CRD Roof Photographs.pdf
PDF 4 MB Posted
- Attached to
- Facility Roof Maintenace, applying multi-layer polyurethane based coating system for each of 5 facilities
- Solicitation number
- 1240BJ23R0012
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains photographs of roofs at various facilities owned by the Civilian Conservation Corps that require maintenance or replacement. The photographs depict issues such as aging roof stacks and boots, valleys in need of repair, water damage to soffits and fascia, and deteriorated ridge caps. Locations include two residences, a fourplex, two crewhouses of different sizes, a boat storage building, a fourplex carport, and a warehouse.
The related federal contract opportunity is a solicitation from the Department of Agriculture Forest Service to apply a multi-layer polyurethane based coating system to the roofs of five unspecified facilities. The solicitation number is 1240BJ23R0012 and the opportunity type is listed as a solicitation. No further details are provided regarding response dates, pricing terms, set asides, or other salient information.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CRD Roof Photographs
TAKEN 10/2022
Page | 1
Table of Contents Residence #1
Residence #2
CWC Fourplex
CWC 8-Person Crewhouse
CWC 12-Person Crewhouse
CWC Boat Storage
CWC Fourplex Carport
CWC Warehouse
Page | 2
421000 Cordova Residence #1
View of main roof Stack to be replaced Example boot to be replaced
Example boot to be replaced
Valley by the entry Water damaged soffit and fascia at valley
Page | 3
421001 Cordova Residence #2
View of main roof Aging stack and boot to be replaced
Problematic valley, looking down
View of valleys near front entry
Soffit where water passed through to penetrate window
Water damaged fascia and soffit
Page | 4
421006 CWC Fourplex
Minimal photographs due to access limitations at the time of site visit.
Page | 5
421103 CWC 8 Person Crewhouse
View of main roof Screws were backing out, new ones will be needed
Stack in need of replacement
Boot in need of replacement
Flashing to be coated
Page | 6
421104 CWC 12 Person Crewhouse
Overall roof, with small patches visible
Typical penetration, to be replaced
Abandoned stacks to be removed and patched
Abandoned stacks from below, to be removed
Drip edge/flashing requiring replacement
Page | 7
422003 CWC Boat Storage
Main roof area Typical corrosion and rust throughout
Ridge cap with corrosion
Patch to be sealed and coated
Page | 8
422010 Fourplex Carport
Main roof area Snowguard to be replaced Ridge cap with moderately deteriorated finish
Roof as seen from below – snow guards and gutters to be replaced Deterioration where ridge cap meets the panels
Page | 9
422011 CWC Warehouse
Snow guards and boot to be replaced
Stack to be replaced
Recurring leak to be resealed and coated
General view of roof with snow guards to be replaced
File details come from the government source that posted it. Updated .