CSA 70 BL Electrical Svc Line and Flow Meter Install - Section E - Special Conditions.pdf

PDF 268 KB Posted

Attached to
Request for Bids - CSA 70BL Electrical Service Line and Flow Meter Installation Project
Solicitation number
SPD126-SANIT-6304
Issued by
San Bernardino County, California

About this file

This is a Special Conditions document for a contract opportunity involving County Service Area (CSA) 70 BL in Bloomington, California, under the jurisdiction of San Bernardino County. The project involves electrical service line and flow meter installation work at 18694 Valley Boulevard, Bloomington, including installation of an electrical service meter, cabinet, handhole, trench, conduit, electrical service line, pavement, sidewalk and manhole repairs, and installation of a District-owned Flo-Dar meter liquid level monitoring device with subsequent testing. The contractor is required to attend a pre-construction conference with major subcontractors prior to beginning construction, which will be scheduled shortly after contract execution. The contractor must provide a field superintendent on-site during all construction activities and supply a 24-hour emergency phone number prior to construction commencement. Written notification of impending work must be provided to the Project Manager at least seven days prior to beginning construction. All work must comply with plans, specifications, and bid documents, with daily completion requirements including backfilling and securing trenches, placement of concrete, site cleanup, traffic control, signage, and barricades.

Key requirements include that the contractor assumes sole responsibility for jobsite safety and must comply with California Occupational Safety and Health Program (CAL/OSHA) standards, maintain a complete copy of California Administrative Code Title 8, and employ a safety officer thoroughly familiar with safety orders. The contractor must obtain all necessary permits at its own expense, including permits from San Bernardino County Department of Public Works, State of California Department of Transportation (Caltrans) District 8, and the State of California Department of Industrial Safety for excavation. All underground utilities must be identified through Underground Service Alert (1-800-227-2600 or 811) at least 48 hours prior to construction, with exploratory excavation (potholing) required at least ten days before ordering materials. The contractor is responsible for all water supply for construction, dust control, testing, and cleanup, with strict adherence to environmental measures including fugitive dust controls consistent with South Coast Air Quality Management District Rule 403. A Supplemental Work at Force Account is included for unforeseen utility conflicts, subsurface conditions, or latent physical conditions differing materially from contract indications, with unused amounts not payable at project closeout.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION E

SPECIAL CONDITIONS

CSA 70 BL ELECTRICAL SERVICE LINE

AND FLOW METER INSTALLATION

PROJECT

FOR

COUNTY SERVICE AREA (CSA) 70 BL

BLOOMINGTON, CALIFORNIA

PROJECT NO.: 30.30.0215

AND FLOW METER INSTALLATION PROJECT

TABLE OF CONTENTS

Special Conditions Page

1. The Requirement............................................................................................... SC-1

2. Location of Contract Work Site ....................................................................... SC-1

3. Job Site Safety................................................................................................... SC-1

4. Miscellaneous Special Conditions ................................................................... SC-2

5. Sanitary Facilities.............................................................................................. SC-2

6. Permits, Certificates, Laws, and Ordinances ................................................... SC-2

7. Construction Water .......................................................................................... SC-3

8. Trash and Debris Removal ............................................................................... SC-3

9. Plan Set ............................................................................................................ SC-4

10. Notifications ..................................................................................................... SC-4

11. Compliance with Contract Documents ............................................................ SC-4

12. Survey Monuments and Benchmarks .............................................................. SC-4

13. Emergency Vehicle and Response Access ...................................................... SC-4

14. Data to be Submitted by Contractor ................................................................. SC-4

15. Existing Underground Utilities…… ................................................................. SC-5

16. Exploratory Excavation (Potholing) ................................................................ SC-6

17. Landscaping………………………. ................................................................. SC-6

18. Remove Concrete ………………….................................................................. SC-7

19. Excavation, Bedding, and Backfill ................................................................. .. SC-7

20. Excess Excavated Materials ........................................................................... SC-7

21. Restoration....................................................................................................... SC-7

22. Local Conditions............................................................................................. SC-8

23. General Environmental Measures.................................................................... SC-9

24. Supplemental Work At Force Account (Unforeseen Subgrade, Stablization, Agency Mitigation Requirements) .............................................. SC-9

SC - i

FOR

AND FLOW METER INSTALLATION PROJECT

1. THE REQUIREMENT

The work includes, but is not limited to, providing all necessary supervision, labor, equipment, materials, and tools to satisfactorily perform the work of installing electrical service meter, cabinet, handhole, trench, conduit, electrical service line, pavement, sidewalk and manhole repairs and installation of District owned Flo-Dar meter liquid level monitoring device and subsequent testing. Work to be performed in accordance with plans, specifications, and bid documents.

2. LOCATION OF CONTRACT WORK SITE

The contract work site is located on 18694 Valley Boulevard, Bloomington, San Bernardino

County, State of California.

3. JOB SITE SAFETY

a. Responsibility

Jobsite safety is the sole exclusive responsibility of the Contractor. This responsibility covers his/her own work force, all subcontractors, visiting personnel and officials, and the public which may have access to the jobsite. The Contractor shall exercise complete control over who has access to the jobsite to ensure jobsite safety. The Owner does not assume any responsibility for job site safety expressed or implied. The Owner relies on the experience, knowledge, and innovative skills of the Contractor to deliver the most effective construction system to the Owner in a safe and responsible manner.

The Contractor acknowledges responsibility for jobsite safety and acknowledges that the Owner will not have such responsibility.

b. Construction Safety Orders

Construction of this project must comply with all safety orders of the California Occupational

Safety and Health Program (CAL/OSHA) as published by the Department of Industrial Relations.

The Contractor’s safety officer shall maintain at the jobsite a complete copy of the California

Administrative Code, Title 8 – Industrial Relations, latest edition.

When applicable, the Contractor’s operation shall also comply with General Industry Safety

Orders.

The jobsite safety officer shall be thoroughly familiar with the safety orders and shall so instruct, inform, or notify all personnel on the jobsite to ensure safety at all times. The safety officer shall also be responsible for all record keeping and reporting requirements, specified in Record

Keeping and Reporting Requirements Under the California

c. Occupational Safety and Health Act, available from the California Division of Labor

Statistics and Research.

The Contractor shall comply with the accident prevention program which includes instructions to workers in safe working practices as well as scheduled periodic safety inspection of all work areas on the jobsite.

Contractor shall provide and perform necessary traffic control during periods of road and street impacts while engaged in his/her operations. Sufficient signage, message boards, detour signs and flagmen will be employed during any impacts. Contractor will use the current California

Manual of Uniform Traffic Control Devices (MUTCD), Caltrans Traffic Control Standards and any approved traffic control plan. Traffic Control Plan, when prepared, shall be submitted for review at least 4 weeks prior to the expected issuance of permit. A comprehensive traffic control plan, showing detour routes and sign locations, etc., signed by a Registered Civil or

Traffic Engineer must be submitted by the permittee (Contractor) to be reviewed and approved by the Traffic Division of the San Bernardino County Department of Public Works for traffic control implementation and compliance. Temporary DAILY road closures may be allowed provided proper detours are provided and residents receive at least 72 hours prior notification.

All impacted roads will be made available immediately to any emergency vehicle traffic if warranted. Road closures will be opened at the end of each day and made safe for residents to include any transition ramping, steel plating for open trenches, etc. Contractor at all times

(within reason) will work with the residents regarding property ingress and egress.

4. MISCELLANEOUS SPECIAL CONDITIONS

a. Pre-Construction Conference

The Contractor, together with his/her major subcontractors, will be required to attend a pre-construction conference prior to beginning construction. The Owner will set up this conference shortly after execution of the contract.

b. Contractor’s Field Superintendent

The Contractor shall be required to have a field superintendent, from his/her organization, on the jobsite during construction activities, to receive directions or instruction from the Owner or Engineer. Contractor shall provide the Owner with a 24-hour emergency phone number for field superintendent prior to beginning of construction.

c. Final Inspection

The Contractor shall schedule a final inspection with the appropriate District staff to ensure that all work as identified in these documents are completed to the satisfaction to the District.

5. SANITARY FACILITIES

Contractor shall supply appropriate and in sufficient number, temporary sanitary facilities for his/her workmen to use during the course of the project, Contractor shall be responsible for the regular maintenance, cleaning and pumping of such facility(ies).

6. PERMITS, CERTIFICATES, LAWS, AND ORDINANCES

Contractor shall, at his/her own expense, procure all permits, certificates and licenses required of him by law for the execution of the work. Contractor shall comply with all Federal, State, and local laws, ordinances or rules and regulations relating to the performance of said work. The following agencies have jurisdiction with the project.

A. San Bernardino County Department of Public Works

In the event of any conflict between the Contract Documents and the San Bernardino

County Department of Public Works encroachment permit requirements, the most stringent requirement shall prevail. All permit requirements shall be satisfied by

Contractor and accepted by the District and Owner before the project is accepted and a

Notice of Completion is recorded.

B. State of California Department of Transportation Permit (Caltrans)

District shall obtain an encroachment permit from the State of California Department of

Transportation (Caltrans) District 8 and Contractor shall obtain a rider to that permit and shall comply with all the requirements of same. Prior to construction, Contractor shall submit a copy of the encroachment permit rider to Owner.

C. State of California Department of Industrial Safety Excavation Permit

Contractor shall obtain an excavation permit from the State of California Department of

Industrial Safety and shall comply with the requirements of same. Prior to construction, Contractor shall submit a copy of the excavation permit to Owner.

D. General

Contractor shall, at his/her own expense, procure any additional permits, certificates, and/or licenses required of him/her by law for the execution of the work, including all permits required for storm water pollution control. He/she shall comply with all federal, state, and local laws, ordinance, and/or rules and regulations relating to the performance of said work.

All the permit requirements shall be satisfied by Contractor and accepted by all issuing agencies and Owner before a notice of completion will be recorded for the project. In the event of conflict between said permit requirements and the other contract documents, the most stringent requirements shall prevail.

7. CONSTRUCTION WATER

Water for the work, dust control, testing, cleaning, curing, and compaction or as required will be furnished by the Contractor, and will adhere to all regulations of appropriate Water and Fire agencies for the usage, disposal and connection to fire hydrants or standpipes. Contractor shall control water run-off and comply with NPDES discharge requirements.

8. TRASH AND DEBRIS REMOVAL

Contractor shall be responsible in removing and hauling off all trash and/or debris created by him during the construction process. Debris materials (trash, washed out or over spilled concrete, material spoils, etc.) shall be hauled off and disposed of in a manner acceptable and to approved facilities that will dispose of those materials.

9. PLAN SET

Contractor will not contact the design engineer directly unless instructed to by the Project or

District Manager. All RFI’s and clarifications will be submitted to the District’s Project Manager who will route through the engineer as required.

Contractor will maintain a field “as-built” set and will turn a legible copy of the “as- builts” over to the Project Manager at the conclusion of the project. As-builts will document any deviations to include accurate dimensions and locations of any work not accomplished per plans. Any deviations to the plans must first receive Project Manager review and District approval as stated in the General Conditions.

10. NOTIFICATIONS

Contractor shall provide written notification to Project Manager of the work of impending work at least seven (7) days prior to beginning construction. Said notices shall first be approved by

Project Manager and shall contain a general description of the work, dates work will be performed, descriptions of areas where travel and parking will be restricted, and access roads which will be closed to through traffic or where traffic will be restricted. Contractor shall maintain, as a minimum, one (1) access location to each treatment facility at all times.

11. COMPLIANCE WITH CONTRACT DOCUMENTS

Contractor shall comply with the Contract Documents, including timely completion of work each day, backfilling and securing trenches each day, placement of concrete, work site cleanup, control of traffic, placement of signs, placement of barricades, and use of flashing lights. If

Contractor does not comply with the Contract Documents, then Owner shall provide the required labor, materials, and equipment to perform same and shall deduct the cost from monies otherwise due Contractor under the contract.

12. SURVEY MONUMENTS AND BENCHMARKS

The Contractor shall not disturb existing survey monuments or benchmarks. Contractor shall locate, mark, reference and prepare a Corner Record prior to construction, for all monuments that might be disturbed pursuant to Business and Professions Code, Sections 8700 to 8805 of the Land

Surveyor's Act, specifically Section 8771(b). Contractor shall notify Owner at least 72 hours prior to working near any monuments or benchmarks. Should these monuments be destroyed or disturbed, Contractor shall have a Licensed Land Surveyor registered in the State of California reset the monuments and file a Corner Record or a Record of Survey with the County Surveyor prior to Owner recording a Certificate of Completion for the project.

13. EMERGENCY VEHICLE AND RESPONSE ACCESS

Access for emergency vehicle response shall be provided as required throughout the project. All conditions imposed by emergency agencies (police, fire, or ambulance) due to access limitations shall be the responsibility of the Contractor, including costs of same.

14. DATA TO BE SUBMITTED BY CONTRACTOR

Contractor shall furnish Owner the following data and said data shall be approved by Owner prior to ordering materials. Data (two copies) shall be submitted to Owner for approval. Contractor shall then submit three copies of all approved data to Owner for use during construction.

A. All data required by the Contract Documents including but not limited to trench protection, construction schedule, encroachment and excavation permits, and emergency telephone numbers.

B. Site specific Injury and Illness Prevention Plan, Safety Plan and Confined Space

Program.

C. All data and submittals on imported backfill materials, Portland Cement Concrete, Storm

Drain Materials, Retaining Wall Materials and crushed miscellaneous base.

D. A detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during excavation of any trenches five feet or more in depth. Said plan shall be signed and stamped by a registered civil or structural engineer licensed in the State of California. Contractor will not be allowed to excavate until the executed and approved shoring plan has been submitted.

15. EXISTING UNDERGROUND UTILITIES

The Contractor is to notify Underground Service Alert at 1-800-227-2600 (or 811), 48 hours prior to any construction operations in order for utilities to mark and identify locations of existing facilities.

Special precaution shall be taken by the Contractor to protect existing utilities that may not be noticeably visible while working in the road shoulder areas.

Unless otherwise indicated on the plans or directly by the utility owner, all utilities shall be protected in place and service maintained. The utilities were plotted based on information provided from the respective utility owners. The accuracy of plotted utilities is not guaranteed.

Throughout the project, utility poles, fire hydrants, water meters, gas meters, water valves and gas valves will be located in the construction area. If applicable, the Contractor shall perform his/her grading operations around these and construct embankment using pneumatic tampers to achieve the required compaction.

The Contractor shall protect existing manholes in place and costs therefor shall be considered as included in the prices paid for Pavement and Sidewalk Repairs. No prior arrangements have been made with utility owners to lower, raise, or otherwise adjust existing manholes. It is the

Contractor’s responsibility to make such arrangements and adjustments, at no additional cost to the Department. Where utility owners do not participate in such arrangements, and finished grade of proposed pavement is above existing manholes, said manholes shall be marked and paved over.

The Contractor shall protect existing valve cans in place and adjust those that are adjustable to finished grade during paving operations. The Contractor shall be solely responsible for coordinating valve can adjustments with utility owners, at no additional cost to the

Department. Where valve cans cannot be adjusted, and utility owners do not participate in coordinating adjustments, and finished grade is above existing valve cans, said valve cans shall be marked and paved over. The Contractor is responsible for performing exploratory excavations

(hand-augering or air knifing) to clear the borehole locations All associated costs with hand-augering or air knifing shall be included in the unit bid price per lineal foot of drilling and no additional compensation will be allowed.

16. EXPLORATORY EXCAVATION (POTHOLING)

Existing utility locations shown on the Construction Drawings are based on available records and are considered approximate. Water service locations, where shown, are based on approximate locations of existing meter boxes. Gas services, where shown, are based on approximate location of visible "gas" markings. Where underground main conductors or conduits such as water, gas, sewer, telephone, electric power, cable television, or other utilities are shown on construction drawings, Contractor shall assume that a service lateral from each utility facility extends to every parcel or property, whether or not a service lateral is shown.

All facilities shown specifically on the construction drawings, or which have been marked by their respective owners and impact the construction to include storm drain installation shall be potholed. All potholing shall be completed, and the results furnished to the Owner at least ten days prior to ordering any materials. Changes or delays caused by Contractor's failure to perform

"potholing" and resultant interference with location of work shall not be eligible for extra work compensation or time extension.

Upon learning of the existence or location of any utility facility omitted from or shown incorrectly on construction drawings, or improperly marked or otherwise indicated, Contractor shall immediately notify the Owner, providing full details as to depth, location, size and function and impacts to proposed construction.

Contractor shall not interrupt or disturb any utility facility without authority from the utility company or order from Owner. Where protection is required to ensure integrity of utility facilities located as shown on the construction drawings or visible to Contractor or marked or otherwise indicated as stated herein, Contractor shall, unless otherwise provided, furnish and place all necessary protection at no additional cost to Owner.

Owner has no information about compaction of trench backfill for said existing utilities and improvements. If said trench backfill fails during construction of proposed road and storm drain facilities, Contractor shall remove and replace said backfill, repair existing facilities (if damaged), compact as specified herein, and remove and replace any asphalt concrete pavement and Portland cement concrete as required, all at no additional cost to the Owner.

17. LANDSCAPING

All existing landscape, sprinklers and irrigation lines in conflict with construction shall be salvaged, removed or relocated and capped, only as necessary to clear the way for rough and final grading for construction of graded sidewalk. The Contractor has an option to replace defective or old materials with new sprinkler system and irrigation lines. Contractor shall provide additional length of lines and sprinklers system if needed in an area as directed by the Dis or as shown on the plan.

Prior to backfilling, the Contractor shall test the sprinklers and irrigation lines at each and every station to ensure the system is working properly. Any leaks shall be repaired and replaced in kind immediately at the expense of the Contractor. If replacement is necessary, sprinkler heads including new pipe and fitting ranging from ½” to 1” in sizes, shall be Polyvinyl Chloride (PVC) Pipe, Sch

80 and use an approved quality solvent and primer for pipe and fitting connections.

18. REMOVE CONCRETE

This work shall consist of removal and disposal of existing Portland Cement Concrete within the limits shown on the plans and set in the field by the District, and shall conform to the provisions in these Special Provisions.

Portions of existing concrete sidewalks, curbs, gutters, ramps, spandrels and driveways which interfere with construction shall be removed.

Portions of existing concrete sidewalks shall be saw cut and removed as necessary for installation of the roadside sign posts.

Where no joint exists between concrete to be removed and concrete to remain in place, the concrete shall be saw cut in a neat, true line to a minimum of 0.17 foot before concrete is removed. The locations of the cut lines shown on the plans are approximate only; the exact location will be determined by the District.

Removed concrete shall become the property of the Contractor and disposed of properly in compliance with local codes at Contractor’s expense.

19. EXCAVATION, BEDDING, AND BACKFILL

Contractor is advised that rock or unacceptable backfill material may be encountered during

Contractor’s operations and course of work. Where such materials may be encountered, Contractor shall excavate said material by any method Contractor deems necessary and as approved by the Owner and furnish and install suitable bedding and backfill material all in accordance with the Contract Documents.

Backfill materials shall be either approved commercial import material or select native material

(screened or washed). All rock or unacceptable trench backfill material shall be hauled to and discarded at a legal disposal site at Contractor's expense. Contractor shall not dispose of such material on vacant private or public property with or without permission.

20. EXCESS EXCAVATED MATERIALS

Excess soils from excavation shall be spoiled entirely at Contractor's expense off the project site at an approved legal disposal area. In no instances shall excess spoil become a public nuisance or threat to public safety.

21. RESTORATION

All work sites shall be restored to pre-job conditions and shall meet the requirements of District and property owner(s). The Contractor shall repair or replace damaged improvements as directed by the District.

The District is obligated to keep visual impact of the work sites to a minimum; therefore, the

Contractor is required to restore all areas altered by construction to pre-existing conditions, unless shown otherwise on the Drawings.

Such areas shall include but shall not be limited to areas used for travel, parking, and storage of vehicles, equipment and materials or adjacent areas impacted by facilities construction.

The Contractor shall be responsible for the proper disposal of all waste materials resulting from project operations, including rubbish, packaging materials, discarded equipment parts, and damaged construction materials, in a manner and at locations suitable to the District and all health and other regulatory agencies. All pavement grindings shall be hauled offsite to an approved disposal area through the City or County.

Contractor shall protect in place or remove and replace all existing utilities and public and private improvements (except those improvements specified to be removed) including, but not limited to, berms, curbs, gutters, concrete pavement, asphalt concrete pavement, walkways, sidewalks, cross gutters, spandrels, medians, driveways, mailboxes, newspaper stands, bikeways, trail ways, bus stops, storm drains, landscaping, landscaping materials, landscape irrigation systems, traffic striping, power poles, guy wires, street lights, signs, guardrails, traffic signal facilities, fences, and walls. If said facilities are undermined or disturbed as determined by District, said facilities shall be removed and replaced. Contractor shall correct or replace any damaged utilities or improvements as part of the contract work at no additional cost. Certain existing improvements are to be protected in place or removed and replaced. Contractor shall protect in place or remove and replace all damaged existing public and private improvements whether they are specifically noted on the technical specifications or plans or not.

If colored or textured sidewalk, curb and gutter, or stamped concrete medians are removed, Contractor shall replace with colored and/or textured sidewalk or stamped concrete medians to match existing.

Daily Restoration. Contractor shall, as a minimum, have accomplished by the end of each work period, the following:

a. Remove all debris, construction materials, and equipment from public and private streets, and private property.

b. Clean all work areas including, but not limited to, washing and sweeping all streets, driveways, gutters, sidewalks, bikeways, and trail ways, and removing all trash. Contractor shall sweep work areas more than once a day if requested by District.

In addition, Contractor shall inspect entire job site at the end of each workday and frequently on

Saturdays, Sundays, and holidays and correct any traffic, pavement (temporary or permanent pavement) or backfill deficiencies. Contractor shall maintain streets including backfilled trenches in good repair.

If District receives complaints from individuals or agencies affected by the project, Contractor shall take immediate action to correct the situation as directed by the District. If Contractor receives complaints directly, Contractor shall report same immediately to District. Thereafter, Contractor shall take immediate action to correct the situation as directed by the District.

22. LOCAL CONDITIONS

The Contractor shall assess, by personal investigation, local conditions affecting the work. Neither the information contained in this section nor that derived from any maps or plats, or from the

County or employees shall act to relieve the Contractor of any responsibility herein or from fulfilling any and all of the terms and requirements of this Contract.

Nuisance water, such as rainfall, irrigation water, or local surface runoff may occur within construction areas during the period of construction under this contract. The Contractor, by submitting their bid, will be held responsible for having investigated the risks arising from such water and shall take all due measures to prevent delays in progress of the work caused by such waters.

23. GENERAL ENVIRONMENTAL MEASURES

A-1: The Contractor shall comply with the following mitigation measures to reduce impacts from construction equipment:

a) Construction equipment shall be maintained in proper tune.

b) Gasoline, CNG or electrical powered equipment instead of diesel powered equipment shall be used whenever possible;

c) Use of heavy equipment shall be suspended during first stage smog alerts.

d) All construction equipment shall be prohibited from excessive idling; and

e) The use of “clean diesel” equipment if modified engines (catalyst equipped, or newer

Moyer Program retrofit) are available at reasonable cost shall be encouraged.

A-2: To reduce fugitive dust emissions during construction, the use of best available control measures (BACMs) consistent with Rule 403 for control of fugitive dust (South Coast Air

Quality Management District 2005) shall be implemented during grading. These measures include the following:

a) Prior to moving any soil, apply water to the surface of the soil not more than 15 minutes prior to moving soil.

b) For any stockpiled soils, either cover soils or apply water twice per hour.

c) Water all active construction areas at least three times daily when active earthwork is occurring or as needed to minimize dust emissions. If evidence of dust is observed, increase to a minimum of four times per day.

d) Cover all haul trucks or maintain at least two feet of freeboard in trucks used to transport soil to the site.

e) Pave or apply water twice per hour to all unpaved parking or staging areas during active operations.

f) Reduce speed on unpaved roads to less than 15 miles per hour.

g) Sweep or wash any site access points within 30 minutes of any visible dirt deposition on any public roadway.

h) Cover or water twice daily any on-site stockpiles of debris, dirt, or other dusty materials.

i) Suspend all operations on any unpaved surface if winds exceed 25 miles per hour.

j) Limit daily disturbance areas to 5 acres or less.

k) Move no more than 5,000 cubic yards of soil daily.

l) Encourage carpooling for construction workers.

m) Park construction vehicles off traveled roadways.

n) Wet down or cover dirt hauled off-site.

o) Wash or sweep access points daily.

p) Encourage receipt of materials during non-peak traffic hours; and

q) Sandbag the construction site for erosion control.

24. SUPPLEMENTAL WORK AT FORCE ACCOUNT (UNFORESEEN SUBGRADE,

STABLIZATION, UTILITY, AND AGENCY MITIGATION REQUIREMENTS)

Supplemental work shall consist of extra work, related to specified items of work, necessary to address unforeseen position, location, and/or dimensions of existing underground utilities. Extra work addressed under the provisions of this section will be work as determined by the Engineer to be necessary to the completion of specified construction within the functional range, scope, and intent of the contract.

Extra work to address subsurface or latent physical utility conditions that differ materially from those indicated in the contract; or unknown utility physical conditions of an unusual nature, differing from those initially encountered and generally recognized as inherent in the work provided for in the contract will be addressed in accordance with Section 3.12, "Site Conditions", of the General

Conditions.

Prospective bidders shall include the Contract Amount printed in the proposal for "Supplemental

Work At Force Account (Unforeseen Utility Conflicts)" as their bid for this contract item. The amount shown is purely arbitrary and no guarantee is given or implied that any payments will be made.

Furnishing all labor, equipment, material, tools and incidentals and doing all work determined by the Engineer to fall under this section shall be considered to be included in Force Account made for

Supplemental Work At Force Account (Unforeseen Utility Conflicts), and no separate payment will be made therefor.

Supplemental Work at Force Account (Unforeseen Utility Conflicts) shall only be used as directed by the Department and as outlined in Article VII of the Contract Documents.

Changes that exceed the amount of Supplemental Work at Force Account (Unforeseen Utility

Conflicts) will be processed as a Change Order per Contract Documents. This section shall take precedence over Article VII of Contract Documents.

A detailed breakdown of all cost associated with the work requested by the Department within the defined scope of work shall be provided.

At project closeout, unused Supplemental Work at Force Account (Unforeseen Utility Conflicts) amounts shall not be payable or disbursed by the Department.

END OF SPECIAL CONDITIONS