This document is an eleventh amendment to a contract between the Arizona Department of Economic Security and Yuma Community Food Bank for the Hunger Relief Program, specifically The Emergency Food Assistance Program (TEFAP). The contract amendment modifies the Itemized Service Budget for the period of July 1, 2023, through June 30, 2024, and involves multiple funding streams including TEFAP Admin, TEFAP American Rescue Plan Act (ARPA), and various Commodity Credit Corporation (CCC) Phase allocations.
The total contract reimbursement ceiling is revised from $388,892.93 to $400,892.93, with specific funding allocations across different program components. These include $2,567.25 for One-Time Additional Admin funding, $198,496.22 for TEFAP Admin reimbursement, $83,050.00 for ARPA, $27,500.00 for CCC Phase 2, $11,250.00 for CCC Phase 3, a new $12,000.00 for CCC Phase 4 (covering October 1, 2023 through June 30, 2024), and $66,029.46 for the TEFAP Reach and Resiliency Grant Round 2. The budget details personnel costs, with various positions allocated across different funding sources, and includes provisions for employee-related expenses, occupancy, materials, and supplies.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT AMENDMENT
Arizona Department of Economic Security
1789 W Jefferson Street, Mail Drop 1541, Phoenix, AZ 85007
CONTRACT NUMBER: AMENDMENT NUMBER:
CTR053771 Eleven (11)
DESCRIPTION/ LABEL: Hunger Relief Program – The Emergency Food Assistance Program (TEFAP)
CONTRACTOR NAME: Yuma Community Food Bank
THE ABOVE REFERENCED CONTRACT IS HEREBY MODIFIED AS FOLLOWS:
In accordance with the Special Terms and Conditions, Section 25, Levels of Service, the purpose of this amendment is to revise the Itemized Service Budget for the period of July 1, 2023, through June 30, 2024. The total contract reimbursement ceiling for the period of July 1, 2023 through June 30, 2024 is revised from $388,892.93 to $400,892.93. The funding allocations are as follows:
• The Emergency Food Assistance Program (TEFAP) One-Time Additional Admin funding for the period of July 1, 2023 to September 30, 2023 remains $2,567.25.
• TEFAP Admin reimbursement ceiling for the period of July 1, 2023 through June 30, 2024 remained
$198,496.22.
• TEFAP American Rescue Plan Act (ARPA) reimbursement ceiling for the period of July 1, 2023 through
June 30, 2024 remains $83,050.00.
• TEFAP Commodity Credit Corporation (CCC) Phase 2 reimbursement ceiling for the period of July
1, 2023 through June 30, 2024 remains $27,500.00.
• TEFAP Commodity Credit Corporation (CCC) Phase 3 reimbursement ceiling for the period of July
1, 2023 through June 30, 2024 remains $11,250.00.
• TEFAP Commodity Credit Corporation (CCC) Phase 4 reimbursement ceiling is being added for the period of October 1, 2023 through June 30, 2024 in the amount of $12,000.00.
• TEFAP Reach and Resiliency Grant Round 2 reimbursement ceiling for the period of July 1, 2023 through June 30, 2024 remains $66,029.46.
The Itemized Service Budget is attached as part of this amendment.
ALL OTHER REQUIREMENTS, SPECIFICATIONS, AND TERMS AND CONDITIONS REMAIN UNCHANGED
ACKNOWLEDGEMENT AND AUTHORIZATION
This Amendment shall be fully executed by means of electronic approval in APP.
based on %
2,567.25$ 198,496.22$ 83,050.00$ 27,500.00$ 11,250.00$ 12,000.00$ 66,029.46$ 400,892.93$
7/1/23 to 09/30/23 7/1/23 to 6/30/24 7/1/23 to 6/30/24 7/1/23 to 6/30/24 7/1/23 to 6/30/24 10/1/23 to 6/30/24 7/1/23 to 6/30/24
*MUST SPEND
$2567.25 BY 09/30/23
*MUST SPEND
$40,235.58 BY
09/30/23
1. Personnel SFY24 SFY24 SFY24 SFY24 SFY24 SFY24 SFY24
# Pos FTE Position Total Service
Cost
DES %
TEFAP One-Time Additional Admin
TEFAP Admin TEFAP ARPA
TEFAP CCC
Phase 2
TEFAP CCC
Phase 3
TEFAP CCC
Phase 4 TEFAP Reach &
Resiliency R2 TOTAL DES Cost
1 0.2 President/CEO 20,756.40 20% 3,600.00 3,600.00
1 0.3 COO 22,239.00 30% 5,000.00 5,000.00 10,000.00
1 0.5 Warehouse & Production Manager 21,921.30 45% 12,000.00 12,000.00 1 0.2 Accounting Manager 13,904.67 20% 4,800.00 4,800.00 1 0.9 Driver 32,115.66 90% 605.75$ 19,232.00 3,000.00 22,232.00 1 0.9 Driver 34,137.75 90% 605.75$ 19,232.00 3,000.00 22,232.00 1 0.9 Driver 32,115.66 90% 605.75$ 19,232.00 3,000.00 22,232.00 1 0.9 Driver, Lead 38,162.12 90% 750.00$ 20,000.22 3,000.00 23,000.22 1 0.7 Government Program Specialist 23,223.28 65% 8,000.00 10,000.00 18,000.00 1 0.7 Government Program Specialist 19,328.87 65% 8,000.00 10,000.00 18,000.00 1 0.2 Admin Assistant & Data Manager 9,531.00 20% 2,400.00 2,400.00 1 0.9 Volunteer Coordinator 19,031.50 90% 6,000.00 6,000.00 1 0.3 Warehouse Supervisor 11,894.69 30% 3,000.00 3,000.00 1 0.7 Operations Assistant 22,908.29 65% 6,000.00 6,000.00 1 0.9 Warehouse Associate 25,771.82 90% 20,000.00 20,000.00 1 0.8 Agency and Programs Manager 29,652.00 80% 22,000.00 10,000.00 32,000.00 1 0.9 La Paz Staff - Parker 11,437.20 90% 10,000.00 20,000.00 30,000.00 1 0.9 La Paz Staff - Wendon 10,484.10 90% 10,000.00 10,000.00 1 0 Food Sourcer - 0% - 1 0 Fundraiser - 0% -
1. Personnel - Salaries Total 398,615.31 2,567.25 198,496.22 0.00 0.00 0.00 12,000.00 55,000.00 268,063.47
2. Employee Related Expense (E.R.E.) - payroll taxes and benefits 53,932.59 - - ERE Total 53,932.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
Salaries and ERE Total 452,547.90 2567.25 198,496.22 - - - 12,000.00 55,000.00 396,992.44
3. Professional & Outside Service
Professional & Outside Service Total 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 -
4. Travel
Travel Total 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 -
5. Occupancy
Occupancy Total 0.00 0.00 - 25,000.00 0.00 0.00 0.00 0.00 25,000.00
6. Equipment
Equipment Total 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 -
7. Materials & Supplies
Materials & Supplies Total 0.00 - 0.00 58,050.00 0.00 0.00 0.00 0.00 58,050.00
8. Operating Services
Operating Services Total 0.00 0.00 0.00 0.00 27,500.00 11,250.00 0.00 11,029.46 49,779.46
Direct Costs 452,547.90 2,567.25 198,496.22 83,050.00 27,500.00 11,250.00 12,000.00 66,029.46 400,892.93
9. Indirect Cost 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
Total Service Costs/CSA Total Cost: 452,547.90 2,567.25$ 198,496.22$ 83,050.00$ 27,500.00$ 11,250.00$ 12,000.00$ 66,029.46$ 400,892.93$
Contract Period
State Fiscal Year
Total Funding Allocation
Special Instructions:
Yuma Community Food Bank Itemized Service Budget
Service: TEFAP CCC Phase 4 Contract # CTR053771
Contract Period: 7/1/2023 to 6/30/2024