This document is a Construction Cost Budget for the Frasers Seniors Activities Center RTU (Rooftop Unit) Replacement project, located in Fraser, Michigan, prepared by AEW, Inc. with a project number of 0190-0519, dated 10/07/24. The project involves replacing two rooftop units and associated electrical and fire alarm system work, with specific line items including RTU Replacement 1 at $35,000 and RTU Replacement 2 at $45,000, along with electrical rework at $15,000 and a fire alarm system upgrade at $5,000.

The total construction cost is budgeted at $155,000, which includes base construction costs of $100,000, a 20% construction contingency of $20,000, general conditions at 10% ($10,000), insurance and bonding at 5% ($5,000), and overhead and profit at 20% ($20,000). No specific funding sources or set-asides are noted in the document. The budget covers HVAC, electrical, and fire alarm system components for the seniors activities center, with no additional details provided about the specific mechanical or technological requirements of the rooftop unit replacements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spreadsheet 4-A

Construction Cost Budget Project: Frasers Seniors Activities Center

RTU Replacement

Location: Fraser, MI

Design Professional: AEW, Inc.

Building Area: N/A

Date: 10/07/24

AEW Project Number: 0190-0519

Division Item Quantity Unit Unit Cost Cost Notes

Div 2 Demolition

0 sf $0.00 $0.00

Division 2 Subtotal $0.00

Div 4 Masonry

0 sf $0.00 $0.00

Division 4 Subtotal $0.00

Div 8 Openings

0 ea $0.00 $0.00

Division 8 Subtotal $0.00

Div 9 Finishes

0 sf $0.00 $0.00

Division 9 Subtotal $0.00

Div 10 Specialties

0 ea $0.00 $0.00

Division 10 Subtotal $0.00

Div 12 Furnishings

0 lf $0.00 $0.00

Division 12 Subtotal $0.00

Div 21 Fire Suppression

0 sf $0.00 $0.00

Division 21 Subtotal $0.00

Div 23 HVAC

RTU Replacement 1 1 ea $35,000.00 $35,000.00

RTU Replacement 2 1 ea $45,000.00 $45,000.00

Division 23 Subtotal $80,000.00

Div 26 Electrical

Rework Electrical 2 ea $7,500.00 $15,000.00

Division 26 Subtotal $15,000.00

Div 28 Fire Alarm

Fire alarm system 1 ea $5,000.00 $5,000.00

Division 28 Subtotal $5,000.00

Base Construction Costs $100,000.00

20% Construction Contingency $20,000.00

General Conditions (10%) $10,000.00

Insurance & Bonding (5%) $5,000.00

Overhead & Profit (20%) $20,000.00

Utility Allowance

Permit Allowance

Total Construction Cost $155,000.00