This document contains a cost estimate worksheet for project number 890CM3014 titled "Gravesite Expansion" along with details of a related federal contract opportunity.

The cost estimate worksheet breaks down anticipated costs by construction division including general conditions, site work, concrete, and other categories. It requires lump sum estimates for any divisions to be utilized and includes spaces for additional line items. The worksheet will be used by the offeror to develop their total proposed cost.

The related federal contract opportunity is solicitation number 36C78623B0024 for improvements at the Marietta National Cemetery. It is being issued by the Department of Veterans Affairs National Cemetery Administration. The improvements include work under divisions for earthwork, exterior work, utilities, and other construction categories. Responses are due based on the standard solicitation timeline.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number:

Solicitation Number:

Project Title:

Division Unit of Measure # of Units Unit Cost $ Extended/Total

Cost $ Comments / Remarks Division 0 - Special Sections

General Conditions and Administration

JB 1

Division 01 - General Requirements

Mobilization JB 1

Division 02 - Existing Conditions

Site Investigation JB 1

Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastic, and Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings (Doors, Windows, etc...)

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12- Furnishings

Division 13 - Special Construction

Division 14 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 25 - Integrated Automation

Division 26 - Electrical

Gravesite Expansion

Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number.

If a Division is not being used put N/A in that field.

Additional lines/items can be added if needed or appropriate.

IFB Contractor Cost Estimate Worksheet

890CM3014

36C78622B0016

Offeror shall use and edit to fit Task Order Project

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Mechanical, Electrical, Plumbing Subtotal

General Construction Subtotal

Total Base Construction Cost

Insurance (if applicable)

Bonding (if applicable)

Overhead ________ % $0.00

Profit ________ % $0.00

GRAND TOTALS $

Sheet1

File details come from the government source that posted it. Updated .