Construction Schedule rev March 2024.pdf

PDF 140 KB Posted

Attached to
RBPF Police Training College Renovation
Solicitation number
19AQMM24N0047
Issued by

About this file

This document is a Construction Schedule for the renovation of the Royal Bahamas Police Force (RBPF) Police Training College. The renovation project, with an estimated cost of $1,000,000 - $5,000,000, is being managed by the U.S. Department of State, Bureau of International Narcotics and Law Enforcement Affairs (INL). The scope of work includes the renovation of four buildings totaling 19,872 square feet, with elements such as demolition, concrete and masonry work, steel work, water and sewer upgrades, electrical, mechanical and HVAC work, carpentry, and painting. The anticipated period of performance is 180 calendar days from the issuance of the Notice to Proceed. This is not a solicitation, but rather a Sources Sought/Request for Information notice to conduct market research and gather data for planning purposes. Responses are requested by May 31, 2024.

View the file

Other files

File Type Posted
RBPF College Upgrades SOW.docx DOCX document
100p Specifications combined.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

hollingsworth pack

BASE BID INCL ALTERNATES CONSTRUCTION SCHEDULE

RBPF College Upgrades Rev. March 2024

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

Site Office & staging area, containers

Equipment; scaffolding, fence etc..

Demolition

Demolition work inside

Demolition work outside

Demolition windows and doors

CONCRETE & MASONRY WORK

Floor tile work

Floor and wall tiles Toilet room 5‐28

Windows sills

Mason repairs around windows and doors

Concrete and mason repairs

STEEL WORK

Auditorium

WATER & SEWER

Toilet room 5‐28 kitchen sink room 5‐25

Greas tank room 5‐23

ELECTRICAL, MECHANICAL & HVAC

Outside work

Inside work

Aircon

Computerroom

Light fixtures

Kitchen

Panels

Cables

Outside: lighting and conection to existing

CARPENTRY WORK, doors, windows, shutters

Doors and windows

Roof

Inside finish

PAINT WORK

Inside finish

Outside finish

Site Development

Garbage area

Close up, punch list Close up & punch list Demobilization

1 2 3 4 5 6

MOBILIZATION

TASK Description 7 8 9

Hollingsworth Pack

Construction Schedule (Ext): Page 1 of 1