This is a vendor quote and product specification document for the City & County of San Francisco related to recreational equipment procurement under contract CON26-0042, a Micro Locally Based Enterprise (LBE) set-aside solicitation for Coastal Parks Alliance (CPA) replacement at various parks throughout San Francisco. The quote, issued by Ross Recreation Equipment on December 29, 2025, with an expiration date of January 28, 2026, provides pricing and specifications for multiple playground equipment components including Sunset Wobble Pod Springs, Bow Ladder Evos, Pod Climb Across equipment, Swiggle Stix Bridge structures, and associated hardware and installation materials. The quote details specific product quantities: 2 Spring Assemblies with Plates, 1 Bow Ladder Connector, 4 Clamps and 4 Retainer Clamps, 2 EVOS Pod Climb Across units, 14 Single Post Footers, and various chains and fasteners. Lead time is 4-6 weeks from order confirmation. Questions regarding the project must be submitted by March 11, 2026 by 5:00 PM to the Project Manager, and bids are due by March 18, 2026 at 2:30 PM. No pre-bid meeting or bidders conference will be held; however, site visits may be arranged by contacting the project manager.

The total quote amount is $15,176.64, comprising materials costs of $12,798.75, San Francisco County sales tax of $1,103.89 at 8.6250%, and freight charges of $1,274.00. Payment terms are Net 30 on materials shipment, with no installation, bonds, engineering calculations, permits, inspections, or storage included unless specifically noted. The quote explicitly excludes offload services, and the freight cost assumes semi-truck access without lift-gate service; the customer is responsible for providing equipment such as forklifts for unloading. Ross Recreation Equipment holds California Contractor's License #520752 and Oregon Contractor's License #186870, with DIR registration number 1000003500. The equipment specifications indicate fall heights ranging from 16 inches to 9 feet, with installation requirements involving concrete footings, protective surfacing materials, and stainless steel fasteners meeting ASTM standards. The project budget estimate is $608,000 per the related solicitation documentation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUOTE

100 Brush Creek Rd #206, Santa Rosa, CA 95404

Rebecca Whitten

707.538.3800 | (707) 736-6895 rebeccaw@rossrec.com

Quote #: 00049405

Quote Name: Sunset Wobble Pod Springs

Quote Total: $15,176.64

Billing Address:

City & County of San Francisco

501 Stanyan St, 2nd FL (Golden Gate Park)

San Francisco, California 94117

Shipping Address:

City & County of San Francisco

100 Martin Luther King Jr. Dr.

Golden Gate Park

San Francisco, California 94122

Quote Date: 12/29/25

Expiration Date: 1/28/26

100 Brush Creek Rd, #206, Santa Rosa, CA 95404 • 707.538.3800 • www.rossrec.com •

CA Contractors License #520752 • OR Contractors License #186870 • Tax ID #68-0103540 • DIR 1000003500

Opportunity Name Lead Time Payment terms

Sunset Wobble Pod Springs 4-6 weeks Net 30 On Materials Shipment

QTY PRODUCT DESCRIPTION UNIT PRICE SUBTOTAL

2.00 156913 Spring Assembly With Plates for Wobble pod, Specify Color- Matte Warm Bronze $595.00 $1,190.00

1.00 156980 Hdw Pkg Wobble Pod $50.85 $50.85

1.00 Install Instructions Install Instructions 157472 INST EVOS WOBBLE POD $0.00 $0.00

1.00 154782 Bow Ladder Connector Pnt, Matte Warm Bronze $1,770.00 $1,770.00

4.00 156699 Clamp, 1-7/8" Ball, Specify Color -Red $81.00 $324.00

4.00 156700 Retainer Clamp, 1-7/8" Ball, Specify Color-Red $160.00 $640.00

1.00 156984 Hdw Pkg Bow Ladder $84.00 $84.00

1.00 Install Instructions Install Instructions157463 INST EVOS BOW LADDER® $0.00 $0.00

2.00 155157 EVOS POD CLIMB ACROSS, Matte Warm Bronze $1,095.00 $2,190.00

4.00 156699 Clamp, 1-7/8" Ball, Specify Color-Red $81.00 $324.00

4.00 156700 Retainer Clamp, 1-7/8" Ball, Specify Color-Red $160.00 $640.00

14.00 164367 SINGLE POST FOOTER, Matte Warm Bronze $270.00 $3,780.00

4.00 179682 Chn 1/4I P70 13I $27.35 $109.40

4.00 179687 Chn 1/4I P70 14 1/4I $27.85 $111.40

2.00 198497 Chn 1/4I P70 17-5/16I Long $30.75 $61.50

4.00 179695 Chn 1/4I P70 15 1/2I $28.40 $113.60

2.00 180147 Hdw Pkg Swiggle Stix $705.00 $1,410.00

1.00 Install Instructions Install Instructions179891 INST EVOS SWIGGLE STIX $0.00 $0.00

Totals

County/ City Tax (San Francisco County 8.6250 %) Materials $12,798.75

Sales Tax $1,103.89

Labor/ Fees $0.00

Freight $1,274.00

Total $15,176.64

707.538.3800 | (707) 736-6895 rebeccaw@rossrec.com

Quote #: 00049405

Quote Name: Sunset Wobble Pod Springs

Quote Total: $15,176.64

CA Contractors License #520752 • OR Contractors License #186870 • Tax ID #68-0103540 • DIR 1000003500

Notes to Customer

707.538.3800 | (707) 736-6895 rebeccaw@rossrec.com

Quote #: 00049405

Quote Name: Sunset Wobble Pod Springs

Quote Total: $15,176.64

CA Contractors License #520752 • OR Contractors License #186870 • Tax ID #68-0103540 • DIR 1000003500

TERMS AND CONDITIONS

Thank you for choosing Ross Recreation Equipment for your project. This document outlines the arrangements for your selected products, labor and services. It will serve as a Contract Agreement (“Contract”) between City & County of San Francisco

(“Customer”) and Ross Recreation Equipment (“Ross Recreation”). All arrangements described in this Contract will be confirmed by returning your signed Contract Agreement no later than 1/28/26.

PLEASE NOTE: This quote does not include installation, offload, payment and performance bonds, engineering calculations, security, storage, permits, inspections or any other materials or labor unless specifically noted and outlined on this quote. Unless noted, freight costs are based on semi-truck access and do not include a lift-gate. The freight carrier and driver will not offload the shipment. You will need a forklift or similar equipment to offload equipment.

Your purchase is subject to the terms and conditions of this quote. Approval of this quote agrees to those terms.

Ross Recreation coordinates the ordering, production and shipment of materials. Customer and site readiness is a critical component of shipping coordination. If project and/or site readiness changes after materials are already produced, neither th e manufacturer nor Ross Recreation, can hold and store such materials. Once materials ship, the materials will be invoiced based on customer's terms. Payment for materials is required regardless of installation status.

Deposits may be required before an order can be placed depending on customer credit terms. Credit terms are established by

Ross Recreation and for this order are as follows: Net 30 On Materials Shipment. Pay when paid by the Owner is not accepted as alternative payment terms.

• First Deposit Due with Signed Quote: $0.00

If ordering materials after 1/28/26, please contact your sales representative for current pricing. Ross Recreation cannot hold pricing past the stated Expiration Date on this quote. To secure current pricing, Ross Recreation will require the following:

• Purchase Order (PO), signed quote or executed contract with approval for the order.

• Deposit, if required by credit terms.

• Color selections and/or approved submittals.

• Acceptance of delivery when materials or equipment are ready to ship from the respective manufacturer/s. Products cannot be held nor stored by Ross Recreation nor the manufacturer/s.

If this quote is for a bid, it is the responsibility of the General Contractor to adjust and increase their bid pricing to ac commodate the project timeline if materials are needed after the expiration date on the provided quote and/or Ross Recreation's scope of work is expected to be completed after the expiration date on the provided quote.

Sales tax rates will be charged and determined by the Department of Tax and Fee Administration at the time of shipping, not t he order date. Any changes to the City/County tax rate and/or a change to the ship to address may affect the final total due on this contract. Customers will be required to pay for any changes to sales taxes. For this order, the sales tax rate was calculated using: (San Francisco County 8.6250 %).

Customer Signature

Customer Print Name

Date

© 2006 by Landscape Structures. All rights reserved.

SAFETY NOTE

Choose a protective surfacing material that has a Critical Height Value of at least the height of the Highest Accessible Part/Fall Height of the adjacent equipment. (Ref.

ASTM F1487.)

601 7TH STREET SOUTH, DELANO, MINNESOTA 55328-8605 888-574-4678 LSI Install Help 888-438-6574 LSI Direct 763-972-5200 Int. FAX (763) 972-3185 Document #15746300

156463 Bow Ladder®Evos®

DETAIL

BOW LADDER ATTACHMENT

(4) 5" Clamp Assemblies Ref. To Plan View

Bow Ladder

(4) Ball Retainers

(4) Ball Clamps

(8) 3/8" x 1 1/8 BHCS w/Pin (8) 5/8" x 1 1/2

BHCS w/Pin #100201 (Orange Patch)

(4) 5" Clamp Assemblies Ref. To Plan View

Bow Ladder

Protective Surfacing

(4) Arches

Arch

(16) 3/8" x 1 1/8" BHCS w/Pin(4) 1/4" x 5/8"

Drive Rivets

(4) E-Pods

(4) Pod Castings

8" 20

Specifications are subject to change without notice.

Evos® 156463 Bow Ladder®

Parts List

Part#DescriptionQty.
154782Bow Ladder, Specify Color............................................1
156699Ball Clamp, Specify Color.............................................4
156700Ball Retainer, Specify Color...........................................4
154461E-Pod, Specify Color......................................................4
156806Pod Casting, Specify Color............................................4
156968Pod Hardware Package ............................................4
1001983/8" x 1 1/8" BHCS w/Pin, SST.......................................16
1006101/4" x 5/8" Drive Rivet, AL/SST.......................................4
156984Bow Ladder Hardware Package ...............................1
1001983/8" x 1 1/8" BHCS w/Pin, SST........................................8
1002015/8" x 1 1/2" BHCS w/Pin, SST........................................8

Specifications Bow Ladder: Weldment comprised of 1.315 O.D. RS20 (.080-.090

Wall) galvanized steel tubing, 2.375 O.D. RS20 (.095-.105 Wall) galvanized steel tubing, and 1 7/8" steel ball. Finish: ProShield®, color specified.

Ball Clamp/

Ball Retainer: Cast from 535 almag. Finish: ProShield, color spec-ified.

E-Pod: Rotationally molded from U.V. stabilized linear low density polyethylene, color specified.

Pod Casting: Fabricated from sand cast alloy 356 in accordance with ASTM B26. Finish: ProShield, color specified.

Fasteners: Primary fasteners shall be socketed and pinned tam-perproof in design, stainless steel (SST) per ASTM F 879 unless otherwise indicated (see specific product installation/specifications).

Installation Time:Approx. 1 man hour
Area Req.:6'/1830 mm minimum use zone
Weight:143 lbs.
Fall Height:82"/ 2080 mm

Installation Instructions

1) Attach bow ladder to ball retainers using ball clamps and 3/8" x 1 1/8"

BHCS w/pin. Refer to the Bow Ladder Attachment Detail. NOTE:

5" Clamps may need to be turned to connect and position bow ladder properly. Retighten 5" clamp fasteners when bow ladder is in proper position.

2) Attach e-pods and pod castings to arches at dimensions shown, using 3/8" x 1 1/8" BHCS w/pin.

3) Drill through hole in pod casting and into noodle post with a 1/4" or "F" (only) drill bit. Insert 1/4" x 5/8" rivet in hole and hammer rivet pin in until it is flush with head.

4) Install protective surfacing before users are allowed to play on the structure.

© 2006 by Landscape Structures. All rights reserved.

SAFETY NOTE

Choose a protective surfacing material that has a Critical Height Value of at least the height of the Highest Accessible Part/Fall Height of the adjacent equipment. (Ref.

ASTM F1487.)

601 7TH STREET SOUTH, DELANO, MINNESOTA 55328-8605 888-574-4678 LSI Install Help 888-438-6574 LSI Direct 763-972-5200 Int. FAX (763) 972-3185 Document #15747200

156452 Wobble Pod® BouncerEvos®

DETAIL

SPRING LEG ATTACHMENT

(2) Spring Legs

(8) 3/8" Standard Hex Nuts w/ 3/8" SAE Flat Washers

(8) 3/8" x 1 1/8" BHCS w/Pin w/ 3/8" SAE Flat Washers

3"/80 Min.

(2) Spring Assemblies

(2) Spring Legs

Loose Fill Protective Surfacing

(2) Spring Assemblies

" M in

Concrete

Subgrade 34

Crushed Rock

18" Min.

24"

(8) 3/8" x 7/8" BHCS w/Pin w/ 3/8" SAE Flat Washers

(2) Spring Assemblies

Wobble Pod

DETAIL

DIRECT BURY

18" Min.

15747200

Evos® 156452 Wobble Pod® Bouncer

Parts List

Part#DescriptionQty.
115154Spring Leg, Specify Color..............................................2
154631Wobble Pod, Specify Color............................................1
156913Spring Assembly w/Plates, Specify Color......................2
156980Wobble Pod Hardware Package ................................1
1001963/8" x 7/8" BHCS w/Pin, SST...........................................8
1001983/8" x 1 1/8" BHCS w/Pin, SST........................................8
1003273/8" Standard Hex Nut, SST............................................8
1003653/8" SAE Flat Washer, SST.............................................24

Specifications Wobble Pod: Rotationally molded from U.V. stabilized linear low density polyethylene, color specified.

Spring Assembly: Comprised of 5 5/8" diameter 13/16" tempered alloy steel coil, 1/4" thick HRPO zinc plated steel, 1/4" thick HRPO sheet steel and spring wedge casting made from A-356 T-6 aluminum. Finish: ProShield®, color specified.

Spring Leg: Weldment comprised of 3 1/2" O.D. RS20 (.120" - .130" Wall) galvanized steel tubing and 1/4" x 10" diameter HRPO zinc plated steel mounting plate.

ProShield, color specified.

Fasteners: Primary fasteners shall be socketed and pinned tam-perproof in design, stainless steel (SST) per ASTM F 879 unless otherwise indicated (see specific product installation/specifications).

Installation Time:Approx. 2 man hours
Concrete Req.:Approx. 6 cu. ft.
Area Req.:6' (1,83 m) minimum use zone
Weight:122 lbs.
Fall Height:16" (410 mm)

Specifications are subject to change without notice.

Installation Instructions

1) Dig footing holes as shown. Refer to the Site Plan for proper location of Wobble Pods.

2) Attach spring assemblies to Wobble Pod, using 3/8" x 7/8" BHCS w/pin with 3/8" SAE flat washers, as shown.

3) Attach spring legs to spring assemblies, using 3/8" x 1 1/8" BHCS w/ pin with 3/8" SAE flat washers and 3/8" standard hex nuts with 3/8" SAE flat washers, as shown. Refer to the Spring Leg Attachment Detail.

4) With Wobble Pod propped in plumb position, pour concrete footings.

Allow concrete footings to cure for a minimum of 72 hours before users are allowed to play on the structure.

5) Install protective surfacing before users are allowed to play on the component.

© 2011 by Landscape Structures. All rights reserved.

601 7TH STREET SOUTH, DELANO, MINNESOTA 55328-8605 888-574-4678 LSI Install Help 888-438-6574 LSI Direct 763-972-5200 Int. FAX (763) 972-3185

Document #17989100

156450 Swiggle Stix® BridgeEvos®

DETAIL

POD CABLE ATTACHMENT

Pod Climb Across

(7) .439" I.D. x 1.156" Bushings

(7) 7/16" x 2" BHCS w/Pin Limited Thread

(7) Pod Cable Assemblies

DETAIL

SUPPORT ATTACHMENT

Pod Climb Across

Support

1/4" x 3/8" Drive Rivet

Support

Protective Surfacing

Pod Climb Across

Pod Cable #2

DETAIL

POD ATTACHMENT

(7) Pod Cable Assemblies

(21) 3/8" x 7/8" BHCS w/Pin w/ 3/8" SAE Flat Washers

Arch #4

Arch #2

Sleeve

(2) 5" Clamp Assemblies Ref. To Plan View

Sheet 1 of 2

(7)Tabs

17989100

(14) Connecting Plugs

SAFETY NOTE

Choose a protective surfacing material that has a Critical Height Value of at least the height of the Highest Accessible Part/Fall Height of the adjacent equipment. (Ref. ASTM F1487.)

(7) Bolt Links

(7) 1 5/16" O.D. x 1 5/8" Long Spacers

(7) Pod Bolt Plates

(7) Chains

(7) 3/8" x 7/8" BHCS w/Pin Limited Thread

(7) Pods

(14) 5/8" O.D. x 3/8" Long Bushings

(7) 3/8" x 1 1/4" BHCS w/Pin Limited Thread

Pod Cables #1

Pod Cables #1

Pod Cables #1

Chain (10 Links)

Chain (10 Links)

Chain (11 Links) Chain

(12 Links)

Chain (11 Links)Chain

(12 Links)

Chain (13 Links)

DETAIL

DIRECT BURY

Support

Loose Fill Protective Surfacing

Subgrade

Concrete

Crushed Rock

12"

M in

DETAIL

BALL CLAMP ATTACHMENT

Arch

(2) 5" Clamp Assemblies Ref. To Plan View

(2) Ball Retainers

(2) Ball Clamps

(4) 3/8" x 1 1/8

BHCS w/Pin

(4) 5/8" x 1 1/2

BHCS w/Pin #100201-00

Pod Climb Across

12"

M in

Crushed Rock

Concrete

Subgrade

Loose Fill Protective Surfacing

(7) Footers

DETAIL

FOOTER ATTACHMENT

DETAIL

(7) Chains

(7) Footers

(7) Bolt Links

(7) 5/8" O.D. x 1/2" Bushings

(7) 3/8" x 1 1/4" BHCS w/Pin Limited Thread

NOTE: The hole depth for the footer needs to be deep enough, so the footer plate doesn't contact the bottom of the hole. The weight of the concrete will force the footer plate down, tightening the cable.

© 2011 by Landscape Structures. All rights reserved.

SAFETY NOTE

Choose a protective surfacing material that has a Critical Height Value of at least the height of the Highest Accessible Part/Fall Height of the adjacent equipment. (Ref. ASTM F1487.)

179891a

(7) Chains

156450 Swiggle Stix® BridgeEvos®

601 7TH STREET SOUTH, DELANO, MINNESOTA 55328-8605 888-574-4678 LSI Install Help 888-438-6574 LSI Direct 763-972-5200 Int. FAX (763) 972-3185

© 2011 by Landscape Structures. All rights reserved.

601 7TH STREET SOUTH, DELANO, MINNESOTA 55328-8605 888-574-4678 LSI Install Help 888-438-6574 LSI Direct 763-972-5200 Int. FAX (763) 972-3185

Sheet 2 of 2

Document #17989100

SAFETY NOTE

Choose a protective surfacing material that has a Critical Height Value of at least the height of the Highest Accessible Part/Fall Height of the adjacent equipment. (Ref. ASTM F1487.)

12"

M in

Concrete

Footer

Chain

Pea Gravel

Pour-In-Place Surfacing

Crushed Rock

DETAIL

DIRECT BURY WITH

POUR-IN-PLACE SURFACING

( PEA GRAVEL)

12"

M in

Concrete

Footer

Chain

DETAIL

DIRECT BURY WITH

POUR-IN-PLACE SURFACING

Subgrade

Concrete Slab

Pour-In-Place Surfacing

8"-10" Diameter Concrete Form Tube (Not Supplied)

1"-3" Diameter 25-76

Pea Gravel, Sand Or Sub Grade

Crushed Rock

179891b

1"-3" Diameter 25-76

Subgrade

156450 Swiggle Stix® BridgeEvos®

Evos® 156450 Swiggle Stix® Bridge

Parts List

Part# Description Qty.

155157-00 Pod Climb Across, Specify Color 177938-00 60 7/8" Long Pod Cable #1 Assembly 178984-00 56 7/8" Long Pod Cable #2 Assembly 177932-00 Pod Bolt Plate, Specify Color 178586-00 1 5/16" O.D. x 1 5/8" Long AL. Spacer 179682-00 13" Long (10 Links) Chain 179687-00 14 1/4" Long (11 Links) Chain 179695-00 15 1/2" Long (12 Links) Chain 179689-00 16 3/4" Long (13 Links) Chain 156203-00 Pod Climb Across Support, Specify Color 164367-00 Footer, Specify Color 156699-00 Ball Clamp, Specify Color 156700-00 Ball Retainer, Specify Color 154460-00 Pod, Specify Color

180147-00 Swiggle Stix Hardware Package 100196-00 3/8" x 7/8" BHCS w/Pin, SST 100198-00 3/8" x 1 1/8" BHCS w/Pin, SST 100201-00 5/8" x 1 1/2" BHCS w/Pin, SST 100292-00 3/8" x 1 1/4" BHCS w/Pin Limited Thread, SST 100365-00 3/8" SAE Flat Washer, SST 100611-00 1/4" x 3/8" Drive Rivet, AL/SST 157704-00 7/16" x 2" BHCS w/Pin Limited Thread, SST 138915-00 Bolt Link, SST 157224-00 .439" I.D. x 1.156" Bushing, SST 156962-00 5/8" O.D. x 1/2" Bushing, SST 127179-00 5/8" O.D. x 3/8" Bushing, SST 162729-00 Connecting Plug 100290-00 3/8" x 7/8" BHCS w/Pin Limited Thread, SST

Specifications

Cable Assembly: (Cable) Made of tightly woven polyester-wrapped, six-stranded galvanized-steel cable with a polypropylene core. (Cable Connectors) 6063-T6 aluminum.

Pod: Rotationally molded from U.V. stabilized linear low density polyethylene, color specified.

Chain: Steel 1/4" (6,35 mm) straight link chain, 3,150 lb (1428,82 kilograms) working load limit. Finish: Peer Gold.

Pod Bolt Plate: Weldment consists of 3/16" (4,75 mm) HRPO steel plate and 3/8" (9,53 mm) thick HRPO steel plate. Finish:

ProShield®, color specified.

Ball Clamp/ Ball Retainer: Cast from 356-T6 aluminum. Finish: ProShield, color specified.

Pod Climb Across: Weldment comprised of 2.375" (60,33 mm) O.D. RS20 (.095"-.105") (2,41 mm-2,67 mm) wall galvanized steel tubing, 3/8" (9,53 mm) thick HRPO steel plate, and 1 7/8" (47,63 mm) steel ball. Finish: ProShield, color specified.

Support: Fabricated from 2.375" (60,33 mm) O.D. RS20 (.095"- .105") (2,41 mm-2,67 mm) wall galvanized steel tub-ing. Finish: ProShield, color specified.

Footer: Weldment comprised of 1.660" (42,16 mm) O.D. RS20 (.120" - .130") (3,05 mm-3,30 mm) wall galvanized steel tubing and 3/16" (4,75 mm) HRPO sheet steel.

ProShield, color specified.

Fasteners: Primary fasteners shall be socketed and pinned tamperproof in design, stainless steel (SST) per ASTM F 879 unless otherwise indicated (see specific prod-uct installation/specifications).

Installation Time: Approx. 4 1/2 man hours Concrete Req.: Approx. 10.25 cu. ft.

Area Req.: 6' (1,83 m) minimum use zone Weight: 151 lbs.

Fall Height: 36" (910 mm)

Installation Instructions

1) (Direct Bury) Refer to the Site Plan for footing locations.

2) Attach ball retainers to 5" clamps using 5/8" x 1 1/2" BHCS w/pin. Fasten pod climb across to ball retainers using, ball clamps and 3/8" x 1 1/8" BHCS w/pin. Refer to the Ball Clamp Attachment Detail. NOTE: 5" Clamps may need to be turned, or moved up or down to connect and position pod climb across properly. Check to make sure pod climb across is level, if not adjust 5" clamps. Retighten 5" clamp fasteners when pod climb across is in proper position.

3) Slide support into pod climb across sleeve. Drill through hole in sleeve and into support with a 1/4" or "F" (only) drill bit. Insert 1/4" x 3/8" rivet into hole and hammer rivet pin in until it is flush with head.

Refer to the Support Attachment Detail.

4) Attach pod cable assemblies to pod climb across tabs using .439" I.D. x 1.156" bushings, connecting plugs and 7/16" x 2" BHCS w/pin limited thread bolts. Refer to the Pod Cable Attachment Detail.

NOTE: Pod cable assemblies are numbered #1 and #2, and must be attached to pod climb across as shown.

5) Feed cables through 1 5/16" O.D. x 1 5/8" long spacers and holes in pods. Attach pod bolt plates to cables, using 3/8" x 7/8" BHCS w/pin limited thread bolts and 5/8" O.D. x 3/8" bushings. Refer to the Pod Attachment Detail.

6) Attach pod bolt plates to pods, using 3/8" x 7/8" BHCS w/pin with 3/8" SAE flat washers. Refer to the Pod Attachment Detail.

7) Attach chains to pod bolt plates, using bolt links, 3/8" x 1 1/4" BHCS w/pin limited thread bolts and 5/8" O.D. x 3/8" bushings. Refer to the Pod Attachment Detail. NOTE: Chains are different lengths, and must be attached to pod bolt plates as shown.

8) Attach footers to chains, using bolt links, 5/8" O.D. x 1/2" bushings, and 3/8" x 1 1/4" BHCS w/pin limited thread bolts, as shown. Refer to the Footer Attachment Detail.

9) With support plumb and pod cable assemblies positioned properly, pour concrete footings. Allow concrete footings to cure for a mini-mum of 72 hours before users are allowed to play on the structure.

(Direct Bury With Pour-In Place Surfacing) Cut 7 lengths of con-crete form tubes (not supplied) long enough to set on top of concrete footings and be level with top of concrete slab. Concrete form tubes should be 8"-10" in diameter. Disconnect bolt links from pod bolt plates. Place concrete form tubes over chains and footers. Connect bolt links to pod bolt paltes. Fill concrete form tubes with pea gravel, sand or sub grade. Pour concrete slab. After concrete slab has cured, pour surfacing. NOTE: When pouring surfacing leave a 1"-3" di-ameter opening around chains. Refer to the DirectBury Pour-In-Place Surfacing Detail.

10) Install protective surfacing before users are allowed to play on the structure.

Specifications are subject to change without notice.

J:\INSTSPEC\SPECS\179\17989100.P65

Eco #54371 Document 17989100 replaces 17704400. Changed cable part numbers and added chains and pod bolt plates to Parts List..

1-877-854-3319 info@elephantplay.comE L E P H A N T P L AY elephantplay.com

S P I N N E R O U N D S E R I E S

AVAIL ABLE COLORS - STRUCTURE

AVAIL ABLE COLORS - CABLES

C U T S H E E T

2024.05

AVAIL ABLE COLORS - STRUCTURE

Ral 9003

Ral 6026

Ral 4003

Ral 7035

Ral 1019Ral 1018

Ral 5021

Ral 4006 Ral 5002

Ral 8024

Ral 6018

Ral 2011

Black

Ral 5012

Silver matte

Ral 1028

Ral 6027Ral 6019Ral 5017

Ral 4001

Ral 3000

11800 Avenue Adolphe-Caron Montreal, Qc, H1E 7J3

Toll free 1-877-854-3319 info@elephantplay.com

AVAIL ABLE COLORS - CLIMBING HOLDS

AVAIL ABLE COLORS - ROTOMOLDED PL ASTIC

TACY

DR

CB

HY DY

GRPU GC

LGY

KG

WO

SG

OR

BL

ATTE

BUFU

Slate black Mapple valley

AVAIL ABLE COLORS - WOOD FIBER PANNEL

Color and material chart

AVAIL ABLE COLORS - CABLES

Black Blue Green Red

Galvanised

SWING BUMPER

YellowBlack Blue Green Red

Ral 1005 Ral 1014

Ral 3022 Ral 3027

Ral 6011

Ral 6033 Ral 7024

AVAL AIBLE COLORS - PL ASTIC

Black Green Red Grey BrownBlue Yellow

Sand Urban GrayCedar

Plastic Wood Sand

Plastic Wood Urban Gray

Plastic Wood Cedar

AVAIL ABLE - WOOD & PL ASTIC WOOD

Wood Ipe Wood Robinia

RobiniaWhite Cedar

NATURE SERIE - AVAIL ABLE WOOD

Eastern white cedar is installed by default.

The robinia is also available on request at an additional cost.

11-12 14-01

16-09

15-1207-13

16-13

13-01

18-09

11-11

ACH-9ACH-5

11-25

ACH-3 ACH-10

Elephant Play • 2023

RH01 RH10 RH20 RH26 RH30

RH31 RH41 RH40 RH50 RH61

AVAIL ABLE COLORS - RUBBER

AVAIL ABLE COLORS - STRUCTURE

Ral 9003

Ral 6026

Ral 4003

Ral 7035

Ral 1019Ral 1018

Ral 5021

Ral 4006 Ral 5002

Ral 8024

Ral 6018

Ral 2011

Black

Ral 5012

Silver matte

Ral 1028

Ral 6027Ral 6019Ral 5017

Ral 4001

Ral 3000

11800 Avenue Adolphe-Caron Montreal, Qc, H1E 7J3

Toll free 1-877-854-3319 info@elephantplay.com

AVAIL ABLE COLORS - CLIMBING HOLDS

AVAIL ABLE COLORS - ROTOMOLDED PL ASTIC

TACY

DR

CB

HY DY

GRPU GC

LGY

KG

WO

SG

OR

BL

ATTE

BUFU

Slate black Mapple valley

AVAIL ABLE COLORS - WOOD FIBER PANNEL

Color and material chart

AVAIL ABLE COLORS - CABLES

Black Blue Green Red

Galvanised

SWING BUMPER

YellowBlack Blue Green Red

Ral 1005 Ral 1014

Ral 3022 Ral 3027

Ral 6011

Ral 6033 Ral 7024

AVAL AIBLE COLORS - PL ASTIC

Black Green Red Grey BrownBlue Yellow

Sand Urban GrayCedar

Plastic Wood Sand

Plastic Wood Urban Gray

Plastic Wood Cedar

AVAIL ABLE - WOOD & PL ASTIC WOOD

Wood Ipe Wood Robinia

RobiniaWhite Cedar

NATURE SERIE - AVAIL ABLE WOOD

Eastern white cedar is installed by default.

The robinia is also available on request at an additional cost.

11-12 14-01

16-09

15-1207-13

16-13

13-01

18-09

11-11

ACH-9ACH-5

11-25

ACH-3 ACH-10

Elephant Play • 2023

RH01 RH10 RH20 RH26 RH30

RH31 RH41 RH40 RH50 RH61

AVAIL ABLE COLORS - RUBBER

INSTALL ATION DETAILS

CHARACTERISTICS

Age Group: 5-12 years old Fall Height: 9’-0’’ (2.74m) Capacity: 30 Safety zone: Ø22’-10’’’ (Ø6.96m) The equipment is design to be installed in a 12’’ (300mm) of resilient material (EWF, rubber or sand).

MATERIALS

Inner Post : heavy-duty galvanized steel;

Outer Post, Hardware and Fasteners : powder coated stainless steel*;

Deck : reinforced perforated aluminum*;

Ring : rolled aluminum tubing*;

Cap : half-sphere aluminum*;

Cables : braided UV-resistant nylon over seven (7) galvanized steel cables; 0,8’’ (20mm) diameter;

Cable Hardware : cast aluminum*;

Rotative Device : maintenance-free, self-lubricated nylon.

*All painted parts are powder coated with UV-resistant polyester.

INTALL ATION METHOD

In-ground galvanized steel freestanding footing.

PL AY VALUE

The Spinneround Serie enhance general playful freedom of movement, stability, hanging and running. This equipement favorize group interaction and create high sensory stimulation. Moreover, the moving of the center of mass constitute a highly amusing physical training for its users.

Pyramid Full with deck

EP-SS-ERN1300D (ASTM)

CON26-0042 Attachment 2.pdf
Sunset Wobble Pod Springs - Proposal Document 00049405 2025-12-30 091020
15746300 Bow Ladder
15747200 Wobble Pod
17989100 Swiggle Stix
Pod Chain 198497a

EP-SS-ERN1300D Pyramid Full with deck_ASTM.pdf

File details come from the government source that posted it. Updated .