Second Set of Q As issued w/Amendment No. 003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No._008.zip | ZIP file | |
| Amendment_No._007.zip | ZIP file | |
| Amendment_No._006.zip | ZIP file | |
| Amend_No._004_Signed_SF30.pdf | ||
| Amendment_No._005.zip | ZIP file | |
| Amend_No._005_Qs_and_As_.docx | DOCX document | |
| Amendment_No._004.zip | ZIP file | |
| Amend_No._004_FINAL_SET_of_QsAs_thru_478_.doc | DOC document | |
| Amend No. 003 Signed SF30.pdf | ||
| Q As 1st set Pre-Prop Conf 8-2 thru 8-8-2012.doc | DOC document | |
| Amendment No. 003.zip | ZIP file | |
| Amendment No. 002.zip | ZIP file | |
| Amend No. 002 to D12PS00316.pdf | ||
| Amendment No. 001.pdf | ||
| Section J Attachments 1 through 45.zip | ZIP file | |
| RFP D12PS00316 - Sections B-M.zip | ZIP file |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation D12PS00316 Questions and Answers Amendment No. 003 Foundation Cloud Hosting Services
| Item |
| Page No. |
| Paragraph |
Ref/Sentence
| Question/Comment |
| Government Response |
| RFP Change |
| 83 |
| N/A |
| N/A |
| Based on past experience the list of pre-proposal attendees is made public. I was just curious who was there. Due to the newness of Federal Cloud opportunities I am curious about who the players are, I was not planning on contacting them for teaming. |
Is this information restricted?
No, the list of attendees from the pre-proposal conference will not be made available. However, as stated in Section L10.1, Partnering/Teaming List, as a courtesy we will compile a list of those offerors that wish to be incorporated on a list that are interested in subcontracting and partnering opportunities with other potential offerors. A current list has been posted to the AQD website shown below. It may be modified as others submit their information http://www.aqd.nbc.gov/Business/solic_details.aspx?solid=499
Also, the slide presentation from the pre-proposal conference has been posted to the AQD website identified above.
No
| 84 |
| Attch 2, p. 9 |
C-3 Attch 10, p. 4 Attachment 2 C-3, Attachment 10 Att 2, p. 9: The Infrastructure as a Service (IaaS), Platform as a Service (PaaS), and Software as a Service (SaaS) cloud solution(s) shall be Government only communities (including United States federal, state, local and tribal) provided the communities have similar and compatible security control objectives, requirements, and compliance considerations, or private clouds, certified under FISMA with a security categorizations of either “LOW”, “MODERATE”, or “HIGH” commensurate with the security categorizations of the DOI hosted applications.
C-3: The Web Hosting Services Technical Service Line includes, but is not limited to cloud Based Web Hosting Services in public, private, community and hybrid cloud environments.
Att 10, p. 4: For Information Systems with “Low” sensitivity and impact, Virtual Machine Hosting Services may be hosted on a Public cloud.
The task order requirement appears to be in conflict with the enterprise requirement. Is the solution restricted to private or government community clouds only, or are public and hybrid clouds permitted for specific task orders?
Response will be provided in a forthcoming amendment.
| 85 |
| 4 of 8 |
| Section J, Attachment 5, 1.9, Maintenance Personnel |
| Please clarify as to what type of background investigation and/or security clearance is required for access to facilities and/or systems. |
| Specific details related to background investigations and/or security clearances are provided in Section J, Attachment 2, Chapter 4 (Personnel Security Background Investigations and Clearances) |
| No |
| 86 |
| 4 of 8 |
| Section J, Attachment 5, 1.9, Maintenance Personnel |
| Please clarify if persons other than maintenance personnel supporting this effort will require a background investigation and/or security clearance. |
| Specific details related to background investigations and/or security clearances are provided in Section J, Attachment 2, Chapter 4 (Personnel Security Background Investigations and Clearances) |
| No |
| 87 |
| 4 of 8 |
| Section J, Attachment 5, 1.9, Maintenance Personnel |
| Please clarify if the DOI will accept prior background investigations and/or security clearances from other agencies. |
| Specific details related to background investigations and/or security clearances are provided in Section J, Attachment 2, Chapter 4 (Personnel Security Background Investigations and Clearances) |
| No |
| 88 |
| 4 of 8 |
| Section J, Attachment 5, 1.9, Maintenance Personnel |
| Please clarify if the DOI will provide contractors with all security requirements and reference material prior to award. |
| Specific details related to background investigations and/or security clearances are provided in Section J, Attachment 2, Chapter 4 (Personnel Security Background Investigations and Clearances) |
| No |
| 89 |
| 4 of 8 |
| Section J, Attachment 5, 1.9, Maintenance Personnel |
| Please clarify if back investigations or security clearances may be in process after award of a Day 1 Task Order. |
| Specific details related to background investigations and/or security clearances are provided in Section J, Attachment 2, Chapter 4 (Personnel Security Background Investigations and Clearances) |
| No |
| 90 |
| Attch 6 |
| None |
| Will the government provide a server and storage inventory (or architecture diagram) of the FBMS architecture in each data center, that includes |
· Make
· Model
· CPU / RAM
· How used (which SAP components or other purpose)
· Storage array type (make/model)
· Storage Resource Management software
· Raw/usable/used GB (direct attached on servers and SAN/NAS) Note virtual/physical relationships
| No, that information is not required and/or necessary in order to prepare a proposed solution. The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate. |
| No |
| 91 |
| 18 |
| Attachment 6, 12.1.1 |
| Is the Quality Assurance Plan included in the 70-page count for SAP Hosting? |
| Attachment 6, Section 21.4, sub-section 21.4.1, has been changed to read: Technical proposal will be limited to seventy (70) pages, excluding cover sheets, reference pages, and the Quality Assurance Plan. |
| Yes, change made as stated in response. |
| 1.1 “…associated transition support…” |
| Will DOI perform the migration of the SAP application components and data to the cloud-based infrastructure? Or does DOI expect these to be part of “associated transition support”? |
| Yes. DOI is intending to perform the migration of the SAP components to the cloud-based infrastructure and has estimated DOI staffing assuming no conversion/porting will be required by the Contractor. Perhaps. DOI may expect some level of “associated transition support” depending upon the specific solution proposed. |
The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate.
No
| Attachment 6, 4.1 |
| 4.1…"In-depth requirements analysis suggests that transitioning FBMS to a different OS/DBMS environment would introduce significant cost, performance, and schedule risk into the program; there would have to be a clear and compelling ROI advantage to make such a transition feasible." |
Would DOI be willing to share the "in-depth requirements analysis" for the offerors’ consideration in developing the appropriate solution?
No. Many of the inputs and, in particular, the decisional discussions, are not in a format that can be shared. The information is not required and/or necessary in order to prepare your proposed solution.
No
| 94 |
| 11 |
| Attachment 6, 4.8.2 |
FBMS serves an array of end-users nation-wide through the DOI’s Enterprise Services Network (ESN). Given a change in hosting providers, the only change to connectivity will be the addition of one or more links from the new hosting provider into the DOI ESN and deletion of connections to the current provider.
Will the government provide the current connectivity bandwidth in use?
Currently FBMS is connected to the DOI ESN (private Verizon cloud) via a tiered DS3 45mbs connection. At this time the Government sees a 15% average utilization on that connection with it expected to be at 40% utilization by Fiscal Year 14.
All new circuits should have sonet capability and be fully redundant.
No.
| 95 |
| 11 |
| Attachment 6, 4.8.2 |
FBMS serves an array of end-users nation-wide through the DOI’s Enterprise Services Network (ESN). Given a change in hosting providers, the only change to connectivity will be the addition of one or more links from the new hosting provider into the DOI ESN and deletion of connections to the current provider.
Will the government be providing the new links from the DOI ESN into the new hosting provider facility?
The only change to connectivity will be the addition of one or more links from the new hosting provider into the DOI ESN and deletion of connections to the current provider.
Therefore, offerors shall assume the Government is providing any required primary connectivity.
Attachment 6 has been revised to include sub-section 21.5.1, Government Provided Assumptions, which includes item 1 and states, Offerors shall assume the Government is providing any required primary connectivity with regards to Section 4.8.2 of this document.
Yes, change made as stated in the response.
| Attachment 6, Section 4.5 |
| a. Table 4 and Table 5 storage amount matches each other, even though Table 5 identifies as storage for database only, and Table 4 is identified as projected storage. |
b. Please provide storage breakdown by application & database
| DB usable SAN and total usable SAN (at the OS level) projections are provided by environment and DB instance in the attached Addendum 1 added to Attachment 6. These are projections based on the current FBMS Technical infrastructure. The total SAN requirements associated with a particular vendor proposal may differ. |
| Yes, an addendum 1 has been added to Attachment 6. |
| Attachment 6, Section 4.6 |
| Table 6 does not provide any CPU data. Please provide CPU data. |
| The attached Addendum 2 added to Attachment 6 provides the physical server specifications and how FBMS runs on the current server infrastructure projected through FY14. |
However, this information is not required and/or necessary in order to prepare your proposed solution.
The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate.
Yes, an addendum 2 has been added to Attachment 6.
| Attachment 6 |
| There is no backup breakdown and retention policy; please provide detail breakdown with retention policy for backup. |
| Although this information is not required and/or necessary in order to prepare your proposed solution, the following is the current backup and retention for FBMS. However, the Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate. |
Databases larger than one TB are mirrored daily and dumped to tape for offsite retention. Smaller databases are backed-up directly to tape. Retention of back-ups of the development, quality assurance, and training environments is 30 days, while retention of the production environment is 35 days.
No
| Attachment 6 |
| Does the scope of work include all the software listed in Table 3 - Attachment 6? If so the personnel requirements in 9.2 only lists SAP ERP. |
| Yes, FBMS is looking to run all the listed software components on the proposed infrastructure. |
The Government’s intention is not a “one-for-one” correlation to the software components identified in Table 3. Section 9 of the PWS identifies the qualification requirements for the FBMS proposed personnel.
No
| Attachment 6 |
| Can you provide daily utilization pattern? Weekends, Holidays, after hours? |
| The requirement for available active memory is already identified within |
Attachment 6, specifically Section 4.4, Table 1. The daily utilization patterns are not necessary in order to provide a proposed solution. Daily and weekly fluctuation in-demand are already included in the information contained in Table 1.
No
| Attachment 6 |
| Do any of the BOBJ BPC/PRF/PCM system exists or are they all planned for D8? |
| The BobJ BI components exist and go live in October 2012. According to the current FBMS schedule, the BobJ Public Budget Formulation will exist in Dev2 at the time of migration. |
BobJ PCM will be built out on the new hosting environment immediately after the environment migrations are complete, currently anticipated for the first quarter of FY15.
No
| Attachment 6 |
| Are there 2 development systems for each SAP application or just for ECC (i.e. BI, PI) |
| No, there are not 2 development systems for each SAP application. The, the FBMS program uses the standard five-box SAP development model; there are thus two development environments, two test (QA) environments, and a production environment. Ancillary environments include training, disaster recovery, and a copy of production. Most of the SAP modules in FBMS are present as instances in each of these environments. |
| No |
| Attachment 6 |
| Are there 2 QAS systems for each SAP application or just for ECC (i.e. BI, PI) |
| No, there are not 2 development systems for each SAP application. The, the FBMS SAP project utilizes a 5- box SAP development model which includes instance of all SAP applications. |
| No |
| Attachment 6 |
| How are the DR systems kept in sync with the production SAP systems |
| The present Disaster Recovery strategy is a “Hot Standby” environment (DR) with full tape restore annually during the DR test. The Government keeps the basic server configuration, patching and settings in synch with all environments. |
| No |
| Attachment 6 |
| Is SAP’s adaptive computing environment being used |
| No, the SAP Adaptive Computing Controller is not being used. |
| No |
| 106 |
| 10 |
| Attachment 6, Paragraph 4.7.1 Responsibilities |
| “The proposed hosting solution will include an equivalent split of responsibilities in the solution developed” to that shown in the table in 4.7.1. Will the BMC Software Control-M licenses used for production management and job control be provided as government furnished property (GFP). |
| The Government owns and maintains Control-M licensing as part of its suite of management tools, and production control will continue to monitor and control Production Operations (batch jobs) from the existing production management infrastructure. Thus, the BMC licenses will not be GFP but DOI shall retain the ability to monitor the cloud based containers/guest with its existing BMC installation. See Section 4.7.1 of Attachment 6 for revision. |
| Yes, Section 4.7.1 has been revised to reflect retention of ability to monitor. |
| 107 |
| all |
| Attachment 6 |
| Is it DOI’s intention to make a single award for the Day 1 Task Order described in the Performance Work Statement for SAP Hosting? We understand DOI may award multiple contracts for the SAP Application Hosting Service Line. This question seeks to clarify the number of awards for the Day 1 task order. |
| Yes, the current “Day 1 task order” for FBMS is anticipated to be awarded to one vendor. However, there could be multiple IDIQ awards for the SAP Application Hosting technical service line. |
| No |
| 108 |
| all |
| Attachment 6 |
| Please clarify the relationship between the Day 1 Task Order for SAP Hosting and the DOI FBMS services prime contract awarded to IBM Global Business Services in 2006. |
Does the Day 1 Task Order include the FBMS services currently provided by IBM Global Business Services? If not, is IBM Global Business Services eligible to bid on the SAP Hosting Day 1 Task Order, or does IBM GBS have a COI for this Day 1 Task?
The current systems integration effort is completely separate from the requirements of the Day 1 task order identified within the PWS, Attachment 6. The “Day 1 Task Order for SAP Hosting” is for Cloud services to host the FBMS infrastructure. The IBM Global Business Services system integrator services are to assist DOI in deploying FBMS.
The “Day 1 Task Order for SAP Hosting” does NOT include any services currently being provided by IBM GBS. Therefore, the Government’s position is that IBM GBS is eligible to participate by submitting a proposed solution for any/all of the technical service lines to include SAP Application Hosting.
No
| 109 |
| 13 |
| Attachment 6, Section 5.8 |
| Does the SAP hosting partner certification required at time of award have to be held by the prime contractor, or can this certification be held by a subcontractor/teaming partner and not the prime? |
| The SAP cloud services certification must be held by the business entity or entities actually providing the services itemized in Section 11, Attachment 6, in Section J of the RFP. |
The proposed solutions must clearly identify who holds the SAP certification.
This would depend on the solution and be seen as differencing and/or risk factors in the technical evaluation.
No
| as per Table 3 for FY2014-2015 |
| Please provide additional tables detailing FY2015-FY2016 and FY2016-FY2017 SAPS estimates per SAP application tier |
| This information is not required and/or necessary in order to prepare your proposed solution. |
| No |
| FY15 through FY18 SAPS estimates, shown in Table 6 in section 4.6.1 of Attachment 6 |
| Please provide additional tables detailing NON-Production SAPS per SAP application (ECC, BW, etc…) and estimates per application tier (App, CS, DB) for Denver and Herndon datacenters. |
| This information is not required and/or necessary in order to prepare your proposed solution. |
| No |
| Can we substitute the SAP HANA platform for the database tier as of FY14 and beyond for SAP BW, SAP BPC and other SAP applications? |
| Yes, offerors may substitute the SAP HANA platform for the database tier. However, risk, migration and all the requirements listed in Attachment 6 must be addressed. The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate. |
| No |
| Does DOI utilize a SAP Java database schema in their SAP BW environment? |
| Yes, FBMS utilizes a JAVA stack in the following applications BW, XI, GRC, Portal, Solution Manager, and BobJ. XI, Solman, and GRC are dual-stack. BW is MCOD for Java and ABAP. |
| No |
| Is the design of a database solution with Oracle RAC, for the database tier, is an accepted option? |
| The RFP does not prohibit this as a proposed solution. However, risk, migration and all the requirements listed in Attachment 6 must be addressed. The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate. |
| No |
| Please define third-party (non SAP) applications that interface with the SAP applications (besides OpenText, PRISM and Apache)? |
| The Government has provided all current necessary information pertaining to applications in the PWS contained in Attachment 6, specifically, Section 4.4, Table 3. Therefore, any additional information is not necessary in order to provide a proposed solution. |
| No |
| per section 4.1 of Attachment 6 |
| Is a Red Hat Linux with Oracle solution considered an equivalent variation of a Unix/Oracle solution |
| The RFP does not prohibit this as a proposed solution. However, risk, migration and all the requirements listed in Attachment 6 must be addressed. The Government desires the most cost effective, best value proposed solution. Therefore, it is up to the vendor to propose the solution not for the Government to dictate. |
| No |
| 117 |
| 10 |
| Attachment 6, 4.6.1 |
| Are the non-production SAPs and memory configurations for FY14\15 available to broken down and provided for each product? Production is only provided on Table 3, Page 8. |
| This information is not required and/or necessary in order to prepare your proposed solution. |
| No |
| 118 |
| 19 |
| Attachment 6, 12.3 |
| How long does it take to perform the processes for System Copy, System Refresh, and creating a new instance in the existing DOI production environments? |
| The Government will perform the processes for System Copy, System Refresh, and creating a new production environment. Therefore, DOI shall retain the ability to perform the same capabilities for ProdCopy and backups via the next technical platform in the cloud. |
Section 12.3 was deleted with the revisions in Amendment No. 002, See Section 21 for submission instructions and evaluation criteria. However, Section 2.5 has been revised to read as follows: DOI shall retain the ability to perform the same capabilities for ProdCopy and backups via the next technical platform in the cloud.
Yes, change made as stated in the response.
| 119 |
| 5 |
| Attachment 6, 4.1 |
| Is DOI currently leveraging virtualization? If so, to what extent, ie. Application Tier, DB Tier or both? |
| Currently FBMS is running on Oracle Enterprise class M8000 and M5000 servers and 3 clustered windows servers. Currently FBMS is fully virtualized across ALL tiers and for both Solaris and windows. |
| No |
| 120 |
| 5 |
| Attachment 6, 4.1 |
| How is the Oracle DB Licensed? Is it On RUN time from SAP or CPU based from Oracle? |
| CPU-based for Denver Data Center M8000 cluster and user-based for the Eastern Service Center M8000 cluster. |
| No |
| 121 |
| 19 |
| Attachment 6, 12.3 |
| What is DOI’s current performance testing tool? Will this tool be available for performance testing? Are there existing scripts that will be available from DOI for performance testing |
| Yes, FBMS intends to leverage the Loadrunner testing scripts from our existing Loadrunner testing servers to performance test the pilot transition environment mentioned in section 11.1 of attachment 6. |
| No |
| 122 |
| 5 |
| Attachment 6, 4.1 |
| What SAP Operation tools need to be migrated and integrated? |
| The Government has provided all current necessary information pertaining to SAP Operation tools to be migrated in the PWS contained in Attachment 6, specifically, Section 4.1 and Table 2 contained in Section 4.4. The operational tools are contained in applications that are already identified (i.e. ECC and Solution Manager). |
Therefore, any additional information is not necessary in order to provide a proposed solution.
No
| 123 |
| 22 |
| Attachment 6, 20 |
| For the FBMS Day 1 Task Order, “Time & Materials” is listed as the contract type. |
Would DOI entertain alternate pricing models such as Firm, Fixed Price? If T&M is required, does the contract type require Cost Accounting Standard (CAS) compliance?
Yes, the Government will consider a firm-fixed-price solution for the FBMS Day 1 task order.
Per 48 CFR 9903.201-1 - CAS Applicability, specifically, subsections (b)(2), negotiated contracts in excess of the Truth in Negotiations Act (TINA) threshold would not be exempt from CAS. However, TINA applies where the Government required cost or pricing data. This acquisition is being conducted in accordance with FAR Parts12, Acquisition of Commercial Items, and 15, Contracting by Negotiation. FAR 15.403-1(c)(3) exempts commercial items from the requirement for cost or pricing data.
Therefore, this is not a CAS covered acquisition.
No
| 124 |
| 14 |
| Attachment 6, 6.5 and J 32 |
| The provisioning interval for resources in Attachment 6 is shown as 72 hours for SAP resources. The provisioning interval listed as a maximum threshold in Attachment 32 is 24 hours. Will the government please clarify this apparent discrepancy? |
| The service levels addressed in Section C.7 and the corresponding service bands in the attachments in Section J are starting points against which an offeror can propose alternatives. |
Section C.7 does establish that specific requirements may be contained in the individual task orders. In the case of the SAP Application Hosting service line, the maximum provisioning period will be 72-hours.
No
| 125 |
| 9-10 |
| Attachment 6, 4.5 Table 5; |
4.6 Table 6
| The compute, RAM and Storage requirements listed in Tables 5 and 6 are significant in scope. Although the overall requirements indicate a multi-tenant cloud environment will the DOI accept proposals that include a private cloud environment? |
| The RFP does not prohibit this as a proposed solution. However, all the requirements listed in Tables 5 and 6, Attachment 6 must be addressed. |
| No |
| 126 |
| 18-21 of 23 & L-7 |
| Attachment 6 - 12.4 - 18.0 Performance Work Statement for SAP Hosting |
| Are the SAP Hosting Technical and SAP Hosting Cost Volumes delivery instructions (date/time, addresses, number of copies, POCs, CD) the same as those identified in Section L.13? Are the page format (…TNR Size 12, single-spaced, double-sided, 81/2 x 11 one inch margins. Tables, charts, and figures may use font size other than 12 as long as it is legible. The page limitation excludes the cover page, table of contents, listing(s) of tables, drawings, and/or exhibits.) the same as L.14.2? |
| Yes the instructions in Section L pertain to the Day 1 task orders unless otherwise specified within the task orders contained in Section J. |
| No |
| 127 |
| All |
| Attachment 6 |
| Will the Government please provide the FBMS D8 high-level/notional timeline and quality gates? |
| No. This information is not required in order to formulate a responsive proposal to the solicitation. |
| No |
| 128 |
| 17 |
| Attachment 6, 11.1(3) |
| What are the current Database sizes? Please breakdown at the product and landscapes level. |
Will DOI release the latest EWA (Early Watch Alert) Report to offerors?
DB usable SAN and total usable SAN (at the OS level) projections are provided by environment and DB instance in the attached Addendum 1 added to Attachment 6. These are projections based on the current FBMS Technical infrastructure. The total SAN requirements associated with a particular vendor proposal may differ.
The latest EWA information is not necessary in order to provide a proposed solution.
Yes, an addendum 1 has been added to Attachment 6.
| 129 |
| 13 of 23 |
| Attachment 6- section 5.8 SAP Certification |
| Will the government allow for an on-ramping period to finalize SAP hosting partner certification? |
| It appears the “on-ramping” language contained in Section H.16 has been misunderstood. The purpose of the on-ramping is to afford the Government an opportunity to initiate an open season to add new contractors to the Basic Contract. This does not pertain to the required SAP certification specified in Attachment 6, Section 5.8. |
However, Attachment 6, Section 5.8 has been changed to remove “…at the time of award.” Also, Section 21.2, Technical Proposal, has been revised to add a sub-section 21.2.1.5 which states, “Demonstrated proof the service provider is a certified SAP hosting partner.”
Yes, change made as stated in the response.
| Attachment 7 |
| Should there be a database? |
| Response will be provided in a forthcoming amendment. |
| Attachment 7 |
| What is the bandwidth for the 1GB per day? |
| This information is not required in order to formulate a responsive proposal to the solicitation. Offeror should include any specific assumptions regarding bandwidth requirements within the submission. |
| No |
| All |
| Attachment 7, Statement of Work for Development and Test: USGS-CIDA Java Sandbox, provides no proposal response instructions or evaluation criteria. |
Can the Government please provide proposal instructions on how the proposal response should be structured and how the proposal response will be evaluated?
The Day 1 task order statement of work was revised to include language regarding instructions and evaluation criteria specific to the task orders in Amendment No. 002.
No
| Attachments 7-11, Enhancements to Service Level Requirements |
| If all attributes of a given Service Portfolio cannot be met exactly as specified, is submission of an alternative service portfolio acceptable? |
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements and to articulate the value of their offering. |
No
| Section J, Attachment 7, J.1, Overview of Task, and J.2, Summary of Anticipated Award |
| Please clarify if Attachment 7 is the Statement of Work for Development and Test Service Line or for the Virtual Machine Hosting Service Line. There are contradictions within the attachment as to which service line this is for. |
| Section J, Attachment 7 has been changed to reflect Development and Test Environment. |
The Task Order intent is to provide a range of Virtual Machines (para J.4 “Resource Demand Summary”, in a non-production environment, with administrative rights and permissions unique to the development environment.
Yes, change made as stated in the response.
| C-2; Attch 8 page 3 |
| Attachment 7 & 8 |
| J.4 – Resource Demand Summary; Attachment 8 Section J.4 – Resource Demand Summary, Sub Section J.4.1 Virtual Machine Configuration and Capacity |
The Resource Demand Summary provided in both Section J’s Attachment 7 and Attachment 8 are identical. Please confirm that this is correct.
| This is correct. The Resource Demand Summary for Attachments 7 and 8 are identical. |
| No |
| J.3 - Section J Attachment 8 |
| Section J, Attachment 8 – Statement of Work for Public Web Hosting: USGS-CIDA Publication Library - J.3 SCOPE AND DESCRIPTION states: |
“A web-based application provides access to citations, electronic publications and publications available through the USGS Store. The application provides a sophisticated search mechanism, as well as thematic, programmatic and temporal approaches to locating and displaying information about publications. Where a publication is available in electronic format, a user may immediately access and download the publication.”
Since there are no Storage Services identified in the J.2 SUMMARY OF ANTICIPATED AWARD, Technical Service Line, or Capacity/Volume, it appears the publications are not moving into the Cloud.
a. How will the Government ensure access, availability, and throughput to the publications adequate enough for the contractor to meet the Service Level Alternatives in J.7 ENHANCEMENTS TO SERVICE LEVEL REQUIREMENTS?
b. Are the publications located in one location or many?
c. What is the file format of the publications?
The data supporting this Task Order will be hosted within a single facility, which initially will be the DOI infrastructure, located at the CIDA facility in Middleton, Wisconsin.
The web host “calling” information has been designed to minimize the communications requirements with the “storing” database.
The file format for the transported information is not required in order to formulate a responsive proposal to the solicitation. Offeror should include any specific assumptions regarding file formats within the submission.
The dialog between the “calling” and “storing” hosts will be completed via the DOI Trusted Internet Connection (TIC).
The DOI retains responsibility for service level impacts based solely upon DOI owned and operated infrastructure, however the contract service provider shall cooperate with the DOI to configure and maintain system infrastructure elements to ensure end-to-end latency is in compliance with IT system and end-user service level commitments, where technically feasible.
No
| Section J, Attachment 8, J.1, Overview of Task, and J.2, Summary of Anticipated Award |
| Please clarify if Attachment 8 is the Statement of Work for Public Web Hosting Service Line or the Virtual Machine Hosting Service Line and Database Hosting Service Line. There are contradictions within the attachment as to which service lines these are for. |
| This Task Order is for Web Hosting. Section J, Attachment 8, J.2 has been changed to reflect Web Hosting in the “Technical Service Line”. Web Hosting is an aggregate requirement that includes other pre-defined service lines; Virtual Machine Hosting and Database Hosting. Proposed solutions shall meet demand requirements identified in Section J.4 “Resource Demand Summary” |
| Yes, change made as stated in the response. |
| 138 |
| All |
| Attachment 8 |
| Attachment 8, Statement of Work for Public Web Hosting: USGS-CIDA Publication Library, provides no proposal response instructions or evaluation criteria. Can the Government please provide proposal instructions on how the proposal response should be structured and how the proposal response will be evaluated? |
| The Day 1 task order statement of work was revised to include language regarding instructions and evaluation criteria specific to the task orders in Amendment No. 002. |
No
| Attachment 8 |
| The category is defined as non-production system although it is public facing. |
| This is correct. The CIDA development process routinely includes testing and collaborative development of applications with external stakeholders via public hosting. |
| No. |
| Attachment 8 |
| Operating Capability: Is File System Space of 3GB, allocated or consumed? |
| It is based upon allocated space. |
| No |
| Attachment 8 |
| If there is an unexpected spike in usage, since we are prohibited from automatically scaling up, are we exempt from not meeting latency requirements in those cases? |
| For this Day 1 task order, the DOI retains responsibility for service level impacts based solely upon unexpected spikes in usage in cases where automated scaling could have reasonably been expected to enable the service provider to meet agreed upon latency requirements. |
If applicable for subsequent task orders any requirements would be handled on an individual task order basis.
No
| Attachment 8 |
| In J.5, there is a reference to a pilot phase. Please explain the duration and scope of the rollout phases. |
| Yes, Section J, Attachment 8, J.5, last sentence of this paragraph has been changed to read as follows: |
“There are no anticipated changes to usage patterns during this task order that would require run time elasticity in either expanding or contracting the computing requirements beyond those described in the day one “operating conditions.
Yes, change made as stated in the response.
| Attachment 8 |
| Instructions state that contractor has the option of providing o/s SW licenses. |
What about other licenses such as Oracle for data base?
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements and to articulate the value of their offering. If the Contractor recommends the option of contractor provided “other licenses”, then identify specific assumptions, constraints and pricing related to these options in the response. |
| No. |
| Attachment 8 |
| In Section J.6.1, states that government will do all the installation and configuration of SW - does that include O/S and Database? |
Will the government transfer and conduct testing of the content?
| Yes, the Government expects to install and configure all software at the level of the virtual machine instance, for this Task Order, including the operating system and any required databases. Additionally, the government will transfer and conduct testing of all content. However, the Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements and to articulate the value of their offering. |
| No. |
| 145 |
| All |
| Attachment 9 |
| Attachment 9, Representative Use Case for Storage Services, provides no proposal response instructions or evaluation criteria. Can the Government please provide proposal instructions on how the proposal response should be structured and how the proposal response will be evaluated? |
| The instructions contained in Section L, and the evaluation criteria as stated in Section M, applies to the Representative Use Cases. This clarification and subsequent RFP change was reflected in Amendment No. 002 |
No
| Attachment 9 |
| Does Portfolio A, B apply to storage class C, D |
| The distribution of storage classes for both Portfolio A and Portfolio B are identical and are identified in Paragraph J.4 Resource and Demand Summary, and apply to all classes of storage: |
From 500 Terabytes to 4.8 Petabytes
| Class A- | 20% |
| Class B- | 40% |
| Class C- | 10% |
| Class D- | 30% |
| No |
| Attachment 9 |
| Is the back-up 100% of the content? Is the back-up included in the storage consumption? Does back-up apply only to storage class A,B |
| The back-up requirement applies to 100% of the primary data and applications hosted by the contractor. |
Current Off-line backup storage consumption is not included in the range of storage capacity identified in paragraph J.4 Resource Demand Summary.
The projected aggregate volumes could include a limited amount of cross-site on-line backup stores.
The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions, which best meets the requirements and recommending the specific solution for each storage class identified in paragraph J.5.1.
No
| Attachment 9 |
| Is the pricing based on Raw or configured storage? |
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements, |
| No. |
| Attachment 9 |
| Is the pricing based on allocated or consumed storage? |
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements, |
| No |
| Attachment 9 |
| What is the minimum order size |
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements, |
| No |
| Attachment 9 |
| What is the consumption demand per year? |
| The range of expected backup storage consumption is described in paragraph J.4 Resource Demand Summary. |
| No |
| Attachment 9 |
| Please clarify the requirements and services required for performing back-up restore and DR/Coop testing? Who is responsible and what is the frequency of the tests? |
| For proposal preparation purposes offerors shall assume that the Government will requests and the Contractor will execute CoOP/DR testing on each system annually. These pre-planned tests will consist of two tests: 1) Interupt access to primary data store to demonstrate fail over to backup data store; 2) Restore system or data store at new hosting location from a backup source. Contractor must demonstrate service levels identified in paragraph J.7 for both tests. |
| Yes, Section L.16 created to capture all Government provided assumptions. |
| 153 |
| 2 |
| Attachment 9, J.5 |
| The Use Case for Storage Services indicates that offerors shall provide the ability to provision storage resources for three additional categories. Please clarify the following: |
(1) What percentage of the 500-4.8 PB will be utilized or is targeted for DCCI-Datacenter Consolidation /Staging/Support? What type of storage service – block, file or object-based storage, will be required for this category? What protocol(s) will be used to access this storage?
(2) What percentage of the 500-4.8 PB will be utilized or is targeted for CoOP/DR-Contingency Support? What type of storage service – block, file or object-based storage, will be required for this category? What protocol(s) will be used to access this storage?
(3) What percentage of the 500-4.8 PB will be utilized or is targeted for Other? What type of storage service – block, file or object-based storage, will be required for this category? What protocol(s) will be used to access this storage?
The volume of services is not required in order to formulate a proposed solution.
The three additional categories (Datacenter Consolidation/Staging/Support, CoOP/DR Contingency Support, and Other) are identified primarily to accommodate internal activity-based cost of service reporting.
To the extent that the type of storage and protocols would be cost or performance drivers, the impact on cost should be specified in the pricing response, and the impact on performance should be specified in the technical response and/or specified within the assumptions section.
No
| 154 |
| 2 |
| Attachment 9, J.4 Transport Volume per Month |
| Can DOI clarify if the transportation of inbound and outbound volumes per month is to be accomplished by encrypted tape transportation services and, if so, how frequently? |
| The volume of inbound and outbound transport volumes is not required in order to formulate a proposed solution. |
For proposal preparation purposes assume the primary mode of transport for DOI is over the network via Trusted Internet Connection (TIC). Bulk Transfer via tape or other media is anticipated for service initiation for large data stores, restoration services for IT Systems when not available at the commercial hosting facility, and migration of data and systems between portfolio service providers.
Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements with regards to transfer of information via physical media. This may include describing break-points for a wide range of volumes in the pricing response. (See Section C.6.2.2.1) Yes, Section L.16 created to capture all Government provided assumptions.
| 155 |
| 3 |
| Attachment 9, J.7.8 |
| Can DOI clarify if the additional bulk transfer throughput is in addition to the volume per month mentioned in Attachment 9, Section J.4 or the aggregate amount expected to be supported by the cloud? |
Is an encrypted tape transportation solution option available and, if so, how frequently?
The volume of inbound and outbound transport volumes is not required in order to formulate a proposed solution.
For proposal preparation purposes assume the following: The primary mode of transport for DOI is over the network via Trusted Internet Connection. Bulk Transfer via tape or other media is anticipated for service initiation for large data stores, restoration services for IT Systems when not available at the commercial hosting facility, and migration of data and systems between portfolio service providers.
The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements with regards to transfer of information via physical media. This may include describing break-points for a wide range of volumes in the pricing response. (See Section C.6.2.2.1) Yes, Section L.16 created to capture all Government provided assumptions.
| 156 |
| 2 Table 1 |
| Attachment 9, Proposed Storage Class/Tiers |
| Can the DOI define the throughput requirements between the Primary and DR datacenters? |
| The volume of transport volumes between the primary and DR data centers is not required in order to formulate a proposed solution. |
The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements with regards to transfer of information between primary and DR data centers. This may include describing break-points for a wide range of transport volumes in the pricing response.
No
| 157 |
| 2 |
| Attachment 9, Table1 |
| Storage Class A and B stated a need for 100% uptime/availability. |
Does this refer to the multi-path connection between host and storage controller only – or does this imply that all data stored in Class A and Class B require a complete replica that is constantly in-sync and online?
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements. This includes the determination of “how” the solution is architected to ensure that service levels can and will be met. |
| No |
| 158 |
| 1 |
| Attachment 9 |
| Is the storage limit per request or will DOI not approve any storage requests in excess of 5 Petabytes? |
| The projected consumption volumes, resources, service levels and optional features for each service line in paragraph J.4 of this attachment are provided for proposal preparation and evaluation purposes only. These volumes represent an aggregate requirement. |
Specific ranges of storage and transport volumes will be identified in the individual task orders.
No
| 159 |
| 1 |
| Attachment 9 |
| Is the 5 Petabyte limit inclusive of online and offline storage? |
| Current Off-line backup storage consumption is not included in the range of storage capacity identified in paragraph J.4 Resource Demand Summary. |
The projected aggregate volumes could include a limited amount of cross-site on-line backup stores.
No
| 160 |
| 2 |
| Attachment 9, J.5 |
| Do the references to DCCI-Data Center Consolidation Staging/Support / Data Center Consolidation Transition Support Requirements indicate that the data will be moved to another location after the staging is complete? |
| This category indicates all data staging and storage directly related to Data Center Consolidation requirements. This includes, but is not limited to: Data and Applications that will be moved to another location after staging; and/or temporary staging and storage to enable reconfiguration and optimization of the site of origin, and then return to the site of origin. |
| No |
| 161 |
| 3 |
| Attachment 9, J.7 |
| How does Service Portfolio A combine with Storage Class A or B since these have different Availability service levels defined? |
| The uptime/availability requirements identified under Storage Classes apply to the design, specifications and architecture for the contractor storage infrastructure and connection to contractor hosted systems. The uptime/availability requirements identified for Portfolio A and Portfolio B in paragraph J.7.1 refer to overall Solution Uptime and Availability (cross reference section C, paragraph C.7.3) which includes external availability via the internet and Trusted Internet Connections. |
| No |
| Attach 9 (J.4 & J.6) |
| This use case provides storage capacity range, which is further quantified by storage class as a percentage. How should the Offeror apply the percentage against a range? |
What quantities are should be used for each evaluated contract year to arrive at an evaluated price for this service area?
What are the specific scenarios intended for evaluation purposes and will the Government provide these quantities on a monthly or annual basis?
Will the Government provide evaluated quantities for each service level alternative?
The specific volume of storage capacity by class of service is not required in order to prepare a proposed solution.
The range of storage volumes were provided only to establish the scope and context for the offeror to propose appropriate “per unit of service” price breaks appropriate to their business model. Therefore, no additional scenario information is necessary nor will be provided, and no evaluated quantities are required in order to prepare a proposed solution.
No
| Attach 9; J.8.1 |
| The use case references a “Government Community Cloud” for meeting resource segregation. If a public offering is A&A’ed as moderate, is the public option acceptable as an alternative to a Government Community Cloud? |
| Response will be provided in a forthcoming amendment. |
| 164 |
| 2 |
| Attachment 10, J.4 |
| Government asks for annual declining prices. |
a. Is the minimum guaranteed consumption per year the lower number shown in the “range of the concurrent Virtual Machines” table?
b. Do we need to provide prices for lower consumption than listed in the schedule?
The projected consumption volumes, resources, service levels and optional features for each service line in paragraph J.4 of this attachment are provided for proposal preparation and evaluation purposes only. The government makes no representations regarding minimum guaranteed consumption per year.
The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements. This would include identifying any assumptions and volume requirements that would be associated projecting declining prices.
No
| 165 |
| 3 |
| Attachment 10, J-5.1 |
| Is the High Compute Cluster considered to be a single VM? |
| The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP. Therefore, it is up to the vendor to identify and propose their solutions which best meet the requirements. |
| No |
| Attachment 10, J.7 |
| In the table, line J.7.12, it appears that the values for portfolio A and B are reversed. Is this correct? |
The table appears in all of the Task Orders.
| Correct, the values for portfolio A and B were inadvertently reversed. All representative use cases, Attachment 9 through 11, are revised to reverse the values between portfolio A and B. |
| Yes, change made as stated in the response. |
| Attachment 10 |
| How would the government evaluate rates of consumption that vary by the unit of time (e.g. hour, day, month)? |
For example, to equalize an hourly rate to a day rate, would the government multiply the hourly rate by 24?
The government will evaluate rates of consumption based on the fixed price per unit of service as it correlates to the proposed technical solution.
No
| Attachment 10, Instructions |
| a. How would the government evaluate the cost of the licenses brought by the contractor if one contractor did not supply prices? |
b. Do we need to incorporate the cost of installation into the license costs?
The Government desires the most cost effective, best value proposed solution for each service of the technical service lines defined within the RFP.
When evaluating pricing, the government will consider the total cost of service for the government for the services offered.
Per Section M.4.4.3, Price/Cost Evaluation, the Government may conduct a sensitivity analysis. This analysis may be used to identify and analyze the overall costs associated with any life cycle expenses the Government would potentially incur as they relate to the proposed solutions.
The Government reserves the right to make any adjustment in costs, for evaluation purposes, in order to assess the overall cost to the Government depending on the outcome of the sensitivity analysis based on the proposed solution. This would include any costs, not included in the vendor’s proposal that the Government may incur, based on the proposed solution.
No
| 169 |
| All |
| Attachment 10 |
| Attachment 10, Representative Use Case for Virtual Machine Hosting Services, provides no proposal response instructions or evaluation criteria. |
Can the Government please provide proposal instructions on how the proposal response should be structured and how the proposal response will be evaluated?
The instructions contained in Section L, and the evaluation criteria as stated in Section M, applies to the Representative Use Cases. This clarification and subsequent RFP change was reflected in Amendment No. 002
No
| 170 |
| 3 |