About this file

This is a Quality Assurance Surveillance Plan (QASP) document for a VA contract at the Louis Stokes Cleveland VA Medical Center. The document serves as a living template that establishes systematic methods for evaluating contractor performance against specified standards and acceptable quality levels (AQLs).

The QASP identifies key government personnel responsible for oversight: Contracting Officer Angela Higgins (NCO 10) and Contracting Officer's Representative India Brown (Louis Stokes Cleveland VA Medical Center). The plan establishes nine primary performance measures with corresponding surveillance methods and AQLs: Housing Facilities & Management (100% compliance via random VA inspection), Personnel (100% compliance via periodic inspection), Records and Reports (100% compliance via periodic inspection), Mandatory Training (100% compliance via periodic sampling), Housing Placement (100% compliance monitoring 55% of exits via record reviews), Therapeutic Services (95% compliance via periodic sampling), Staffing (95% compliance via periodic sampling), Documentation (95% compliance via periodic sampling), and Meals (95% compliance via periodic sampling). Performance ratings utilize a five-tier CPARS system: Exceptional, Very Good, Satisfactory, Marginal, and Unsatisfactory. The document includes procedures for documenting performance deficiencies through Contract Discrepancy Reports (CDRs), which require contractor acknowledgment and corrective action plans when performance falls below acceptable levels. The COR provides quarterly progress reports to the CO, and all performance documentation may be used to establish past performance ratings under CPARS.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quality Assurance Surveillance Plan (QASP)

The contractor will be evaluated in accordance with the following:

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:

• What will be monitored?

• How will monitoring take place?

• Who will conduct the monitoring?

• How will monitoring efforts and results be documented?

This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.

This QASP is a “living document” and the Government may review and revise it on a regular basis.

However, the Government shall coordinate changes with the contractor through contract modification.

Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.

2. GOVERNMENT ROLES AND RESPONSIBILITIES

The following personnel shall oversee and coordinate surveillance activities.

a. Contracting Officer (CO) – The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.

Assigned CO: Angela Higgins

Organization or Agency: NCO 10

b. Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance.

The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.

Assigned COR: India Brown

Organization or Agency: Louis Stokes Cleveland VA Medical Center

3. CONTRACTOR REPRESENTATIVES

The following employee(s) of the contractor serve as the contractor’s program manager(s) for this contract.

Primary:

4. PERFORMANCE STANDARDS

The contractor is responsible for performance of ALL terms and conditions of the contract. CORs will provide contract progress reports quarterly to the CO reflecting performance on this plan and all other aspects of the resultant contract. The performance standards outlined in this QASP shall be used to determine the level of contractor performance in the elements defined. Performance standards define desired services. The Government performs surveillance to determine the level of Contractor performance to these standards.

The Performance Requirements are listed below in Section 6. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the standard and assign a rating. At the end of the performance period, these ratings will be used, in part, to establish the past performance of the contractor on the contract.

5. METHODS OF QA SURVEILLANCE

Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.

a. DIRECT OBSERVATION. 100% surveillance:

b. PERIODIC INSPECTION. Inspections scheduled and reported quarterly per COR delegation or as needed.

c. VALIDATED USER/CUSTOMER COMPLAINTS. If this method is used, explain how data will be collected and reported.

d. RANDOM SAMPLING. If this method is used, define what and how often it will be sampled.

e. VERIFICATION AND/OR DOCUMENTATION PROVIDED BY CONTRACTOR. Review PWS and if this method of surveillance is selected, define how documentation will be verified and how assessment will be conducted.

6. QASP PERFORMANCE REPORT DATE: __________________

Measures PWS Reference

Performance Requirement

Standard Acceptable Quality Level

Surveillance Method

Met AQL/DID

NOT MEET

AQL-

CPARS

RATING/ADD

COMMENTS

1-Housing Facilities & Management

1 - I Facility meets fire, safety, ADA, licensure and veteran privacy and additional safety for female veterans.

Passing facility inspection and documentation of meeting the performance standards.

100% of the time Random VA team Inspection of records.

2- Personnel 1 - II Full-time administrative staff on duty and sufficient case management personnel; evidence of site supervision;

coordinated case management

Passing random inspection and documentation of meeting the performance standards

100% of the time Random Periodic Inspection

3 – Records and Reports

1 - III Daily sign-in sheets signed by veterans.

Passing random inspection and documentation of meeting the performance standards

100% of the time Random Periodic Inspection

Revision 04/01/2025

4 – Mandatory Training

1 - IV Contractor shall complete all required training on time per VAMC policy

All training required is completed on time by contractor employees

100% compliance

Periodic Sampling

5 – Housing Placement

1 - V Monitors 55% of exits to permanent housing. Negative exits will not be greater than 20%.

Passing random inspection and documentation of meeting the performance standards.

100% compliance of monitoring 55% of exits

Random Record Reviews

6 – Therapeutic Services

1 - VI Therapeutic Services provided by contractor to include group therapy, social skills training, vocational counseling

Passing random inspection 95% of the time Periodic Sampling

7 - Staffing 1 - VII Sufficient staff in number and position qualifications to carry out the policies and responsibilities of the facility

Passing periodic inspection 95% of the time Periodic Sampling

8 - Documentation 1 - VIII The contractor shall maintain individual case records on each veteran.

Passing periodic inspection 95% of the time Periodic Sampling

9 - Meals 1 - IX At least three meals to be served daily with not more than a 14-hour span between evening meal and breakfast

Passing periodic inspection 95% of the time Periodic Sampling

7. CPARS RATINGS ASSIGNED TO QASP ITEMS:

Metrics and methods are designed to determine rating for a given standard and acceptable quality level.

The following ratings shall be used (Reference: CPARS User Manual https://www.cpars.gov/documents/CPARS-Guidance.pdf)

EXCEPTIONAL: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT. However, a singular event could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

VERY GOOD:

Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.

SATISFACTORY:

Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract. Also, there should have been NO significant weaknesses identified.

MARGINAL:

Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Note: To justify Marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g. Management, Quality, Safety or Environmental Deficiency Report or letter).

https://www.cpars.gov/documents/CPARS-Guidance.pdf https://www.cpars.gov/documents/CPARS-Guidance.pdf

UNSATISFACTORY

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Note: To justify an Unsatisfactory rating, you should identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety or Environmental Deficiency Reports, or letters).

8. DOCUMENTING PERFORMANCE

a. The VA shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS).

b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This shall normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and place it in the contract file. When the COR and the CO determines formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR), and present it to CO. The CO shall in turn review and shall present to the contractor's program manager for corrective action.

The contractor shall acknowledge receipt of the CDR in writing. The CDR shall specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR shall also state how long after receipt the contractor has to present this corrective action plan to the CO. The VA shall review the contractor's corrective action plan to determine acceptability. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance and the acceptability of the Contractor’s corrective action plan.

Any CDRs may become a part of the supporting documentation for any contractual action deemed necessary by the CO. See Sample on following page.

9. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP

SIGNED:

India Brown, Social Worker ____

COR NAME/TITLE DATE

SIGNED:

CONTRACTOR NAME/TITLE DATE

CONTRACT DISCREPANCY REPORT

1. CONTRACT NUMBER 2. REPORT NUMBER FOR THIS

DISCREPANCY

3. TO: (Contracting Officer) 4. FROM: (Name of COR)

5. DATES

a. CDR PREPARED

b. RETURNED BY

CONTRACTOR:

c. ACTION COMPLETE

6. DISCREPANCY OR PROBLEM (Describe in detail. Include reference to PWS Directive; attach continuation sheet if necessary.)

7. SIGNATURE OF COR Date:

8. SIGNATURE OF CONTRACTING OFFICER Date:

9a. TO (Contracting Officer) 9a. FROM (Contractor)

10. CONTRACTOR RESPONSE AS TO CAUSE, CORRECTIVE ACTION AND

ACTIONS TO PREVENT RECURRENCE. (Cite applicable quality control program procedures or new procedures. Attach continuation sheet(s) if necessary.)

11. SIGNATURE OF CONTRACTOR REPRESENTATIVE Date:

12. GOVERNMENT EVALUATION. (Acceptance, partial acceptance, reflection. Attach continuation sheet(s) if necessary.)

13. GOVERNMENT ACTIONS (Acceptance, partial acceptance, reflection. Attach continuation sheet(s) if necessary.)

14. CLOSE OUT

NAME TITLE SIGNATURE DATE

a. CONTRACTOR

NOTIFIED

b. COR c.

CONTRACTING

OFFICER

Quality Assurance Surveillance Plan (QASP)
1. PURPOSE
2. GOVERNMENT ROLES AND RESPONSIBILITIES
3. CONTRACTOR REPRESENTATIVES
Quality Assurance Surveillance Plan (QASP)
5. METHODS OF QA SURVEILLANCE
6. QASP PERFORMANCE REPORT DATE: __________________
8. DOCUMENTING PERFORMANCE
9. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP