Digitization QASP.DOCX
DOCX document 47 KB Posted
- Attached to
- WV ARNG records digitilization and indexing services Federal contract opportunity
- Solicitation number
- W912L820Q0021
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Digitization PWS021220.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
WVARNG Permanent Records Digitization Initiative, MNCI i
TABLE OF CONTENTS
| 1 | INTRODUCTION | 1 |
| 1.1 | Purpose | 1 |
| 1.2 | Performance Management Approach | 1 |
| 1.3 | Performance Management Strategy | 2 |
| 2 | ROLES AND RESPONSIBILITIES | 2 |
| 2.1 | The Contracting Officer | 2 |
| 2.2 | The Contracting Officer’s Technical Representative | 2 |
| 3 | IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS | 3 |
| 4 | METHODOLOGIES TO MONITOR PERFORMANCE | 3 |
| 4.1 | Surveillance Techniques | 3 |
| 4.2 | Customer Feedback | 3 |
| 4.3 | Acceptable Quality Levels | 4 |
| 5 | QUALITY ASSURANCE DOCUMENTATION | 4 |
| 5.1 | The Performance Management Feedback Loop | 4 |
| 5.2 | Monitoring Forms | 4 |
| 6 | ANALYSIS OF QUALITY ASSURANCE ASSESSMENT | 4 |
| 6.1 | Determining Performance | 4 |
| 6.2 | Reporting | 4 |
| 6.3 | Reviews and Resolution | 5 |
| ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY | 6 | |
| ATTACHMENT 2: SAMPLE QUALITY ASSURANCE MONITORING FORM | 8 |
ii
QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
INTRODUCTION
This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) titled WVARNG Permanent Records Digitization Initiative. This plan sets forth the procedures and guidelines Joint Force HQ, West Virginia Army National Guard will use in ensuring the required performance standards or services levels are achieved by the contractor.
Purpose The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received.
This QASP defines the roles and responsibilities of all members of the integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.
Performance Management Approach The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by JFHQ-WV, Admin Services Branch, to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.
Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints. The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.
Performance Management Strategy The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the contractor’s QC program.
1.3.2 The government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The government will make determination regarding incentives based on performance measurement metric data and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.
ROLES AND RESPONSIBILITIES
The Contracting Officer The contracting officer (KO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the JFHQ-WV contracting officer's representative (COR) SGT Brandon Hodge and the contractor. The KO will designate one full-time COR, who is the government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the KO.
The Contracting Officer’s Technical Representative The contracting officer’s technical representative (COTR) is designated in writing by the KO to act as his or her authorized representative to assist in administering a contract. COTR limitations are contained in the written appointment letter. The COTR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COTR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the KO for action. The COTR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS
The required performance standards and/or quality levels are included in the PWS and in Attachment 1, “Performance Requirements Summary.” If the contractor meets the required service or performance level, it will be paid the monthly amount agreed on in the contract. If the contractor exceeds the service or performance level, it is eligible to receive an incentive or award fee as stated in the contract. Failure to meet the required service or performance level will result in a deduction from the monthly amount.
METHODOLOGIES TO MONITOR PERFORMANCE
Surveillance Techniques In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance are (include those that apply)
· Random monitoring, which shall be performed by the COTR/COR designated inspector.
· 100% Inspection – Each month, the COTR/COR, shall review the generated documentation and enter summary results into the Surveillance Activity Checklist.
· Periodic Inspection – COTR/COR typically performs the periodic inspection on a monthly basis.
Customer Feedback The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction. Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the KO, as opposed to the contractor.
Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COTR/COR. The COTR/COR will accept those customer complaints and investigate using the Quality Assurance Monitoring Form – Attachment 2.
Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.
Acceptable Quality Levels The acceptable quality levels (AQLs) included in Attachment 1, Performance Requirements Summary Table, for contractor performance are structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls. For certain critical activities such as those involving preparation of the paper records, scanning/digitization of paper or Micro-Film and the indexing of all files, the desired performance level is established at 100 percent. Other levels of performance are keyed to the relative importance of the task to the overall mission performance at JFHQ-WV, Admin Services Office.
QUALITY ASSURANCE DOCUMENTATION
The Performance Management Feedback Loop The performance management feedback loop begins with the communication of expected outcomes. Performance standards are expressed in the PWS and are assessed using the performance monitoring techniques shown in Attachment 1.
Monitoring Forms The government’s QA surveillance, accomplished by the COR, will be reported using the monitoring form in Attachments 2. The forms, when completed, will document the government’s assessment of the contractor’s performance under the contract to ensure that the required results in accordance with task are being achieved.
The COR, will retain copies of all completed QA surveillance forms.
ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
Determining Performance Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels. Failure to meet the AQL may result in a deduction from the monthly payment, using the deduction percentages shown in Attachment 1. Likewise, if the contractor exceeds the performance standards, an incentive or award fee will be paid, in accordance with the incentive fee or award fee plan included in the contract.
Reporting At the end of each month, the contractor’s COR, will prepare a written report for the JFHQ-WV COR summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submitted monthly report and the completed quality assurance monitoring forms (Attachment 2), will become part of the QA documentation. It will enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.
Reviews and Resolution The KO may require the contractor’s project manager, or a designated alternate, to meet with the KO and COR and other government IPT personnel as deemed necessary to discuss performance evaluation. The KO and COR will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with COR, as often as required or per the contractor’s request. The agenda of the reviews may include:
· Monthly performance assessment data and trend analysis
· Issues and concerns of both parties
· Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis
· Recommendations for improved efficiency and/or effectiveness
· Issues arising from the performance monitoring processes will be addressed immediately by the COR to the contractor’s COR.
The QAR must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the KO.
ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY
| PWS Paragraph |
| Task |
| Performance Standard |
| Acceptable Quality Levels (AQL) |
| Surveillance Method / By Whom |
Step 1:
Determine the important task of the contract to be monitored over the course of the performance period, ensure this task is captured in the PWS and reference the specific subparagraph in the PWS where the task can be found.
| Step 2: State the specific task to be monitored, as stated in the PWS. |
| Step 3: Determine the performance standard for the task (NOTE: Be careful setting the standard of 100% or zero defects. This requires the Government to do 100% inspection as a surveillance method which is administratively burdensome and often unnecessary. This standard should only be used for areas related to security, safety/life support, force protection or other critical issues.) |
| Step 4: Determine the AQL (or defect rate) for each task to be monitored |
| Step 5: Determine how this task will be monitored and by whom. (NOTE: The individual monitoring contractor performance should always be the COR unless there is sufficient rationale why it should be the KO.) |
| 5.1.1 |
| Micro-Film Digitization; Digitize Micro-Film into PDF format |
| 100% |
| 100% Clarity must be comparable to original documents |
| Random Files will be selected by COR prior to transfer to monitor for completeness and clarity |
| 5.1.2 |
| Micro-Film File consolidation; Combine all files of any given soldier into one retrievable file |
| 100% |
| 100% |
No soldiers should have multiple files either unique or duplicated COR will review and verify files are created to specified requirements
| 5.1.3 |
| Micro-Film Indexing; Index PDF Files created from Micro-Film using the following fields, full SSN or service #, last name, first name, middle initial, Date of Birth, Date of Discharge |
| 100% |
| 100% |
All files should have accurately indexed fields as indicated COR will review and verify files are created to specified requirements
| 5.1.8 |
| Paper Records preparation Prepare paper records for digitization to include removal of staples, binder clips, paper clips and/or removal of documents from records jackets with 2 hole prong clips |
| 100% |
| 100% of paper based records must be prepared for scanning |
Random Files will be selected by COR prior to transfer to monitor for completeness
| 5.1.9 |
| Paper Records Scanning/digitization; Digitize each piece of paper in every file to include single sided and duplex pages, multi part fan fold pages, “onion-skin”, non-standard pages, 3x5 cards, notes and any other additional paper based information contained in each file. |
| 100% |
| 100% |
Clarity must be comparable to original documents.
Random Files will be selected by COR prior to transfer to monitor for completeness and clarity
| 5.1.10 |
| Paper Records Indexing; Index each PDF file created from paper records into a single file using the following index fields, full SSN or service #, last name, first name, middle initial, date of birth, date of discharge |
| 100% |
| 100% |
No soldiers should have multiple files either unique or duplicated.
All files should have accurately indexed fields as indicated COR will review and verify files are created to specified requirements
ATTACHMENT 2: SAMPLE QUALITY ASSURANCE
MONITORING FORM
SERVICE or STANDARD:
SURVEY PERIOD:
SURVEILLANCE METHOD (Check):
X Random Sampling 100% Inspection X Periodic Inspection Customer Complaint LEVEL OF SURVEILLANCE (Check):
| X Monthly | Quarterly | X | As needed | |
| PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: | ______ % |
ANALYSIS OF RESULTS:
Observed Service Provider Performance Measurement Rate: ______%
| Service Provider’s Performance (Check): | Meets Standards |
| Does Not Meet Standards |
Narrative of Performance During Survey Period:
PREPARED BY: ___________________________________ DATE: _________________