Atch 6 - RFI Response.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- CRWU24-1037
About this file
This document is a Request for Information (RFI) issued under GSA eBuy for a project to modify the range power and structures for a target retrieval system at Building 1145 at Buckley Space Force Base in Colorado. The RFI responds to questions from potential bidders regarding as-builts, stamped drawings, range closure, target system installation, demolition requirements, tax exemption, and proposal requirements. It clarifies that the awarded contractor will be responsible for providing as-builts, there is no need for stamped drawings, the range will be closed during construction, the target system will be installed by the manufacturer, and only limited demolition is required. The project is tax exempt, and material quantities are an additional proposal requirement beyond the pricing breakout. The summary of the related federal contract opportunity indicates this is a solicitation to raise safety baffles, demolish the existing target rotation system, move lighting, install electrical outlets and conduit, and replace door hinges.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Request for Quote (RFQ) issued under GSA eBuy at Buckley Space Force Base, CO for: Project: CRWU 24-1037 - Modify Range Power and Structures For Target Retrieval System Building 1145 | |
| #1 | Can As builts be provided? |
| As builts have been provided. | |
| #2 | Action Point has provided shop drawings, for bid but they do not appear to be stamped by a PE(specifically regarding electrical) does the government anticipate the need of engineered drawings and who's responsibility will that be? |
| There is no need for stamped drawings. The awarded contractor will be required to provide as-builts of the system they install. | |
| #3 | Confirm that the existing range will be closed from NTP to project |
| The range will be entirely closed during construction. | |
| #4 | Please confirm the new range system will be installed by others. They RFP does not clarify who's responsibility this is. |
| The range system will be installed by the manufacturer, Action Targets. | |
| #5 | Can demo be performed during regular working hours and are there any conditions/technical aspects with the facility bidders should account for. |
| All work is the take place during normal business hours. The range will be closed during construction. | |
| #6 | Please provide additional information an or a basis of design allowing for accurate pricing of hinge replacements. |
| The exact hinge type is to be determined by the awarded contractor. The selected hinge will need to be approved by CE before purchase and installation. | |
| #7 | Please provide additional information an or a basis of design allowing for accurate pricing of the additional wall deflectors |
| Please reference "Small Arms Range Complex_As-builts" section Z519.5 for installation instructions. | |
| #8 | Can a shop drawing showing of the range plan reflecting the safety baffles be provided? Right now this SOW is hard to |
| Please reference "Small Arms Range Complex_As-builts" for existing conditions and "Buckley AFB_100_Rev0" for new requirements. | |
| #9 | With Demo being a significant portion of this project Can demo drawings be provided? We feel The provided shop drawings and narrative do not clearly convey what is scheduled for demo and what is to remain. |
| The only demo required for this project is the demo of the existing target rotations system and associated uni-strut, electrical, and pneumatic lines. There are no special requirements for the demo, no drawings will be provided. | |
| #10 | Is this project tax exempt? |
| Yes, the project is tax exempt. | |
| #11 | Are there additional proposal requirements beyond the pricing breakout noted on the solicitation? |
| Material quantities | |
| #12 | Confirm the Divisions other than 1, 2, 8, 13, and 26 will be performed by others if required. |
| Division 6 has been added as a revision dated 26 Aug. All divisions include: 1, 2, 6, 8, 13, and 26. | |
| #13 | Please expand on 5.5.5.1 of the RFP. Does this only apply to electrical conduit penetrations? Is there a testing and or commissioning of the air barrier's integrity that we will need to account for at the end of the project? |
| Referenced section is now 5.6.5.1. Electrical conduit should be the only wall penetrations required. Testing and commissioning will not be required. It is expected that the contractor will seal the penetrations to industry standards. |