This is a Design Build Contract bidding and contract document issued by the State of Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, on behalf of the Department of Corrections for the Chippewa Correctional Facility. The project involves the design and replacement of an existing steam surge tank located in the powerplant at Chippewa Correctional Facility, 4269 M-80, Kincheloe, MI 49788. The scope includes removal of the existing surge tank and associated piping and equipment, with installation of a new steam purge tank, piping, valves, and controls to be integrated with the existing DA tank for system redundancy. The purge tank and control system shall be Cleaver Brooks brand. Construction activities requiring boiler or steam system shutdown cannot occur during the heating season. A mandatory pre-bid conference and facility tour are scheduled for July 31, 2025, at 1:00 PM ET at the powerplant, with attendance required for all prospective bidders. Electronic bids must be submitted through the SIGMA website by 2:00 PM ET on August 20, 2025. The contract completion date is June 1, 2026, with a final completion date of July 1, 2026, and liquidated damages of $500 per calendar day for delays beyond substantial completion.

The base bid must be structured as a not-to-exceed bid broken down into compensation categories including design services, construction and trade labor, general conditions, overhead and profit, and management services. A five percent bid guarantee is required, with performance and payment bonds mandated for all bids exceeding $50,000. The project includes a $25,000 provisional allowance within the Construction, Trade Labor, and Subcontractors line item. Prevailing wage rates apply to all construction mechanics on the project, with comprehensive wage schedules provided for various classifications. The State reserves the right to reject any or all bids, waive irregularities, or re-bid the work. Bidders must comply with Michigan Qualified Disabled Veteran (QDV) business requirements, provide Michigan business certifications for contracts over $250,000, and complete asbestos abatement attestations as applicable. The project is subject to Department of Corrections special working conditions, including security clearance requirements, restricted access protocols, tool control restrictions, and environmental compliance requirements. Funding source and total project budget are not specified in the available documentation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No. 472/25324.ABG

State of Michigan Department of Technology, Management and Budget

State Facilities Administration

DESIGN BUILD CONTRACT

Bidding and Contract Document Minor Projects

File No.: 472/25324.ABG Department of Corrections

Powerplant Steam Surge Tank Replacement Chippewa Correctional Facility

Bid Date: August 20, 2025, 2:00 p.m. ET

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[i]

Table of Contents

DESIGN BUILD BID SUMMARY

BID SCHEDULE

QUALIFIED DISABLED VETERAN (QDV) BUSINESS REPRESENTATION

CERTIFICATION OF A MICHIGAN BASED BUSINESS

ASBESTOS ABATEMENT ATTESTATION................................................................................. Error! Bookmark not defined.

BID BOND

BID SUBMITTALS

PERFORMANCE BOND

PAYMENT BOND

SECTION ONE – PRE-BID INFORMATION

SECTION THREE – SUPPLEMENTARY INSTRUCTIONS

SECTION FOUR – INFORMATION FOR BIDDERS

SECTION FIVE – GENERAL PROVISIONS

SECTION SIX – RIGHTS AND RESPONSIBILITIES

SECTION EIGHT – SPECIAL WORKING CONDITIONS

SECTION NINE - SUPPLEMENTARY CONDITIONS

APPENDIX I – GLOSSARY

APPENDIX II – SPECIAL WORKING CONDITIONS

DEPARTMENT OF HEALTH AND HUMAN SERVICES (Community Health Facilities) ........... Error! Bookmark not defined.

DEPARTMENT OF HEALTH AND HUMAN SERVICES.............................................................. Error! Bookmark not defined.

DEPARTMENT OF NATURAL RESOURCES ............................................................................. Error! Bookmark not defined.

APPENDIX III – SPECIAL PROJECT PROCEDURES

DEMOLITION/REMODELING PROJECT PROCEDURES

HAZARDOUS MATERIALS PROJECT PROCEDURES

APPENDIX IV – PROJECT SIGNAGE

APPENDIX V

FEDERAL PROVISIONS ADDENDUM ............................................................................... Error! Bookmark not defined.

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[1]

DESIGN BUILD BID SUMMARY

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

DESIGN AND CONSTRUCTION DIVISION

3111 W. St. Joseph Street Lansing, Michigan 48917

Bids must be submitted electronically through the SIGMA website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

FILE NUMBER

472/25324.ABG

DEPARTMENT/AGENCY

Department of Corrections

LOCATION

Chippewa Correctional Facility

CONTRACT COMPLETION DATE

June 1, 2026

PROJECT NAME/PROJECT SCOPE

Powerplant Steam Surge Tank Replacement

BID OPENING DATE

August 20, 2025, 2:00 p.m. ET

FOR AN EXAMINATION OF THE SITE CONTACT

Alan Goschka – goschkaa@michigan.gov

BY SIGNING AND SUBMITTING THE BID SUMMARY, THE BIDDER CERTIFIES THEY COMPLY

WITH ALL PROVISIONS OF THE CONTRACT SOLICITATION.

WE PROPOSE TO FURNISH, PERFORM, AND COMPLETE THE ENTIRE WORK IN

ACCORDANCE WITH THE CONTRACT DOCUMENTS IN CONSIDERATION FO THE BID

PRICE(S) STATED BELOW.

FIRM NAME AND COMPLETE ADDRESS

☐ Qualified Disabled Veteran

TELEPHONE NUMBER

EMAIL ADDRESS

SIGMA VENDOR NUMBER

BIDDER’S SIGNATURE AND TITLE DATE WITNESS’ SIGNATURE DATE

By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan Based Business Certification

BASE BID FROM BID SCHEDULE (Include Specified Allowances):

Dollars $ (use words) (in figures)

Alternate 1: (add / subtract) Dollars $ (use words) (in figures)

Alternate 2: (add / subtract) Dollars $ (use words) (in figures) https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService mailto:goschkaa@michigan.gov

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[2]

A PERFORMANCE BOND AND A PAYMENT BOND ARE REQUIRED FOR ALL BIDS OVER

$50,000.00. EACH BID MUST BE ACCOMPANIED BY A FIVE (5) PERCENT BID GUARANTEE.

BUILDERS RISK INSURANCE IS REQUIRED TO BE PROVIDED BY THE CONTRACTOR UNLESS

OTHERWISE INDICATED IN THE BID DOCUMENTS.

BIDDERS ARE ALSO CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL CONDITIONS OF

THE CONTRACT.

Project Scope of Work (Also see the Design Build Project Advertisement):

The Department of Technology, Management and Budget (DTMB) on behalf of the Department of Corrections is requesting a Design Build Entity for the development of design documents and replacement of the existing steam surge tank located in the powerplant.

The Bidder shall figure its Base Bid on the specified or Addendum-approved materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.

Addenda: Bidder acknowledges receipt of Addenda:

No. dated:

FIRM NAME TELEPHONE NUMBER AND EMAIL ADDRESS

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[3]

BID SCHEDULE

Not-To-Exceed Base Bid Schedule – The Not-to-Exceed Bid shall be broken down into compensation categories as shown below. The Not-To-Exceed Bid will be compensated according to actual costs per Section 6, Paragraphs 8.1 to 8.15

1. Design Services $

2. Construction, Trade Labor, and Subcontractors $

3. General Conditions $

SUBTOTAL $

4. Overhead and Profit (Percentage of Sub-Total Above) % $

5. Management $

TOTAL NOT TO EXCEED BID $

Allowances:

(a) Bidders must include in their Base Proposal Sum Construction, Trade Labor, and Subcontractors line a Provisional Allowance of $25,000.00

Not-to-Exceed Base Bid (Sum of Item Bid Prices for all Not-To-Exceed Bid Items):

Dollars and No/Costs (use words)

(in figures)

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[4]

If requested below, Bidder shall provide unit prices.

Item No. Bid Quantity

Description Unit Price

Item Bid Price

N/A

Schedule of Alternates – The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices

Alternate Item No.

Bid Quantity

Description Unit Price

Item Bid Price

N/A

The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[5]

QUALIFIED DISABLED VETERAN (QDV) BUSINESS REPRESENTATION

‘Qualified Disabled Veteran,’ means a business entity that is 51% or more owned by one or more veterans with a service-connected disability.

‘Qualified Disabled,’ means a business entity that is 51% or more owned by one or more with a service-connected disability.

The vendor represents that it IS , a qualified disabled veteran.

The contractor represents and warrants that the company meets the above (when checked) and has attached supporting documentation per the following:

Each bid requesting the Qualified Disabled Veterans (QDV) preference, in accordance with Public Act 22 of 2010, MCL 18.1241.3 shall include,

1. DD214 Proof of Service and Discharge,

2. Veterans Administration rating decision letter, proof of disability (if the disability is not indicated on the DD214), and

3. appropriate legal documents setting forth the 51% natural persons QDV ownership.

Fraudulent Certification as a Qualified Disabled Veteran may result in debarment under MCL 18.264.

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[6]

CERTIFICATION OF A MICHIGAN BASED BUSINESS

(Information Required Prior to Contract Award for Application of State Reciprocity Provisions)

To qualify as a Michigan Based Business:

Vendor shall have, during the 12 months immediately preceding this bid deadline:

or

If the business is newly established, for the period the business has been in existence, it has:

(check all that apply):

☐ Filed a Michigan single business tax return showing a portion or all of the income tax base allocated or apportioned to the State of Michigan pursuant to the Michigan Single Business Tax Act, 1975 PA 228, MCL 208.1 – 208.145.

☐ Filed a Michigan income tax return showing income generated in or attributed to the State of Michigan.

☐ Withheld Michigan income tax from compensation paid to the bidder’s owners and remitted the tax to the Department of Treasury.

I certify that I have personal knowledge of such filing or withholding, that it was more than a nominal filing for the purpose of gaining the status of a Michigan business, and that it indicates a significant business presence in the state, considering the size of the business and the nature of its activities.

I authorize the Michigan Department of Treasury to verify that the business has or has not met the criteria for a Michigan business indicated above and to disclose the verifying information to the procuring agency.

Bidder shall also indicate one of the following:

☐ Bidder qualifies as a Michigan business (provide zip code: )

☐ Bidder does not qualify as a Michigan business (provide name of State: )

☐ The principal place of business is outside the State of Michigan, however service/commodity provided by a location within the State of Michigan (provide zip code

Fraudulent Certification as a Michigan business is prohibited by MCL 18.1268 § 268. A

BUSINESS THAT PURPOSELY OR WILLFULLY SUBMITS A FALSE CERTIFICATION THAT IT IS

A MICHIGAN BUSINESS OR FALSELY INDICATES THE STATE IN WHICH IT HAS ITS PRINCIPAL

PLACE OF BUSINESS IS GUILTY OF A FELONY, PUNISHABLE BY A FINE OF NOT LESS THAN

$25,000 and subject to debarment under MCL 18.1264

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[7]

ASBESTOS ABATEMENT ATTESTATION

SUBMISSION REQUIRED WITH ALL BIDS

Pursuant to the Public Entity Asbestos Removal Verification Act, PA 59 of 2024, MCL 338.3371 et seq. (“the Act”), the Owner will conduct the background investigation as required of any asbestos abatement contractor, or a general contractor that contracts with an asbestos abatement contractor, for the abatement of asbestos. Under the Act, an "Asbestos abatement contractor" means a business entity that is licensed under the asbestos abatement contractors licensing act, 1986 PA 135, MCL 338.3101 to 338.3319, and that carries on the business of asbestos abatement on the premises of another business entity and not on the asbestos abatement contractor's premises. Asbestos abatement contractor includes an individual or person with an ownership interest in a business entity described in MCL 338.3373(b).

(INSTRUCTIONS: Project Director selects one of these two statements, then delete the not selected statement and instructions.)

☐ THE SCOPE OF WORK TO BE COVERED UNDER THIS CONTRACT CONTAINS ASBESTOS

ABATEMENT AND THIS ATTESTATION MUST BE COMPLETED.

☒ THE SCOPE OF WORK TO BE COVERED UNDER THIS CONTRACT DOES NOT CONTAINS

ASBESTOS ABATEMENT AND THIS ATTESTATION IS TO BE LEFT BANK.

DB Entity attests that: (check one:)

1. ☐ The DB Entity will self-perform all asbestos abatement project work and attests that DB Entity has not been issued 5 or more notices of violation of environmental regulations (State and/or Federal), nor has it been subject to an administrative consent order or a consent judgment involving environmental regulations.

2. ☐ The DB Entity will self-perform all asbestos abatement project work; however, DB Entity has been issued 5 or more notices of violation of environmental regulations (State and/or Federal), or has been subject to an administrative consent order or a consent judgment involving environmental regulations, requiring Owner to conduct a background investigation and a public hearing pursuant to PA 59 of 2024, MCL 338.3371 et seq.

3. ☐ The DB Entity nominates the following Sub-contractor for all asbestos abatement project work and attests that the nominated Sub-contractor has not been issued 5 or more notices of violation of environmental regulations (State and/or Federal), nor has it been subject to an administrative consent order or a consent judgment involving environmental regulations:

Nominated Sub-contractor:

4. ☐ The DB Entity nominates the following Sub-contractor for all asbestos abatement project work; however, the nominated Sub-contractor has been issued 5 or more notices of violation of environmental regulations (State and/or Federal), or has been subject to an administrative consent order or a consent judgment involving environmental regulations, requiring Owner to conduct a background investigation and a public hearing pursuant to PA 59 of 2024, MCL

338.3371 et seq.

Nominated Sub-contractor:

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[8]

BID BOND

BID SUBMITTED ON the day of , 20 .

Bid Security is attached and in the form of: ☐ Bid Bond – Bid Bond form has been duly executed; or

☐ Bank Certified; or

☐ Cashier’s Check or Money Order (Check or Money Order must be delivered to issuing office prior to Bid Closing Time in addition to normal SIGMA submittals.)

If the Bidder is an Individual:

Name of Individual:

Name and Title of Person Authorized to sign:

Signature:

(If not the Individual, attach Power of Attorney) Date

Doing Business As:

Business Address:

County of Registration:

Telephone: Fax:

If the Bidder is a Partnership:

By:

(True Name of Partnership)

Partner authorized to sign:

(Attach evidence of Authority to sign) Date

Business Address:

County of Registration:

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[9]

If the Bidder is a Corporation:

By:

(Legal Corporation Name)

Name and Title of Authorized Officer:

(Attach evidence of Authority to sign) Date

Name and Title of Officer Attesting:

Business Address:

Date

State of Incorporation:

If The Bidder is A Joint Venture: JOINT VENTURE SIGNATURES SHALL BE AS PROVIDED IN

INSTRUCTIONS TO BIDDERS. EACH JOINT VENTURER SIGNING THE BID SHALL SIGN IN THE

MANNER INDICATED FOR AN INDIVIDUAL, A PARTNERSHIP, OR A CORPORATION. IF MORE

THAN TWO JOINT VENTURERS OF THE SAME TYPE ARE INCLUDED, USE ADDITIONAL PAGES.

JOINT VENTURE STATE OF INCORPORATION OR COUNTY OF

REGISTRATION .

BID SUBMITTALS

See the attached Project Description, which includes the scope of work, and the Owner’s requirements for schedule, quality, budget, and other needs.

Bid submittals are required to be provided at the time of Bid, in the format outlined below:

1. Business Organization, Team Composition, and Experience:

Provide the full names and addresses of the DB Entity, the DB Entity’s Architect/Engineer, and any other team member firms that will provide design or construction services. List a minimum of three similar projects successfully completed by the DB Entity, with reference contact information.

2. Understanding of the Project Scope of Work and Requirements:

Concisely describe your understanding of the project scope of work and your understanding of the schedule, quality, budget, and other requirements. Describe your proposed solution to the project scope of work.

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[10]

3. Work Plan and Schedule:

Concisely describe your plan for successful completion of the project and how you will meet the schedule, quality, budget, and other requirements. Provide your preliminary schedule with major milestones.

4. Key Personnel:

Identify the DB Entity’s Project Manager, Superintendent, and Architect/Engineer, with resumes.

5. Design Build (BD) Entity Hourly Billing Rate Schedule:

Attach a list of the hourly billing rates for the DB Entity’s staff, by job title and individual. These rates will form the basis for invoicing self-performed design services, general conditions, and management against the Not-To-Exceed Bid categories.

6. Additional Information:

Include any additional information you believe to be pertinent to the project problem but not specifically requested elsewhere in the Bidding Documents.

LIST OF SIMILAR PROJECTS COMPLETED BY THE BIDDER

Please list at least three (3) completed projects of similar size and complexity to the project being bid, with reference contact information.

REFERENCE #

Owner:

Project/Contract Name:

Location of Project/Contract:

Contract Price: Project/Contract Started:

Completed:

Owner's Representative (Name and Telephone):

Scope of Project/Contract:

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[11]

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[12]

PERFORMANCE BOND

SURETY COMPANY REFERENCE NO.

That "the DB Entity," , a corporation ☐, individual ☐, partnership ☐, joint venture ☐ of the State of , qualified to do business in the State of Michigan, as Principal, and "the Surety," , of the State of , as surety, are held and bound unto the State of Michigan, "the Owner," as Obligee, in the amount of Dollars ($ ), for the payment of which the DB Entity and Surety bind themselves, their respective heirs, successors, legal representatives and assigns, jointly and severally, in compliance with 1963 PA 213, as amended, MCL 129.201 et seq.

The DB Entity has entered into "the Contract" with the Owner for , "the Work," covered by the Contract Documents, which are incorporated into this Performance Bond by this reference.

If the DB Entity faithfully performs and fulfills all the undertakings, covenants, terms, conditions, warranties, indemnifications and agreements of the Contract Documents within the Contract Time (including any authorized changes, with or without notice to the Surety) and during the Correction Period, and if the DB Entity also performs and fulfills all the undertakings, covenants, terms, conditions, warranties, indemnifications and agreements of any and all duly authorized modifications of the Contract Documents, then THIS OBLIGATION IS VOID, OTHERWISE TO REMAIN IN FULL FORCE AND

EFFECT.

A. No change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion, or other revision) releases the Surety of its obligations under this Performance Bond. The Surety expressly waives notice of any such change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion, or other revision).

B. This Performance Bond shall be solely for the protection of the Owner and its successors, legal representatives, or assigns.

C. It is the intention of the DB Entity and Surety that they shall be bound by all terms and conditions of the Contract Documents (including but not limited to General Conditions and this Performance Bond). However, this Performance Bond is executed pursuant to 1963 PA 213, as amended, MCL 129.201 et seq., and if any provision(s) of this Performance Bond is/are illegal, invalid, or unenforceable, all other provisions of this Performance Bond shall nevertheless remain in full force and effect, and the Owner shall be protected to the full extent provided by 1963 PA 213, as amended, MCL

129.201 et seq.

IMPORTANT: The Surety shall be authorized to do business in the State of Michigan by the

Department of Licensing and Regulatory Affairs − Insurance Bureau, shall be listed on the current U.S.

Department of the Treasury Circular 570, and, unless otherwise authorized by the Owner in writing, shall have at least an A− Best's rating and a Class VII or better financial size category per current A. M.

Best Company ratings.

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[13]

Name, Address, and Telephone of the Surety Name and Telephone of Agent, who is either resident of, or whose principal office is maintained in the State of Michigan

Signed and sealed this day of , 20 .

THE DB ENTITY: (Print Full Name and Sign) By:

WITNESS Name & Title:

Telephone No.:

THE SURETY: (Print Full Name and Sign) Agent:

WITNESS Attorney-in-Fact:

Email:

Bidding and Contract Document (R 03/25) Project Name: Chippewa CF - Steam Surge Tank Replacement File No.: 472/25324.ABG

[14]

PAYMENT BOND

SURETY COMPANY REFERENCE NO.

"the DB Entity," , a corporation , individual , partnership , joint venture of the State of , qualified to do business in the State of Michigan, as Principal, and "the Surety," , of the State of , as surety, are held and bound unto the State of Michigan, "the Owner," as Obligee, in the amount of Dollars ($ ), for the payment of which the DB Entity and Surety bind themselves, their respective heirs, successors, legal representatives and assigns, jointly and severally, in compliance with 1963 PA 213, as amended, MCL 129.201 et seq.

The DB Entity has entered into "the Contract" with the Owner for , "the Work," covered by the Contract Documents, which are incorporated into this Payment Bond by this reference.

If the DB Entity promptly pays all claimants supplying labor or materials to the DB Entity or to the DB Entity’s subcontractors in the prosecution of the Work, then THIS OBLIGATION IS VOID, OTHERWISE TO REMAIN IN FULL FORCE AND

EFFECT.

A. All rights and remedies on this Payment Bond are solely for the protection of all claimants supplying labor and materials to the DB Entity or the DB Entity’s subcontractors in the prosecution of the Work and shall be determined in accordance with Michigan Law.

B. No change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion, or other revision) shall release the Surety of its obligations under this Payment Bond. The Surety hereby expressly waives notice of any such change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion, or other revision).

C. It is the intention of the DB Entity and Surety that they shall be bound by all terms and conditions of the Contract Documents (including, but not limited to this Payment Bond). However, this Payment Bond is executed pursuant to 1963 PA 213, as amended, MCL 129.201 et seq., and if any provision(s) of this Payment Bond is/are illegal, invalid, or unenforceable, all other provisions of this Payment Bond shall nevertheless remain in full force and effect, and the Owner shall be protected to the full extent provided by 1963 PA 213, as amended, MCL

129.201 et seq.

Bidding and Contract Document (R 03/25) Project Name: File No.:

[15]

IMPORTANT: The Surety shall be authorized to do business in the State of Michigan by the Department of Licensing and Regulatory Affairs - Insurance Bureau, shall be listed on the current U.S.

Department of the Treasury Circular 570, and, unless otherwise authorized by the Owner in writing, shall have at least an A- Best's rating and a Class VII or better financial size category per current A.

M. Best Company ratings.

Name, Address, and Telephone of the Surety Name and Telephone of Agent, who is either resident of, or whose principal office is maintained in the State of Michigan

Signed and sealed this day of , 20 .

THE DB ENTITY: (Print Full Name and Sign) By:

WITNESS Name & Title:

THE SURETY: (Print Full Name and Sign) Agent:

WITNESS Attorney-in-Fact:

Email:

[16]

SECTION ONE – PRE-BID INFORMATION

1. INVITATION TO BID (ITB): Your firm is invited to submit a Bid. See the attached Project Description, which includes the scope of work, any other documents provided, and the Owner’s requirements for schedule, quality, cost, and other needs.

The State of Michigan as the Owner will receive bids electronically through the SIGMA website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService, for the Chippewa Correctional Facility, Powerplant Steam Purge Tank Replacement until 2:00 p.m., ET, on August 20, 2025.

The State reserves the right to cancel this Invitation to Bid (ITB) or change the date and time for submitting Bids by announcing same at any time before the established date and time for Bid opening. Bids must remain open for acceptance by the Owner for no less than the Bid hold period.

DB Entity may agree to extend the Bid hold period. However, any such extension shall be based upon no increase in the Bid Price and/or Contract Time.

2. WORK DESCRIPTION: The Work (Project Title), Chippewa Correctional Facility, Powerplant

Steam Purge Tank Replacement DTMB File No. 472/25324.ABG includes, but is not necessarily limited to: (see attached Project Description Form)

Requesting a Design Build entity for the development of design documents and replacement of the existing steam surge tank located in the powerplant at Chippewa Correctional Facility.

The project is to include the removal of the existing surge tank and associated piping and equipment (will require design and details to remove the existing steam tank (the existing skid should be able to remain) – removal will likely have to go through the existing insulated metal panel wall system) and the installation of a new steam purge tank, piping, valves and controls that is to be tied together with the existing DA tank for system redundancy. There is a high-pressure drip line that is currently tied into a low-pressure line that will need to be reworked and tied into the existing DA tank. The purge tank and associated control system shall be Cleaver Brooks.

Construction activities that require the boiler/steam system to be shut down cannot occur anytime during the heating season.

The site is located at the Chippewa Correctional Facility, 4269 M-80, Kincheloe, MI 49788.

3. PRE-BID CONFERENCE: A mandatory pre-bid conference will be held at Chippewa Correctional

Facility Powerplant, 4269 M-80, Kincheloe, MI 49788., on July 31, 20 25, at 1:00pm ET. A mandatory tour will be held on the same day, starting at 1:30pm ET. All prospective Bidders are required to attend the tour, if held. Other parties interested in the Work are encouraged to attend the tour. Addenda may be issued, in response to issues raised at the pre-bid conference and tour, or as the Owner may otherwise consider necessary.

FOR CORRECTIONAL FACILITIES ONLY: All contractor/vendor representatives attending a Pre-Bid Walk Through Meeting must submit a Vender/Contractor LEIN Request five business days prior to the meeting date, (LEIN Request For CAJ-1037 attached to Bid posting). Send the LEIN Request form, filled out and signed, by email to SmithD76@michigan.gov & FrostS1@michigan.gov . The email “Subject” must include (Facility Name, Project Name, Date & Time of Pre-Bid Walk Through Meeting).

https://sam.gov/content/entity-registration mailto:SmithD76@michigan.gov mailto:FrostS1@michigan.gov

[17]

4. SIGMA VENDOR NUMBER: If you are bidding a State job for the first time, visit the State of Michigan SIGMA website, https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService, and follow the “SOM VSS User Guide for New Vendors” instructions, located under Forms and Reference Documents. Registration is required for bid submission. Do not wait until the last minute to submit a proposal, as the SIGMA system requires the creation of an account and entry of certain information, in addition to uploading and submitting the materials. The SIGMA system will not allow a proposal to be submitted after the proposal deadline, even if a portion of the proposal has been updated.

Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 373-4111 or (888) 734-9749.

5. EQUAL EMPLOYMENT OPPORTUNITY: Covenants to not discriminate in employment by

Design-Build Entities, Subcontractors, and Suppliers required by Law are contained in this Contract and are applicable to the Work and any Sub-agreement under the Contract.

6. CONTRACT TIMES: The Contract Times and the associated liquidated damages are specified in the Contract.

7. CONTACT PERSON: All requests or inquiries concerning the Bidding Documents, or the Work shall be addressed to: Alan Goschka (Project Director) emailed to goschkaa@michigan.gov.

8. AWARD: Subject to any agreed extension of the period for holding Bids, Bids shall remain valid for acceptance by the Owner for 60 Calendar Days after the date of Bid opening. In addition, the Owner expressly reserves the right, within the Owner's sole discretion, to reject any or all Bids, to waive any irregularities, to issue post-Bid Addenda and re-bid the Work without re-advertising, to re-advertise for Bids, to withhold the award for any reason the Owner determines and/or to take any other appropriate action.

9. PERFORMANCE AND PAYMENT BONDS: A performance bond and a payment bond are required for all contracts over $50,000.00.

END OF SECTION ONE

https://www.archives.gov/federal-register/codification/executive-order/12549.html mailto:goschkaa@michigan.gov

[18]

SECTION TWO – INSTRUCTIONS TO BIDDERS

1. PREPARATION OF BID: Execute Bid fully and properly. Bid Summary Form and Bid Form Attachments shall be used and completely filled out for the Bid to be considered responsive and meeting the requirements of the contract solicitation. All Bid prices shall be printed or typed in both words and figures.

2. BID CHECKLIST: Submit Bid Summary Form with original signatures plus Bid Form Attachments in accordance with the electronic bidding procedures on the SIGMA VSS website.

A complete bid will consist of the following forms, which are included immediately following the Bid Summary Form:

Bids SUBMIT THESE Bid Forms and Bid Form Attachments

All Bids □ Signed and completed Bid Summary Form

□ Bid Schedule

□ Qualified Disabled Veteran (QDV) Business Representation

□ Bid Security in the amount of 5% of Base Bid Price

If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to:

State Facilities Administration Design & Construction Division

3111 W. St. Joseph Street Lansing, Michigan 48917

All other Bid information must be submitted via SIGMA as per standard bidding procedure.

Signature Authorization or copy of the partnership agreement if signed by all partners

□ Byrd Anti-Lobbying Certification (Only when Federal Provisions Addendum is included)

□ Asbestos Abatement Attestation

□ State Project Registration (SPR) for the Contractor and subcontractors (if applicable pursuant to 2023 PA 10, as amended, MCL

408.1101 et seq.)

Over $50K □ Forms listed under All Bids

□ Payment and Performance Bond (upon issuing the Notice of Award

Over $100K □ Forms listed under All Bids

□ Certification of a Michigan Based Business

□ Payment and Performance Bond (upon issuing the Notice of Award).

Over $250K □ Forms listed under All Bids

□ Certification of a Michigan Based Business

□ Payment and Performance Bond (upon issuing the Notice of Award).

□ Bid Submittals

[19]

3. BID SUBMISSION: Bids must be submitted electronically through the SIGMA website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService.

4. Left Blank Intentionally.

5. MICHIGAN PREFERENCE CERTIFICATION: All Bidders submitting Bids in excess of

$250,000.00 shall complete the Certification of Michigan Based Business. This information will determine if a Bidder qualifies as a "Michigan" business for purposes of application of reciprocity where applicable.

6. BID SUBMITTAL: For projects over $250,000, the Owner requires a Bid Submittal from the

Bidders. The Bid Submittals will be used in evaluating the Best Value Bids under Section 2, paragraph 17. Failure to provide the submittals may disqualify the Bid.

7. SIGNATURES: All Bids, notifications, claims, and statements shall be signed as follows:

(a) Corporations: Signature of official shall be accompanied by a certified copy of the Resolution of the Board of Directors authorizing the individual signing to bind the corporation.

(b) Partnerships: Signature of one partner shall be accompanied by a signed copy of the legal document (e.g. Power of Attorney or partnering agreement) authorizing the individual signing to bind all partners. If Bid is signed by all partners, no authorization is required.

(c) Individual: No authorization is needed. Each signature shall be witnessed.

8. BID PRICES: The Bidder’s Not-To-Exceed Bid and Alternate Bid prices shall include, and payment for completed Work will compensate in full for: all professional design, services, obligations, responsibilities, management, supervision, labor, materials, devices, equipment, construction equipment, general conditions, permits, patent fees and royalties, testing, inspection and approval responsibilities, warranties, temporary facilities, small tools, supplies, Bonds, insurance, taxes, mobilization, close-out, overhead and profit and all connections, appurtenances and any other incidental items of any kind or nature, as are necessary to complete the Work, in a neat, first quality, workmanlike and satisfactory manner as required to fulfill the Owner’s Project requirements as described on the attached Project Description and as approved through the project design process by the Owner. For each Cash Allowance item, the Bidder shall include, within the Bid, all labor costs, construction equipment costs, insurance and Bond premiums and other general conditions costs and Fees (for both the Bidder’s and any Subcontractors) to complete Work associated with the material, equipment, or other designated item to be furnished under the Cash Allowance. For each Provisionary Allowance, the Bidder shall include, within the Bid, insurance, premiums (not recoverable as labor burden) and Bond premiums required to complete Work that may be ordered under a Provisionary Allowance.

9. INSPECTION OF BIDDING DOCUMENTS AND SITE CONDITIONS: The Bidder shall carefully review and inspect all documents referenced and made part of this ITB, site conditions, all applicable statutes, regulations, ordinances, and resolutions addressing or relating to the goods and services under this contract. Failure to do so or failure to acquire clarifications and answers to any discovered conflicts, ambiguities, errors, or omissions in the Bidding Documents will be at the Bidder’s sole risk.

https://www.govinfo.gov/content/pkg/FR-1986-02-21/pdf/FR-1986-02-21.pdf

[20]

10. INTERPRETATIONS AND ALTERATIONS TO THE BID AND BIDDING DOCUMENTS: All requests for clarification or interpretation of the Bidding Documents, all proposals for any modifications to the Bidding Documents, all requests for information and all other questions or inquiries about the Bidding Documents and/or the Work shall be submitted in writing to the Project Director. Requests or inquiries received less than seven Calendar Days before the date of Bid opening will be answered only if the response can be given through an Addendum made available at least seventy-two hours before Bid opening (counting Business Days only), the Bid opening is postponed by Addendum, or the Work is rebid without readvertising following the issuance of post- Bid Addenda.

Bidders shall not rely upon any oral statements or conversations regarding interpretations, clarifications, corrections, additions, deletions or other revisions or information to the Bidding Documents. Any addition, limitation or provision made with or attached to the Bid may render it non-responsive and/or irregular and be a cause for rejection. The Owner reserves the right to issue a post-Bid Addendum after opening the Bids and set a new date for the receipt and opening of sealed Bids. The Bidder acknowledges that the scope of construction included in the Work is not defined at the time of Bidding and payments will be made only for actual construction trade work completed in accordance with the approved Contract Documents.

11. MODIFICATION OF RECEIVED BID: The entire bid must be resubmitted on the SIGMA website.

12. BID WITHDRAWAL: Except for timely filed claims of mathematical or clerical errors granted by the State, no Bid may be withdrawn within sixty Calendar Days after the Bid Opening time and date or before the Bid expiration date. The request to withdraw a Bid due to error shall be submitted in writing along with the supporting documents within two Business Days after the date of Bid Opening. The claim shall describe in detail the error(s), include a signed affidavit stating the facts of the alleged error(s) and request that the Bidder be released from its Bid. The review of the claim and its supporting documents by the State is only for the purpose of evaluating the Bidder’s request and shall not create duty or liability on the State to discover any other Bid error or mistake. The sole liability of any Bid error or mistake rests with Bidder.

13. BID OPENING: N/A.

14. BID IRREGULARITIES: The following irregularities on any Bid Form or Bid Form Attachment shall be resolved as follows:

(a) between SIGMA entry and signed Bid Summary attachment, the signed Bid Summary attachment will be used.

(b) between words and figures, the words shall be used.

(c) between any sum, computed by the Bidder, and the correct sum, the sum computed by the

Bidder shall be used.

(d) between the product, computed by the Bidder, of any quantity and Bid Unit Price and the correct product of the Unit Price and the quantity of Unit Price Work, the product extended by the Bidder shall be used.

(e) between a stipulated Allowance and the amount entered, the Allowance shall be used.

(f) any mobilization pay item exceeding the maximum specified shall be ignored and the Bid shall remain unchanged.

(g) if any Bidder fails or neglects to bid a Unit Price for an item of Unit Price Work but shows a

"Bid Price" for that item, the missing unit price shall be computed from the respective quantity and the Item Bid Price shown.

(h) if any Bidder fails or neglects to show a "Bid Price" for an item of Unit Price Work but bids a unit price, the missing Bid Price shall remain as “zero”; and

(i) if any Bidder fails or neglects to enter a Bid Price in both words and figures, the Bid Price printed or typed, whether in words or figures, shall be used.

[21]

15. CERTIFICATION: The bidder certifies to the best of its knowledge and belief that, within the past three (3) years, the bidder, an officer of the bidder, or an owner of a 25% or greater interest in the bidder:

(a) Has not been convicted of a criminal offense incident to the application for or performance of a contract or subcontract with the State of Michigan or any of its agencies, authorities, boards, commissions, or departments.

(b) Has not had a felony conviction in any state (including the State of Michigan).

(c) Has not been convicted of a criminal offense which negatively reflects on the bidder’s business integrity, including but not limited to, embezzlement, theft, forgery, bribery, falsification, or destruction of records, receiving stolen property, negligent misrepresentation, price-fixing, bid-rigging, or violation of state or federal anti-trust statutes.

(d) Has not had a loss or suspension of a license or the right to do business or practice a profession, the loss or suspension of which indicates dishonesty, a lack of integrity, or a failure or refusal to perform in accordance with the ethical standards of the business or profession in question.

(e) Has not been terminated for cause by the Owner.

(f) Has not failed to pay any federal, state, or local taxes.

(g) Has not failed to comply with all requirements for foreign corporations.

(h) Has not been debarred from participation in the bid process pursuant to Section 264 of 1984

PA 431, as amended, MCL 18.1264, or debarred or suspended from consideration for award of contracts by any other State or any federal Agency.

(i) Has not been convicted of a criminal offense or other violation of other state or federal law, as determined by a court of competent jurisdiction or an administrative proceeding, that in the opinion of DTMB indicates that the bidder is unable to perform responsibly or which reflects a lack of integrity that could negatively impact or reflect upon the State of Michigan, including but not limited to, any of the following offenses under or violations of:

(i) The Natural Resources and Environmental Protection Act, 1994 PA 451, MCL 324.101 to 324.90106.

(ii) A persistent and knowing violation of the Michigan Consumer Protection Act, 1976 PA

331, MCL 445.901 to 445.922.

(iii) A finding that the bidder failed to pay the wages and/or fringe benefits due within the time period, as may be required by applicable law.

(iv) Repeated or flagrant violations of 1978 PA 390 MCL 408.471 to 408.490 (law relating to payment of wages and fringe benefits).

(v) A willful or persistent violation of the Michigan Occupational Health and Safety Act, 1974, PA 154, MCL 408.10001 to 408.1094, including: a criminal conviction, repeated willful violations that are final orders, repeated violations that are final orders, and failure to abate notices that are final orders.

(vi) A violation of federal or state civil rights, equal rights, or non-discrimination laws, rules, or regulations.

(vii) Been found in contempt of court by a Federal Court of Appeals for failure to correct an unfair labor practice as prohibited by Section 8 of Chapter 372 of the National Labor Relations Act, 29 U. s. C. 158 (1980 PA 278, as amended, MCL 423.321 et seq).

(j) Is NOT an Iran linked business as defined in MCL 129.312.

A false statement, misrepresentation, or concealment of material facts on this certification may be grounds for rejection of this proposal or termination of the award and may be grounds for debarment.

[22]

16. REJECTION OF BID: The Bidder acknowledges the right of the Owner to reject any Bids and to waive any defects or irregularity in any Bid received. In addition, the Bidder recognizes the right of the Owner to reject a Bid if:

(a) The Bid is in any way incomplete or irregular.

(b) The Bidder does not have satisfactory response for issues listed on the Responsibility

Certification attached to the Bid or is not responsible as determined by the Owner.

(c) The Bidder’s performance as a DB Entity was unsatisfactory under a prior Contract with the

Owner for the construction, repair, modification, or demolition of a facility with the Owner, or under any other Contract, which was funded, directly or indirectly, by the Owner.

(d) There are reasonable grounds for believing that collusion or unlawful agreements exist between any Bidders, that a Bidder is interested in more than one Bid, or that the Bid is not genuine or

(e) The Bid exceeds the funds available.

17. CONTRACT AND CONTRACT AWARD:

17.1 If the Owner elects to award the Contract, the Owner will make the award to the responsive and responsible best value bidder. Determination of the lowest three Bidders shall be on the basis of the sum of the Base Bid and any additive and deductive Alternates the Owner accepts, in the order in which they are listed only. The Owner will accept an Alternate only if all other previously listed Alternates are also accepted unless acceptance by the Owner of Alternates in a different order does not affect determination of the lowest three bidders in any way.

17.2 The bids will be evaluated for best value based on price and qualitative components by comparing the qualitative components of the three lowest responsive and responsible Bidders.

The comparison may also include other Bidders whose bids are within 10% of the lowest responsive and responsible Bidder.

17.3 For the purpose of evaluating and determining the three low responsive bids, 10% of the lowest responsive bid (the bid that would otherwise receive the contract award if the preference were not being considered) will be deducted from all QDV bids. The original QDV bid amount will be the basis of the contract award.

Example:

Lowest Responsive Bid $100,000 Lowest Responsive QDV Bid $109,000 Preference (10% of the Lowest Responsive Bid) $ 10,000 Lowest Responsive QDV Bid Less Preference $ 99,000 ($109,000 - $10,000) Official Low Responsive Bid $109,000

17.4 The Apparent Low Bidders will be evaluated for responsiveness and responsibility based on the following:

• Compliance with the bid specifications and requirements.

• The Bidder’s financial resources.

• The Bidder’s technical capabilities.

• The Bidder’s technical experience.

• The Bidder’s past performance.

• The Bidder’s insurance and bonding capacity.

• The Bidder’s business integrity.

[23]

Some qualitative components that may be evaluated are:

• Technical approach.

• Quality of proposed personnel.

• Management plans.

• Past performance of any nominated asbestos abatement subcontractor(s).

17.5 For contracts under $250,000, the best value will primarily be based on the lowest responsive and responsible bid.

18. CONTRACT TIME; LIQUIDATED DAMAGES: The Project described in the Contract Documents shall be completed by June 1, 2026, based on Notice-to-Proceed, except for Punch List items that do not interfere with the complete operation and use of all parts of the Contract Work. This Contract Time is of the essence and liquidated damages for each Calendar Day that expires after Substantial Completion of the entire Work shall be in the amount of $500.00. Final completion is July 1, 2026, and liquidated damages for each Calendar Day that expires after it shall be in the amount of $500.00. Liquidated damages are not a penalty, are cumulative and represent a reasonable estimate of the Owner’s extra costs and damages, which are difficult to estimate with accuracy in advance.

19. MOBILIZATION: The costs to establish temporary site offices, to obtain required permits for commencing the Work and for bonds and insurance premiums are examples of costs to the DB Entity that are covered by the mobilization pay item. This cost shall not exceed four percent (4%) of the Not-To-Exceed Bid, unless otherwise expressly provided in the Bidding Documents.

20. SAFETY REQUIREMENTS AND LAWS: The Bidder awarded the Contract shall comply with all applicable federal, state, and local Laws including health and safety regulations, environmental protection, permits and licensing.

21. MICHIGAN PRODUCTS AND RECYCLED PRODUCTS: All DB Entities, Subcontractors, DB Entity Architect-Engineers, and Suppliers are encouraged to specify and/or provide Michigan-made products, whenever possible where price, quality, and performance are equal or superior to non-Michigan products. All DB Entities, Subcontractors, DB Entity Architect- Engineers, and Suppliers are encouraged to specify and/or provide recycled products, green products, and/or environmentally friendly products whenever possible where price, quality, and performance meet the Project requirements. The DB Entity will be required to use alternatives to landfills for waste disposal such as reuse or recycle of asphalt, bricks, concrete, masonry, plastics, paint, glass, carpet, metals, wood, drywall, insulation, and any other waste materials to the extent practical.

22. As a public record, all portions of the proposal response and resulting contract are subject to disclosure as required under Michigan’s Freedom of Information Act (FOIA), MCL 15.231, et seq. However, the State may exempt some information from disclosure as permitted by law.

The State reserves the right to determine whether materials submitted by a bidder fall under applicable FOIA exemptions

23. SOIL EROSION AND SEDIMENTATION CONTROL: All Work under this Contract shall meet the storm water management requirements of the Project and comply with the applicable Soil Erosion and Sedimentation Control (SESC) rules and regulations and specific provisions for the same. SESC measures will be monitored and enforced by DTMB-SFA, or another authorized enforcing agency if so delegated, through the review of the DB Entity’s implementation plans and site inspections.

[24]

SFA or the other authorized enforcing agency will notify the DB Entity in writing of any violation(s) of the applicable SESC statutes and/or the corrective action(s) undertaken by the Owner and may issue stop work orders. DTMB-SFA has the right to assess a fine to the DB Entity for noncompliance with the SESC regulations applicable to this Work and fines shall be in addition to any other remediation costs or liquidated damages applicable to the Project and may exceed the value of the Contract.

END OF SECTION TWO

SECTION THREE – SUPPLEMENTARY INSTRUCTIONS

1. The provisions of this Section amend or supplement Section Two – Instructions to Bidders and those other provisions of the Bidding Requirements that are indicated below. All other Bidding Requirements that are not so amended or supplemented remain in full force and effect.

END OF SECTION THREE

SECTION FOUR – INFORMATION FOR BIDDERS

1. PERMITS, APPROVALS, LICENSES AND FEES

1.1 If the Owner has secured or will secure any permits, approvals and licenses and has paid or will pay any associated charges and fees, any such permits, approvals and licenses are itemized in this paragraph: Click here to enter text.

1.2 If any permits, approvals, and licenses itemized above have been obtained by the Owner and the fees have been paid, copies of those permits, approvals, licenses, and corresponding fee receipts are attached to this Invitation to Bid.

1.3 Except for any permits, approvals, licenses, and fees identified above, the DB Entity shall be responsible for all permits, approvals, licenses, and fees applicable to Work.

2. TAXES: The DB Entity must pay all Michigan sales and use taxes and any other similar taxes covering the Work that are currently imposed by legislative enactment and as administered by the Michigan Department of Treasury, Revenue Division. If the DB Entity is not required to pay or bear the burden or obtains a refund of any taxes deemed to have been included in the Bid and Contract Price, the Contract Price must be reduced by a like amount and that amount, whether as a refund or otherwise, must ensure solely to the benefit of the State of Michigan.

3. SEQUENCING REQUIREMENTS: Refer to the Bidding Documents for information, data, and criteria on sequences of Work…