About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to provide skilled professional support for the conversion of 73 Air Force air traffic control towers from analog to digital video display signaling for the Standard Terminal Automation Replacement Systems (STARS).
The SOW outlines the scope of work, which includes providing and installing fiber optic cables, reconfiguring equipment racks, testing audio/video/serial connectivity, and coordinating with the government. Two professionals will be required per site, with some sites having one government and one contractor employee. The work must be completed within an aggressive two-year schedule across 62 CONUS and 11 OCONUS locations. The contractor will be required to provide daily status reports and comply with various security requirements, including access to government facilities and information systems. The contract is anticipated to be a single firm-fixed-price award, with the possibility of other CLIN types as needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought for Digital Video.pdf | ||
| Digital Video Locations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Digital Video
STATEMENT OF WORK
Background There are potentially seventy-three Air Force; Air Traffic Control Towers operating Standard Terminal Automation Replacement Systems (STARS) will be converted from analog to digital video display signaling. Eleven facilities will be OCONUS and 62 will be Conus. Will need skilled professionals that has worked in Air Traffic Control Environment. The personnel will be required to relocate/install electronic equipment, provide/install fiber from equipment room to the cab, install GFE cables/equipment in the cab, and assist in video testing new fiber and equipment.
Challenge will be to meet aggressive schedule in two years. Two professionals per site will be needed; some sites will have one government and one contractor. At the first site, the government will train personnel on what is expected, and the contractor will be expected to train their remaining personnel.
• Background materials:
• OM3 Plenum Aqua 6 Strand Tight-Buffered Distribution Indoor Fiber Armor w/2ft
2.0mm Breakout Each End Staggered in a 3/4" Pull eye Both Ends Corning 006T88- 31190-D3 or equivalent o The fiber has nonmetallic armor; there is a minimum buy of 15,000’. The Dielectric armor cable 6 EA fiber will need to be terminate with ST on one end and the other 4EA LC fiber connectors and 2 EA ST connectors. On Each end will require a pulling eye. Labeled fiber appropriately to avoid confusion.
Federal Networks or equivalents would be able to terminate, but their order will need to be equivalent to 15,000’ or the remainder fiber will need to be purchased.
• Or the contractor can purchase the 15000’ of fiber and have a professional termination of the fiber as described above.
o Federal Networks or equivalents would need a monthly storage fee if the fiber spool were provided to them and terminated on an as needed basis.
Another option: The above fiber can be provided as GFE, and the contractor can have it terminated and/or stored by a fiber professional.
o Each fiber purchased will need to be at least 150’: Length will be provided.
• If the above fiber can’t be purchased then OM3 Plenum Aqua 6 Strand Tight-Buffered Distribution Indoor Fiber Armor w/2ft 2.0mm Breakout Each End Staggered in a 3/4" Pull eye fiber with 6 EA ST fiber connectors on one end and 4 EA LC fiber connector and 2 EA ST fiber connectors on the other end. Labeled fibers appropriately to avoid confusion. Plus, 2 EA LC to LC couplers and 3’ 2 EA LC fiber connector to 2 EA ST fiber connector fiber pigtail will be needed.
• The contractor will provide hand tools, to include fish tape.
• The contractor will provide tie wraps and electrical tape, rack clip nuts.
• The contractor will provide Mule tape, flat pull tape, or equivalent.
• The contractor will provide LC, SC, & ST fiber power meters, to test fiber once installed.
Scope Scope of the contract: Provide skilled professional support for STARS digital video upgrade.
Fiber optic cable will need to be provided/installed at each site. The professional must coordinate with Volpe and site POC and 3 weeks prior to travel and prior work start onsite, and the Volpe government rep is CC on any correspondence. See if the POC can provide pictures of the fiber transceiver and the video splitter in the cab. It will assist in determining what fiber connectors are needed for the spare fiber if the second option of fiber is being provided. Each site will need two personnel, two days onsite and two days travel for conus, three to four additional days for combined sites. Provide a Daily status report.
Tasks
Each of the below tasks must be accomplished prior to leaving each site
3.1.1 Task 1 – Reconfigure the STARS LT1/RT1 rack
• Assist site in powering down the L1/RT1 rack
• Relocate the existing CPU and MSA and associated cabling up the existing rack in spare space location, and place the new CPU and MSA (Monitor Switch Assembly) in its exact location of legacy equipment that was just relocated.
o Install the associated cabling to the new CPU and MSA and install new fiber modules in existing Emcore chassis and associated fibers All cabling and new equipment will be GFE MSA DEC faceplate will be re-utilized.
• Procedure will be provided once there is a signed NDA.
3.1.2 Task 2 – Provide/Install fiber optic cable
• Provide/Install fiber optic cable to connect STARS LT1/RT1 to audio, video, and serial devices.
o If the Dielectric armor cable is able to be provided then it can be installed without innerduct.
o If the Dielectric armor cable is not feasible, then 6 fiber cable will need to be provided The existing fiber will need to be pulled out of innerduct, and a pull string installed Then the new 6 fiber and the existing fiber will need to be installed in the innerduct via the pull string.
The existing fiber will need to be reconnected and tested that it still operates.
• To mitigate risk the 3 spare fibers in the new cable will be utilized if the existing fiber has been damaged during the new fiber install.
o The 2 EA LC to LC couplers and the 3’ 2 EA LC to ST pigtail will need to be utilized in the cab.
• Install GFE new video splitter adjacent to existing video splitter in the cab under the console.
o Install GFE fiber from video splitter to Each Tower Display monitor
Provide/install small amount of 1” plenum innerduct for the TDM fiber install o Install GFE fiber from video splitter to Supplemental Display Monitor Provide/install small amount of 1” plenum innerduct for the SDM fiber install
• Install GFE Emcore fiber Transceiver and modules adjacent to existing fiber transceivers in the cab under the console.
o Install GFE cable from new Emcore fiber module to two EA Keyboard and trackball.
o Install GFE cable from new Emcore Fiber module to speaker
3.1.3 Task 3 - Test audio, video, and serial (keyboard) connectivity
• Test audio, video, and serial (keyboard) connectivity via the newly installed fiber
• Utilize existing Maintenance Laptop with assistance of site personnel.
• Procedure will be provide once there is a signed NDA.
Delivery
• Provide Daily status report
• Provide pictures of installation
Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, GFI)
Volpe Center does not anticipate providing any Government-Furnished Property (GFP) at this time at the master contract level.
Security
Security is a factor in this procurement when it comes to access to Government facilities, infrastructure, and computers. The security office will review this action and maintain involvement with the contract, surveillance, vetting and review. The contractor may be required to
1) Access and handle sensitive but unclassified information (SUI)
2) Sign a non-disclosure agreement (NDA) and/or organizational conflict of interest (OCI)
3) Be granted routine access to government (JBCC or another field test site)
4) Be granted routine access to DOT information technology (IT) infrastructure and systems.
5) Be granted a DoD-issued CAC or base pass for Air Force bases access
The solicitation will also incorporate Transportation Acquisition Regulation (TAR) Clause 1252.237-70 Qualification of Contractor Employees (APR 2005); and Volpe Center's special provisions "Security Measures on the Volpe Center Premises (APR 2005)", “U.S. DOT Information Security Requirements (APR 2003)", “Handling of Data (May 2007)”, and “U.S.DOT Contractor Personnel Security and Agency Access (Nov 2011)” or similar provisions, as applicable or necessary.
Lastly, no Federal contract information will reside in or transit through contractor information systems.
Travel The three tasks described above shall occur at specific locations to be determined but within the following parameters potential:
• Sixty-two (62) CONUS bases
• Eleven (11) OCONUS bases
Special Material Requirements and Considerations
The contractor will need to provide hand tools, including but not limited to, fish tape.
Place of Performance
The three tasks described above shall occur at specific locations to be determined but within the following parameters potential:
• Sixty-two (62) CONUS bases
• Eleven (11) OCONUS bases
Attachment “Digital Video Locations”: Includes potential locations.
Period of Performance
The period of performance for this work is from the date this contract is awarded through September 2026.