This document contains a statement of work for a construction contract opportunity with the Department of Veterans Affairs National Cemetery Administration. The contract is for gravesite expansion construction services at Fort McPherson National Cemetery in Maxwell, Nebraska, including site preparation, demolition, excavation, and completion of all work required by associated drawings and specifications. The contractor will be responsible for management, supervision, labor, equipment, materials and tools to perform the scope of work, which includes site investigation, material approvals, inspection of completed work, and a one-year warranty on all workmanship and materials. The performance period is 365 calendar days from notice to proceed. The contractor must follow all standards of conduct and employee behavior requirements, as well as comply with dignified burial and historic preservation protocols, at the national cemetery.

View the file

Other files

File Type Posted
36C78623B0021 0003.docx DOCX document
36C78623B0021 0004.docx DOCX document
36C78623B0021 0002.docx DOCX document
4-IFB SOW 837CM3001 New Albany NC - Copy.docx DOCX document
36C78623B0021 0001.docx DOCX document
Past Performance.pdf PDF
Wage Determination.pdf PDF
3-867CM3001-NANC-BidDoc-Dwgs 00-13.pdf PDF
RFI Form.pdf PDF
3-867CM3001-NANC-BidDoc-Dwgs 14-26.pdf PDF
3-867CM3001-NANC-BidDoc-Specs.pdf PDF
36C78623B0021_1.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number:

Solicitation Number:

Project Title:

Division Unit of Measure # of Units Unit Cost $ Extended/Total

Cost $ Comments / Remarks Division 0 - Special Sections

General Conditions and Administration

JB 1

Division 01 - General Requirements

Mobilization JB 1

Division 02 - Existing Conditions

Site Investigation JB 1

Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastic, and Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings (Doors, Windows, etc...)

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12- Furnishings

Division 13 - Special Construction

Division 14 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 25 - Integrated Automation

Division 26 - Electrical

Gravesite Expansion

Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number.

If a Division is not being used put N/A in that field.

Additional lines/items can be added if needed or appropriate.

IFB Contractor Cost Estimate Worksheet

890CM3014

36C78622B0016

Offeror shall use and edit to fit Task Order Project

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Mechanical, Electrical, Plumbing Subtotal

General Construction Subtotal

Total Base Construction Cost

Insurance (if applicable)

Bonding (if applicable)

Overhead ________ % $0.00

Profit ________ % $0.00

GRAND TOTALS $