Contracting Briefing 3 Aug 26.pptx

PPTX presentation 278 KB Posted

Attached to
Industry Day C-5M Super Galaxy Structural Honeycomb Panels
Solicitation number
Not on record
Issued by

About this file

This is a contracting briefing presentation outlining the Defense Logistics Agency Aviation's (DLA) acquisition strategy for C-5M Super Galaxy structural honeycomb panels. The 409th Supply Chain Management Squadron at Robins Air Force Base is expanding its qualified vendor list for over 500 National Stock Numbers (NSNs) of honeycomb panels used in the aircraft. The current strategy involves an Industry Day scheduled for August 3-4, 2026, in Warner Robins, Georgia, to attract new vendors. Historical procurement data shows that since 2020, the government has awarded 26 different NSNs totaling $1,713,102 through 18 delivery orders among three small businesses, with individual delivery orders ranging from $6,725 to $497,000 and averaging $97,389. Most orders involve low-volume, high-value procurements typically ranging from 1 to 10 units per NSN, with initial tooling and set-up costs covered through a Material Related Set-up CLIN.

Qualified contractors must meet specific requirements including Source Qualification Statement (SQS) compliance, approval from the C-5 Engineering Division (AFLCMC/WLSEBA), ISO 9002 or AS9100 certification, registration in System for Award Management (SAM) and Enhanced Joint Certification Program (EJCP), and Cybersecurity Maturity Model Certification (CMMC) Level II. The government seeks manufacturers capable of producing complex, adhesive-bonded structural honeycomb panels with expertise in facility contamination control, autoclave operations, adhesive life tracking, bond line surface preparation, aircraft loft data interpretation, and 3D model generation. No first articles are required for qualification. The government's acquisition approach will be determined by industry responses to a forthcoming Sources Sought notice on SAM.gov, which may result in either a small business set-aside or full and open competition. Standard delivery timelines include 180 days for material set-up, 180 days for production, and 90 days for follow-on delivery orders.

View the file

Other files

File Type Posted
EN Industry Day Brief.pptx PPTX presentation
Industry Day for HCS 3-4 Aug 26.pdf PDF
C-5 Honeycomb Panels SQS for Industry Day.pdf PDF
Industry Day for HCS 3-4 Aug 26.docx DOCX document
Industry Day for HCS 3-4 Aug 26.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Honeycomb Contract Strategy Timothy “Adam” Randall Contracting Officer

AFMC DLA/AW4

3 Aug 2026

448th Supply Chain Management Wing

UNCLASSIFIED

UNCLASSIFIED

CUI Registry: https://www.dodcui.mil/

Classification The classification of the brief is Unclassified

Supplying Warfighter Dominance

Government Intentions The Government’s plans and intentions are subject to change. Any formal request to provide information, collaboration or take any further action will be in writing to protect the interest of both the vendor and the Government.

Previous Honeycomb Panel Contract Strategy Previous 2 contracts were Multiple Award IDIQs between 3 Small Businesses (SBs) Only 26 different NSNs were awarded via a Delivery Order since 2020 Total dollars awarded via Delivery Orders since 2020 were $1,713,102

Honeycomb Panel Acquisition History

FY 20NSNQTYTotal Production Unit Cost
20201560-01-116-19193$46,500.00
1560-01-179-17046$36,660.00
1560-00-241-09952$164,262.00
1560-01-093-97962$16,650.00
1560-00-358-10911$19,915.00
Subtotal514$283,987.00
FY 21NSNQTYTotal Production Unit Cost
20211560-01-179-170410$61,100.00
1560-01-093-97961$8,325.00
1560-00-241-09951$82,131.00
1560-00-246-726916$71,200.00
1560-00-824-642518$111,780.00
1560-00-824-642618$111,780.00
1560-01-093-97961$8,325.00
1560-01-178-347023$140,530.00
Subtotal888$595,171.00
FY 23NSNQTYTotal Production Unit Cost
20231560-00-220-28825$93,125.00
1560-00-404-18031$6,500.00
1560-00-878-44352$23,607.00
1560-00-824-64812$23,607.00
1560-01-178-91835$32,011.00
1560-00-762-76435$53,474.00
1560-00-485-14691$27,661.00
1560-01-116-22235$60,175.00
1560-00-161-41345$36,725.00
1560-00-484-205712$80,700.00
1560-00-239-14991$7,036.00
1560-00-484-20601$6,105.00
Subtotal1245$450,726.00
FY 24NSNQTYTotal Production Unit Cost
20241560-00-878-44351$11,803.00
1560-00-824-64811$11,803.00
1560-00-404-18034$25,271.00
1560-00-484-20571$6,725.00
1560-01-116-19181$20,125.00
Subtotal58$75,727.00
FY 25NSNQTYTotal Production Unit Cost
20251560-00-220-28823$55,875.00
1560-00-492-12171$68,649.00
1560-00-120-01492$10,840.00
1560-00-824-64815$83,780.00
Subtotal411$219,144.00
FY 26NSNQTYTotal Production Unit Cost
20261560-00-220-28823$55,875.00
1560-00-227-89101$32,472.00
Subtotal24$88,347.00

Previous Honeycomb Panel Contract Strategy Each Delivery Order was competed among all 3 SBs 18 Delivery Orders since 2020 Largest DO was for $497K and Smallest DO was for $6,725 Average DO was $97,389.12

The goal was for each NSN to be awarded using LPTA (Total Evaluated Price based on the Material Set Up Fee + Production Unit Price) Speedy and requires no additional cost or price analysis due to adequate price competition IAW FAR15.403-1(b)(1)

Competition wasn’t always achieved, and as a result IAW R-DFARS 215.202-71 Only one offer, cost or price analysis was required Slow process and requires the Government to ask the contractor for justification of price and can be frustrating to the contractor who submitted a competitively priced quote originally

Current Honeycomb Panel Acquisition Strategy Industry Day Kick off 3-4 Aug 2026 to gain exposure of industry

Future Sources Sought Notice to be posted on SAM.gov Industry responses will drive either SB Set Aside or Full and Open Competition Lack of Industry Responses can hurt the Government’s acquisition strategy

Requirements to Remember CMMC Level 2 requirement by Nov 2026 IAW DFARS 252.204-7021 CMMC Implementation Phase 2 was set to begin on 10 Nov 2026; however, as of 13 Jul 2026, all CMMC Implementation Phase 2 requirements (and beyond) are suspended EJCP certified (DLA Requirement) IAW DLAD 25.79 Must be certified to receive Government data/drawings so you can bid on NSNs

Q&A for Everyone What issues are you experiencing in the market with suppliers?

Can any of the issues be forecasted or fixed?

Is there any way to get the material faster?

Are the Government delivery times realistic?

180 days for Material Set up 180 days for Production 90 days for a follow-on Delivery Order previously awarded/delivered

Do you have preference over a long-term contract that locks prices in for 2,3,4 years at a time OR break it up into multiple purchase orders each Fiscal Year that could be priced more accurately/aggressively?