DB Construction Experience Sheet.docx
DOCX document 15 KB Posted
- Solicitation number
- 36C25924R0030
About this file
This scope of work document outlines the requirements for a design-build contract to renovate Building 43 at the Fort Harrison VA Medical Center in Montana. Key details include:
-
The contractor will finalize the 35% design plans and perform repairs and renovations to the building to convert it into administration and training space while retaining its historic character. Work includes HVAC, electrical, architectural, fire protection and security system upgrades.
-
The contractor must provide project management and quality control oversight. Submissions are required at 65%, 95% and 100% design milestones. A multi-phased construction period not to exceed 406 days is outlined.
-
The contractor shall obtain all required permits and comply with VA, NFPA and other codes. Prevailing wage rates apply. Work hours are generally 7:00AM to 5:00PM with afterhours work requiring approval.
-
The scope includes hazardous materials abatement, accessibility upgrades, and bringing systems up to current codes and standards. The electrical system will be entirely replaced. Fire suppression is required.
-
The contractor must develop project schedules, safety plans and conduct a pre-construction risk assessment. A one-year warranty is required upon final acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25924R0030 0001.docx | DOCX document | |
| Drawings with basement.pdf | ||
| Master Specifications.pdf | ||
| Site Utility.pdf | ||
| Past Performance Questionnaire.pdf | ||
| Structural REPORT.pdf | ||
| Mechanical Calcs.pdf | ||
| 36C25924R0030.docx | DOCX document | |
| Partial 1 line.pdf | ||
| LOS Certificate.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION EXPERIENCE PROJECT DATA SHEET
36C25924R0019 DB Renovate 3rd Floor Cowboy
Project No. (check one) : |_| CON #1 |_| CON #2 |_| CON #3 |_| CON #4 |_| CON #5
1. Experience for: |_| Offeror |_| Joint-Venture |_| Other (Explain)
Firm Name:
Address:
Phone Number:
DUNS Number:
Point of Contact: Contact Phone Number:
2. Work Performed as: |_| Prime Contractor |_| Sub Contractor |_| Joint Venture |_| Other (Explain)
Percent of project work performed:
If subcontractor, who was prime (Name/Phone #):
3. Contract Number: Delivery/Task Order Number:
Title:
Location:
4. Award Date (mm/dd/yy): Completion Date (mm/dd/yy):
5. Type of work:
|_| New Construction |_| Renovation |_| Repair |_| Alteration |_| Other (explain):
6. Type of Contract/Task Order: (Check ALL that apply)
|_| Firm-Fixed Price |_| Cost/Time and Material |_| Other (explain):
7. Construction Project:
Award Amount: Final Price:
Type of Contract/Task Order: (Check ALL that apply)
|_| Design-Build |_| Design-Bid-Build |_| Delivery/Task Order (IDIQ) |_| Other (explain):
If Design-Build, identify the Lead Design Firm:______________________________________________
8. Customer/Owner Name:
Point of Contact (POC): POC Phone Number:
FAX Number: POC E-mail address:
9. Provide a detailed description of the project and the relevancy to the project requirements of this RFP (i.e.: unique features, square footage, construction methods), including any sustainable features or USGBC LEED certifications. If design-build, include a description of the design-effort.
10. Provide a detailed description of what work your firm self-performed on this project:
11. Other Information:
File details come from the government source that posted it. Updated .