areas shall be included with the Contractor's proposed 2-week work schedule. At this meeting, the Contractor shall also submit his schedule of proposed dates and times of all preparatory inspections to be performed during the next 2 weeks. If Section 01 32 01.00 10 PROJECT SCHEDULE is included in the task order, the items of work listed on the proposed 2-week schedule are to be keyed to the NAS by activity number and description for each activity anticipated to be performed during the next 2-week period. Coordination action by the Contracting Officer relative to these schedules will be accomplished during these weekly meetings. Daily reports shall be completed and given to the
Contracting Officer or Representative within 24 hours of work. All official correspondence such as serial letters and RFIs, with attachments are to be provided in one hardcopy original with original signatures and one electronic (Adobe pdf format) copy by email. The Government will consider the correspondence to be received when the hardcopy is received by the designated office.
1.37 AS-BUILT DRAWINGS
See SECTION 01 78 39.00 24 - AS-BUILT DRAWINGS
1.38 SIGN (FOR MILITARY TASK ORDERS ONLY, IF REQUIRED)
On commencement of work on this project, the Contractor shall furnish and erect the temporary sign in the location selected by the Contracting Officer near the project site. The Contractor shall maintain the sign in good condition through the project construction period. Upon completion of the project the Contractor shall remove the sign from the premises. The project sign shall conform to standard drawing bound herein. A decal of the "Engineer Castle" and the U. S. Air Force emblem (if applicable) will be furnished the Contractor upon request.
1.39 GOVERNMENT-FURNISHED PROPERTY
Pursuant to CONTRACT CLAUSES clause: "Government Property " the Government will furnish to the Contractor the following property to be incorporated or installed in the work. Such property will be furnished FOB or from storage/warehouse at the project site and the Contractor shall accept delivery when made, and unload and transport the property to the jobsite at his own expense. All such property will be installed or incorporated into the work at the expense of the Contractor. The Contractor shall verify the quantity and condition of such Government-furnished property when delivered to him and report the receipt of Government-Furnished Property in accordance with Section 00 72 00 GENERAL CONDITIONS (CONTRACT CLAUSES) DFARS 252.211-7007 REPORTING OF GOVERNMENT-FURNISHED PROPERTY. For damage or loss or property follow Section 00 72 00 GENERAL CONDITIONS (CONTRACT CLAUSES)
DFARS 252.245-7002 REPORTING LOSS OF GOVERNMENT PROPERTY.
Any Government Furnished property will be listed in the individual task order.
1.40 EQUIPMENT ROOM DRAWINGS
Prior to construction, the Contractor shall prepare and submit room plans for all mechanical, electrical, and communication rooms or similar areas.
The plans shall be consolidated for all trades, shall be to scale, and shall show all pertinent structural features. In addition, other items such as doors, windows, and cabinets required for installation and which will affect the available space, will be shown. All mechanical and electrical equipment and accessories shall be shown to scale in plan and elevation and/or section in their installed positions. All duct work and piping shall be shown.
1.41 CONTRACTOR FURNISHED EQUIPMENT DATA
See Section 01 78 36.00 24 WARRANTY OF CONSTRUCTION for Contractor Furnished Equipment Data to be submitted as part of the Warranty Equipment Booklet.
1.42 ACCOMMODATIONS FOR GOVERNMENT INSPECTORS (FOR MILITARY TASK ORDERS
ONLY)
The Contractor shall furnish a temporary office facility approximately 10 feet x 20 feet with a minimum of 200 square feet of floor space. It shall be located where directed and shall be reserved for Government personnel only. Drinking water facilities, adequate lighting, high-speed internet air-conditioning, heating equipment, and a partition enclosed chemical toilet shall be furnished and maintained by the Contractor. The office shall be furnished with one legal size filing cabinet with four drawers, one drafting table with stool, one plan rack, one desk, and three chairs. Used furniture, in good condition, will be acceptable. Entrance doors shall be equipped with a substantial lock. The Contractor shall provide janitor service, fuel for the heating facilities, electricity, high-speed internet and water, all at no cost to the Government, except the Contractor will not be liable for Government long-distance calls. The entire facility, including furniture, will remain the property of the Contractor and shall be removed from the site after completion of the work.
1.43 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS (FOR TASK ORDERS NOT
INCLUDING SECTION 01 32 01.00 10 PROJECT SCHEDULE ONLY)
To be submitted in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Schedules for Construction Contracts" shall indicate the required data for each of the principal features of the work. Contract changes or modifications will not include extensions of time unless the updated progress chart shows that the contract completion date is delayed due to the affect of the change on one or more principal features of the work.
1.44 ASBESTOS AND LEAD
a. The Contractor is warned that inhalation of asbestos and lead has been associated with health hazards.
b. See task order for information related to the presence of lead and/or asbestos.
1.45 PARTNERING
a. The…