Control Wing North Exterior Stair Replacement SOW v1.pdf
PDF 132 KB Posted
- Solicitation number
- 6973GH-25-R-00116
About this file
This Statement of Work (SOW) outlines requirements for Design-Build services at the Salt Lake Air Route Traffic Center in Salt Lake City, Utah, involving the demolition of an existing exterior stair system and installation of a new prefabricated commercial stair system. The project requires demolition and disposal of existing steel and concrete stairs and railing covering approximately 130 square feet with a 12-foot height, followed by construction and installation of a new prefabricated commercial stair system that meets or exceeds International Building Codes.
The SOW references specific drawing numbers for existing stair location and details (A212A, A216A, S208A) and metal grating stairs specification Section 055119. The contractor is responsible for verifying all dimensions and quantities, which are provided as approximations only. All work must comply with latest building codes and Authority Having Jurisdiction requirements for building, plumbing, electrical, and mechanical components. The associated federal contract opportunity indicates this is a small business set-aside under NAICS 236210 with a size standard of $39.5M, estimated project magnitude of $50,000-$100,000, and proposals due April 4, 2025 at 12:00pm MT.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ZLC: Salt Lake City ARTCC
Title: Control Wing North Exterior Stair Replacement
Scope of Work (SOW): At the Salt Lake Air Route Traffic Center 2150 West 700 North, Salt Lake City, Utah, 84116.
The Federal Aviation Administration (FAA) requires that the contractor provide the following:
• Complete Design-Build services for the demolition of an existing exterior stair system and the design, construction, and installation of a new prefabricated commercial stair system. A description of the work that needs to be completed is also found below. The description is not exhaustive but encompasses a general definition of the work to be completed.
o Note: Refer to the pdf document titled “Control Wing North Exterior Stair Mark
Ups and Specs” as it pertains to this scope of work.
• Demolition o Existing Stair
Demolish and dispose of existing steel and concrete stairs and railing which encompasses and area of approx. 130sft and have an overall height of approx. 12ft.
See the following drawing numbers for existing stair location and details.
• No. A212A “AIR TOUTE TRAFFIC CONTROL CENTER ISSS
AREA MODIFICATIONS CONTROL WING FIRST FLOOR-FIRST
FLOOR PLAN”
• No. A216A “AIR TOUTE TRAFFIC CONTROL CENTER ISSS
AREA MODIFICATIONS CONTROL WING FIRST FLOOR-
BUILDING SECTION ”A”.
• No. S208A “AIR TOUTE TRAFFIC CONTROL CENTER ISSS
AREA MODIFICATIONS CONTROL WING FIRST FLOOR-STAIR
PLANS, SECTIONS AND DETAILS
• Installation o New Stair Construct and install new prefabricated commercial stair system which meets or exceeds all International Building Codes.
See the following specification for stair construction and other details.
• SECTION 055119-METAL GRATING STAIRS
General Requirements:
All sizes, dimensions, quantities are approximations only. Contractor is responsible to verify all sizes, dimensions, and quantities.
All work will be completed in compliance with the latest building codes and Authority Having Jurisdiction (AHJ) (i.e. building, plumbing, electrical, and mechanical, etc.).
End of Scope of Work