Cost Estimate Worksheet.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Y1AZ--953-MM22-002: Site Improvements - Committal Shelter, Fort Sheridan National Cemetery
- Solicitation number
- 36C78622B0009
About this file
This document contains a cost estimate worksheet for a federal construction project. The worksheet requires lump sum pricing for various construction divisions that will be used in site improvements for a committal shelter at the Fort Sheridan National Cemetery. Divisions include general conditions, mobilization, site investigation, concrete work, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and general and mechanical/electrical/plumbing construction. Offerors are to use the worksheet to provide pricing, including subtotals by construction division and an overall total base construction cost. Pricing must also account for any applicable insurance, bonding, overhead and profit.
The related federal contract opportunity is solicitation number 36C78622B0009 for site improvements to the committal shelter at Fort Sheridan National Cemetery, issued by the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GSLM_Fort Sheridan_Set_JAN_2022 (June 22 Version).pdf | ||
| 971857 Fort Sheridan Boundary Survey.pdf | ||
| Pages from 124810 Fort Sheridan Cemetery Road Repaving.pdf | ||
| Pre-fab storage building.pdf | ||
| Map-Cemetery.pdf | ||
| Site Plan.pdf | ||
| 36C78622B0009 0001.docx | DOCX document | |
| DOL Wage Determination _ Lake County.pdf | ||
| Cemetery Map.pdf | ||
| 36C78622B0009_1.docx | DOCX document | |
| AsBuilts Drawings.pdf | ||
| Technical Specifications.pdf | ||
| Spec Attachments.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| IFB Contractor Cost Estimate Worksheet |
| Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number. |
If a Division is not being used put N/A in that field.
Additional lines/items can be added if needed or appropriate.
| Offeror shall use and edit to fit Task Order Project | |
| Project Number: | 953-MM22-002 |
| Solicitation Number: | 36C78622B0009 |
| Project Title: | Site Improvements - Committal Shelter, Fort Sheridan |
| Division | Unit of Measure | # of Units | Unit Cost $ | Extended/Total Cost $ | Comments / Remarks |
| Division 0 - Special Sections | |||||
| General Conditions and Administration | JB | 1 | |||
| Division 01 - General Requirements | |||||
| Mobilization | JB | 1 |
| Division 02 - Existing Conditions | ||
| Site Investigation | JB | 1 |
| Division 03 - Concrete |
Division 04 - Masonry
Division 05 - Metals
Division 06 - Wood, Plastic, and Composites
Division 07 - Thermal and Moisture Protection
Division 08 - Openings (Doors, Windows, etc...)
Division 09 - Finishes
Division 10 - Specialties
Division 11 - Equipment
Division 12- Furnishings
Division 13 - Special Construction
Division 14 - Fire Suppression
Division 22 - Plumbing
Division 23 - Heat, Ventilating, and Air Conditioning
Division 25 - Integrated Automation
Division 26 - Electrical
Division 27 - Communications
Division 28 - Electronic Safety and Security
Division 31 - Earthwork
Division 32 - Exterior Improvements
Division 33 - Utilities
| Mechanical, Electrical, Plumbing Subtotal | ||
| General Construction Subtotal | ||
| Total Base Construction Cost | ||
| Insurance (if applicable) | ||
| Bonding (if applicable) | ||
| Overhead | ________ % | $0.00 |
| Profit | ________ % | $0.00 |
| GRAND TOTALS | $ |