This is a bid solicitation document from Lewis County, Washington for the Community Development/EH Acoustic Ceiling Project, a re-bid (Project 31-2102-Ceiling 2). The project involves providing and installing an acoustical drop ceiling in the new Community Development/Environmental Health offices, with 2' x 4' tiles to be hung in an aesthetically pleasing layout. The bid was released on January 10, 2024, with a site visit scheduled for January 17, 2024, at 11:00 am. Prospective bidders must submit questions by January 19, 2024, at 3:00 pm, and proposal submissions are due by January 24, 2024, at 2:00 pm. Lewis County is utilizing the MRSC Vendor and Small Works Rosters for this solicitation and requires bidders to be members of the appropriate roster.
The project is subject to Washington State Prevailing Wage Laws, with current wage rates available online. Bidders must be licensed to perform this type of work in Washington and complete a vendor questionnaire, including a non-collusion affidavit. The bid includes provisions for trench safety (if applicable) and allows for potential bid alternates. Bidders must conform to specific technical specifications for metal suspension systems and acoustical ceiling panels, including detailed requirements for materials, installation, and finish. The county reserves the right to accept or reject any bid and may negotiate with the lowest responsive bidder to bring the bid within available funding.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAPITAL FACILITIES
Project: Community Development/EH Acoustic Ceiling Project, Re-Bid, 31-2102-Ceiling 2
Effective Date: undefined
1. Introduction
Project Description
1.1. Summary
Lewis County is looking for a qualified vendor to complete the Acoustical Drop Ceiling for the new Community Development Building.
1.2. Background
Lewis County has been purchasing historic buildings with the goal of creating a "County
Campus" downtown Chehalis, with the intent of better consolidating County Government buildings and staff to improve accessibility while rejuvenating the Historic Downtown area. This plan when executed will provide a closely knit series of county owned and operated facilities, that provide a central hub, allowing Lewis County citizens to find and access a majority of
County services within walking distance of each other. Lewis County has assumed the role of
General Contractor, overseeing any and all 3rd party vendors utilized in the preservation/rejuvenation of these historic buildings. Lewis county is looking for the help of local trade specific vendors to make this goal a reality. By utilizing the skillset of the best tradesman available, we can oversee these projects, while ensuring the highest level of craftsmanship and quality, while simultaneously leveraging construction funds for the greatest result possible.
1.3. Contact Information
Project Contact:
Andrew Fagerness
Construction Supervisor
571 NW Prindle
Chehalis, WA 98532
Email: andrew.fagerness@lewiscountywa.gov
Phone: (360) 880-5374
Procurement Contact:
Doug Carey
Capital Manager mailto:andrew.fagerness@lewiscountywa.gov tel:(360)880-5374
351 NW North St
Chehalis, WA 98532
Email: doug.carey@lewiscountywa.gov
Phone: (360) 740-1337
Department:
Capital Facilities
Department Head:
Doug Carey
Capital Facilities Manager
1.4. Timeline
Release Project Date January 10, 2024
Site Visit January 17, 2024, 11:00am
Question Submission Deadline January 19, 2024, 3:00pm
Proposal Submission Deadline January 24, 2024, 2:00pm
2. Call for Bids
NOTICE
SMALL WORKS CALL FOR BIDS
For
Community Development/EH Acoustic Ceiling Project, Re-Bid 31-2102-Ceiling 2
Lewis County is soliciting bids from qualified firms to provide bids for the Community
Development/EH Acoustic Ceiling Project, Re-Bid 31-2102-Ceiling 2, located in Chehalis WA.
Firms desiring consideration shall submit a complete bid package based on the plans and specifications on file at https://procurement.opengov.com/portal/lewiscountywa
Lewis County has partnered with OpenGov and is excited to announce that in August 2023, we will transition to OpenGov Procurement/ProcureNow, a fully automated web-based electronic bidding and vendor management system. To continue to receive bid notifications, you will want to register for a FREE account today at https://procurement.opengov.com/portal/lewiscountywa.
In addition, Lewis County is using the MRSC Vendor and Small Works Rosters for Small Works or Vendor solicitations. Go to https://mrscrosters.org/ for more information and to register. You must be a member of the appropriate roster to be eligible. Please make sure you select mailto:doug.carey@lewiscountywa.gov tel:(360)740-1337 https://procurement.opengov.com/portal/lewiscountywa https://procurement.opengov.com/portal/lewiscountywa https://mrscrosters.org/
Lewis County so that your firm is displayed on our rosters. The MRSC Process may take up to 2 weeks to complete!
Lewis County is an equal opportunity and affirmative action employer. Minority- and women-owned firms are encouraged to submit bids.
3. Instructions to bidders
3.1. Instructions to Bidders
FOR LEWIS COUNTY FACILITIES CONSTRUCTION PROJECTS
0.01 EXPLANATION TO PROSPECTIVE BIDDERS
A. Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must submit a request in writing to the Architect/Engineer (A/E) or owner if no A/E, 7 calendar days before the bid due date. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders by addendum to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
B. In accordance with the legislative findings and policies set forth in Chapter 39.19 RCW, the
State of Washington encourages participation in all of its contracts by Minority and Women’s
Business Enterprises (MWBE) firms certified by the Office of Minority and Women’s Business
Enterprises (OMWBE). Participation may be either on a direct basis in response to this invitation or as a subcontractor to a bidder. However, unless required by federal statutes, regulations, grants, or contract terms referenced in the contract documents, no preference will be included in the evaluation of bids, no minimum level of MWBE participation shall be required as a condition for receiving an award, and bids will not be rejected or considered non-responsive on that basis.
C. Any affirmative action requirements set forth in federal regulations or statutes included or referenced in the contract documents will apply.
D. In accordance with RCW 39.04.320 the State of Washington requires 15% Apprenticeship
Participation for all projects estimated to cost one million dollars or more. On applicable projects the bid advertisement and Bid Proposal form shall establish a minimum required percentage of apprentice labor hours compared to the total labor hours. Bidders may contact the Department of
Labor and Industries, Specialty Compliance Services Division, Apprenticeship Section, P.O. Box
44530, Olympia, WA 98504-4530, by phone (360) 902-5320, and e-mail at thum235@lni.wa.gov, to obtain information on available apprenticeship programs.
0.02 PREPARATION OF BIDS – CONSTRUCTION
A. Bids must be: (1) submitted on the bid proposal forms, or copies of forms, furnished by the
Owner or the Owner’s agent, and (2) signed in ink. The person signing a bid must initial each change appearing on any bid form. If the bid is made by a corporation, it shall be signed by the corporation’s authorized designee. The address of the bidder shall be typed or printed on the bid form in the space provided.
B. The bid form may require bidders to submit bid prices for one or more items on various bases, including: (1) lump sum base bid; (2) lump sum bid alternate prices; (3) unit prices; or (4) any combination of items (1) through (3) above.
C. If the solicitation includes alternate bid items, failure to bid on the alternates may disqualify the bid. If bidding on all items is not required, bidders should insert the words “no bid” in the space provided for any item on which no price is submitted.
D. Substitute bid proposals will not be considered unless this solicitation authorizes their submission.
0.03 BID GUARANTEE
A. When the sum of the base bid plus all additive bid alternates is $125,000.00 or less, bid security is not required. When the sum of the base bid plus all additive alternates is greater than
$125,000.00, a bid guarantee in the amount of 5% of the base bid amount is required. Failure of the bidder to provide bid guarantee when required shall render the bid non-responsive.
B. Acceptable forms of bid guarantee are: A bid bond or postal money order, or certified check or cashier’s check made payable to the Lewis County Treasurer. The Owner will return bid guarantees (other than bid bond) to unsuccessful bidders as soon as practicable, but not sooner than the execution of a contract with the successful bidder. The successful bidder’s bid guarantee will be returned to the successful bidder with its official notice to proceed with the work of the contract.
C. The bidder will allow 60 days from bid opening date for acceptance of its bid by the
Owner. The bidder will return to the Owner a signed contract, insurance certificate and bond or bond waiver within 15 days after award of the contract. If the apparent successful bidder fails to sign all contractual documents or provide the bond and insurance as required or return the documents within 15 days after award of the contract, the Owner may terminate the award of the contract.
D. In the event a bidder discovers an error in its bid following the bid opening, the bidder may request to withdraw its bid under the following conditions:
1. Written notification is received by the Owner within 24 hours following bid opening.
2. The bidder provides written documentation of the claimed error to the satisfaction of the
Owner within 72 hours following the bid opening. The Owner will approve or disapprove the request for withdrawal of the bid in writing. If the bidder’s request for withdrawal of its bid is approved, the bidder will be released from further obligation to the Owner without penalty. If it is disapproved, the Owner may retain the bidder’s bid guarantee.
0.04 ADDITIVE OR DEDUCTIVE BID ITEMS
A. The low bidder, for purposes of award, shall be the responsive bidder offering the low aggregate amount for the base bid item, plus additive or deductive bid alternates selected by the
Owner, and within funds available for the project. The bidder agrees to hold all bid alternate prices until bid award and contract execution.
0.05 ACKNOWLEDGEMENT OF ADDENDA
A. Bidders shall acknowledge receipt of all addenda to this solicitation by identifying the addenda numbers in the space provided for this purpose on the bid proposal form. Failure to do so may result in the bid being declared non-responsive.
0.06 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
A. The bidder acknowledges that it has taken steps necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and road; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during the work. The bidder also acknowledges that it has satisfied itself as to character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including exploratory work done by the Owner, as well as from the drawings and specifications made a part of this contract. Any failure of the bidder to take the actions described and acknowledged in this paragraph will not relieve the bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work.
0.07 BID AMOUNTS
A. The bid prices shown for each item on the bid proposal shall include all labor, material, equipment, overhead and compensation to complete all of the work for that item.
B. The actual cost of building permit (only) and the public utility hookup fees will be a direct reimbursement to the Contractor or paid directly to the permitting agency by the Owner. Fees for these permits should not be included by the Bidder in the bid amount.
C. The Bidder agrees to hold the base bid prices until bid award and contract execution.
0.08 TAXES
A. The bid amounts shall not include Washington State Sales Tax (WSST). All other taxes imposed by law shall be included in the bid amount. The Owner will include WSST in progress payments. The Contractor shall pay the WSST to the Department of Revenue and shall furnish proof of payment to the Owner if requested. [NOTE: Contractor must bond for contract amount plus the WSST.]
0.09 SUBMISSION OF BIDS
A. Bid Proposals must be submitted on or before the time specified in the Advertisement for
Bids.
B. If the base bid and the sum of the additive alternates is one million dollars or more, the Bid
Proposal shall comply with the following requirements:
1. Pursuant to RCW 39.30.060, if the base bid and the sum of the additive alternates is one million dollars or more, the Bidder shall provide names of the Subcontractors with whom the
Bidder will subcontract for performance of heating, ventilation and air conditioning (HVAC), plumbing, and electrical.
2. The Bidder can name itself for the performance of the work.
3. The Bidder shall not list more than one Subcontractor for each category of work identified
UNLESS Subcontractors vary with bid alternates, in which case the Bidder must indicate which
Subcontractor will be used for which alternate.
4. Failure of the Bidder to submit as part of the bid the NAMES of such Subcontractors or to name itself to perform such work shall render the Bidder's bid nonresponsive and, therefore, void.
C. The Bid Proposal shall be submitted through the OpenGov.com portal https://procurement.opengov.com/portal/lewiscountywa
D. Prior to the bid opening, the Owner’s representative will designate the official bid clock.
Any part of the bid proposal or bid modification not received prior to the times specified, per the designated bid clock, will not be considered and the bid will be returned to the bidder unopened.
E. A bid may be withdrawn in person by a bidder’s authorized representative before the opening of the bids. Bidder(s) representative will be required to show ID and sign on bid summary sheet before it will be released.
F. People with disabilities who wish to request special accommodation, (e.g., sign language interpreters, Braille, etc.) need to contact the Owner ten (10) working days prior to the scheduled bid opening.
0.10 BID RESULTS
A. After the Bid Opening, a tabulation of the bids will be posted as a notice for the project in the OpenGov portal. Bidders may obtain the tabulation of apparent bids from Lewis County by
Contacting the procurement contact listed in the bid documents.
0.11 LOW RESPONSIBLE BIDDER
A. If applicable, it is the intent of the Owner to award a contract to the low responsible bidder.
In determining the bidder’s responsibility, the Owner shall consider an overall accounting of the attached “DIVISION 00 RESPONSIBILITY CRITERIA”. Upon Owner’s request, the apparent low bidder must supply the requested information within two (2) business days of request by
Owner. Withholding information or failure to submit all the information requested within the time provided shall render the bid nonresponsive. If the Owner determines that the apparent low bidder is not responsible, the Owner will notify the bidder of its preliminary determination in writing. Within three (3) days after receipt of the preliminary determination, the bidder may withdraw its bid or request a hearing. The Owner will schedule a hearing within three (3) working days of receipt of the bidder’s request. The hearing members will include the Central
Services Director, Public Works Director and Central Services Project Manager. The Owner will issue a Final Determination after reviewing information presented at the hearing. The
Owner’s Final Determination is specific to this project, and will have no effect on other or future projects.
B. “SUBCONTRACTOR RESPONSIBILITY CRITERIA” In accordance with SHB 2010 amending RCW 39.04 the Contractor shall include the language of this paragraph in each of its first tier subcontracts, and shall require each of its subcontractors to include the same language of this section in each of their subcontracts, adjusting only as necessary the terms used for the contracting parties. The requirements of this paragraph apply to all subcontractors regardless of tier. At the time of subcontract execution, the Contractor shall verify that each of its first tier https://procurement.opengov.com/portal/lewiscountywa subcontractors meets the following bidder responsibility criteria:
1. Have a current certificate of registration as a contractor in compliance with chapter 18.27
RCW, which must have been in effect at the time of subcontract bid submittal;
2. Have a current Washington Unified Business Identifier (UBI) number; and if applicable, have:
a. Have Industrial Insurance (workers’ compensation) coverage for the subcontractor’s employees working in Washington, as required in Title 51 RCW;
b. A Washington Employment Security Department number, as required in Title 50 RCW;
c. A Washington Department of Revenue state excise tax registration number, as required in
Title 82 RCW;
d. An electrical contractor license, if required by Chapter 19.28 RCW;
e. An elevator contractor license, if required by Chapter 70.87 RCW.
f. Not be disqualified from bidding on any public works contract under RCW 39.06.010 or
39.12.065 (3).
0.12 CONTRACT AWARD
A. The Owner will evaluate bid responsiveness and bidder responsibility.
A bid will be considered responsive if it meets the following requirements:
1. It is received at the proper time and place.
2. It meets the stated requirements of the bid proposal.
3. It is submitted by a licensed/registered contractor within the State of Washington at the time of bid opening and is not banned from bidding by the Department of Labor and Industries.
4. It is accompanied by a bid guarantee, if required.
A bid will be considered responsible if it meets the following requirements:
1. It meets an overall accounting of the responsibility criteria established for the project.
B. The Owner reserves the right to accept or reject any or all bid proposals and to waive informalities that do not affect the essential fairness of the bidding process.
C. The Owner may negotiate bid price adjustments with the low responsive bidder, including changes in the contract documents, to bring the bid within the available funding per RCW
39.04.015.
D. The apparent low bidder, for purpose of award, shall be the responsive bidder offering the low aggregate amount for the base bid plus selected additive or deductive bid alternates and meeting all other bid submittal requirements.
E. The Contract will only become effective when signed by the Owner. Prior to the Owner’s signature, any and all costs incurred shall be the sole responsibility of the bidder.
It is the intent of the Owner to award a contract to the low responsible bidder. Public Agency
Debarment- Debarment by any Public agency within the last two (2) years may render bid non-responsive.
3.2. Small Works Bids
Lewis County may choose to utilize a Small Works bid or Limited Small Works bid process. Bidders must be a member of the appropriate small works list to submit a responsive bid. Lewis County is using the MRSC Small Works Rosters to solicit these bids.
Please note that MRSC roster membership may take up to 2 weeks to complete. Please choose
Lewis County or your membership will not show on the appropriate roster.
4. Scope and specifications
Provide and install an acoustical drop ceiling in the new Community
Development/Environmental Health offices as per the attached drawings and specifications. Tiles shall be 2' x 4' and shall be hung in a aesthetically pleasing layout. Note that there are several areas with other types of material. Hard lids will be installed by sheetrock sub and the wood ceiling will be installed by owner's forces.
SECTION 09 22 26
METAL SUSPENSION SYSTEMS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Suspended metal ceiling support system for new furred down gypsum board ceilings.
1.02 RELATED WORK IN OTHER SECTIONS
A. Lightgauge metal stud framing covered under Section 05 40 00.
B. Section 09 29 00 - Gypsum Board.
C. Section 09 51 00 - Acoustical Ceilings.
1.03 QUALITY ASSURANCE
A. Standard Specifications
1. General: Where "USG" is used herein it shall mean "United States Gypsum Company".
2. For Gypsum Board Suspended Ceiling Framing: For the installation of suspended steel framing members for gypsum board conform to the American National Standard "Standard
Specifications for the Installation of Steel Framing Members to Receive Screw Attached
Gypsum Board, ASTM C754", hereinafter called "ASTM C754".
1.04 SUBMITTALS
A. Manufacturer's Data: Furnish manufacturer's literature for support framing materials and accessories.
B. Shop Drawings
1. Submit shop drawings showing typical details for all work and relationship of work adjacent thereto. Include methods of joining, fastening, and other pertinent information.
2. Furnish samples for approval of each different member to be used on the work, upon request of the Architect.
1.05 PRODUCT DELIVERY, STORAGE & HANDLING
A. Delivery, Storage & Protection
1. All materials shall be delivered in original packages, containers, or bundles bearing the brand name and the name of the manufacturer or the supplier for whom the product is manufactured.
2. All materials shall be kept dry, stored inside the building under roof, or where necessary to store outside, shall be stacked off the ground, properly supported on a level platform and fully protected from the weather.
PART 2 - PRODUCTS
2.01 METAL FRAMING MATERIALS
A. Standard Suspended Ceiling Members & Accessories For Gypsum Board Work
1. Hanger Wires and Clips: Galvanized steel No. 8 gauge wires for vertical hangers, hung from clips secured to structural members above ceiling, lengths as required for tying to steel runner channels at 48 inches o.c. For seismic bracing wire, furnish of galvanized steel No. 12 gauge wire.
2. Main Runner Channels: Furnish 1-1/2 inch x 16 gauge cold rolled steel channels weighing 475 lbs. per 1000 lin. ft., galvanized finish.
3. Compression Struts: Furnish of steel stud sections of size and gauge required for each respective ceiling condition as set forth in Detail 3/A9.7, complete with necessary bolt anchors.
SECTION 09 22 26
METAL SUSPENSION SYSTEMS
SECTION 09 51 00
ACOUSTICAL CEILINGS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Suspended metal grid ceiling systems.
B. 2' x 4' Acoustical lay-in panels.
C. 2' x 8' Wood lay-in panels.(Not part of scope)
1.02 RELATED WORK IN OTHER SECTIONS
A. Mechanical work penetrating acoustical materials covered under Division 23 and the
Mechanical Work Drawings.
B. Electrical work penetrating acoustical materials covered under Division 26 and the Electrical
Work Drawings.
1.03 REFERENCE STANDARDS
A. ASTM C635 - Standard Specification for the Manufacture, Performance, and Testing of
Metal Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings; 2007.
B. ASTM C636/C636M - Standard Practice for Installation of Metal Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels; 2008.
C. ASTM E580/E580M - Standard Practice for Installation of Ceiling Suspension Systems for
Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions; 2011.
D. ASTM E1264 - Standard Classification for Acoustical Ceiling Products; 2008e1.
1.04 QUALITY ASSURANCE
A. Qualifications: All work covered by this Section to be provided by a firm regularly engaged, and licensed in the area of the work, as an acoustical subcontractor approved by the acoustical material manufacturer and the Architect.
B. Requirement Of Regulatory Agencies: Conform to the requirements of local building codes and ordinances, governing fire officials, and Underwriters' Laboratories design test requirements, for suspended ceiling work specified herein.
C. Seismic & Uplift Bracing Requirements
1. Provide lateral force bracing in conformance with ASTM E580.
2. Provide vertical bracing to prevent uplift.
1.05 SUBMITTALS
A. Submittals
1. Samples and Technical Data: Furnish samples and technical data for each type and pattern of acoustical tile and panels and each part of metal suspension system, all in accordance with
Section 01 33 00.
2. Shop Drawings: Submit in accordance with Section 01 33 00. Include all details of all connections including supporting details, light fixture attachments, lateral force bracing, partition bracing, etc.
1.06 PRODUCT DELIVERY, STORAGE & HANDLIING
A. Product Handling
1. Furnish all materials specified herein, suitably boxed and wrapped to protect against damage.
2. Store materials in heated, covered location in the building, off floor; protect materials from all damage before and during installation.
1.07 JOB CONDITIONS
A. Environmental & Job Conditions: Coordinate sequence of work that the following is completed by other trades and conditions maintained as noted before starting work in this
Section:
1. Concrete and other "wet" work is completed, cured and dry.
2. Exterior doors are installed and closed, windows glazed.
3. Heating system installed and operating to maintain specified minimum temperature of not less than 60 degrees F. before, during and after acoustical work installation.
4. Other "Job Conditions" are maintained as set forth in the CISCA "Installation
Recommendations".
PART 2 - PRODUCTS
2.01 MATERIALS
A. Mineral Fiber Acoustic Panels : Furnish conforming to the following:
1. Ceiling Type ACP1: 2x4 Scored Mineral Fiber Panels :
a. Size: 24 x 48 inches
b. Minimum thickness: 3/4 inch.
c. NRC: 0.65 minimum (ASTM E1264)
d. CAC: 0.35 (ASTM E1264)
e. Light Reflectance: 0.85 (ASTM E1477)
f. Flame Resistance: "A"
g. Flame Spread: 25 or less (ASTM E1264)
h. Exposed Edges: Beveled Tegular for 15/16” exposed grid.
i. Substrate: Water felted mineral fiber.
j. Pattern: Armstrong World Ind. "Cirrus Second Look II" #513 (24” x 24” square scored pattern) or USG #78085 “Eclipse Illusion Two/24” panel, or approved.
k. Finish: Factory-applied white vinyl-latex paint.
2. Mineral Fiber Acoustic Panels : Furnish conforming to the following:
a. Ceiling Type ACP2: 2x4 Scored Mineral Fiber Panels with 6" x 4' Look:
1) Size: 24 x 48 inches
2) Minimum thickness: 3/4 inch.
3) NRC: 0.65 minimum (ASTM E1264)
4) CAC: 0.35 (ASTM E1264)
5) Light Reflectance: 0.85 (ASTM E1477)
6) Flame Resistance: "A"
7) Flame Spread: 25 or less (ASTM E1264)
8) Exposed Edges: Beveled Tegular for 15/16” exposed grid.
9) Substrate: Water felted mineral fiber.
10) Pattern: Armstrong World Ind. "Cirrus Second Look III" #514 (6” x 48” linear plank scored pattern) or USG #78011 “Eclipse Illusion Four/48” panel, or approved.
11) Finish: Factory-applied white vinyl-latex paint.
2.02 METAL SUSPENSION SYSTEMS
A. Exposed Grid Metal Suspension System
1. System type: ASTM C635 - defined Intermediate Classification steel non-fire- endurance-rated grid system, of exposed 15/16-inch grid (USG “DXDXL System” or equal) for all acoustical lay-in panels. For linear wood ceiling panels furnish heavy duty main beams equal to
Armstrong "Prelude XL" HD main beam suspension members along with 2-foot cross tees that are full height (1-11/16").
2. Approved manufacturers:
a. U.S. Gypsum (Donn Products Inc.)
b. Chicago Metallic Corp.
c. Armstrong World Ind.
3. Steel Non-Fire-Endurance-Rated Systems:
a. ASTM C635, manufacturer's standard sections of formed cold-rolled steel, electro-galvanized and factory painted satin white standard coating for mineral fiber panel grid assemblies and black premium color coating for linear wood panels.
b. Include main and cross runner members, assembly devices, wall molding, all other accessories required for the complete non-fire-endurance-rated system hereinbefore specified.
c. Where employing indirect-hung suspension system, furnish 1-1/2 inch cold-rolled carrying channels, 475 lbs. per 1000 lin. ft., protective painted.
d. Hanger wires, galvanized, for direct-hung work, soft-annealed mild steel wire of gauge certified by load test data as capable of carrying five times the design load but in no case less than No. 12 gauge or U.L. Inc. requirements, whichever is greater; with indirect-hung suspension systems, conform to MLA Specifications for galvanized wire, No. 2 size, of type, and spacing requirements.
e. Hangers conforming to ASTM C636 and as approved.
f. Main runners for 4 feet o.c. spacing; support wire 4 feet o.c. maximum.
g. Cross runners as required for panel system and as required for mechanical and electrical equipment and fixture support.
h. Compression Struts: Furnish of steel stud sections of size and gauge required for each respective ceiling condition, complete with necessary anchors for securing to main runners and ceiling structure above.
PART 3 - EXECUTION
3.01 INSPECTION OF SURFACES & CONDITIONS
A. Condition Of Surfaces & Prior Work (For suspended ceiling work in this Section)
1. Make certain that perimeter wall work, where ceiling abuts, is completed and that all work has been installed and completed above ceiling.
2. Comply with ASTM C636 Article 3, “Interference of Ceiling Related Components”;
coordinate with other trades in this matter.
3. Consult mechanical and electrical drawings for type and extent of their work becoming a part of or penetrating ceiling.
4. Provide approved hangers for attaching suspension wires.
3.02 INSTALLATION OF SUSPENDED CEILING GRID SYSTEM
A. Ceiling Suspension System
1. General:
a. Conform to ASTM C636, Article 2, as if included herein verbatim, and the suspension system manufacturer's instructions for component assembly for the non-rated systems hereinbefore specified and as supplemented hereinafter.
b. Erect ceiling system level within 1/8 inch in 12 feet tolerance when measured in any direction, non-cumulatively; exposed members parallel with one another, parallel with perimeter walls.
c. Make sure that all grilles and diffusers are in place, properly supported and connected lighting fixtures are to be individually supported from structure above by electrical trade.
2. Direct-hung suspension system:
a. Install with hanger wires and their anchors and attachment devices, direct-suspended main runners, cross runners, spanning main runners, assembly devices, perimeter wall moldings and metal trim, as required, for a complete installation and as approved. Wires shall attach directly to framing members; attachment to finish materials not permitted.
b. Arrange that perimeter borders be not less than one-half lay-in panel width when measured perpendicularly to wall or panel edge.
c. Install grid systems in the various patterns shown on Reflective Ceiling Plans for each respective space.
d. Compression Struts: Install in conformance with suspension system details, secured to main runner channels and ceiling structure above.
3.03 INSTALLATION OF LAY-IN PANELS
A. Panels Suspended Ceiling Work
1. Lay-in Panels:
a. Install panels in suspension systems specified hereinabove.
b. Edge joints tight, in straight line.
2. Panel Edges at Perimeters: Cut carefully to suit border sizes allowing for full bearing on perimeter angles or support, or kerf tile or concealed perimeter support angles, where so detailed;
provide a tapered cut 'tegular' or 'shadowline' edge along cut edges of perimeter panels to maintain 'tegular' or 'shadowline' appearance and fit, as applicable. Provide similar treatment at diffuser and other penetrations, as necessary.
3.04 CLEANING & REPAIRING DENTS, SCRATCHES & ABRASIONS ON NEW WORK
A. Dents: Where damaged by denting or otherwise during or subsequent to installation and dents cannot be repaired only by painting, without use of spackle or fillers, remove and replace with new material. Replace work damaged by other trades, after installation at the expense of trades causing such damage
B. Scratches & Abrasions
1. Where acoustical units and exposed suspension members are slightly scratched or abraded subsequent to installation, repair by painting.
2. Use only paint of same type, color and manufacture as recommended and furnished by the manufacturer of the scratched or abraded material.
END OF SECTION
5. Prevailing Wage
Notice
Prevailing Wage Requirement
This project has been determined to be “Public Works” as defined by RCW 39.04 and WAC
296-127 and is subject to Washington State Prevailing Wage Laws. Current Prevailing Wage
Rates for work performed in Lewis County can be found at https://secure.lni.wa.gov/wagelookup/. The bid date used isWednesday, January 24, 2024. These rates apply to Lewis County and may not apply to work performed outside Lewis
County.
A printed copy is available in the issuing office and a printed copy may be mailed upon request.
In addition, successful Contractor and any subcontractors are required to file Statement of Intent to Pay Prevailing Wages, Affidavits of Wages Paid and file Certified Payroll Records as per L&I requirements.
6. Bid Form
Bid Form https://secure.lni.wa.gov/wagelookup/
6.1. Bid Form
Project Name: Community Development/EH Acoustic Ceiling Project, Re-Bid 31-2102-Ceiling 2
Name of Firm:
LEWIS COUNTY
DEPARTMENT OF INTERNAL SERVICES
CAPITAL FACILITIES DIVISION
351 NW NORTH ST.
CHEHALIS, WA 98532
B I D P R O P O S A L
In compliance with the contract documents, the following bid proposal is submitted:
6.2. Base Bid
Print Dollar Amount
6.3. Trench Safety
Trench Safety Provisions
Included in Base Bid
If the bid amount contains any work which requires trenching exceeding a depth of four feet, all costs for trench safety shall be included in the Base Bid and indicated above for adequate trench safety systems in compliance with Chapter 39.04 RCW. 49.17 RCW and WAC 296-155-
650. Bidder must include a lump sum dollar amount in blank above (even if the value is $0.00) to be responsive.
6.4. Bid Alternates (Specify whether Additive or Deductive)
Do not include Washington State Sales Tax in alternate amounts.
The Owner reserves the right to accept or reject any or all bid prices within sixty (60) days of the bid date.
Time for Completion
The undersigned hereby agrees to complete all the work under the Base Bid (and accepted alternates) within _______ calendar days after the date of Notice to Proceed.
7. Vendor Questionnaire
7.1. Are you licensed to do this type of work in the State of Washington?* ☐ Yes
☐ No
*Response required
7.2. Non-Collusion Affidavit
Please download the below documents, complete, and upload.
• Non_Collusion_Affidavit.docx
7.3. Bid Bond (if Required
Please upload your bid bond.
Original shall be mailed or hand delivered no later than the bid due date and time. Envelope shall be clearly marked and delivered to:
7.4. Bid form*
Please download the below documents, complete, and upload.
• Bid_Form_Blank.docx
*Response required
7.5. Are you a member of the MRSC Small Works Rosters?*
Answer yes or no
☐ Yes
☐ No
*Response required
7.6. MRSC Small Works Roster?*
Upload documentation https://government-project.s3.us-west-2.amazonaws.com/57949/e622e43f-8c39-4007-b820-c159fe3800a0_Non_Collusion_Affidavit.docx?AWSAccessKeyId=AKIARC2J5PZDCCU66EXN&Expires=1705004850&Signature=%2Be1naPcgbbziCNMahsSLG6IpXlY%3D&response-content-disposition=attachment%3B%20filename%3D%22Non_Collusion_Affidavit.docx%22 https://government-project.s3.us-west-2.amazonaws.com/57949/9e43a7b4-4b45-4fe6-be3c-99a47f5f124a_Bid_Form_Blank.docx?AWSAccessKeyId=AKIARC2J5PZDCCU66EXN&Expires=1705004850&Signature=8AJ%2B6TVdCS5J4tGxRk3hgCv7hKk%3D&response-content-disposition=attachment%3B%20filename%3D%22Bid_Form_Blank.docx%22