This is a Design Build Project Advertisement issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design & Construction Division for the Department of Natural Resources (DNR). The project involves designing and constructing solar array installations at five DNR locations: Cadillac Customer Service Center, Traverse City Customer Service Center, Gaylord, Escanaba, and the Gaylord Repair Center. A mandatory pre-proposal Teams meeting is scheduled for May 15, 2025, with bids due on May 28, 2025, at 2:00 p.m. Eastern time. The Design Build Entity (DBE) will be responsible for conducting a comprehensive study, including site placement, interconnection points, utility conflict assessment, and complete design and construction services. The project targets specific energy generation goals for each location, with the Traverse City site designated as a Deduct Alternate.

The project has a proposed schedule with contract approval expected on June 23, 2025, the Design Build Entity to be under contract by July 7, 2025, construction commencing in August 2025, and substantial completion targeted for January 3, 2025. A 5% bid security is required, and all bid responses must be uploaded to SIGMA VSS. The project requires compliance with state and local codes, including SESC and EGLE regulations, and necessitates a State Project Registration (SPR). Attachments include site diagrams, utility bills, existing prints, and electrical panel photos. Bidders are limited to two attachments (each under 25 MB) and must follow specific submission guidelines, with questions to be emailed to the project director by May 22, 2025.

View the file

Other files

File Type Posted
Escanaba 3.jpg JPG image
Cadillac 4.jpeg JPEG file
Gaylord CSC 1.jpg JPG image
Gaylord CSC 2.jpg JPG image
Cadillac 2.jpeg JPEG file
CHERRYLAND T.C. FY25.pdf PDF
Design Build (Rev03-2025).pdf PDF
Gaylord CSC 4.jpg JPG image
Esc. Dist. Offic Bldg. and Maintenance Garages.pdf PDF
Escanaba 2.jpg JPG image
Cadillac Site Diagram.pdf PDF
Escanaba Site Diagram.pdf PDF
Escanaba 1.jpg JPG image
Gaylord CSC 3.jpg JPG image
CHERRYLAND T.C. FY24.pdf PDF
Cadillac 1.jpeg JPEG file
Cadillac 3.jpeg JPEG file
Consumers Cadillac FY24.pdf PDF
Consumers Cadillac FY25.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0415 (R 9/24)

DESIGN BUILD PROJECT ADVERTISEMENT

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

DESIGN & CONSTRUCTION DIVISION

This form is required for the advertisement of all construction projects. (1984 PA 431)

DTMB FILE NO.

751/24228.SAA

DATE

Monday, May 12, 2025

ADVERTISEMENT DATE

May 12, 2025 – May 28, 2025

BID DUE DATE

Wednesday, May 28, 2025 @ 2:00 p.m. EASTERN time

PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)

Department of Natural Resources – Finance and Operations Division – Solar Arrays:

DNR Cadillac Customer Service Center, 8015 Mackinaw Trail, Cadillac, MI 49601 DNR Traverse City Customer Service Center, 2122 M-37, Traverse City, MI 49685 DNR Gaylord, 1732 M-32, Gaylord, MI 49735 DNR Escanaba, 6833 US-2, Gladstone, MI 49837

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION

A MANDATORY PRE-PROPOSAL MEETING will be conducted at 9:00am on Thursday, May 15, 2025, via a Teams meeting.

Please RSVP to the DTMB-DCD Director prior to 2:00pm on May 14, 2025, and the Project Director will send a Teams meeting link to join the meeting.

MANDATORY Yes No

NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.

DESCRIPTION OF WORK:

Requesting a Design Build Entity (DBE) to provide services for a study for proposed placement, design and construction of a new solar array at the 4 site locations listed above (plus an additional location at the Repair Center at Gaylord, for a total of 5 locations). Solar panels will be added at each site noting points of interconnect, PV concept, and addressing possible utility location conflicts. Traverse City site to be a Deduct Alternate.

Additional Considerations:

• Ground penetrating radar may be needed to locate existing utilities

• There will be one contract issued for all 4 sites

• All sites will need field verification

• Include topography survey, push-pull testing and soil borings as needed to perform the work

• Target design goals for energy are as follows: Cadillac (target 110% 32 kw annually) Traverse City (20 kw annual utility limit) Gaylord (32 kw Repair Center / 16 kw CSC) Escanaba (31 kw)

• The connection of new service to the existing service shall be underground for ground mounted locations.

DBE to work with local utility company for electrical interconnection

• DBE to provide all items necessary for design and construction, including grading and soil considerations, foundation design, solar array design targeted goals

• DBE to submit 50% and 90% contract document design review drawings for owner review 7 days prior to review meeting. Virtual Teams meetings are acceptable for document review.

• DBE to provide updated schedule at each meeting

• DNR will be responsible for the demolition of any trees, if needed

• All solar arrays are assumed to be located on the roof with the exception of Cadillac, and possibly Escanaba.

Roof mounted panels will require the existing structure will support the solar panel load. This will require a structural analysis at each building.

• Include time for team meetings – twice a month progress meetings are required during the construction phase. Virtual Teams meetings are acceptable.

• Meet State and local codes including SESC and EGLE as required. Submit sealed plans to LARA plan review and permits.

• State Project Registration (SPR) is required. SPR registration information (including Online Certified Payroll Submission through LCP Tracker) is at: LEO - Prevailing Wage

During the term of the contract, the Design Build Entity must maintain a current and valid SPR.

• Additional requirements as outlined in the Design Build Contract

Proposed project schedule:

May 28, 2025, Bids Due June 23, 2025, State Ad Board contract approval July 7, 2025, Design Build Entity under contract August 2025 construction to commence January 3, 2025, Substantial Completion

Attachments:

Site Diagrams FY24 & FY25 Utility bills Escanaba Existing Prints Gaylord Site Existing Prints Electrical panel photos

Please NOTE:

• Bid responses and bid attachments MUST be uploaded to SIGMA VSS.

• Contractors should only submit a maximum of two (2) attachments (both being less than 25 MB) for bid responses. One attachment is to be bid documents (i.e., Bid Summary, Bid Schedule, Bid Bond, Certification forms, Signature Authority, etc.) and if applicable, the other attachment should be Qualified Disabled Veteran (QDV) information (DD214, Proof of 51% Ownership and Proof of Service-Connected Disability).

•• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your bid response. SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the bid response has been uploaded.

•• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749.

You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov

• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).

• You may be asked by our contract specialists to email your bid response. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.

• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.

• Bid Responses should not be emailed to the Project Director.

5% BID SECURITY REQUIRED

mailto:sigma-procurement-helpdesk@michigan.gov mailto:WatrosA@michigan.gov mailto:KleinD4@michigan.gov

NIGP CODES: 90625, 90628, 90692, 90921, 92531, 92533, 90524, 92578, 92595, 91016, 91438

ACCEPTING QUESTIONS UNTIL:

Please do not submit online questions via SIGMA VSS. ALL questions should be emailed to Sheryl Ananich at ananichs@michigan.gov address no later than 2:00 p.m., Eastern on Thursday, May 22, 2025.

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers’ safety rules that are administered by federal agencies (EPA, OSHA and DOT), state agencies (DHHS, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.

Documents & Bid Results may be obtained from:

https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

Project Director: Sheryl Ananich

Address: 3111 W St Joseph Street, Lansing, MI 48917

Phone: (517) 243-7605

Email: ananichs@michigan.gov

Approved by: Sheryl Ananich mailto:ananichs@michigan.gov https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

File details come from the government source that posted it. Updated .