Cost Breakdown Mather B647 Re-Roof Install Ladder.pdf

PDF 100 KB Posted

Attached to
Z1DA--Mather B647 Re-Roof/Install Ladder Project # 612A4-25-018
Solicitation number
36C26125R0065
Issued by

About this file

This document is a detailed cost breakdown template for a roofing project at the VA Mather facility (Building 645). The solicitation (36C26125R0065) covers a re-roofing and ladder installation project for the Veterans Health Administration, with the template designed to capture comprehensive project costs across multiple categories including roofing work (demolition, preparation, installation), project management (project manager, superintendent, 3rd party inspector), and additional expenses like overhead, profit, insurance, taxes, and bonds. The template requires contractors to provide line-item material, labor, and total costs for each project component, with the final total price proposal to be recorded on Standard Form 1442, Block 17.

View the file

Other files

File Type Posted
612A4_25_018 Mather Bldg 647 Roofing Scope of work 9.3.25 .pdf PDF
36C26125R0065 0004.docx DOCX document
Site Visit Log -7-22-2025 B647 Re-Roof Install Ladder.pdf PDF
36C26125R0065 0003.docx DOCX document
36C26125R0065 0002.docx DOCX document
36C26125R0065 0001.docx DOCX document
VAAR 852.219-75.pdf PDF
Specifications - Building 647 Roofing.pdf PDF
612A4-25-018 Mather Bldg 647 Roofing SOW 7.8.2025.pdf PDF
Davis-Bacon Act WD CA20250019.pdf PDF
36C26125R0065.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION: 36C26125R0065 PROJECT: 612A4-25-018

VANCHCS, Mather B645 Re-Roof/Install Ladder

PROVIDE COMPLETE DIVISIONAL COST BREAK-OUT FOR COMPLETE PROJECT

REF DESCRIPTION Material Labor Total

ROOFING

Demolition $ $ $ Roofing Preparation

Roofing Installation Stainless Steel

Installation

Drain Replacement and Addition

SUB TOTAL:

Project Management Project Manager Superintendent 3rd Party Inspector Premium Time Work Design/Layout Mobilization

SUB TOTAL:

TOTAL:

OVERHEAD

PROFIT

Insurance and Taxes

BONDS

TOTAL PRICE PROPOSAL:

*Total Price Proposal amount to be recorded on SF1442, block 17