Atch 7 - AF66.xlsx
XLSX spreadsheet 20 KB Posted
- Solicitation number
- CRWU24-1037
About this file
This document is an Attachment (Atch 7) titled "AF66 SCHEDULE OF MATERIAL SUBMITTALS" related to the federal contract opportunity "Modify Electrical and Structure for Target Retrieval System B1145" with Solicitation Number CRWU24-1037.
The key details are: The project involves raising safety baffles, demolishing an existing non-functioning target rotation system, relocating electrical lighting, installing electrical outlets and conduit for wireless access points, and replacing hinges on shooting lane doors. The contractor is required to submit various items for review and approval, including a construction schedule, outage request, submittals for materials and equipment, meeting minutes, and as-built drawings. Submission deadlines range from 3 to 30 calendar days after notice to proceed or other events. The contracting agency is the Department of the Air Force Space Command.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF66
| SCHEDULE OF MATERIAL SUBMITTALS | CRWU 24-1037 - Modify Electrical and Structure for Target Retrieval System B1145 | Date: 29 Aug 2024 | ||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||
| ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NUMBER OF SUBITTALS | REQUIRED SUBMISSION DATE (No Later Than) | REVIEWER (PM/Insp) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | AF3000 SUBMITTAL NUMBER | DATE CONTRACTOR NOTIFIED APPROVED / DISAPPROVED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| CPM MS Project 2022 construction schedule | 1 | 5 BD after Kickoff Meeting | PM | |||||||||
| Kick Off Meeting - Minutes | 1 | 3 BD After Kickoff Meeting | PM | |||||||||
| Outage Request/Plan | 1 | 14 CD before requested outage | PM | Outage request may be provided on company letterhead which includes outage start and stop dates. | ||||||||
| Laydown Area (Work Staging Area) | 1 | 30 CD After NTP | PM | |||||||||
| AF 3064 - Progress Schedule | 1 | 5 BD after Kickoff Meeting | INSP | |||||||||
| Demo Plan | 1 | 30 CD After NTP | PM | |||||||||
| Wire, Devices, Fittings and Conduit Cut Sheet | 1 | 30 CD After NTP | PM/INSP | |||||||||
| Hinge Cut Sheet | 1 | 30 CD After NTP | INSP | |||||||||
| Wall Deflector Plan | 1 | 30 CD After NTP | INSP | |||||||||
| Lane Post Covering Plan | 1 | 30 CD After NTP | INSP | |||||||||
| Wall Penetration Sealant Cut Sheet | 1 | 30 CD After NTP | PM/INSP | |||||||||
| Recycle Tranmittal | 1 | 5 BD After Recycle | INSP | |||||||||
| Progress Meeting Minutes | 1 | 2 BD after each meeting | INSP | |||||||||
| Red Zone Meeting Minutes | 1 | 5 BD After Red Zone Meeting | INSP | |||||||||
| Pre-Final Inspection - Minutes | 1 | 3 BD after Pre-Final Meeting | INSP | |||||||||
| Red Line Drawings | 1 | 3 BD after Pre-Final Meeting | INSP | |||||||||
| Closeout Documents | ||||||||||||
| Final Inspection - Meeting Minutes | 1 | 3 BD after final inspection | PM | |||||||||
| Certification that no LBP, ACM or PCB was used. | 1 | 3 BD after final inspection | PM | Statement that no HM was used. Can be provided on company letterhead. | ||||||||
| As-built (RECORD) Drawings | 1 | 10 CD after final inspection | PM | |||||||||
| Additional Submittals |