CONTINUATION OF SF 1442 BLOCK 17 ROME CHILLER.pdf
PDF 144 KB Posted
- Attached to
- Z1DA--528A7-23-102 ADD CHILLER ROME VA CBOC
- Solicitation number
- 36C24222B0076
About this file
This document is a continuation sheet for SF 1442 Block 17 providing additional details for a federal contract solicitation to renovate a chiller at the Rome VA Community Based Outpatient Clinic. The contractor shall completely prepare the site, including demolishing existing structures, and furnish labor, materials, and equipment to install a new government furnished, contractor installed water-cooled chiller and relocate an existing water-cooled chiller as required by the drawings and specifications. Key deliverables and dates include submittals within 30 days of award, making the existing chiller 501-WC-2 operational by April 1, 2023, and completing the remainder of the base bid work within 90 days thereafter. Liquidated damages of $5,000 may apply if the chiller is not installed by 180 days after notice to proceed. The period of performance is 270 days from notice to proceed. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24222B0076 0003.docx | DOCX document | |
| split shipped chiller dimensions.pdf | ||
| 36C24222B0076 0002.docx | DOCX document | |
| york chilller selection.pdf | ||
| 36C24222B0076 0001.docx | DOCX document | |
| Wage Detrmination NY20220013 8-5-22.pdf | ||
| Combined Specifications 528A723102.pdf | ||
| 528A7-23-102_FULLSET-FINAL_06-28-2022.pdf | ||
| 36C24222B0076_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTINUATION OF SF 1442 BLOCK 17
ITEMS COST
BASE ITEM
Scope of Work:
1) Renovate Chiller at Rome CBOC
TOTAL COST FOR ALL ITEMS $_________________
Item Total time in calendar days Submittals 30 Chiller 501-WC-2 relocated and operational NLT April 1, 2023, 90 Remainder of Base Bid 60
Period of performance is 270 days from NTP Includes lead time of VFDs
Mobilization and Demolition will not begin until submittals for specifications 010000 General Requirements, 013526 Safety Requirements, 014500 Quality Control, 017419 Construction Waste Management, and 024100 Demolition are approved. Material submittals shall be approved prior to installation. Existing chiller 501-WC-2 shall be installed and operational by April 1, 2023. If chiller is not operational by April 1, 2023, liquid damages may be applied
DATE:______________________________
AUTHORIZED COMPANY OWNER SIGNATURE:_______________________________________
- $5,000 Liquidated damages IF the Chiller is not installed by 180 days after the NTP is issued approx. 1- 10 April
- The VFDs do not need to be in place to meet the need of a chiller operational by 1-10 April .
- The Chiller is Govt Furnished