CONTINUATION OF SF 1442 BLOCK 17 ROME CHILLER.pdf

PDF 144 KB Posted

Attached to
Z1DA--528A7-23-102 ADD CHILLER ROME VA CBOC
Solicitation number
36C24222B0076
Issued by

About this file

This document is a continuation sheet for SF 1442 Block 17 providing additional details for a federal contract solicitation to renovate a chiller at the Rome VA Community Based Outpatient Clinic. The contractor shall completely prepare the site, including demolishing existing structures, and furnish labor, materials, and equipment to install a new government furnished, contractor installed water-cooled chiller and relocate an existing water-cooled chiller as required by the drawings and specifications. Key deliverables and dates include submittals within 30 days of award, making the existing chiller 501-WC-2 operational by April 1, 2023, and completing the remainder of the base bid work within 90 days thereafter. Liquidated damages of $5,000 may apply if the chiller is not installed by 180 days after notice to proceed. The period of performance is 270 days from notice to proceed. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.

View the file

Other files

File Type Posted
36C24222B0076 0003.docx DOCX document
split shipped chiller dimensions.pdf PDF
36C24222B0076 0002.docx DOCX document
york chilller selection.pdf PDF
36C24222B0076 0001.docx DOCX document
Wage Detrmination NY20220013 8-5-22.pdf PDF
Combined Specifications 528A723102.pdf PDF
528A7-23-102_FULLSET-FINAL_06-28-2022.pdf PDF
36C24222B0076_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION OF SF 1442 BLOCK 17

ITEMS COST

BASE ITEM

Scope of Work:

1) Renovate Chiller at Rome CBOC

TOTAL COST FOR ALL ITEMS $_________________

Item Total time in calendar days Submittals 30 Chiller 501-WC-2 relocated and operational NLT April 1, 2023, 90 Remainder of Base Bid 60

Period of performance is 270 days from NTP Includes lead time of VFDs

Mobilization and Demolition will not begin until submittals for specifications 010000 General Requirements, 013526 Safety Requirements, 014500 Quality Control, 017419 Construction Waste Management, and 024100 Demolition are approved. Material submittals shall be approved prior to installation. Existing chiller 501-WC-2 shall be installed and operational by April 1, 2023. If chiller is not operational by April 1, 2023, liquid damages may be applied

DATE:______________________________

AUTHORIZED COMPANY OWNER SIGNATURE:_______________________________________

- $5,000 Liquidated damages IF the Chiller is not installed by 180 days after the NTP is issued approx. 1- 10 April

- The VFDs do not need to be in place to meet the need of a chiller operational by 1-10 April .