DD260_FA_REPORT.pdf

DoD Form PDF 114 KB Posted

Attached to
Spares Buy Seals, Metallic, Aircraft
Solicitation number
FA812124Q0008
Issued by

About this file

This document is a First Article Requirements form for a federal contract opportunity. The key details are:

The contract is for NSN 2840003438336NZ, which are metallic aircraft seals. The contractor must provide 3 first article units, with 2 being part of the production quantity and 1 additional. The first articles must be inspected and tested per the requirements in LPF-QAR-003, with one article being destructively tested. The detailed test plan must be provided to the government within 0 calendar days of contract award, and the test report is due 60 calendar days after testing. The government will provide written approval or disapproval of the first articles within 45 days of receiving the contractor's report. Approved first articles will be retained by the government, while disapproved articles will be returned to the contractor. First article testing may be waived if the contractor has previously provided satisfactory production quantities of the same or similar items to the government within the past 36 months. The cognizant government engineering authority will make the final determination on waiving first article testing.

View the file

Other versions and copies of DD Form 260

File Revision Posted Attached to
DD260 28Jan2010.xfdl Jan 28, 2010 Communication, Detection, and Coherent Radiation Equipment
DD260 28Jan2010.xfdl Jan 28, 2010 Noun: Interconnecting Box, NSN: 5895-01-368-3961GC, P/N: 9095520-10
DD260_First_Article_Requirements_and_Waiver.pdf Revision not stated C-130 Companion Flange
First Article Requirements DD Form 260_24-00055.pdf Revision not stated C130H Air Data Computer
DD260_FA_REPORT.pdf Revision not stated Duct, Turbine, Aircraft
DD260_FA_REPORT.pdf Revision not stated Seal, Metallic, Aircraft
FA825116Q00618_DD260_FA_00618.pdf Revision not stated BELLMOUTH ASSEMBLY
DDForm260FirstArticleRequirements.pdf Revision not stated Aircraft and Airframe Structural Components
FA820614R0002_DD260FA.pdf Revision not stated Qualification Article
FA820614R00779_DD260FA.pdf Revision not stated Qualification Article
FA820613Q00998_dd260.pdf Revision not stated SHIELDING GASKET, EL
FA825013Q00982______0001_dd260.pdf Revision not stated PACKING, PREFORMED
DD260.pdf Revision not stated Communication, Detection, and Coherent Radiation Equipment
DD260FirstArticleRequirements.pdf Revision not stated TUBE ASSEMBLY, ACFT
DD260FirstArticleRequirementrs.pdf Revision not stated SHROUD, COMPRESSOR
SPRTA111R0025_DDFORM260.pdf Revision not stated RUDDEVATOR, BOOM
DD260.pdf Revision not stated Repair Contract for ALR 56A Oscillators
DDForm260.pdf Revision not stated ALQ-172 LRU-7 Power Supply
Show all 18

Who attaches DD Form 260

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

29 MAR 2024(AFMCI 23-110, AFMCDAFI 20-102, and FAR, Subpart 9.3) (additional instructions on page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

77445 / 4032669

4. NSN

2840003438336NZ

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 3 UNIT(S) OF LOT / ITEM 1

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

WILL X WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

X REQUIRED NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are identified in drawing 4001863, sub-tier drawings (if an assembly), and specifications identified therein.

B. The detailed technical requirements for First Article approval tests are contained in block 12 of this form and LPF-QAR-003.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

(3) Number of days for government approval / disapproval days.

(1) DD Form 1423 ELIN

(2) Delivery due calendar days from date of contract.

D. Contractor's notification to ACO and

PCO

(Requesting Activity) of test time and location due 30 days prior to start of testing.

E. X TEST REPORT REQUIRED

(3) Forwarded to

AFLCMC/LZPED

FA MONITOR DODAAC FA8111

3001 STAFF DRIVE, STE 1AB85A

Tinker AFB, Oklahoma 73145

(4) Government written notice of approval / disapproval due

(2) Due

(1) DD Form 1423 ELIN days after receipt of contractor's report.

N/A

N/a calendar days from date contract.

AFMC IMT 260, 20230316, V-5,

Version 7Generated by PRPS using Jasper Reports on 17 Apr 2024

PREVIOUS EDITION IS OBSOLETE

Prescribed by: AFMCI23-110

F. FIRST ARTICLE DELIVERY

(1) Due within 0 calendar days from date contract.

(2) Notify 0 calendar days prior to shipment.

(3) Delivered to government at

N/A

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 0 days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

$2,500.0000

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

(insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

X Other Disposition:

see the block 12 remark

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. X Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, X DoD, Air Force.

b. X Offerors currently in production of the same or similar article for a Government, X DoD, Air Force contract and who have received First Article approval under the existing contract.

c. X Offerors who have previously furnished production quantities of the same or similar articles to the Government, X DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 36 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. X See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

AFMC IMT 260, 20230316, V-5,

Version 7Generated by PRPS using Jasper Reports on 17 Apr 2024

12. REMARKS

Nguyen, Hanson VNAME: 10 APR 2024DATE:

5. First Article Quantity is 3 parts:

2 parts will be part of production quantity 1 part will be in addition to production quantity Block 9.B First article test requirements shall be per LPF-QAR-003 and the following:

a. All three first articles shall be inspected in accordance with the requirements of paragraphs 3.1, 3.2, 3.3, 3.4, and 3. Block 5 of LPF-QAR-003.

b. The assembly detail part numbers (if an assembly), shall be inspected per paragraphs 3.1, 3.2, 3.3, 3.4, and 3.5 of LPF-QAR-003 prior to assembly.

c. After completion of inspections per 9.B.a above, one article shall be destructively tested/evaluated in accordance with the requirements of paragraph 3.6 of LPFQAR-003.

NOTE: Deliveries (FAT test plan and Reports) are preferably submitted on ISO-10149 compliant CD-ROM in Adobe Acrobat Portable Document Format.

Block 10. Disposition of First Articles:

Destructively tested first article assets will be condemned and disposed of at vendor's facility.

Block 11. The cognizant Government engineering authority shall be the final authority for determining if a contractor meets the conditions of waiver identified in 11.a and/or 11.c.

First article testing is waived if the offeror is the prime contractor, Pratt & Whitney.

This is a critical part used in the F100 series turbine engine. Poor quality parts will have an adverse effect on mission capability and system safety. For this reason, First Article Testing is required to insure first time manufacturers or manufacturers that have not produced the item within three years manufacture parts in accordance with the drawing and specification requirements.

Block 3: Part Number: __4032669____ Block 9: additional information for part C&E:

C. 1) DD Form 1423 ELIN:

2) Deliver due _____ calendar days from date of contract E. 1) DD Form 1423 ELIN:

2) Due ______ calendar days from date of contract

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING

(Name, Organization, Phone)

Nguyen, Hanson V

AFLCMC / LP S E A 3

405-734-7603

884-7603

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

AFMC IMT 260, 20230316, V-5,

Version 7Generated by PRPS using Jasper Reports on 17 Apr 2024

File details come from the government source that posted it. Updated .