Contractor Progress and Status Report.pdf

PDF 118 KB Posted

Attached to
Mexico F-5 Repair and Return / Overhaul
Solicitation number
FA822026RB005
Issued by

About this file

This is a DD Form 1423-1, Contract Data Requirements List (CDRL), which specifies data deliverables required from a contractor under a federal contract. The form documents one data item requirement for repair or overhaul services related to an F-5 aircraft system.

The required data item is a Contractor's Progress and Status Report (Data Item A001) with a monthly status report subtitle. The contractor must reference DID MGMT-81928 for content specifications and follow PWS Para 1.2.9, 1.2.11, and 4.7.4 as the contract reference. The requiring office is AFLCMC/WNDI, located at Hill Air Force Base, Utah. The contractor must submit the initial status report within 5 working days of the month following induction of the first part for repair or overhaul, then continue submitting monthly reports within 5 working days of each month's beginning until final parts are shipped. The report should indicate the as-of date and cover period and may omit cost curves, man-hours expended, employee movement figures, financial/labor data, and other specified elements. Distribution is authorized to the Department of Defense and U.S. DoD contractors only. The estimated total price for this data requirement is $0.00, indicating it is classified as a Group IV item with minimal contractor effort. The CDRL was prepared by Joseph Jackson on 9 June 2026 and required approval from the government issuing contracting officer.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, FEB 2001 PagesPage of

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

16. REMARKS

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15.TOTAL

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, FEB 2001 PagesPage of

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DRAFT

SAMPLE

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

DRAFT

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item) Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130 The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES Draft Final Reg Repro

15.TOTAL

G. PREPARED BY

I. APPROVED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

C. CATEGORY:

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785 DD Form 1423-1, "CONTRACT DATA REQUIREMENTS LIST (1 Data Item) "

Click this button to save this form.:
Click this button to print this form.:
Click this Reset button to erase data from all fields.:
Enter total page numbers.:
A. CONTRACT LINE ITEM NUMBER: TBD
EXHIB: A
Select for "TDP.": 0
Select for "TM.": 0
Enter specification for "Other.": MGMT
SYS: FMS - F-5
PR: TBD
CONF: TBD
TextField2: A001
TextField2: CONTRACTOR'S PROGRESS AND STATUS REPORT
TextField2: Monthly Status Report
TextField2: DI-MGMT-81928
TextField2: PWS Para 1.2.9, 1.2.11, 4.7.4
TextField2: AFLCMC/WNDI
TextField2: N/A
TextField2: A
TextField2: D
TextField2: MTHLY
TextField2: Contract Award
TextField2: BLK 16
TextField2: BLK 16
TextField2: Contractor format is acceptable.

DISTRIBUTION STATEMENT D. Distribution authorized to Department of Defense and U.S. DoD contractors only (category) (date of determination). Other requests for this document shall be referred to FMS Program Office, 6057 Box Elder Lane, Bldg 1285, Hill AFB, UT 84056-5811

BLK 8: Approval Required. The AFLCMC/WNDI branch shall review the status report for approval/disapproval within ten (10) working days of receipt of submittal. Contractor will have five (5) working days to submit corrected report.

BLK 11: As of Date. The Contractor's Progress and Status Report should indicate the as of date of the report.

BLK 12: Date of First Submission. The Contractor shall submit the initial status report within 5 working days of the beginning of the month following the date of induction of first part for repair or overhaul.

BLK 13: Date of Subsequent Submission. The Contractor shall submit a status report within 5 working days of the beginning of the month until the final part submitted for repair or overhaul has been return shipped. The final status report shall be submitted the month following the shipment of the final part.

BLK 14: Distribution. The CDRL shall be submitted via email to the identified addresses.

Mr. Joseph Jackson joseph.jackson.4@us.af.mil

Mr. Marshall Neilson marshall.neilson.1@us.af.mil

The Contractor shall provide Contractor's Progress and Status Reports per DID DI-MGMT-81928 except as modified per the following:

The Contractor may submit the status report in a format of their choosing. The report shall contain the date of the report and the period covered by the report.

The Contractor may omit the following: 2.4 cost curves, 2.5 man-hours expended, 2.6 employee movement, 2.7 figures, 2.5 Financial/Labor Data (2.5 c, 2.5 d, and 2.5 e)

TextField2: DODAAC FA8220
TextField2: AFLCMC/WNDI
TextField2: Mr. Joseph Jackson
TextField2: Program Manager
TextField2: Bldg 1285
TextField2: 6057 Box Elder Lane
TextField2: Hill AFB, UT 84056
TextField2: AFLCMC/WNDT
TextField2: Mr. Marshall Neilson
TextField2: Contracting Officer
TextField2: 6072 Fir Ave
TextField2: Bldg 1233
TextField2: Hill AFB, UT 84056
TextField2: IV
TextField2: Joseph Jackson
TextField2: 9 Jun 2026
TextField2:
Total draft copies is automatically calculated.:
Total final regular copies is automatically calculated.: 1
Total final regular copies is automatically calculated.: 1
Total final regular copies is automatically calculated.: 2
Total final reproducible copies is automatically calculated.:
DecimalField1: 0.00
G. PREPARED BY (Signature):
I. APPROVED BY (Signature):

File details come from the government source that posted it. Updated .