Atch 7 - AF66.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Modify Electrical and Structure for Target Retrieval System B1145 -
Solicitation number
CRWU24-1037
Issued by

About this file

This document is an Attachment (Atch 7) titled "AF66 SCHEDULE OF MATERIAL SUBMITTALS" related to the federal contract opportunity "Modify Electrical and Structure for Target Retrieval System B1145" with Solicitation Number CRWU24-1037.

The key details are: The project involves raising safety baffles, demolishing an existing non-functioning target rotation system, relocating electrical lighting, installing electrical outlets and conduit for wireless access points, and replacing hinges on shooting lane doors. The contractor is required to submit various items for review and approval, including a construction schedule, outage request, submittals for materials and equipment, meeting minutes, and as-built drawings. Submission deadlines range from 3 to 30 calendar days after notice to proceed or other events. The contracting agency is the Department of the Air Force Space Command.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF66

SCHEDULE OF MATERIAL SUBMITTALSCRWU 24-1037 - Modify Electrical and Structure for Target Retrieval System B1145Date: 29 Aug 2024
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALNUMBER OF SUBITTALSREQUIRED SUBMISSION DATE (No Later Than)REVIEWER (PM/Insp)DATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATEAF3000 SUBMITTAL NUMBERDATE CONTRACTOR NOTIFIED APPROVED / DISAPPROVEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
CPM MS Project 2022 construction schedule15 BD after Kickoff MeetingPM
Kick Off Meeting - Minutes13 BD After Kickoff MeetingPM
Outage Request/Plan114 CD before requested outagePMOutage request may be provided on company letterhead which includes outage start and stop dates.
Laydown Area (Work Staging Area)130 CD After NTPPM
AF 3064 - Progress Schedule15 BD after Kickoff MeetingINSP
Demo Plan130 CD After NTPPM
Wire, Devices, Fittings and Conduit Cut Sheet130 CD After NTPPM/INSP
Hinge Cut Sheet130 CD After NTPINSP
Wall Deflector Plan130 CD After NTPINSP
Lane Post Covering Plan130 CD After NTPINSP
Wall Penetration Sealant Cut Sheet130 CD After NTPPM/INSP
Recycle Tranmittal15 BD After RecycleINSP
Progress Meeting Minutes12 BD after each meetingINSP
Red Zone Meeting Minutes15 BD After Red Zone MeetingINSP
Pre-Final Inspection - Minutes13 BD after Pre-Final MeetingINSP
Red Line Drawings13 BD after Pre-Final MeetingINSP
Closeout Documents
Final Inspection - Meeting Minutes13 BD after final inspectionPM
Certification that no LBP, ACM or PCB was used.13 BD after final inspectionPMStatement that no HM was used. Can be provided on company letterhead.
As-built (RECORD) Drawings110 CD after final inspectionPM
Additional Submittals