About this file

This is a Cost Proposal Form for the City of Dania Beach, Florida's CCTV Preventative Maintenance, Installation, and Network Cabling Services solicitation. The project encompasses four primary service categories: hourly labor for security system and cabling work (removal, repair, and installation) estimated at 200 hours; quarterly preventative and corrective maintenance for 200 CCTV cameras including inspections, cleaning, adjustments, and mounting hardware verification; material and equipment mark-up services; rental equipment mark-up for items such as hoists, cranes, and trenchers; and sub-contractor mark-up for specialized services including engineering firms. Proposals must remain valid for ninety (90) days after proposal opening, and the solicitation deadline is Monday, May 11, 2026 at 10:00 am with submission required through the OpenGov procurement portal at https://procurement.opengov.com/portal/daniabeachfl.

Contractors must provide pricing on a per-hour basis for labor services, a quarterly per-camera rate for maintenance services, and percentage mark-ups not to exceed 15 percent on parts and equipment, rental equipment, and sub-contractor services. The cost proposal form requires contractors to specify their hourly rate, quarterly camera maintenance rate, and applicable mark-up percentages, with all extended totals calculated and a grand total amount provided in both numeric and written formats. The estimated material and equipment costs ($10,000), rental equipment costs ($5,000), and sub-contractor costs ($5,000) are provided for price evaluation purposes only and do not represent guaranteed amounts. All hours and quantities listed on the form are estimates and not guaranteed by the City.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COST PROPOSAL FORM

ALL PROPOSALS SHALL REMAIN VALID FOR NINETY (90) DAYS AFTER PROPOSAL OPENING

CCTV SURVEILLANCE AND SECURITY SYSTEMS

MAINTENANCE, REPAIR AND ADDITIONS

Item No. Estimated

QTY / UOM

Description Unit Cost Extended Total

1. 200 Hours

Hourly Rate:

Provide the hourly rate for all security system and cabling work (Remove, Repair, Installation) $

(Per Hour)

2. 200 Cameras

Quarterly Rate:

Provide the quarterly rate for preventative and corrective maintenance for CCTV cameras (inspections, cleaning, adjustments, mounting hardware, environmental protection verification)

(Per Camera)

3. $10,000.00

MATERIAL MARK-UP:

Parts and Equipment Mark-up % Percent mark-up on parts and equipment (i.e.

Cameras, Switches etc.)

Formula: $10,000 + % = $ Total (Estimate for parts is for price evaluation purposes only and is not a guaranteed amount. Mark-Up percentage shall not exceed 15%)

% Markup

4. $5,000.00

MATERIAL MARK-UP:

Rental Equipment Mark-up %

Percent mark-up on rental equipment as required (i.e. Hoist, Crane, Trencher)

Formula: $5,000 + % = $ Total (Estimate is for price evaluation purposes only and is not a guaranteed amount. Mark-Up percentage shall not exceed 15%)

% Markup

5. $5,000.00

MATERIAL MARK-UP:

Sub-Contractor Mark-up %

Percent mark-up on Sub-Contractors as required (i.e. Engineering, Specialty Firm)

Formula: $5,000 + % = $ Total (Estimate is for price evaluation purposes only and is not a guaranteed amount. Mark-Up percentage shall not exceed 15%)

% Markup

Note: Parts and materials provided by the contractor shall be reimbursed at cost plus percentage (%) markup as indicated on the bid form. Material and parts shall not exceed 15%. In addition, All hours listed on this form are just estimated and quantity is not guaranteed by the City.

Grand Total Amount: $ Numeric Amount (Sum of Items 1-5)

GRAND TOTAL: Dollars Written Amount (Sum of Items 1-5)

Abbreviations:

QTY = Quantity UOM= Unit of Measure

BUSINESS NAME:

AUTHORIZED NAME/SIGNATURE: DATE

DRAFT - CCTV and Network RFP_25-0XX - DM 5
DRAFT - CCTV and Network RFP_25-0XX - DM 6

File details come from the government source that posted it. Updated .