The Contract_Documents.pdf is a comprehensive set of construction documents for the Leon County Supervisor of Elections Building Re-Roofing project located in Tallahassee, Florida. The project involves a complete roof replacement for approximately 60,000 square feet of low-slope roof system, including structural repairs and the potential replacement of up to ten rooftop-mounted HVAC units. The contract documents, prepared by Barnett Fronczak Barlowe & Shuler Architects and dated June 3, 2021, include detailed architectural, mechanical, electrical, and structural plans for a comprehensive roof renovation. The project scope includes removing existing roofing materials, installing new insulation, a PVC roof membrane, new scuppers and gutters, and raising and reinstalling existing rooftop equipment.
The project documents specify a high-performance roofing system with a targeted 20-year manufacturer's warranty, featuring 4-inch rigid insulation to raise the R-value to R-20, a fully adhered 80 mil PVC single-ply roofing membrane, and new metal parapet caps. The renovation includes mechanical system updates such as relocating and reinstalling HVAC units on new raised curbs, replacing gas piping, and updating electrical components. The contract appears to be funded through Leon County's capital improvement or maintenance budget, with an emphasis on energy efficiency, water management, and long-term building preservation. The comprehensive approach suggests a thorough modernization of the facility's roofing and supporting infrastructure.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OWNER
LEON COUNTY SUPERVISOR OF ELECTIONS
MARK S. EARLEY, SUPERVISOR
2990-1 APALACHEE PARKWAY
TALLAHASSEE, FL. 32301
TEL: 850-606-8683
FAX: 850-606-8601
ARCHITECT
BFB&S ARCHITECTS
2074 CENTRE POINTE BLVD, SUITE 200
TALLAHASSEE, FL 32308
TEL: 850-224-6301
www.bfbsa.com
MECHANICAL ELECTRICAL
TOMAHAWK ENGINEERING & CONSULTING
1940 BUFORD BLVD.
TALLAHASSEE, FL 32308
TEL: 850-402-3040
www.tomahawkengineering.com
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
CS-1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
COVER SHEET
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
PROJECT LOCATION
MAP
AERIAL
PHOTOGRAPH
LEON COUNTY SUPERVISOR OF ELECTIONS
RE-ROOFING
2900-1 Apalachee Parkway Tallahassee, Florida 32301
N
2990-1 APALACHEE PARKWAY
TALLAHASSEE, FL. 32301
PROJECT
DIRECTORY
A101
SIM BUILDING SECTION LETTER
SECTION NUMBER
SHEET NUMBER
BUILDING
SECTION
A101
SIM WALL SECTION NUMBERWALL
SECTION
A101
SIM DETAIL NUMBER
SHEET NUMBER
DETAIL
0 COLUMN LETTER OR NUMBER
A - 9
A - 8
A - 7
A
Room name
A
ROOM NAME AND NUMBER
DOOR NUMBER
WINDOW TYPE (INTERIOR)
P-1 WALL PARTITION TYPE
1i WINDOW TYPE (EXTERIOR)A
B
CARD READERC.R.
90 MIN FIRE RATING
FIRE EXTINGUISHER CABINET
FIRE EXTINGUISHER ON BRACKET -
DOOR HOLD OPENH.O.
A101
SIM
A - 9
DETAIL NUMBER
BUILDING ELEVATION LETTERBUILDING
ELEVATION
A101
INTERIOR ELEVATION LETTERINTERIOR
ELEVATION
FEC
FEB
SHEET NUMBER
SHEET NUMBER
SHEET NUMBER
SHEET NUMBER
A101
1 Ref
R e f
1 Ref
R e f
1 Ref
R e f
1 Ref
R e f
METAL STUD WALL
STRUCTURAL STEEL FRAMING
REVISION CLOUD
REVISION NUMBER
NORTH ARROW
SPOT ELEVATION
ELEVATION HEIGHT
EL. 0.0
CONCRETE MASONRY
EARTH/COMPACT FILL
PORUS FILL/ GRAVEL
CONCRETE
SAND, MORTAR, GYPSUM BOARD, PLASTER
INFILL CONSTRUCTION
COLUMN LINE / CENTER LINE
PROPERTY LINE
HIDDEN LINE (BEYOND)
BREAK LINE
WOOD- CONTINUOUS/ NON CONTINUOUS
FINISH WOOD
BATT INSULATION
RIGID INSULATION
BLOCK
PLYWOOD
FACE BRICK
GYP. BD.
COND.
DIA., D.
AMP.,A
APPROX.
BLDG.
ARCH.
INCAND.
DWG.(S)
EQUIP.
B.T.U.
COMP.
J.B.
JCT.
JT.
INSUL.
INT.
HDWE
HYD.
H.&V.
I.D.
G.P.M.
H.C.
HT.
H.M.
HTG.
HR.
H.P.
GR.
GWB
H.B.
GALV.
G.F.E.
GAL.
GL.
GND.
FTG.
FP
FT.
GA.
FVC
EXT.
F.D.
FL.
FIN.
F.H.C.
F.E.C.
F.E.
EXIST.
F.C.
F.B.C.
F.A.
EXP.
E.J.
E.W.C.
EXH.
EA.
EQ
ELEV
E.F.
E.C.
BM.
DN.
E
D.S.
DR.
DIFF.
D.J.
DIST.
DIM.
DISC.
CT
DET
CU
C.T.B.
CONN.
CJ
CONT.
CONC.
CL
C.M.U.
CPT
C.O.
CLG.
COL.
C.F.M.
C.I.
CIRC.
CKT.
CER.
CAB.
CAP.
C/B
C.D.
C
LC
BAL.
BRG.
B
BD.
BLK.
AN
ALUM.
ALT.
A.C.
ACP
A.F.F.
A.H.U.
A.C.T.
AJ
JUNCTION BOX
JOINT
JUNCTION
INCANDESCENT
INSULATION
INTERIOR
HARDWARE
HYDRANT
INSIDE DIAMETER
HEATING & VENTILATING
WASTE CLEAN OUT
WIDE FLANGE
WINDOW DIMENSION
WATER CLOSET
WEATHERPROOF
WATER GAGEW.G.
WP.
W.C.O.
WD.
W.D.
WF
W.C.
WOOD
GALLONS PER MINUTE
HANDICAP
HOLLOW METAL
HIGH POINT
HEIGHT
HEATING
HOUR
GYPSUM BOARD
GYPSUM WALLBOARD
HOSE BIBB
GRILLE
GOVERNMENT FURNISHED EQUIPMENT
GALVANIZED
GALLON
GLASS
GROUND
FIRE PROOFING
FOOT-FEET
FIRE VALVE CABINET
FOOTING
GAUGE
VENTILATION
VINYL COMPOSITION TILE
VERTICAL EXPANSION JOINT
VERTICAL
VERIFY IN FIELD
VENT THRU ROOFV.T.R.
VERT.
W.
V.I.F.
W/
WATT
WITH
VENT.
V.E.J.
V.C.
VT
V. VOLT
TELEPHONE
TEMPERATURE
THRESHOLD (THRESH)
TYPICAL
UNLESS NOTED OTHERWISE
TOP OF WALL (BEAM)T.O.W.(B)
TYP.
TOIL.
UNO
UR. URINAL
TOILET
THD.
TEMP.
THK.
T
THICK
EXTERIOR
FIRE EXTINGUISHER & CABINET
FIRE EXTINGUISHER & BRACKET
FIRE HOSE CABINET W/ EXTINGUISHER
FLORIDA BUILDING CODE
FLOOR DRAIN
FLOOR
FINISH
FIRE ALARM
FLEXIBLE CONNECTION
EXISTING
ELECTRIC WATER COOLER
EQUIPMENT
EXPANSION
EXPANSION JOINT (EJ)
EXHAUST
ELEVATION
EXHAUST FAN
EMPTY CONDUIT
FLOOR ELEVATION
EACH
EQUAL
SHEETSHT.
STAND PIPE
SPECIFICATIONS
STORAGE
STAINLESS STEEL
STRAIGHT RESILIENT BASE
SUSPENDED
STRUCTURAL
STOR.
SUSP.
STRUC.
STL
SW.
STEEL
SWITCH
SPEC.
SQ. FT.
SP
SS
SRB
REVOLUTION/MINUTE
ROUGH OPENING
SECTION
SUPPLY AIR
SCHEDULE
RAIN WATER LEADER
SERVICE
SUPPLY GRILLE
SUSPENDED ACOUSTICAL TILE
SECT.
SCH.
S.A.T.
SERV.
S.G.
R.P.M.
R.O.
RM.
S.A.
RWL
ROOM
NOT IN CONTRACTN.I.C.
BEAM
COMPRESSER
DOWN
DRAWING (S)
DOWNSPOUT
EAST
DRAIN
DIFFUSER
DUMMY JOINT
DISTRIBUTION
DISCONNECT
DIMENSION
CERAMIC TILE
DIAMETER
CONDENSING UNIT
CERAMIC TILE BASE
DETAIL
CONNECTION
CONTINUOUS
CONDENSATE
CONTROL JOINT
CONCRETE
RETURN AIR GRILLER.A.G.
ROOF DRAIN
RETURN AIR REGISTER
REGISTER
REINFORCING
RECEPTACLE
RECIRCULATING
RETURN GRILLE
REQUIRED
RECP.
REG.
REINF.
REQ.
R.G.
RET. RETURN
R.A.R.
RDY.
RECIRC.
RD.
R.D.
ROUND
READY
QUARTER
QUANTITY
QUARRY TILE
RETURN AIR
PAINTED
PRESSURE TREATED
QUAN.
RAD.
R
R.A.
RADIUS
RADIUS
QTR.
PTD.
QT
P.T.
PAINT
CONCRETE MASONRY UNIT
CLEAR
CLEAN OUT
CARPET
CEILING
COLUMN
CAST IRON
CIRCULATING
CIRCUIT
CERAMIC
CAPACITY
CENTER LINE
CIRCUIT BREAKER
CEILING DIFFUSER
CABINET
CONDUIT
BALANCE
BRITISH THERMAL UNIT
BEARING
PLUMBING
PLYWOOD
PERIMETER
PRECAST CONCRETE
POUNDS/SQUARE INCH
POUNDS/SQUARE INCH GAGE
PNL.
PSTG.
PSI
PER.
PLBG.
PLYW'D
PL.
PC
PLATE
NUMBER
NOT TO SCALE
ON CENTER
OPENING
OPPOSITE
PLASTIC LAMINATE
OVERHEAD
OUTSIDE DIAMETER
PARTITION
OPP.
P. LAM
OPNG.
PART.
O.H.
NO.
NTS
O.D.
O.C.
ARCHITECTURAL
BOTTOM
BOARD
BLOCK
ANODIZED
ALUMINUM
APPROXIMATELY
AIR CONDITIONED
ACOUSTICAL TILE
ACOUSTICAL PANEL
ABOVE FINISH FLOOR
ACOUSTICAL JOINT
AIR HANDLING UNIT
MODIFIED BITUMEN
MOISTURE RESISTANT
MASONRY OPENING
MISCELLANEOUS
MOUNTING
MOUNTED
METAL THRESHOLD
NOT APPLICABLE
MTD.
MTG.
N
N.A.
NORTH
MISC.
MOD.BIT.
MR
M.T.
MO
MIN. MINIMUM
MAINTENANCE
MAXIMUM
MECHANICAL
MAIN DISTRIBUTION PANEL
MOTORM.
M.D.P.
MECH.
MAX.
MAINT.
MTL. METAL
E.W. EACH WAY
ON CENTER EACH WAYO.C.E.W.
AMP.,A
IN.
EL
INCHES
WELDED WIRE FABRIC
WEATHERPROOF
W.W.F.
WP.
VITROUS CLAY
TEL.
SQUARE FEET
PT
PSF
PANEL
BUILDING
AMPERES
ALTERNATE
CUBIC FEET PER MINUTE
POUNDS/SQUARE FOOT
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
CS-2
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
INDEX
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
Checker
INDEX OF DRAWINGSABBREVIATIONSGENERAL LEGEND
CS-1
CS-2
CS-3
COVER SHEET
INDEX SHEET
GENERAL AND MISC. NOTES
ARCHITECTURAL
A0.1 A1.1 A1.2 A2.1 A3.1 A4.1 A5.1 A5.2 A5.3
SITE PLAN
EXISTING AND DEMOLITION ROOF PLAN
ROOF PLAN - NEW WORK
BUILDING ELEVATIONS
ROOF SECTIONS
ROOF DETAILS AND ROOF SECTIONS
PHOTO DOCUMENTATION - LOW ROOF
PHOTO DOCUMENTATION - LOW ROOF
PHOTO DOCUMENTATION - HIGH ROOF ELECTRICAL
MECHANICAL
APPLICABLE CODES
OCCUPANCY
BUILDING
ACCESSIBILITY
MECHANICAL
ENERGY CONSERVATION
FUEL GAS
PLUMBING
FIRE PREVENTION
ELECTRICAL
FLORIDA BUILDING CODE (FBC-B) 2020, 7TH EDITION
FLORIDA BUILDING CODE 2020, 7TH EDITION
FLORIDA BUILDING CODE (FBC-M) 2020, 7TH EDITION
FLORIDA BUILDING CODE 2020, 7TH EDITION
FLORIDA BUILDING CODE (FBC-FG) 2020, 7TH EDITION
FLORIDA BUILDING CODE (FBC-P) 2020, 7TH EDITION
FLORIDA FIRE PREVENTION CODE (FFPC) 2018, 7TH EDITION
NATIONAL ELECTRICAL CODE (NEC) (per FBC) 2017 (per 7th Ed. FBC-B)
M0.1
MD1.1
MD1.2
MD2.1
M1.1 M1.2 M2.1 M5.1 M5.2 M6.1
LEGEND, NOTES AND SCHEDULES - MECHANICAL
PARTIAL FLOOR PLAN - DEMOLITION - MECHANICAL
PARTIAL FLOOR PLAN - DEMOLITION - MECHANICAL
ROOF PLAN - DEMOLITION - MECHANICAL
PARTIAL FLOOR PLAN - RENOVATION - MECHANICAL
PARTIAL FLOOR PLAN - RENOVATION - MECHANICAL
ROOF PLAN - RENOVATION - MECHANICAL
DETAILS - MECHANICAL
CONTROLS - MECHANICAL
GAS PIPING ISOMETRIC, SPECS & DETAILS - MECHANICAL
E0.1
ED2.1
E1.1 E2.1 E6.1 E7.1
LEGEND, NOTES AND SPECS - ELECTRICAL
ROOF PLAN - DEMOLITION - ELECTRICAL
EXISTING PARTIAL FLOOR PLAN - ELECTRICAL
ROOF PLAN - RENOVATION - ELECTRICAL
RISER DIAGRAMS - ELECTRICAL
PANEL SCHEDULES - ELECTRICAL
STRUCTURAL
S1.01 ROOF WIND DIAGRAM
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
CS-3
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
GENERAL AND
MISC. NOTES
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
GENERAL NOTES
1. THE EXISTING OVERALL ROOF PLANS ARE FOR INFORMATIONAL PURPOSES ONLY. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS, ALL PROJECTIONS THROUGH
ROOFS, AND ALL CONDITIONS.
2. BEFORE SUBMITTING PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD TO HAVE EXAMINED THE PREMISES AND SATISFIED HIMSELF AS TO THE EXISTING CONDITIONS UNDER WHICH HE WILL BE OBLIGED TO OPERATE AND COMPLETE THE WORK UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS
CONNECTION ON BEHALF OF THE CONTRACTOR FOR ANY ERROR OR NEGLIGENCE ON HIS PART.
3. NORMAL OPERATIONS OF THE FACILITY SHALL CONTINUE DURING DEMOLITION AND CONSTRUCTION. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE THE WORK WITH ALL SUBCONTRACTOR AND SEQUENCE DEMOLITION AND CONSTRUCTION TO MINIMIZE INTERRUPTIONS TO NORMAL OPERATIONS OF THE FACILITY.
4. ALL PROPOSED INTERRUPTIONS TO OPOERATIONS, SERVICES AND EQUIPMENT SHALL BE REVIEWED WITH AND APPROVED BY OWNER PRIOR TO STARTING SUCH WORK.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING EXIT WAYS CLEAR. WHERE AN EXIT MUST BE TEMPIRARILY BLOCKED, CONTRACTOR SHALL PROVIDE THE
REQUIRED BARRICADES AND DIRECTIONAL SIGNS FOR TEMPORARY EXITING AND SAFETY.
6. CONTRACTOR SHALL ERECT AND MAINTAIN ALL REASONABLE SAFEGUARDS FOR SAFETY AND HEALTH, INCLUDING POSTING DANGER SIGNS AND OTHER WARNING
AGAINST HAZARDS, AS WELL AS PROMULGATING SAFETY REGULATIONS.
7. CONTRACTOR SHALL BE RESTRICTED TO AREAS SPECIFIED BY THE OWNER FOR ON SITE STORAGE OF CONSTRUCTION MATERIALS.
8. CONTRACTOR SHALL TAKE CARE TO DISTRIBUTE LOAD OF EQUIPMENT AND MATERIALS ON ROOF DURING ALL PHASES OF CONSTRUCTION. CONTRACTORS
RESPONSIBILITY NOT TO EXCEED DESIGN LOAD OF EXISTING ROOF STRUCTURE. CONTRACTOR SHALL NOT USE ANY ROOF AREA OUTSIDE AREAS OF THE WORK AND
COMPLETED ROOF AREAS FOR STORAGE, STAGING, OR WORKING.
9. CONTRACTOR SHALL TAKE CARE NOT TO DAMAGE EXISTING SURFACES, AND SHALL BE RESPONSIBLE FOR RETURNING ALL DISTURBED SOD AND REPAIR ALL DAMAGED AREAS (MATERIALS, FINISHES, LANDSCAPING, ETC.) EQUAL TO THEIR ORIGINAL CONDITION. SURFACES SHALL BE REPAIRED TO MATCH THE EXISTING ADJACENT
UNDAMAGED SURFACES.
10. CONTRACTOR SHALL MAINTAIN A CLEAN WORK PREMISE AT ALL TIMES AND SHALL CLEAN CONSTRUCTION SITE OF ALL DEBRIS AT COMPLETION OF THE JOB AND BEFORE
FINAL PAYMENT IS MADE.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR ALLWATER INSTRUSION AND WATER DAMAGE TO THE BUILDING INTERIOR DURING CONSTRUCTION.
12. CONTRACTOR SHALL PROVIDE A PORTABLE FIRE EXTINGUISHER (MINIMUM 25 LB ABC) AT EACH TORCH, OR OPEN FLAME, ON THE ROOF.
13. ALL ROOF SCUPPERS AND DOWNLEADERS SHALL BE INSPECTED, CLEANED, AND FREE FLOWING DURING, AND UPON COMPLETION OF REROOFING.
14. ALL NEW ROOFING AND FLASHING MEMBRANES, LIQUID APPLIED MEMBRANE FLASHING, SEALANTS AND ROOF ACCESSORIES PROVIDED BY ROOFING MANUFACTURER
SHALL BE CONSIDERED A “ROOFING SYSTEM” AND SHALL PROVIDE UL CLASS ‘A’ FIRE RATING AND F.M. CLASS 1-90 WIND UPLIFT CLASSIFICATION FOR 120 MPH WIND ZONE.
15. ALL FLASHING SHALL CONFORM TO MANUFACTURER’S RECOMMENDATIONS, AND COMPLY WITH RECOMMENDED DETAILS OF NRCA ROOFING AND WATERPROOFING
MANUAL AND ARCHITECTURAL SHEET METAL MANUAL, BY THE SHEET METAL AND AIR CONDITIONING CONTRACTORS NATIONAL ASSOCIATION, INC. (SMACNA).
16. CONTRACTOR/INSTALLER SHALL SUBMIT WRITTEN PROOF OF ACCEPTANCE OR APPROVAL FROM THE ROOFING MANUFACTURER FOR THIS ROOFING SYSTEM.
17. CONTRACTOR AND INSTALLER SHALL PROVIDE THREE YEAR WARRANTY WITH NON-PRORATED, NO PENAL SUM, AND NO DOLLAR LIMIT ON MATERIAL AND LABOR ON
ROOFING, WATERPROOFING, AND SEALANTS.
18. JOINT SEALANT MANUFACTURERS TO PROVIDE 20 YEAR WARRANTY ON SILICONE SEALANT. PAINT/COATING MANUFACTURERE TO PROVIDE A 5 YEAR WARRANTY.
19. ROOFING MANUFACTURER TO PROVIDE SPECIFIED 20 YEAR WARRANTY, WITH NON-PRORATED, NO PENAL SUM, AND NO DOLLAR LIMIT WARRANTY TO INCLUDE THE ROOF
SYSTEM.
20. CONTRACTOR SHALL SEPARATE ALL DISSIMILAR METALS WITH TAPE OR COATING.
21. ALL WORK SHALL COMPLY WITH APPLICABLE OSHA AND E.P.A. REGULATIONS AND GUIDELINES.
22. ALL WORK SHALL COMPLY WITH THE FLORIDA BUILDING CODE SEVENTH EDITION 2021.
23. CONTRACTOR SHALL LIST AN EMERGENCY TELEPHONE NUMBER WHERE HE OR SHE MAY BE REACH 24 HOURS A DAY, SEVEN DAYS A WEEK, DURING THE ENTIRE PERIOD
OF CONTRACT TIME. THIS TELEPHONE NUMBER SHALL BE PROVIDED AT THE PRECONSTRUCTION CONFERENCE.
24. CONTRACTOR TO INSPECT METAL ROOF DECK AND REMOVE DAMAGED METAL DECKING AND PREP FOR NEW METAL DECKING TO BE INSTALLED.
DEMOLITION NOTES
CAUTION: CONTRACTOR TO PROVIDE WORKER SAFETY BARRICADES AT ROOF EDGES IN ACCORDANCE WITH OSHA REGULATIONS.
1. CONTRACTOR SHALL FIELD VERUFY ALL THE ITEMS TO BE REMOVED AS INDICATED ON THE PLANS WITHIN THE WORK AREA. CONTRATOR IS RESPONSIBLE FOR ALL
DEMOLITION AND RENOVATION AS REQUIRED FOR NEW WORK.
2. CONTRACTOR SHALL COORDINATE ALL DEMOLITION WORK WITH MECHANICAL, PLUMBING, AND ELECTRICAL SUBCONTRACTORS. THE CONTRACTOR SHALL TAKE THE NECESSARY PRECAUTIONS IN INSTALLING THE ROOFING SYSTEM WITHOUT DAMAGING THE ELECTRICAL CONDUIT OR CONDUCTORS. DAMAGED CONDUIT AND/OR
CONDUCTORS SHALL BE REPLACED TO MATCHED EXISTING.
3. REMOVE ALL EXISTING GUTTER AND DOWNSPOUT SYSTEM FRO THE ROOFS WEST PREIMETER EDGE.
4. REMOVAL ALL VTR FLASHING, PERIMETER FLASHING, COUNTERFLASHING, MEMBRANE FLASHING, ANY ABANDONED ROOF EQUIPMENT IDENTIFIED BY OWNER, CURBS AND
WOOD BLOCKING/NAILERS AS NOTED. REMOVE EXISTING EXPANSION JOINT, COUNTERFLASHING AND MEMBRANE FLASHING (UNLESS NOTED OTHERWISE).
5. REMOVE THE EXISTING GRAVEL, B.U.R. ROOFING INSULATION AND FLASHING SYSTEMS DOWN TO THE STRUCTURAL METAL ROOF DECK.
6. EXISTING EXHAUST FANS/VENTS ARE TO BE TEMPORARILY REMOVED/RAISED, AND REINSTALLED ON RAISED CURBS AS REQUIRED ABOVE NEW ROOF SYSTEM WITHOUT
INTERRUPTION OF FACILITY OPERATIONS (UNLESS NOTED OTHERWISSE).
7. TEMPORARILY RAISE ROOFTOP HVAC EQUIPMENT AND REMOVE ROOF CURBS. TEMPORARILY SHORE UP ALL EQUIPMENT LINES DURING CONSTRUCTION. TEMPORARILY
DISCONNECT REFRIGERANT AND ELECTRICAL LINES TO EQUIPMENT AS REQUIRED TO RAISE EQUIPMENT.
8. CONTRACTOR TO PROTECT EQUIPMENT AND FINISHES BELOW ROOF DURING ROOFING OPERATION INVOLVING PENETRATION OF THE ROOFING SYSTEM OR OPENING OF
ROOF DECK TO BELOW. EQUIPMENT AND FACILITY TO REMAIN OPERATIONAL AT ALL TIMES.
9. CLEAN AND PREPARE ROOF DECK TO RECEIVE NEW ROOFING SYSTEM.
GENERAL PLUMBING NOTES
1. PRIOR TO BIDDING, FIELD VERIFY ALL PLUMBING MODIFICATIONS AND VENTS FOR ROOFING WORK.
2. PRIME CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WORK OF ALL SUBCONTRACTORS.
3. TAKE CARE NOT TO DAMAGE EXISTING EQUIPMENT AND REPAIR TO MATCH EXISTING CONDITIONS, AS REQUIRED.
4. EXTEND PLUMBING VENTS OR VTRS TO ABOVE NEW ROOF AS REQUIRED. INSTALL NEW VTR PIPE TO 10” HEIGHT ABOVE NEW ROOF ELEVATION. CONTRACTOR SHALL PLAN
BEFORE COMMENCING THE WORK AND COORDINATE ANY INTERRUPTION OF FACILITY OPERATIONS WITH THE OWNER.
5. CONTRACTOR SHALL SUBMIT PROPOSED DRAINAGE SYSTEM ROUTE/PLAN AND VERIFY THERE ARE NO OBSTRUCTIONS TO PREVENT REQUIRED SLOPE/FALL.
ROOF RENOVATION NOTES
1. AFTER REMOVAL OF EXISTING INSULATION AND FLASHING SYSTEMS, CLEAN THE EXISTING METAL DECK AND PREP FOR NEW ROOF SYSTEM. PATCH AND REPAIR AS
REQUIRED.
2. RAISE ALL ROOFTOP EQUIPMENT CURBS, VTRs, PENETRATIONS AND EXPANSION JOINTS TO A MINIMUM OF 10” ABOVE THE FINISHED ROOF SURFACE. CLEAN, PRIME AND
PAINT (2) COATS PREVIOUSLY COATED ROOFTOP EQUIPMENT.
3. INSTALLS NEW ‘C’ STUD METAL FRAMING WALL BETWEEN LOW AND HIGH ROOFS WITH BATT INSULATION INFILL AND ½” CDX PLYWOOD SHEATHING TO PROVIDE A
CONSISTENT UNIFORM WALL FACE, AS DETAILED.
4. INSTALL NEW ISOCYANURATE INSULATION AND A ½” HIGH DENSITY COVERBOARD, RAISING THE OVERALL R-VALUE TO R-20. INSTALL NEW TAPERED ISOCYANURATE INSULATION AND ½” HIGH DENSITY COVERBOARD AT CRICKETS WHERE INDICATED, ELIMINATING ANY PONDING AND ENSURING PROPER DRAINAGE.
5. INSTALL FULLY ADHERED HIGH SOLAR REFLECTANCE INDEX (SRI) 80 MIL PVC SINGLE-PLY ROOFING MEMBRANE WITH ADHERED 60 MIL PVC FLASHING SYSTEM WITH LOW RISE FOAM ADHESIVE ACCORDING TO ROOFING MANUFACTURER’S SPECIFICATIONS AND RECOMMENDATIONS OVER THE PREVIOUSLY INSTALLED TO PROVIDE A MANUFACTURER’S 20 YEAR NDL WARRANTY. USE A HEAVY ROLLER TO ENSURE PROPER ADHESIVE DISPLACEMENT AND HEAT WELD ALL LAPS AND SEAMS, AS REQUIRED.
6. INSTALL MANUFACTURER’S PVC BOOT FLASHING AT VTRs AND PIPE PENETRATIONS. INSTALL STAINLESS STEEL DRAW BAND AND SEAL TOP EDGE WITH MANUFACTURER APPROVED SEALANT. INSTALL PVC FLASHING AT ROOFTOP EQUIPMENT CURBS AS DETAILED, HEAT WELD ALL SEAMS AS REQUIRED. INSTALL TERMINATION BAR AT THE TOP OF FLASHING WITH FASTENERS 8” O.C. INSTALL PREFINISHED ALUMINUM COUNTERFLASHING OVER TERMINATION BAR AND SEAL TOP EDGE WITH MANUFACTURER
APPROVED SEALANT.
7. INSTALL PVC FLASHING MEMBRANE UP AND OVER RAISED EXPANSION JOINTS. HEAT WELD LAPS AND SEAMS AS REQUIRED. INSTALL NEW PREFINISHED ALUMINUM
EXPANSION JOINT CAP WITH SEALED JOINT COVERS ON THE EXPANSION JOINT.
8. FULLY ADHERE MANUFACTURER’S WALK TREAD/PROTECTIVE MEMBRANE ON SERVICEABLE SIDE OF EXHAUST FANS, ROOFTOP MECHANICAL EQUIPMENT AND THE OWNERS DESIGNATED ACCESS LOACTION. INSTALL TO MANUFACTURER’S REQUIREMENT AFTER THE ROOFING MEMBRANE AND FLASHING LAPS AN JOINTS HAVE BEEN INSPECTED AND APPROVED BY THE MANUFACTURER’S TECHNICAL REPRESENTATIVE. WALK TREAD COLOR TO CONTRAST THE FINISHED ROOF SURFACE.
GENERAL MECHANICAL NOTES
1. PRIOR TO BIDDING, FIELD VERIFY ALL MECHANICAL MODIFICATIONS FOR ROOFING WORK.
2. CONSTRACTOR SHALL INITIALLY TEST ALL APPLICABLE MECHANICAL EQUIPMENT WITHIN 14 DAYS OF NTP. CONTRACTOR SHALL IMMEDIATELY NOTIFY ARCHITECT AND
OWNER OF ANY NON-OPERATING EQUIPMENT.
3. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WORK OF ALL SUBCONTRACTORS.
4. TAKE CARE NOT TO DAMAGE EXISTING EQUIPMENT AND REPAIR TO MATCH EXISTING CONDITIONS AS REQUIRED.
5. TEMPORARY SHORE UP EXHAUST FANS, AND FAN UNITS, CONDENSING UNITS. EXTND DUCT, CONDUIT, ELECTRICAL WIRE, CONTROL WIRING, AND ASSOCIATED PIPE AS
REQUIRED. RAISE CURBS, INSTALL NEW CURBS TO REQUIRED HEIGHT FROM NEW ROOF DECK ELEVATION TO RAISE HVAC UNITS ABOVE NEW ROOF SURFACE, AS REQUIRED. SEE MECHANICAL AND ELECTRICAL SPECIFICATIONS. CONTRACTOR SHALL PLAN BEFORE COMMENCING THE WORK AND COORDINATE ANY INTERRUPTION OF
FACILITY OPERATIONS WITH THE OWNER.
6. TEMPORARILY SHUT DOWN, CAP OR COVER OUTSIDE AIR INTAKE VENTS, IN AREAS OF WORK. TAJE REQUIRED PRECAUTIONS TO AVOID ADHESIVE FUMES ENTERING BUILDING. COORDINATE INTERRUPTION OF EQUIPMENT WITH OWNER AND BUILDING MAINTENANCE MANAGER.
WORK NOTES
THESE WORK ITEMS ARE TYPICAL AND MAY NOT BE ALL INCLUSIVE BUT INTENDED TO SUPPLEMENT THE DRAWINGS AND DETAILS AND CLARIFY THE SCOPE OF WORK. WORK LEGEND ITEMS ARE TYPICAL FOR SITUATIONS AND WORK SCOPE SHOWN. WORK LEGEND SYMBOLS ARE NOT SHOWN AT EVERY SPECIFIC LOCATION WHICH SCOPE IS TO BE
COMPLETED, UNLESS OTHERWISE NOTED.
1. REMOVE EXISTING ROOFING AND FLASHING SYSTEM AND INSULATION DOWN TO THE METAL DECK. CLEAN THE EXISTING DECK SURFACE REPLACING DAMAGED METAL DECK AS REQUIRED. INSTALL RIGID ISOCYANURATE INSULATION WITH A ½” HIGH DENSITY COVERBOARD, WITH A HIGH SRI 80 MIL PVC FLEECE BACKED CAP SHEET
ROOFING AND 60 MIL PVC FLASHING SYSTEM.
2. REMOVE EXISTING ROOF SCUPPERS ON NORTH AND SOUTH SECTION OF ROOG AND PREP FPR NEW SCUPPERS OPENING AS REQUIRED.
3. REMOVED ABANDONED/UNUSED ROOFTOP EQUIPMENT AND CURBS WHERE INDICATED. INSTALL HEAVY GAUGE METAL DECKING TO MATCH EXISTING.
4. INSTALL NEW ROOFTOP EQUIPMENT CURBS, VTR PENETRATIONS, AND EXPANSION JOINTS TO A MINIMUM OF 10” ABOVE THE FINISHED ROOF SURFACE.
5. RAISE EXPANSION JOINT TO A MINIMUM OF 10” ABOVE THE NEW FINISHED ROOF SURFACE AND INSTALL PREFINISHED ALUMINUM METAL EXPANSION JOINT CAP, AS
DETAILED.
6. REMOVE EXISTING GUTTER AND DOWNSPOUT SYSTEM AT WEST PERIMETER EDGE. PREP FOR NEW GUTTER AND DOWNSPOUTS
GENERAL ELECTRICAL NOTES
1. PRIOR TO BIDDING, FIELD VERIFY ALL ELECTRICAL MODIFICATIONS FOR ROOFING WORK.
2. CONTRACTOR SHALL INITIALLY TEST ALL APPLICABLE ELECTRICAL SYSTEMS WITHIN 14 DAYS OF NTP. CONTRACTOR SHALL IMMEDIATELY NOTIFY ARCHITECT OF NON-
OPERATIONAL SYSTEMS.
3. DISCONNECT, REROUTE, EXTEND AND REONNECT CONDUITS TO ALLOW FOR ELECTRICAL, TELECOMMUNICATION/DATA CONNECTION TO RELOCATED EQUIPMENT AT NEW
ROOF AS DETAILED. PROVIDE NEW CONDUIT AND WIRE FROM THE EXISTING JUNCTION BOX TO THE CONNECTION POINT.
4. CONTRACTOR SHALL, UPON COMPLETION OF WORK, ENSURE ALL CIRCUITS ADJACENT TO THE ROOFING WORK AREAS ARE IN PROPER WORKING CONDITIONS.
5. CONTRACTOR SHALL COORDINATE WORK WITH ELECTRICAL WORK. CONTRACTOR SHALL REROUTE ALL ROOF TOP CONDUIT ELECTRICAL, CONTROL, TELEPHONE, AND
COMMUNICATION CABLE SERVICE ABOVE NEW ROOF SYSTEM AS REQUIRED. VERIFY AND CONFIRM WITH OWNER TO REMOVE ALL ABANDONED ELECTRICAL, TELEPHONE, AND COMMUNICATION CABLE SERVICE ABOVE EXISTING ROOF. CONDUIT TO BE SUPPORTED ON PILLOW BLOCK PIPE SUPPORT AT 4’ O.C. OVER NEW ROOF.
6. CONTRACTOR SHALL INITIALLY TEST ALL APPLICABLE ELECTRICAL SYSTEMS WITHIN 14 DAYS OF NTP. CONTRACTOR SHALL IMMEDIATELY NOTIFY PROJECT DIRECTOR OF
NON-OPERATIONAL SYSTEMS.
WIND PRESSURE NOTES
1. Numbers on this sheet are the components and cladding gross unfactored pressures perpendicular to the surface (in P.S.F.) based on tributary area. Multiply service pressures by 1.67 to obtain W pressures for factored loads using strength design (ASCE 7-16 2.3).
2. Pressures are derived from ASCE 7-16.
3. Directionality factor Kd = .85
4. Negative pressures act away from surface, positive pressures act toward surface.
5. Parapet pressures are the resultant force from positive wall and negative roof pressures
6. All dimensions shown are measured perpendicular to surface.
WIND PRESSURE LEGEND
Denotes wind pressure zone
Denotes wind load separation
12' - 10"
12' - 10"
12' - 10"
1' 111 1'
2 2 1L 2
2L
2L
12' - 10"
3 3
3 3 3
12' - 10"12' - 10" 12' - 10"
2o
3o
2o
2o
GENERAL NOTES
GN-1 The governing Code for this Project is the Florida Building Code, 7th Edition (2020). This Code prescribes which edition of each referenced standard applies to this Project. This is a reroof only and no other structural changes are anticipated.
GN-2 To the best of our knowledge, the Structural Drawings and Specifications comply with the applicable requirements of the governing Building Code.
GN-3 Construction is to comply with the requirements of the governing Building Code and all other applicable Federal, State, and Local Codes, Standards, Regulations and Laws.
GN-4 Use these Notes in conjunction with the Plan Specifications or Project Specifications. If a conflict exists, the more stringent governs.
GN-5 See Plan Specifications or Project Specifications for testing.
GENERAL NOTES - CONTRACTOR REQUIREMENTS
GN-6 Contractor refers to the General Contractor, Construction Manager, or the organization that is assigned to have overall responsibility and supervision of the Project.
GN-7 The Contractor shall be solely responsible for, and have control over, the means, methods, supervision, techniques, sequences, procedures of construction, quality, and correctness of the work. The Contractor is solely responsible for jobsite safety including all OSHA requirements.
GN-8 The Contractor shall coordinate all Contract Documents with field conditions and dimensions and Project Shop Drawings prior to construction. Do not scale drawings; use only printed dimensions. Report any discrepancies in writing to the Architect prior to proceeding with work. Do not change size or location of structural members without written instructions from the Structural Engineer of Record.
GN-9 Contractors who discover discrepancies, omissions or variations in the Contract Documents during bidding shall immediately notify the Architect. The Architect will resolve the condition and issue a written clarification.
GN-10 The Contractor shall protect adjacent property, his own work and the public from harm. The Contractor is advised to document the condition of adjacent property with a photographic survey and other documentation, including crack monitoring, prior to and during construction.
GENERAL NOTES - DRAWINGS
GN-11 The Structural drawings shall be used in conjunction with the architectural drawings and all other drawings and documents, including shop drawings prepared by equipment suppliers and delegated engineers.
GN-12 See Architectural drawings for waterproofing details and requirements.
GENERAL NOTES - DESIGN LOADS
GN-13 Design Wind Loads:
Governing Code FBC 7th Edition (2020) / ASCE 7-16 Building Risk Category II Ultimate Wind Speed Vult = 120 mph Allowable Stress Design Wind Speed Vasd = 93 mph Mean Roof Height 21 feet Directionality Factor Kd = 0.85 Gust-Effect Factor G = 0.85
Exposure C Internal Pressure Coefficient GCpi = +/- 0.18
S T R U C T U R A L N O T E S
ROOF WIND PRESSURES (PSF)
ZONES
TRIBUTARY AREA (SF)
10 20 50 100 200 500
1 -33/+10 -31/+10 -28/+10 -26/+10 -24/+10 -21/+10
1' -19/+10 -19/+10 -19/+10 -19/+10 -16/+10 -13/+10
1L -33/+19 -31/+18 -28/+17 -26/+16 -24/+16 -21/+14
2 -43/+10 -40/+10 -37/+10 -34/+10 -31/+10 -28/+10
2L -43/+19 -40/+18 -37/+17 -34/+16 -31/+16 -28/+14
3 -59/+10 -53/+10 -46/+10 -40/+10 -35/+10 -28/+10
NO. 69782NO. 69782
L I C E N S
E
P R
O F
E
S S
I O NA L E N
G
I N
E E
R
F L
O R I D A
S T A T E O F
NO. 50812
CH
R I STOPHER S . CH I LDERS
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
TO THE BEST OF MY KNOWLEDGE, THE PLANS
AND SPECIFICATIONS COMPLY WITH THE
APPLICABLE MINIMUM BUILDING CODES.
Christopher S. Childers, P.E.
Fla. Reg. No. 50812
BLISS & NYITRAY, INC.
STRUCTURAL ENGINEERS
Certificate of Authorization No. 674 227 N. Bronough Street, Suite 7300
Tallahassee, Florida 32301 Tel. (850) 222-4454 Fax (850) 222-9425 www.bniengineers.com
BNI Job No. 21T11.01
S1.01
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
ROOF WIND
DIAGRAM
CONSTRUCTION
DOCUMENTS
09 APRIL 2021
17990 TLC
CSC
1/32" = 1'-0"
ROOF WINDLOAD PLAN
WALL WIND PRESSURE (PSF)
ZONES
TRIBUTARY AREA (SF)
10 20 50 100 200 500
4 -21/+19 -20/+18 -19/+17 -18/+16 -17/+16 -16/+14
5 -25/+19 -24/+18 -21/+17 -20/+16 -18/+16 -16/+14
OVERHANG PRESSURES (PSF)
ZONE
TRIBUTARY AREA (SF)
10 20 50 100 200 500
2o -47/+10 -47/+10 -37/+10 -29/+10 -29/+10 -29/+10
3o -74/+10 -64/+10 -52/+10 -52/+10 -42/+10 -29/+10
PARAPET PRESSURES (PSF)
ZONES
TRIBUTARY AREA (SF)
10 20 50 100 200 500
4P 56 53 48 44 41 36
5P 72 66 57 51 44 36
This item has been digitally signed and sealed by Christopher S. Childers, PE on the date adjacent to the seal. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
NOTES:
1. REPLACE THE EXISTING 4" SEWER LINE WITH NEW
6" PVC PIPE. CONNECT TO EXISTING MANHOLE.
2. REPAIR MANHOLE AS REQUIRED TO INSTALL NEW
6" PVC PIPE.
3. REPAIR ASPHALT DRIVEWAY, SIDEWALKS, CURBS
AND SPEED BUMPS AS REQUIRED. (MATCH EXISTING)
C.O.
C.O.
C.O.
EXIST. SANITARY
SEWER MANHOLE
EXIST. 4" SANITARY
SEWER LINE
INSTALL APPROX. 300' OF 6" PVC SCHEDULE 40
SANITARY SEWER PIPE @ MIN. 1% SLOPE.
INSTALL CLEAN-OUTS
ADD ALTERNATE NO. 1
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A0.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
SITE PLAN
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
1" = 30'-0"A0.1
SITE PLAN1
APALACHEE PARKWAY
(U.S. HIGHWAY 27)
DEMOLITION
LEGEND
DEMOLITION KEYNOTES:
1. REMOVE EXISTING ROOF MEMBRANES, INSULTATION,
FLASHING AND MISCELLANEOUS ITEMS DOWN TO THE
METAL DECK. CLEAN AND PREP METAL DECK FOR
NEW ROOF SYSTEM.
2. INSPECT METAL DECK AND REMOVE DAMAGED
METAL DECK AND PREP BAR JOIST FOR NEW METAL
DECK TO MATCH EXISTING.
3. REMOVE PARAPET CAPS, FLASHING AND WOOD
BLOCKING AND NAILERS AND PREP FOR NEW
PARAPET CAPS.
4. REMOVE EXISTING ROOF SCUPPERS, 5 AT
NORTH AND 5 AT SOUTH ELEVATIONS AND PREP
FOR NEW SCUPPERS. INSPECT DOWNSPOUTS
AND REMOVE AND PREP FOR REINSTALLATION.
5. REMOVE EXISTING GUTTER AND DOWNSPOUTS
AT WEST SIDE OF BUILDING AND STORE FOR
RE-INSTALLATION.
6. REMOVE EXISTING HVAC UNITS
AND CURBS AND PREP DECK FOR
NEW ROOF CURBS AT EACH UNIT. CONTACTOR
TO VERIFY THAT OPENING AT METAL DECK
IS ADEQUATELY SIZED FOR NEW REPLACEMENT
CURBS.
7. TEMPORARILY REMOVE EXISTING EXHAUST
FAN UNITS AND REMOVE CURBS AND PREP DECK
FOR NEW ROOF CURBS AT EACH UNIT.
PREP METAL DECK FOR NEW ROOF CURBS.
8. REMOVE PVC CONDENSATE PIPING
AND STANDOFF BRACKETS.
9. REMOVE EXISTING LADDER AND PREP
FOR REINSTALLATION.
10. REMOVE EXISTING ROOF MEMBRANE
AND FIBERGLASS REINFORCED PANELS FROM
VERTICAL WALL AT HIGH ROOF AND PREP FOR
NEW FRAMING, PLYWOOD AND PVC ROOF MEMBRANE.
11. REMOVE EXISTING SATELLITE DISH AND CABLING.
12. REMOVE EXISTING ABANDONED ELECTRICAL
CONDUIT AND WEATHER HEAD.
13. REMOVE EXISTING ROOF VENT.
14. REMOVE OLD ROOF CURBS AND PREP FOR NEW
METAL DECK.
15. REMOVE EXISTING EXPANSION JOINT AND PREP
FOR NEW EXPANSION JOINT.
16. PREP EXISTING THROUGH THE ROOF
PLUMBING VENTS FOR NEW ROOF SYSTEM.
17. REMOVE METAL WALL AND ROOF PANELS AT
EAST ENTRY FACADE TO ALLOW FOR NEW ROOF
TO BE INSTALLED. PREP FOR NEW REINSTALLATION.
A2.1
A2.1 4
A2.13
A2.1
250' - 6"
HIGH ROOF
104' - 4"
LOW ROOF
146' - 2"
E J
R
O
F
S
L
P
E
R O O F S L O P E S
G
U
T
T
44 4 4
TYP
TYP
ROOF
HATCH
7 7
A5.3
A5.311
A5.3
A5.3 13
A5.314
A5.3
A5.3
E J
A5.3 1
A5.3
A5.3
A5.3
A5.37
A5.3
A5.3
9 A5.3
SIM/OPP
A5.1
A5.1
A5.1 3 A5.34
A5.1
A5.16A5.1 7
A5.1 8
A5.1
A5.1
A5.1 12
A5.1
A5.1
A5.1
A5.1
A5.2
A5.2
A5.233 & 4
A5.2
A5.2
A5.215
A5.2 8
A5.2
A5.2
1010 & 114
TYP
A5.2
A5.2
A5.2
A5.2 16
LADDER UP
METAL ROOF
SLOPES
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC
UNIT
HVAC
UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
E.F. E.F.
HVAC
UNITHVAC UNIT
SLOPES
EXISTING METAL ROOF
AT FACADE
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A1.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
EXISTING &
DEMOLITION ROOF
PLAN
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
1/16" = 1'-0"A1.1
EXISTING & DEMOLITION ROOF PLAN1
A2.1
A2.1 4
A2.13
A2.1
250' - 6"
HIGH ROOF
104' - 4"
LOW ROOF
146' - 2"
E J
R O O F S L O P E S
G U
TT
E
R
D O
W N
S P
O U
TS
ROOF
HATCH
SSSS
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
SSSS S
A3.1
A3.1
A3.1
A3.1
A3.1
A3.1
A3.1
A3.1
A3.1
SIM/OPP
SIM/OPP
SIM/OPP
NEW PVC ROOF MEMBRANE FULLY
ADVERED TO NEW 4" RIGID INSULATION.
MECHANICALLY ATTACHED TO EXISTING
METAL DECK
NEW PVC ROOF MEMBRANE FULLY
ADVERED TO NEW 4" RIGID INSULATION.
MECHANICALLY ATTACHED TO EXISTING
METAL DECK
LADDER
UP
E J
HVAC UNIT
HVAC UNIT
CONDENSATE
DRAIN
CONDENSATE
DRAIN
CONDENSATE
DRAIN
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
NEW WALKWAY PADS
TO AND AROUND
EQUIPMENT (TYP)
NEW WALKWAY PADS
TO AND AROUND
EQUIPMENT (TYP)
NEW WALKWAY PADS
TO AND AROUND
EQUIPMENT (TYP)
NEW WALKWAY PADS
TO AND AROUND
EQUIPMENT (TYP)
NEW WALKWAY PADS
TO AND AROUND
EQUIPMENT (TYP)
CONDENSATE
DRAIN
CONDENSATE
DRAIN
C O
N D
E N
S A
TE
D
R A
IN
C O
N D
E N
S A
TE
D
R A
IN
C O
N D
E N
S A
TE
D
R A
IN
CONDENSATE
DRAIN
HVAC UNIT
HVAC UNIT
HVAC UNIT
HVAC UNIT
E.F. E.F.
HVAC
UNIT
HVAC
UNIT
HVAC
UNITHVAC UNIT
E.F.
METAL ROOF
SLOPES
METAL ROOF
PANELS
1 2
1 2
3 3
4 4
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
TYP TYP
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
44 4
5 5
7 7 7 7
77 7
9 9
10 10 10 10
SLOPES
EXISTING METAL ROOF
AT FACADE
A4.1
A4.1
A4.1
TYP
A4.1
TYP
A4.1
TYP
A4.1
TYP
A4.1
17 14
TYP
TYP
A4.1
A4.1
SLOPES SLOPES
A4.1
A4.1
A4.1
CONSTRUCTION NOTES
1. CONTRACTOR TO INSPECT METAL DECK AND
REPLACE SECTIONS THAT ARE DAMAGED WITH
HEAVY GAUGE METAL DECK TO MATCH EXISTING.
2. INSTALL AND MECHANICALLY FASTEN
RIGID POLYISOCYANURATE INSULATION
TO METAL DECK. INSTALL 1/2” PER FOOT
TAPERED INSULATION CRICKETS ON THE
UPSLOPE SIDE OF EQUIPMENT CURBS TO
DIVERT WATER FLOW AROUND EQUIPMENT
CURBS. INSTALL COVER BOARD OVER
INSULATION.
3. INSTALL ¼” PER FOOT TAPERED
INSULATION CRICKETS AT CORNERS OF BUILDING
TO DIRECT WATER TO SCUPPERS.
4. INSTALL NEW PVC CLAD ALUMINUM SCUPPERS
AT EXISTING SCUPPER OPENINGS. REFURBISH
AND RE-INSTALL EXIST. 6x6 AND 8x8 DOWNSPOUTS
AND COLLECTOR HEADS.
5. INSTALL NEW EXPANSION JOINT AS SHOW
ON DRAWINGS.
6. RE-INSTALL EXIST. GUTTER AND DOWNSPOUTS
AT WEST SIDE OF BUILDING.
7. INSTALL NEW METAL PARAPET CAPS AND
FLASHING AT PARAPET WALLS.
8. REMOVE THE HVAC EQUIPMENT AND
EXISTING ROOF CURB SUPPORTS. CONTRACTOR
TO VERIFY THAT METAL DECK OPENING IS ADEQUATE
FOR NEW ROOF CURBS. INSTALL NEW
MANUFACTURERS’ PREFABRICATED ROOF
CURBS ON THE METAL DECK AND BAR
JOIST SYSTEM. NEW CURB HEIGHT TO BE
10” ABOVE THE FINISH ROOF ELEVATION.
SET THE EXISTING AND NEW HVAC
MECHANICAL EQUIPMENT ON CURB
ONCE ROOFING AT CURB IS COMPLETE.
CONNECT DUCTWORK, ELECTRICAL
AND REFRIGERANT LINES AS REQUIRED.
INSTALL NEW PVC CONDENSATION PIPING
TO HVAC EQUIPMENT AND ROUTE TO NEAREST
SCUPPER OR GUTTER.
9. INSTALL NEW EXHAUST FAN CURBS AND
COMPLETE INSTALLATION OF ROOFING.
REINSTALL EXHAUST FANS AND CONNECT
TO DUCTWORK AND ELECTRICAL SYSTEM.
10. INSTALL ½ CDX PLYWOOD SHEATHING TO
PARAPET WALLS AND PREP FOR NEW ROOFING.
11. INSTALL METAL STUD FRAMING AT VERTICAL
WALL BETWEEN UPPER AND LOWER ROOFS
AND INSTALL ½” CDX PLYWOOD SHEATHING
TO PROVIDE FLAT SURFACE TO INSTALL NEW
PVC ROOFING MEMBRANE. INSTALL PEEL STOP
BAR AND PVC MEMBRANE COVER AS REQUIRED
BY MANUFACTURER. INSTALL FLASHING ANGLE
AT END OF WALL AND TRANSITION TO
EXTERIOR WALL.
12. INSTALL NEW PVC BOOTS AT THROUGH
THE ROOF PIPE VENTS.
13. INSTALL NEW METAL DECKING AND
ROOFING ASSEMBLY AT EXISTING
OPENINGS. MATCH EXISTING METAL
DECKING.
14. INSTALL NEW OVERFLOW SCUPPERS.
15. INSTALL NEW DOWNSPOUT HORIZONTAL
PIPING TO DIRECT WATER AWAY FROM
ALLEYWAY BETWEEN BUILDINGS.
16. REMOVE 18" OF GRAVEL AND DIRT FROM
DOWNSPOUT CONC. DRYWELLS AND
INSTALL NEW GRAVEL.
17. REFINISH EXISTING COLUMN / PILASTER
METAL CAPS. (TYP)
18. RE-INSTALL LADDER. PROVIDE BLOCKING
AND SEALANT POCKET AS REQUIRED.
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A1.2
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
ROOF PLAN
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
1/16" = 1'-0"A1.2
ROOF PLAN - NEW WORK1
18' - 8"
0' - 0"
18' - 8"
0' - 0"
EXISTING STUCCO GABLED
ENTRY CANOPY
EXISTING METAL ROOFING
PANELS TO REMAIN
REFINISH EXISTING COLUMN
CAP FLASHING (TYP)
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
EXISTING METAL ROOF
PANELS TO BE RE-INSTALLED
AFTER NEW PARAPET CAP
AND FLASHING HAVE BEEN
INSTALLED
V.I.F. V.I.F.
22' - 0"
0' - 0"0' - 0"
D.S. D.S. D.S. D.S. D.S. D.S.
D.S.EXISTING ELECTRICAL PANEL BOXES
EXISTING
TRANSFORMER
EXISTING WOOD FENCE
RE-INSTALL EXISTING
6"x6" GUTTER AND
DOWNSPOUTS
V.I.F.
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
22' - 0"
RE-INSTALL EXISTING
6"x6" GUTTER AND
DOWNSPOUTS
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
NEW PVC ROOF MEMBRANE FULLY
ADVERED TO NEW 4" RIGID INSULATION.
MECHANICALLY ATTACHED TO EXISTING
METAL DECK
22' - 0"
0' - 0"
22' - 0"
0' - 0"
EXISTING 8"x8" DOWNSPOUTS
WITH CONDUCTOR HEAD
CLEAN EXISTING DRYWELL
AND INSTALL 18" OF NEW
GRAVEL
REPLACE EXISTING 8" DIA. PVC
DRAINAGE PIPE
18' - 8"
RE-INSTALL EXISTING
6"x6" GUTTER AND
DOWNSPOUTS
INSTALL NEW EMERGENCY
OVERFLOW ROOF SCUPPERS
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
REFINISH EXISTING COLUMN
CAP FLASHING (TYP)
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
V.I.F.
V.I.F.
18' - 8"
0' - 0"
22' - 0"22' - 0"
0' - 0"
EXISTING 6"x6" DOWNSPOUTS
WITH CONDUCTOR HEAD TO BE
REFURBISHED
EXISTING CONC. FLUME & METAL
COVER PLATES AT SIDEWALK
RE-INSTALL EXISTING
6"x6" GUTTER AND
DOWNSPOUTS
INSTALL NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
NEW EMERGENCY
OVERFLOW
ROOF SCUPPERS
REFINISH EXISTING COLUMN
CAP FLASHING (TYP)
V.I.F.
V.I.F.
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
INSTALL NEW METAL PARAPET
CAPS AT PARAPET WALLS (TYP)
EXISTING METAL ROOF
PANELS TO BE RE-INSTALLED
AFTER NEW PARAPET CAP
AND FLASHING HAVE BEEN
INSTALLED
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A2.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
BUILDING
ELEVATIONS
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB3/32" = 1'-0"A2.1
EAST BUILDING ELEVATION3
3/32" = 1'-0"A2.1
WEST BUILDING ELEVATION4
3/32" = 1'-0"A2.1
NORTH BUILDING ELEVATION1
3/32" = 1'-0"A2.1
SOUTH BUILDING ELEVATION2
EXIST. METAL STUD WALL
P.T. WOOD BLOCKING
PVC COATED ALUM FASCIA
3 5/8" METAL STUDS @ 16" O.C.
WITH F.G. BATT INSULATION
OVER EXISTING PARAPET WALL
1/2" CDX PLYWOOD WITH PVC ROOF
MEMBRANE FULLY ADHERED
PEEL STOP BAR AS REQUIRED
BY ROOF MANUF.
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
EXIST. METAL
DECK
EXIST. STL. BAR JOIST
METAL PARAPET CAP
OVER P.T. WOOD BLOCKING
EXIST. CMU
A4.1
A4.1
V .I
.F
A3.1
SIM / OPP
VAPOR BARRIER
OVER METAL DECK
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
EXIST. METAL
DECK
VAPOR BARRIER
OVER METAL DECK
A4.1
4 SIM / OPP
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
P.T. WOOD BLOCKING
1/2" CDX PLYWOOD
ATTACHED TO EXISTING CMU
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
EXIST. CMU WALL
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
EXIST. METAL CONDUCTER
HEAD AND DOWNSPOUT.
REFURBISH ALL CONDUCTER HEADS
AND/OR DOWNSPOUTS
AS REQUIRED)
P.T. WOOD BLOCKING
1/2" CDX PLYWOOD
ATTACHED TO EXISTING CMU
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
EXIST. CMU WALL
NEW PVC CLAD METAL
ROOF SCUPPERS IN EXIST.
OPENINGS A4.1
3 SIM / OPP
EXIST. STL.
BAR JOIST
EXIST. METAL
DECK
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
P.T. WOOD BLOCKING
EXIST. STL.
BAR JOIST
1/2" CDX PLYWOOD
ATTACHED TO EXISTING CMU
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
EXIST. CMU WALL
NEW 8x8 EMERGENCY OVERFLOW
ROOF SCUPPERS (SIM. TO
DETAIL 2/A4.1)
EXIST. METAL
DECK
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
P.T. WOOD BLOCKING
1/2" CDX PLYWOOD
ATTACHED TO EXISTING CMU
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
A4.1
EXIST. CMU WALL
SIM / OPP
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
EXIST. CMU WALL
STAINLESS STEEL
TERMINATION BAR WITH
SEALANT
EXISTING CMU
BEYOND
PVC ROOF MEMBRANE OVER
1/2" CDX PLYWOOD AT PARAPET
WALL BEYOND
REEFURBISH
EXISTING GUTTER
REFURBISH EXISTING
DOWNSPOUT
P.T. WOOD BLOCKING
PVC COATED ALUM FASCIA
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
A4.1
2 SIM / OPP
EXIST. STL.
BAR JOIST
EXIST. METAL
DECK
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A3.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
ROOF SECTIONS
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
3/4" = 1'-0"A3.1
ROOF SECTION1
1 1/2" = 1'-0"A3.1
ROOF SECTION2
1 1/2" = 1'-0"A3.1
ROOF SECTION4
1 1/2" = 1'-0"A3.1
ROOF SECTION5
1 1/2" = 1'-0"A3.1
ROOF SECTION3
1 1/2" = 1'-0"A3.1
ROOF SECTION6
ROOF SLOPES
PVC CLAD FASCIA COVER HOOKED TO
CLEAT AND FASTENED @ 4" O.C. STAGGERED
(SEE NOTE 4) USING 1 1/4" GALV. ANNULAR RING
NAILS (MIN.) OR APPROPRIATE FASTENER
PVC FLASHING STRIP,
HOT-AIR WELED
PVC ROOF MEMBRANE
(SEE NOTE 2)
WOOD NAILER
(SEE NOTE 1)
STRUCTURAL DECK
(L
1. NEW WOOD NAILERS SHALL BE ATTACHED PER CODE. NAILER HEIGHT TO MATCH TOP SURFACE TO WHICH MEMBRANE
IS TO BE APPLIED.
2. BRING BAREBACK MEMBRANE OVER ROOF EDGE AND DOWN OUTSIDE FACE OF WALL, COVERING WOOD NAILERS
COMPLETELY. BRING FELTBACK MEMBRANE TO ROOF EDGE ONLY.
3. FASTENER WITHDRAWAL RESISTANCE SHOULD BE 100 LB. MIN. USE EITHER GALV. ANNULAR RING NAILS PENETRATING 1 1/4" MIN. OR NO. 8 MIN. SCREWS PENETRATING 3/4". FASTENER IS PLACED EITHER CENTERED INTO TOP WOOD NAILER
OR 1" FROM TOP EDGE OF CLEAT HOOK STRIP @ 4" O.C.
4. FASTENED 4" O.C. AND STAGGERED BETWEEN 1" AND 1 1/2" FROM TOP BACKSIDE EDGE OF FASCIA COVER.
INSULATION
SECURLEY FASTENED
VAPOR BARRIER
COVER BOARD
PVC CLAD METAL FASTENED @ 4" O.C. STAGGERED
USING 1" GALV. ANNULAR RING NAILS OR OTHER
ACCEPTABLE FASTENER
PVC FLASHING STRIP,
HOT-AIR WELED
WOOD NAILER
(SEE NOTE 1)
STRUCTURAL DECK
1. NEW WOOD NAILERS SHALL BE ATTACHED PER CODE. NAILER HEIGHT TO MATCH TOP SURFACE TO WHICH MEMBRANE
IS TO BE APPLIED.
2. BRING BAREBACK MEMBRANE OVER ROOF EDGE AND DOWN OUTSIDE FACE OF WALL, COVERING WOOD NAILERS
COMPLETELY. BRING FELTBACK MEMBRANE TO ROOF EDGE ONLY.
METAL GUTTER
SUPPORT
METAL GUTTER
PVC ROOF MEMBRANE
INSULATION
SECURLEY FASTENED
VAPOR BARRIER
COVER BOARD
1. NAILERS SHALL BE SECURELY ANCHORED TO THE DECK TO RESIST A FORCE OF 300 POUNDS PER LINEAL FT.
IN ANY DIRECTION
PVC STRIP,
HOT-AIR WELDED
PEEL STOP BAR
1. INSTALL PEEL STOP BAR WITH A 1/4" GAP BETWEEN ADJOINING SECTIONS
2. PEEL STOP BAR MUST BE CUT AT INSIDE AND OUTSIDE CORNERS. DO NOT BEND AROUND CORNERS
3. PEEL STOP BAR MUST BE FASTENED WITHIN 1" MAX. OF EACH BAR END
4. VAPOR RETARDER SHALL BE SEALED AT EDGES
5. WALLS 45" OR GREATER IN HEIGHT REQUIRE INTERMEDIATE FIXATION, TO BE LOCATED HALFWAY UP THE WALLS.
1. NAILERS SHALL BE SECURELY ANCHORED TO THE DECK TO RESIST A FORCE OF 300 POUNDS PER LINEAL FOOT
IN ANY DIRECTION
2. VAPOR RETARDER SHALL BE SEALED AT EDGES
1. VAPOR RETARDER SHALL BE SEALED AT EDGES
1. PITCH POCKETS ARE TO BE ELIMINATED WHERE POSSIBLE
2. VAPER RETARDER SHALL BE SEALED AT EDGES
1. VAPER RETARDER SHALL BE SEALED AT EDGES
1. VAPER RETARDER SHALL BE SEALED AT EDGES
1. VAPOR RETARDER SHALL BE SEALED AT EDGES
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
P.T. WOOD BLOCKING
EXIST. CMU WALL
NEW 4" RIGID INSULATION OVER
VAPOR BARRIER
NEW PVC ROOF MEMBRANE
FULLY ADHERED TO NEW
1/2" COVER BOARD
NEW VAPOR BARRIER
OVER METAL DECK
EXISTING STANDING SEAM
METAL ROOF WITH EXPOSED FASTNERS
EXISTING ROOF
BEAM
EXISTING ROOF
PURLIN
NEW 1/2" CDX PLYWOOD WITH PVC ROOF
FLASHING FULLY ADHERED
NEW STAINLESS STEEL
TERMINATION BAR & SEALANT
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
P.T. WOOD BLOCKING
EXIST. CMU WALL
NEW 4" RIGID INSULATION OVER
VAPOR BARRIER
NEW PVC ROOF MEMBRANE
FULLY ADHERED TO NEW
1/2" COVER BOARD
NEW VAPOR BARRIER
OVER METAL DECK
NEW 1/2" CDX PLYWOOD WITH PVC ROOF
FLASHING FULLY ADHERED
EXIST. METAL ROOF
PANELS AND FLASHING.
REMOVE ROOF PANELS
TO INSTALL NEW PVC ROOF
AND RE-INSTALL TO WEATHER
TIGHT CONDITIONS
EXIST. CMU
PARAPET WALL
NEW METAL COPING CAP WITH
WATERTIGHT JOINTS
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
EXIST. CMU WALL
NEW 4" RIGID INSULATION
OVER VAPOR BARRIER
NEW PVC ROOF MEMBRANE
FULLY ADHERED TO NEW
1/2" COVER BOARD
NEW VAPOR BARRIER
OVER METAL DECK
P.T. WOOD BLOCKING
NEW 1/2" CDX PLYWOOD
ATTACHED TO EXISTING FRAMING
NEW METAL PARAPET CAP
WITH CONT. SNAP LOCK FLASHING
NEW PVC ROOF FLASHING
FULLY ADHERED TO NEW
1/2" COVER BOARD
EXISTING METAL STUD FRAMING
AND SLOPED METAL ROOF
NEW PEEL STOP BAR
EXIST. METAL
DECK
EXIST. STL. BAR
JOIST
EXIST. CMU WALL
NEW 4" RIGID INSULATION
OVER VAPOR BARRIER
NEW PVC ROOF MEMBRANE
FULLY ADHERED TO NEW
1/2" COVER BOARD
NEW VAPOR BARRIER
OVER METAL DECK
REMOVE EXIST. METAL WALL PANEL
AS REQUIRED TO INSTALL NEW PVC
ROOFING AND MODIFY EXISTING METAL WALL
PANEL AS REQUIRED TO TO INSTALL
NEW PVC ROOF
EXISTING METAL STUD PARAPET
FRAMING
INSTALL NEW PVC ROOF FLASHING
AND STAINLESS STEEL
TERMINATION BAR & SEALANT
EXIST. CMU WALL AND
PILASTER COLUMN
PVC ROOF FLASHING OVER
1/2" CDX PLYWOOD AT PARAPET WALL
P.T. WOOD BLOCKING
METAL PARAPET CAP
WITH CONT. SNAP LOCK
FLASHING
EXIST. STL.
BAR JOIST
EXIST. METAL
DECK
4" RIGID INSULATION OVER
EXISTING METAL DECK
PVC ROOF MEMBRANE FULLY
ADHERED TO NEW 1/2" COVER
BOARD
VAPOR BARRIER
OVER METAL DECK
REFURBISH EXIST. CMU
PILASTER COLUMN CAP
AND RE-INSTALL
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Phone 850 224-6301 Fax 850 561-6978
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A4.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
ROOF DETAILS
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
3" = 1'-0"A4.1
ROOF EDGE DETAIL1
3" = 1'-0"A4.1
ROOF GUTTER EDGE DETAIL2
N. T. S.
N. T. S.
3" = 1'-0"A4.1
ROOF THRU-WALL SCUPPER3
REFER TO PARAPET AND WALL DETAILS
FOR ACCEPTABLE TERMINATION
ATTACH PVC MEMBRANE TO PLYWOOD SURFACE
PVC FLASHING STRIP, HOT-AIR WELDED
FASTENER
CONT. SEALANT
CONT. SEALANT
PVC CLAD METAL SCUPPER FASTENED 4" INCHES O.C.,
STAGGERED, USING GALV. ANNULAR RING NAILS
PVC FLASHING STRIP,
HOT-AIR WELDED
PVC ROOF MEMBRANE
STRUCTURAL
DECK
TREATED WOOD NAILER TO
MATCH HEIGHT OF INSULATION
N. T. S.
3" = 1'-0"A4.1
ROOF PARAPET CAP DETAIL4
HOT-AIR WELD
PVC ROOF MEMBRANE
PVC FLASHING
ADHERED TO ACCEPTABLE
SUBSTRATE
SPECIFIED SARNAFIL
SECUREMENT
METAL EXTENDER PIECE
AS REQUIRED
METAL COPING CAP WITH
WATERTIGHT JOINTS
CONT. METAL HOOK STRIP
3/4" = 1'-0"A4.1
ROOF HIGH WALL FLASHING5
N. T. S.
G R
E A
TE
R
T H
A N
5"
PVC ROOF MEMBRANE
STRUCTURAL
DECK
PVC FLASHING
ADHERED TO ACCEPTABLE
SUBSTRATE
REFER TO PARAPET AND WALL
DETAILS FOR ACCEPTABLE TERMINATION
INSULATION SECURELY
FASTENED
STRUCTURAL
DECK
VAPOR BARRIER
INSULATION SECURELY
FASTENED
3" = 1'-0"A4.1
EXPANSION JOINT DETAIL6
FLASHING STRIP HOT-AIR WELDED
PVC ROOF MEMBRANE
SPECIFIED
SECUREMENT
STRUCTURAL
DECK
INSULATION SECURELY
FASTENED
FOAM ROD TUBING (COMPATIBLE)
BATT INSULATION
TREATED WOOD NAILERS
SECURELY ANCHORED
3" = 1'-0"A4.1
EQUIPMENT CURB FLASHING7
PVC ROOF MEMBRANE
STRUCTURAL DECK
INSULATION SECURELY
FASTENED
N. T. S.
SELF-FLASHING UNIT
ADDITIONAL WOOD BLOCKING (IF REQUIRED)
TO ACHIEVE AN 8 INCH MIN. FLASHING HEIGHT
GROMMETTED FASTENER 12 INCHES O.C.
METAL EXTENDER PIECE (IF REQUIRED)
PVC FLASHING ADHERED TO ACCEPTABLE
SUBSTRATE
HOT-AIR WELD
SPECIFIED PVC
SECUREMENT
M
IN
M
IN
1 : 5A4.1
SEALANT POCKET8
N. T. S.
N. T. S.
2" MIN
COVERBOARD
STRUCTURAL DECK
INSULATION SECURELY
FASTENED
TREATED WOOD NAILER
APPROVED SEALANT
POCKET FILLER
NON-SHRINK GROUT
PENETRATIONS
PVC ROOF MANUF.
STANDARD METAL PITCH
PAN FASTENED 4 IN. O.C.
USING GALV. ANNULAR
RING NAILS OR OTHER
ACCEPTABLE FASTENER
PVC FLASHING
HOT-AIR WELDED
PVC ROOF MEMBRANE
1/2" CDX PLYWOOD ATTACHED
TO PARAPET
1 : 5A4.1
CONE FLASHING DETAIL9
M
IN
M
IN
STRUCTURAL DECK VAPOR BARRIER
INSULATION SECURELY
FASTENED
PIPE PENETRATION
PVC FLASHING
HOT-AIR WELDED
PVC ROOF
MEMBRANE
SPECIFIED
SECUREMENT
PVC FLASHING
MEMBRANE
SEALANT
S.S. HOSE CLAMP
N. T. S.
1 : 6A4.1
STACK FLASHING DETAIL10
N. T. S.
STRUCTURAL DECK
INSULATION SECURELY
FASTENED
PIPE PENETRATION
HOT-AIR WELDED
SPECIFIED
SECUREMENT
UNIVERSAL PIPE / VENT
STACK
SEALANT
S.S. HOSE CLAMP
M
IN
M
IN
12" O.C.
3" = 1'-0"A4.1
ROOF HATCH FLASHING11
INSULATION SECURELY
FASTENED
INSULATION SECURELY
FASTENED
VAPOR BARRIER
STRUCTURAL DECK
INSULATION SECURELY
FASTENED
EXISTING ROOF HATCH
FRY-TYPE REGLET
PVC FLASHING ADHERED TO
ACCEPTABLE SUBSTRATE
HOT-AIR WELD
SPECIFIED PVC
SECUREMENT
M
IN
M
IN
COVER BOARD
COVER BOARD
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
NOTES:
VAPOR BARRIER
COVER BOARD
VAPOR BARRIER
COVER BOARD
VAPOR RETARDER
COVER BOARD
VAPOR BARRIER
COVER
BOARD
VAPOR BARRIER
PVC ROOF
MEMBRANE
COVER
BOARD
VAPOR BARRIER
PVC ROOF MEMBRANE
COVER BOARD
INSTALL LIQUID
FLASHING AT PIPE
INSTALL LIQUID
FLASHING AT PIPE
1 1/2" = 1'-0"A4.1
ROOF SECTION12
1 1/2" = 1'-0"A4.1
ROOF SECTION13
1 1/2" = 1'-0"A4.1
ROOF SECTION14
1 1/2" = 1'-0"A4.1
ROOF SECTION16
1 1/2" = 1'-0"A4.1
ROOF SECTION15
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A5.1
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
PHOTO
DOCUMENTATION
LOW ROOF
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
12" = 1'-0"A5.1
PHOTO 11
12" = 1'-0"A5.1
PHOTO 22
12" = 1'-0"A5.1
PHOTO 44
12" = 1'-0"A5.1
PHOTO 55
12" = 1'-0"A5.1
PHOTO 33
12" = 1'-0"A5.1
PHOTO 66
12" = 1'-0"A5.1
PHOTO 77
12" = 1'-0"A5.1
PHOTO 88
12" = 1'-0"A5.1
PHOTO 99
12" = 1'-0"A5.1
PHOTO 1010
12" = 1'-0"A5.1
PHOTO 1111
12" = 1'-0"A5.1
PHOTO 1212
12" = 1'-0"A5.1
PHOTO 1313
12" = 1'-0"A5.1
PHOTO 1414
12" = 1'-0"A5.1
PHOTO 1515
12" = 1'-0"A5.1
PHOTO 1616
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A5.2
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
PHOTO
DOCUMENTATION
LOW ROOF
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
12" = 1'-0"A5.2
PHOTO1
12" = 1'-0"A5.2
PHOTO2
12" = 1'-0"A5.2
PHOTO3
12" = 1'-0"A5.2
PHOTO4
12" = 1'-0"A5.2
PHOTO5
12" = 1'-0"A5.2
PHOTO6
12" = 1'-0"A5.2
PHOTO7
12" = 1'-0"A5.2
PHOTO8
12" = 1'-0"A5.2
PHOTO9
12" = 1'-0"A5.2
PHOTO10
12" = 1'-0"A5.2
PHOTO11
12" = 1'-0"A5.2
PHOTO12
12" = 1'-0"A5.2
PHOTO13
12" = 1'-0"A5.2
PHOTO14
12" = 1'-0"A5.2
PHOTO15
12" = 1'-0"A5.2
PHOTO16
Copyright Barnett Fronczak Barlowe & Shuler, Architects. All rights Reserved 2074 Centre Pointe Blvd, Suite #200, Tallahassee, FL 32308
Tallahassee Florida
Revisions
Date
Project Code
Drawn By:
Checked By:
BARLOWE
A
FRONCZAK
BARNETT
SHULER&
R C H I T E C T S
NOTES
A5.3
LEON COUNTY
SUPERVISOR OF
ELECTIONS -
RE-ROOFING
PHOTO
DOCUMENTATION
HIGH ROOF
CONTRACT
DOCUMENTS
3 JUNE 2021
17990 JH
DB
12" = 1'-0"A5.3
PHOTO2
12" = 1'-0"A5.3
PHOTO4
12" = 1'-0"A5.3
PHOTO3
12" = 1'-0"A5.3
PHOTO6
12" = 1'-0"A5.3
PHOTO5
12" = 1'-0"A5.3
PHOTO7
12" = 1'-0"A5.3
PHOTO8
12" = 1'-0"A5.3
PHOTO9
12" = 1'-0"A5.3
PHOTO10
12" = 1'-0"A5.3
PHOTO14
12" = 1'-0"A5.3
PHOTO11
12" = 1'-0"A5.3
PHOTO12
12" = 1'-0"A5.3
PHOTO13
12" = 1'-0"A5.3
PHOTO15
12" = 1'-0"A5.3
PHOTO1
12" = 1'-0"A5.3
PHOTO16
GENERAL HVAC NOTES
1 TOMAHAWK ENGINEERING AND CONSULTING, INC. SHALL NOT BE HELD RESPONSIBLE FOR
ANY MISUSE AND/OR MISREPRESENTATION OF THIS SET OF DOCUMENTS.
2 THE CONTRACTOR ASSUMES RESPONSIBILITY FOR USE OF THE CONTRACT DOCUMENTS.
THE CONTRACTOR SHALL MAKE HIMSELF AWARE OF PROJECT CONDITIONS AND OWNER
REQUIREMENTS PRIOR TO PROCUREMENT OF EQUIPMENT AND SERVICES. CHANGES IN
PROJECT COST WILL NOT BE GRANTED DUE TO FIELD CONFLICTS AND/OR PROJECT
CONDITIONS.
3 THIS SET OF DRAWINGS AND SPECIFICATIONS SHALL NOT BE CONSIDERED A SET OF
CONSTRUCTION DOCUMENTS UNLESS A SIGNATURE AND DATE ARE AFFIXED TO THE
DRAWINGS AND SPECIFICATIONS BY THE ENGINEER IN RESPONSIBLE CHARGE FOR THE
GIVEN DISCIPLINE.
4 CONFLICTS BETWEEN THIS SET OF DRAWINGS AND THE CONTRACT SPECIFICATIONS SHALL
BE RESOLVED BY THE ENGINEER OF RECORD. THE CONTRACTOR DOES NOT HAVE THE
AUTHORITY TO INTERPRET CONFLICTS…