COMBINED SET.pdf
PDF 2 MB Posted
- Solicitation number
- RFP KSD 260000002129 1
- Issued by
- Kent County, Grand Rapids City, Michigan
About this file
This is a project manual and specification document for the Kent ISD Pine Grove Learning Center Boiler Replacement project, a state and local construction contract opportunity in Michigan. The project involves selective demolition of existing boiler systems and installation of new condensing boilers, along with associated plumbing, HVAC, electrical, and building automation system modifications. The scope includes replacement of hydronic piping systems, control systems, and related equipment necessary to support the new boiler installation. The project is managed by GMB (Architect-Engineer, Project 100168) and Owen-Ames-Kimball Co. (Construction Manager). The manual establishes comprehensive requirements for contractor submissions including electronic file exchanges, closeout submittals, demonstration and training, and commissioning procedures. Specific commissioning requirements are detailed for plumbing systems including water heaters and booster pumps, as well as the complete HVAC system including major and minor equipment, control systems, and variable frequency drives.
The document requires contractors to submit operation and maintenance manuals, warranties, and bonds within specified timeframes following equipment installation and substantial completion. Training of Owner personnel is mandated for all software-operated systems, HVAC systems and equipment, and plumbing equipment, with detailed training plans required at least four weeks prior to training sessions. A qualified Commissioning Provider must oversee all commissioning activities, with the Contractor responsible for executing Prefunctional Checklists and Functional Tests demonstrating compliance with Contract Documents. Testing equipment calibration tolerances and sensor accuracy requirements are specified, with the Contractor bearing costs for re-testing due to deficiencies. The document establishes detailed procedures for handling hazardous materials discovery, protection of existing utilities to remain, and comprehensive selective demolition protocols. Contractor qualifications require a minimum of five years documented experience in demolition operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PLC Boiler Replacement CD set.pdf | ||
| 03._-_Advertisement_to_Bid_Notice - Revised.pdf | ||
| Addendum 1.pdf | ||
| CM Project Manual.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Copyright GMB 2026
SECTION 00 01 00 - PROJECT TITLE PAGE
OWNER:
PROJECT:
KENT ISD
KENT ISD PINE GROVE LEARNING CENTER
BOILER REPLACEMENT
PROJECT MANUAL
A/E PROJECT 100168
ARCHITECT-ENGINEER:
616.796.0200
WWW.GMB.COM
CONSTRUCTION MANAGER: OWEN-AMES-KIMBALL CO.
616.456.1521
WWW.OWEN-AMES-KIMBALL.COM
MAY 06, 2026
END OF SECTION
KENT ISD
KENT ISD PINE GROVE LEARNING CENTER BOILER REPLACEMENT
A/E PROJECT 100168
Copyright GMB 2026 SECTION 00 01 10
TABLE OF CONTENTS
SECTION 00 01 10 - TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 00 01 01 - Project Title Page B. 00 01 10 - Table of Contents C. 00 01 15 - List of Drawing Sheets
SPECIFICATIONS
2.1 DIVISION 01 -- GENERAL REQUIREMENTS
A. 01 00 01 - Electronic Model/Drawing File Exchange Agreement B. 01 78 00 - Closeout Submittals C. 01 79 00 - Demonstration and Training D. 01 91 13 - General Commissioning Requirements E. 01 91 14 - Commissioning Provider Responsibilities
2.2 DIVISION 02 -- EXISTING CONDITIONS
A. 02 41 00 - Demolition
2.3 DIVISION 03 -- CONCRETE
A. 03 30 00 - Cast-in-Place Concrete
2.4 DIVISION 04 -- MASONRY
2.5 DIVISION 05 -- METALS
2.6 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
2.7 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
A. 07 84 00 - Firestopping
2.8 DIVISION 08 -- OPENINGS
2.9 DIVISION 09 -- FINISHES
2.10 DIVISION 10 -- SPECIALTIES
2.11 DIVISION 11 -- EQUIPMENT
2.12 DIVISION 12 -- FURNISHINGS
2.13 DIVISION 13 -- SPECIAL CONSTRUCTION
2.14 DIVISION 14 -- CONVEYING EQUIPMENT
2.15 DIVISION 21 -- FIRE SUPPRESSION
2.16 DIVISION 22 -- PLUMBING
A. 22 05 00 - Plumbing Summary Of Work B. 22 05 13 - Common Motor Requirements for Plumbing Equipment C. 22 05 19 - Meters and Gauges for Plumbing Piping D. 22 05 23 - General-Duty Valves for Plumbing Piping E. 22 05 29 - Hangers and Supports for Plumbing Piping and Equipment F. 22 05 53 - Identification for Plumbing Piping and Equipment G. 22 07 19 - Plumbing Piping Insulation H. 22 10 05 - Plumbing Piping I. 22 11 19 - Domestic Water Piping Specialties
A/E PROJECT 100168
Copyright GMB 2026 SECTION 00 01 10
TABLE OF CONTENTS
J. 22 11 23 - Domestic Water Pumps K. 22 30 00 - Plumbing Equipment
2.17 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
A. 23 05 00 - HVAC Summary Of Work B. 23 05 13 - Common Motor Requirements for HVAC Equipment C. 23 05 19 - Meters and Gauges for HVAC Piping D. 23 05 23 - General-Duty Valves for HVAC Piping E. 23 05 29 - Hangers and Supports for HVAC Piping and Equipment F. 23 05 53 - Identification for HVAC Piping and Equipment G. 23 05 93 - Testing, Adjusting, and Balancing for HVAC H. 23 07 16 - HVAC Equipment Insulation I. 23 07 19 - HVAC Piping Insulation J. 23 08 00 - Commissioning of HVAC K. 23 09 13 - Instrumentation and Control Devices for HVAC L. 23 09 23 - Direct-Digital Control System for HVAC M. 23 09 93 - Sequence of Operations for HVAC Controls N. 23 11 23 - Facility Natural-Gas Piping O. 23 21 13 - Hydronic Piping P. 23 21 14 - Hydronic Specialties Q. 23 21 23 - Hydronic Pumps R. 23 25 00 - HVAC Water Treatment S. 23 51 00 - Breechings, Chimneys, and Stacks T. 23 52 16 - Condensing Boilers
2.18 DIVISION 26 -- ELECTRICAL
A. 26 05 00 - Common Work Results for Electrical B. 26 05 05 - Selective Demolition for Electrical C. 26 05 19 - Low-Voltage Electrical Power Conductors and Cables D. 26 05 26 - Grounding and Bonding for Electrical Systems E. 26 05 29 - Hangers and Supports for Electrical Systems F. 26 05 33.13 - Conduit for Electrical Systems G. 26 05 33.16 - Boxes for Electrical Systems H. 26 05 53 - Identification for Electrical Systems I. 26 05 83 - Wiring Connections J. 26 24 16 - Panelboards K. 26 27 26 - Wiring Devices L. 26 28 13 - Fuses M. 26 28 16.16 - Enclosed Switches N. 26 29 13 - Enclosed Controllers
A/E PROJECT 100168
Copyright GMB 2026 SECTION 00 01 10
TABLE OF CONTENTS
2.19 DIVISION 27 -- COMMUNICATIONS
2.20 DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
2.21 DIVISION 31 -- EARTHWORK
2.22 DIVISION 32 -- EXTERIOR IMPROVEMENTS
2.23 DIVISION 33 -- UTILITIES
A/E PROJECT 100168
Copyright GMB 2026 SECTION 00 01 15
LIST OF DRAWING SHEETS
SECTION 00 01 15 - LIST OF DRAWING SHEETS
1.1 LIST OF DRAWING SHEETS
A. The drawings include the Contract Drawings and other drawings listed in the Table of Contents of the separately bound set titled Kent ISD Pine Grove Learning Center Boiler Replacement, along with any modifications made by subsequent Addenda and Contract changes.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 00 01
ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT
SECTION 01 00 01 - ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT
PART 1 GENERAL
1.1 INFORMATION AVAILABILITY
A. Electronic files will not be supplied during the bidding phase of a project. Information will only be available to the awarded contractors upon completion of this form.
1.2 DISCLAIMER FOR USE OF ELECTRONIC FILES
A. The documents contained in the transmitted electronic files are GMB Ecosystem of
Teams’ instruments of service and are dynamic in nature and subject to change, sometimes daily. They are transmitted for use with the understanding that they may in no way be implied to be the actual Contract Documents for the referenced project.
B. We provide electronic files for your convenience and approved uses for the referenced project.
C. The undersigned party of ___________________________ (hereinafter referred to as
Company) hereby accepts electronic model/drawing files as prepared for the referenced project by GMB Ecosystem of Teams. These files may include multiple models, including but not limited to architectural, civil, mechanical, plumbing, electrical and structural models/drawings for Company’s use in preparing submittals, coordination or fabrication drawings.
D. Use of these files is subject to the following terms and conditions:
1. We make no representation as to the compatibility of these files with your hardware or your software. Building Information Models (BIM) will be delivered in Navisworks or Revit, Site/Civil layouts will be delivered in AutoCAD, these files will be delivered in version(s) in which they were originally created in. GMB Ecosystem of Teams will not take responsibility to upgrade or downgrade electronic models/drawing files, or to export to alternative file formats unless listed below.
2. GMB will transmit TIN surface data for site/civil work in the Extensible Markup Language (XML) format. BIM models can be exported to Navisworks or as 2D base plans to AutoCAD (DWG) format upon request.
a. Data contained on these electronic files are part of our instruments of service, are copyrighted and shall not be used for any purpose other than as a convenience in the preparation of submittals, coordination or fabrication drawings (or other approved uses) for the referenced project only. These electronic files are provided for the Company’s convenience only, is not a Contract Document and does not relieve the Contractor from the requirements of the Contract Documents. Any use by Company will be at your sole risk and without liability or legal exposure to us. The Company agrees to make no claim and hereby waive, to the fullest extent permitted by law, any claim or cause of action of any nature against us, our officers, directors, employees, agents or sub consultants that may arise out of or in connection with your use of the electronic files.
b. This information is provided for the express use of Company and is not to be distributed or otherwise reproduced without the express written consent of GMB Ecosystem of Teams. and the re-submittal of this agreement.
c. Where building information modeling (BIM) is being used GMB Ecosystem of Teams models are generally created to a LOD 250-300. Not all elements may be modeled or represented in 3D space. Company is responsible for determining if any conflict exists. By your use of these electronic files, you are not relieved of your duty to fully comply with the contract documents, including, and without limitation, the need to check, confirm and coordinate all dimensions and details, take field measurements, verify field conditions and coordinate your work with that of other contractors for the project.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 00 01
ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT
d. These electronic files are not construction documents. Differences may exist between these electronic files and corresponding hard-copy construction documents.
We make no representation regarding the accuracy or completeness of the electronic files you receive. In the event that a conflict arises between the signed or sealed hard-copy construction documents prepared by GMB and the electronic files, the signed or sealed hard-copy construction documents shall govern. Company is responsible for determining if any conflict exists. By The Company’s use of these electronic files, The Company is not relieved of obligation to fully comply with the contract documents, including, and without limitation, the need to check, confirm and coordinate all dimensions and details, take field measurements, verify field conditions and coordinate their work with that of other contractors for the project.
e. The Company shall, to the fullest extent permitted by law, indemnify and hold GMB harmless against all damages, liabilities or costs, including reasonable attorneys' fees and defense costs, arising out of or resulting from their use of these electronic files.
f. Information presented on the electronic files are dynamic in nature, can be modified, unintentionally or otherwise, GMB Ecosystem of Teams takes no responsibility for the accuracy of information provided, or for changes made after issue to Company, who assumes all risks associated with the use of these Models/Drawing files.
g. All direct and indirect references to GMB Ecosystem of Teams as the preparer of these models/drawing files shall be removed from the models/drawing files by Company.
h. Record Models/Drawing files have been generated using information submitted to GMB by the Contractors. The information and update of the construction documents is based on marked-up drawings of the contractors' addendums, bulletins, change orders and field directives which may or may not have been verified by GMB.
i. Return Submittals to GMB shall include a method for identifying where modifications have occurred to the Drawings/Model, such as a change in line type, clouding, or other method deemed acceptable to GMB Ecosystem of Teams. See specification section 01 30 00 for shop drawing submittal requirements.
j. Two-Dimensional drawing files are provided free of charge so long as there are not excessive requests from the contractor. Three Dimensional Electronic models are subject to processing fees, the fee schedule is attached. Payment, if required, for modeled information is required prior to the release of electronic documents. Under no circumstances shall delivery of the electronic files for use by you be deemed a sale by us, and we make no warranties, either express or implied, of merchantability and fitness for any particular purpose. In no event shall we be liable for any loss of profit or any consequential damages as a result of your use or reuse of these electronic files. GMB will prepare the electronic files for transmission to the Company within 4-5 business days after signed request is received.
k. The information provided in the BIM/CAD files is only diagrammatic, BIM information may be modeled in multiple models, it is the Company’s responsibility to request and cross reference all relevant models. Specifications require that the work and coordinated shop drawings reflect actual field verified conditions with actual equipment/duct sizes, utility locations, and related site/project conditions.
l. Electronic models will be delivered as is and may or may not include all items including but not limited to sheets, schedules, details, legends, annotations, etc. .
E. Prepared Electronic Media will be held for 3 business days from the time the file(s) have been sent from GMB to the company, you agree to the contents of this notice and that the files have been received and opened as requested.
1.3 ELECTRONIC MEDIA PREPARATION FEE SCHEDULE:
A. Civil Model with proposed TIN: No Charge B. 2D AutoCAD (DWG) per Drawing export: No Charge C. 3D Navisworks (NWD) price per discipline file: $500
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 00 01
ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT
D. 3D Revit (RVT) price per discipline model $750 E. Bulletin updates provided upon written request at no additional cost for drawings/model previously purchased.
F. Standard hourly rates apply for additional or special requests.
G. Payment for files is required prior to release (or proof of scanned check with form).
1.4 ELECTRONIC MEDIA REQUEST:
A. PROJECT NAME:
B. GMB Project# (GMB Project Number and Drawing Number are located in the lower right-hand corner of the drawing title block):
C. ELECTRONIC MEDIA REQUESTED: project number, sheet number for 2D DWG files project number, discipline model for 3D files 1.
2.
3.
4.
5.
6.
7.
D. Purpose for Request:
E. UNDERSIGNED:
1. Signature:
2. Date:
3. Printed Name:
4. Title:
5. Company:
6. Address:
7. City, State ZIP:
8. Phone#:
9. Email Address for electronic transfer:
F. Submit completed form to:
1. Email to: dawnb@gmb.com
2. Attn: Dawn Bentall
3. GMB Ecosystem of Teams
a. 85 East Eighth Street, Suite 200
b. Holland, MI 49423
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 78 00
CLOSEOUT SUBMITTALS
SECTION 01 78 00 - CLOSEOUT SUBMITTALS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Operation and maintenance data.
B. Warranties and bonds.
1.2 RELATED REQUIREMENTS
A. Section 01 30 00 - Administrative Requirements: Submittals procedures, shop drawings, product data, and samples.
B. Section 01 70 00 - Execution and Closeout Requirements: Contract closeout procedures.
C. Individual Product Sections: Specific requirements for operation and maintenance data.
D. Individual Product Sections: Warranties required for specific products or Work.
1.3 DEFINITIONS
A. Per requirements set forth in contract or:
1. As-designed record drawings: record of everything the Architect designed for the Project, and include the original Contract Documents plus all addenda, Architect's Supplemental Instructions, Change Orders, Construction Change Directives and minor changes in the work requiring documentation by Architect/Engineer.
2. As-constructed record drawings (commonly call "as-builts") are the record of the Project as constructed based on information the Contractor provides to the Owner under the contract for construction. As-constructed record drawings are the full responsibility of the Contractor.
1.4 SUBMITTALS
A. Operation and Maintenance Data:
1. Preliminary: Submit one digital copy of the Preliminary documents to Architect/Engineer prior to request for final payment.
2. Final: Submit final documents to Architect/Engineer and Owner with claim for final Application for Payment.
a. Unless otherwise directed in other pertinent sections, or in writing by the
Architect/Engineer, submit one digital copy and two paper copies of the final as-constructed Record Documents to the Owner prior to indoctrination of operation and maintenance personnel.
B. Warranties and Bonds:
1. For equipment or component parts of equipment put into service during construction with
Owner's permission, submit documents within 10 days after acceptance.
2. Make other submittals within 10 days after Date of Substantial Completion, prior to final
Application for Payment.
3. For items of Work for which acceptance is delayed beyond Date of Substantial
Completion, submit within 10 days after acceptance, listing the date of acceptance as the beginning of the warranty period.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 OPERATION AND MAINTENANCE DATA
A. Source Data: For each product or system, list names, addresses and telephone numbers of Subcontractors and suppliers, including local source of supplies and replacement parts.
B. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 78 00
CLOSEOUT SUBMITTALS
C. Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams. Do not use Project Record Documents as maintenance drawings.
D. Typed Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions.
3.2 OPERATION AND MAINTENANCE DATA FOR MATERIALS AND FINISHES
A. For Each Product, Applied Material, and Finish:
1. Product data, with catalog number, size, composition, and color and texture designations.
2. Information for re-ordering custom manufactured products.
B. Instructions for Care and Maintenance: Manufacturer's recommendations for cleaning agents and methods, precautions against detrimental cleaning agents and methods, and recommended schedule for cleaning and maintenance.
C. Moisture protection and weather-exposed products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.
D. Additional information as specified in individual product specification sections.
E. Where additional instructions are required, beyond the manufacturer's standard printed instructions, have instructions prepared by personnel experienced in the operation and maintenance of the specific products.
3.3 OPERATION AND MAINTENANCE DATA FOR EQUIPMENT AND SYSTEMS
A. For Each Item of Equipment and Each System:
1. Description of unit or system, and component parts.
2. Identify function, normal operating characteristics, and limiting conditions.
3. Include performance curves, with engineering data and tests.
4. Complete nomenclature and model number of replaceable parts.
B. Where additional instructions are required, beyond the manufacturer's standard printed instructions, have instructions prepared by personnel experienced in the operation and maintenance of the specific products.
C. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and communications; typed.
D. Include color coded wiring diagrams as installed.
E. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions.
Include summer, winter, and any special operating instructions.
F. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.
G. Provide servicing and lubrication schedule, and list of lubricants required.
H. Include manufacturer's printed operation and maintenance instructions.
I. Include sequence of operation by controls manufacturer.
J. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.
K. Provide control diagrams by controls manufacturer as installed.
L. Provide Contractor's coordination drawings, with color coded piping diagrams as installed.
M. Provide charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 78 00
CLOSEOUT SUBMITTALS
N. Provide list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.
O. Include test and balancing reports.
P. Additional Requirements: As specified in individual product specification sections.
3.4 ASSEMBLY OF OPERATION AND MAINTENANCE MANUALS
A. Assemble operation and maintenance data into durable manuals for Owner's personnel use, with data arranged in the same sequence as, and identified by, the specification sections.
B. Where systems involve more than one specification section, provide separate tabbed divider for each system.
C. Binders: Commercial quality, 8-1/2 by 11 inch three D side ring binders with durable plastic covers; 2 inch maximum ring size. When multiple binders are used, correlate data into related consistent groupings.
D. Cover: Identify each binder with typed or printed title OPERATION AND MAINTENANCE INSTRUCTIONS; identify title of Project; identify subject matter of contents.
E. Project Directory: Title and address of Project; names, addresses, and telephone numbers of Architect, Consultants, Contractor and subcontractors, with names of responsible parties.
F. Tables of Contents: List every item separated by a division, using the same identification as on the divider tab; where multiple volumes are required, include all volumes Tables of Contents in each volume, with the current volume clearly identified.
G. Dividers: Provide tabbed dividers for each separate product and system; identify the contents on the divider tab; immediately following the divider tab include a description of product and major component parts of equipment.
H. Text: Manufacturer's printed data, or typewritten data on 20 pound paper.
I. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.
J. Arrangement of Contents: Organize each volume in parts as follows:
1. Project Directory.
2. Table of Contents, of all volumes, and of this volume.
3. Operation and Maintenance Data: Arranged by system, then by product category.
a. Source data.
b. Product data, shop drawings, and other submittals.
c. Operation and maintenance data.
d. Field quality control data.
e. Photocopies of warranties and bonds.
3.5 WARRANTIES AND BONDS
A. Obtain warranties and bonds, executed in duplicate by responsible Subcontractors, suppliers, and manufacturers, within 10 days after completion of the applicable item of work. Except for items put into use with Owner's permission, leave date of beginning of time of warranty until Date of Substantial completion is determined.
B. Verify that documents are in proper form, contain full information, and are notarized.
C. Co-execute submittals when required.
D. Retain warranties and bonds until time specified for submittal.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 78 00
CLOSEOUT SUBMITTALS
3.6 CHANGES SUBSEQUENT TO ACCEPTANCE
A. The Contractor shall have no responsibility for recording changes in the work subsequent to acceptance of the work by the Owner, except for changes resulting from replacements, repairs, and alternations made by Contractor as part of his guarantee.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 79 00
DEMONSTRATION AND TRAINING
SECTION 01 79 00 - DEMONSTRATION AND TRAINING
PART 1 GENERAL
1.1 SUMMARY
A. Training of Owner personnel in operation and maintenance is required for:
1. All software-operated systems.
2. HVAC systems and equipment.
3. Plumbing equipment.
1.2 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures; except:
B. Draft Training Plans: Owner will designate personnel to be trained; tailor training to needs and skill-level of attendees.
1. Submit not less than four weeks prior to start of training.
2. Revise and resubmit until acceptable.
3. Provide an overall schedule showing all training sessions.
4. Include at least the following for each training session:
a. Identification, date, time, and duration.
b. Description of products and/or systems to be covered.
c. Name of firm and person conducting training; include qualifications.
d. Intended audience, such as job description.
e. Objectives of training and suggested methods of ensuring adequate training.
f. Methods to be used, such as classroom lecture, live demonstrations, hands-on, etc.
g. Media to be used, such a slides, hand-outs, etc.
h. Training equipment required, such as projector, projection screen, etc., to be provided by Contractor.
C. Training Manuals: Provide training manual for each attendee; allow for minimum of two attendees per training session.
1. Include applicable portion of O&M manuals.
2. Include copies of all hand-outs, slides, overheads, video presentations, etc., that are not included in O&M manuals.
3. Provide one extra copy of each training manual to be included with operation and maintenance data.
1.3 QUALITY ASSURANCE
A. Instructor Qualifications: Familiar with design, operation, maintenance and troubleshooting of the relevant products and systems.
1. Provide as instructors the most qualified trainer of those contractors and/or installers who actually supplied and installed the systems and equipment.
2. Where a single person is not familiar with all aspects, provide specialists with necessary qualifications.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 TRAINING - GENERAL
A. Conduct training on-site unless otherwise indicated.
B. Owner will provide classroom and seating at no cost to Contractor.
C. Provide training in minimum two hour segments.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 79 00
DEMONSTRATION AND TRAINING
D. Training schedule will be subject to availability of Owner's personnel to be trained; re-schedule training sessions as required by Owner; once schedule has been approved by Owner failure to conduct sessions according to schedule will be cause for Owner to charge Contractor for personnel "show-up" time.
E. Review of Facility Policy on Operation and Maintenance Data: During training discuss:
1. The location of the O&M manuals and procedures for use and preservation; backup copies.
2. Typical contents and organization of all manuals, including explanatory information, system narratives, and product specific information.
3. Typical uses of the O&M manuals.
F. Product- and System-Specific Training:
1. Review the applicable O&M manuals.
2. For systems, provide an overview of system operation, design parameters and constraints, and operational strategies.
3. Review instructions for proper operation in all modes, including start-up, shut-down, seasonal changeover and emergency procedures, and for maintenance, including preventative maintenance.
4. Provide hands-on training on all operational modes possible and preventive maintenance.
5. Emphasize safe and proper operating requirements; discuss relevant health and safety issues and emergency procedures.
6. Discuss common troubleshooting problems and solutions.
7. Discuss any peculiarities of equipment installation or operation.
8. Discuss warranties and guarantees, including procedures necessary to avoid voiding coverage.
9. Review recommended tools and spare parts inventory suggestions of manufacturers.
10. Review spare parts and tools required to be furnished by Contractor.
11. Review spare parts suppliers and sources and procurement procedures.
G. Be prepared to answer questions raised by training attendees; if unable to answer during training session, provide written response within three days.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS
PART 1 GENERAL
1.1 SUMMARY
A. Commissioning is intended to achieve the following specific objectives; this section specifies the Contractor's responsibilities for commissioning:
1. Verify that the work is installed in accordance with Contract Documents and the manufacturer’s recommendations and instructions, and that it receives adequate operational checkout prior to startup: Startup reports and Prefunctional Checklists executed by Contractor are utilized to achieve this.
2. Verify and document that functional performance is in accordance with Contract Documents: Functional Tests executed by Contractor and witnessed by the Commissioning Provider are utilized to achieve this.
3. Verify that operation and maintenance manuals submitted to Owner are complete:
Detailed operation and maintenance (O&M) data submittals by Contractor are utilized to achieve this.
4. Verify that the Owner’s operating personnel are adequately trained: Formal training conducted by Contractor is utilized to achieve this.
B. Commissioning, including Functional Tests, O&M documentation review, and training, is to occur after startup and initial checkout and be completed before Functional Completion.
C. The Commissioning Provider directs and coordinates all commissioning activities; this section describes some but not all of the Commissioning Provider's responsibilities.
1.2 SCOPE OF COMMISSIONING
A. The following are to be commissioned:
B. Plumbing Systems:
1. Water heaters.
2. Booster pumps.
C. HVAC System, including:
1. Major and minor equipment items.
2. Control system.
3. Variable frequency drives.
D. Other equipment and systems explicitly identified elsewhere in Contract Documents as requiring commissioning.
1.3 RELATED REQUIREMENTS
A. Section 01 78 00 - Closeout Submittals: Scope and procedures for operation and maintenance manuals and project record documents.
B. Section 01 91 14 - Commissioning Provider Responsibilities.
C. Section 23 08 00 - Commissioning of HVAC: HVAC control system testing; other requirements.
1.4 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures; except:
1. Make all submittals specified in this section, and elsewhere where indicated for commissioning purposes, directly to the Commissioning Provider, unless they require review by Architect; in that case, submit to Architect first.
2. Submit one copy to the Commissioning Provider, not to be returned.
3. Make commissioning submittals on time schedule specified by Commissioning Provider.
4. Submittals indicated as "Draft" are intended for the use of the Commissioning Provider in preparation of Prefunctional Checklists or Functional Test requirements; submit in editable .rtf or .docx electronic format.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
5. As soon as possible after submittals made to Architect are approved, submit copies of approved submittals to Commissioning Provider.
B. Product Data: If submittals to Architect do not include the following, submit copies as soon as possible:
1. Manufacturer's product data, cut sheets, and shop drawings.
2. Manufacturer's installation instructions.
3. Startup, operating, and troubleshooting procedures.
4. Fan and pump curves.
5. Factory test reports.
6. Warranty information, including details of Owner's responsibilities in regard to keeping warranties in force.
C. Manufacturers' Instructions: Submit copies of all manufacturer-provided instructions that are shipped with the equipment as soon as the equipment is delivered.
D. Startup Plans and Reports.
E. Completed Prefunctional Checklists.
PART 2 PRODUCTS
2.1 TEST EQUIPMENT
A. Commissioning provider is responsible for verifying that each contractor will provide all standard testing equipment required to perform startup and initial checkout and required Functional Testing; unless otherwise noted such testing equipment will NOT become the property of Owner . All testing equipment not provided by the related contractor shall be the responsibility of the commissioning authority to provide.
B. Calibration Tolerances: Provide testing equipment of sufficient quality and accuracy to test and/or measure system performance with the tolerances specified. If not otherwise noted, the following minimum requirements apply:
1. Temperature Sensors and Digital Thermometers: Certified calibration within past year to accuracy of 0.5 degree F and resolution of plus/minus 0.1 degree F.
2. Pressure Sensors: Accuracy of plus/minus 2.0 percent of the value range being measured (not full range of meter), calibrated within the last year.
3. Calibration: According to the manufacturer’s recommended intervals and when dropped or damaged; affix calibration tags or keep certificates readily available for inspection.
C. Equipment-Specific Tools: Where special testing equipment, tools and instruments are specific to a piece of equipment, are only available from the vendor, and are required in order to accomplish startup or Functional Testing, provide such equipment, tools, and instruments as part of the work at no extra cost to Owner; such equipment, tools, and instruments are to become the property of Owner.
D. Dataloggers: Independent equipment and software for monitoring flows, currents, status, pressures, etc. of equipment.
1. Dataloggers required for Functional Tests will be provided by the Commissioning Provider and will not become the property of Owner.
PART 3 EXECUTION
3.1 COMMISSIONING PLAN
A. Commissioning Provider has prepared the Commissioning Plan.
1. Attend meetings called by the Commissioning Provider for purposes of completing the commissioning plan.
2. Require attendance and participation of relevant subcontractors, installers, suppliers, and manufacturer representatives.
B. Contractor is responsible for compliance with the Commissioning Plan.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
C. Commissioning Plan: The commissioning schedule, procedures, and coordination requirements for all parties in the commissioning process.
D. Commissioning Schedule:
1. Submit anticipated dates of startup of each item of equipment and system to
Commissioning Provider within 60 days after award of contract.
2. Re-submit anticipated startup dates monthly, but not less than 4 weeks prior to startup.
3. Prefunctional Checklists and Functional Tests are to be performed in sequence from components, to subsystems, to systems.
4. Provide sufficient notice to Commissioning Provider for delivery of relevant Checklists and
Functional Test procedures to avoid delay.
3.2 STARTUP PLANS AND REPORTS
A. Startup Plans: For each item of equipment and system for which the manufacturer provides a startup plan, submit the plan not less than 8 weeks prior to startup.
B. Startup Reports: For each item of equipment and system for which the manufacturer provides a startup checklist (or startup plan or field checkout sheet), document compliance by submitting the completed startup checklist prior to startup, signed and dated by responsible entity.
C. Submit directly to the Commissioning Provider.
3.3 PREFUNCTIONAL CHECKLISTS
A. A Prefunctional Checklist is required to be filled out for each item of equipment or other assembly specified to be commissioned.
1. No sampling of identical or near-identical items is allowed.
2. These checklists do not replace manufacturers' recommended startup checklists, regardless of apparent redundancy.
3. Prefunctional Checklist forms will not be complete until after award of the contract; the following types of information will be gathered via the completed Checklist forms:
a. Certification by installing contractor that the unit is properly installed, started up, and operating and ready for Functional Testing.
b. Confirmation of receipt of each shop drawing and commissioning submittal specified, itemized by unit.
c. Manufacturer, model number, and relevant capacity information; list information "as specified," "as submitted," and "as installed."
d. Serial number of installed unit.
e. List of inspections to be conducted to document proper installation prior to startup and Functional Testing; these will be primarily static inspections and procedures; for equipment and systems may include normal manufacturer’s start-up checklist items and minor testing.
f. Sensor and actuator calibration information.
B. Contractor is responsible for filling out Prefunctional Checklists, after completion of installation and before startup; witnessing by the Commissioning Provider is not required unless otherwise specified.
1. Each line item without deficiency is to be witnessed, initialed, and dated by the actual witness; checklists are not complete until all line items are initialed and dated complete without deficiencies.
2. Checklists with incomplete items may be submitted for approval provided the Contractor attests that incomplete items do not preclude the performance of safe and reliable Functional Testing; re-submission of the Checklist is required upon completion of remaining items.
3. Individual Checklists may contain line items that are the responsibility of more than one installer; Contractor shall assign responsibility to appropriate installers or subcontractors, with identification recorded on the form.
4. If any Checklist line item is not relevant, record reasons on the form.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
5. Contractor may independently perform startup inspections and/or tests, at Contractor's option.
6. Regardless of these reporting requirements, Contractor is responsible for correct startup and operation.
7. Submit completed Checklists to Commissioning Provider within 2 days of completion.
C. Commissioning Provider is responsible for furnishing the Prefunctional Checklists to Contractor.
1. Initial Drafts: Contractor is responsible for initial draft of Prefunctional Checklist where so indicated in Contract Documents.
2. Provide all additional information requested by Commissioning Provider to aid in preparation of checklists, such as shop drawing submittals, manufacturers' startup checklists, and O&M data.
3. Commissioning Provider may add any relevant items deemed necessary regardless of whether they are explicitly mentioned in Contract Documents or not.
4. When asked to review the proposed Checklists, do so in a timely manner.
D. Commissioning Provider Witnessing: Required for:
1. Each piece of primary equipment, unless sampling of multiple similar units is allowed by the commissioning plan.
2. A sampling of non-primary equipment, as allowed by the commissioning plan.
E. Deficiencies: Correct deficiencies and re-inspect or re-test, as applicable, at no extra cost to
Owner.
1. If difficulty in correction would delay progress, report deficiency to the Commissioning
Provider immediately.
3.4 FUNCTIONAL TESTS
A. A Functional Test is required for each item of equipment, system, or other assembly specified to be commissioned, unless sampling of multiple identical or near-identical units is allowed by the final test procedures.
B. Contractor is responsible for execution of required Functional Tests, after completion of Prefunctional Checklist and before closeout.
C. Commissioning Provider is responsible for witnessing and reporting results of Functional Tests, including preparation and completion of forms for that purpose.
D. Contractor is responsible for correction of deficiencies and re-testing at no extra cost to Owner;
if a deficiency is not corrected and re-tested immediately, the Commissioning Provider will document the deficiency and the Contractor's stated intentions regarding correction.
1. Deficiencies are any condition in the installation or function of a component, piece of equipment or system that is not in compliance with Contract Documents or does not perform properly.
2. When the deficiency has been corrected, the Contractor completes the form certifying that the item is ready to be re-tested and returns the form to the Commissioning Provider; the Commissioning Provider will reschedule the test, and the Contractor shall re-test.
3. Identical or Near-Identical Items: If 10 percent, or three, whichever is greater, of identical or near-identical items fail to perform due to material or manufacturing defect, all items will be considered defective; provide a proposal for correction within 2 weeks after notification of defect, including provision for testing sample installations prior to replacement of all items.
4. Contractor shall bear the cost of Owner and Commissioning Provider personnel time witnessing re-testing.
5. Contractor shall bear the cost of Owner and Commissioning Provider personnel time witnessing re-testing if the test failed due to failure to execute the relevant Prefunctional Checklist correctly; if the test failed for reasons that would not have been identified in the Prefunctional Checklist process, Contractor shall bear the cost of the second and subsequent re-tests.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
E. Functional Test Procedures:
1. Some test procedures are included in Contract Documents; where Functional Test procedures are not included in Contract Documents, test procedures will be determined by the Commissioning Provider with input by and coordination with Contractor.
2. Examples of Functional Testing:
a. Test the dynamic function and operation of equipment and systems (rather than just components) using manual (direct observation) or monitoring methods under full operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump ramps up and down to maintain the differential pressure setpoint).
b. Systems are tested under various modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc.
c. Systems are run through all the HVAC control system’s sequences of operation and components are verified to be responding as the sequence's state.
d. Traditional air or water test and balancing (TAB) is not Functional Testing; spot checking of TAB by demonstration to the Commissioning Provider is Functional Testing.
F. Deferred Functional Tests: Some tests may need to be performed later, after substantial completion, due to partial occupancy, equipment, seasonal requirements, design or other site conditions; performance of these tests remains the Contractor's responsibility regardless of timing.
3.5 SENSOR AND ACTUATOR CALIBRATION
A. Calibrate all field-installed temperature, relative humidity, carbon monoxide, carbon dioxide, and pressure sensors and gauges, and all actuators (dampers and valves) on this piece of equipment shall be calibrated. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated.
B. Calibrate using the methods described below; alternate methods may be used, if approved by Architect beforehand. See PART 2 for test instrument requirements. Record methods used on the relevant Prefunctional Checklist or other suitable forms, documenting initial, intermediate, and final results.
C. All Sensors:
1. Verify that sensor location is appropriate and away from potential causes of erratic operation.
2. Verify that sensors with shielded cable are grounded only at one end.
3. For sensor pairs that are used to determine a temperature or pressure difference, for temperature make sure they are reading within 0.2 degree F of each other, and for pressure, within tolerance equal to 2 percent of the reading, of each other.
4. Tolerances for critical applications may be tighter.
D. Sensors Without Transmitters - Standard Application:
1. Make a reading with a calibrated test instrument within 6 inches of the site sensor.
2. Verify that the sensor reading, via the permanent thermostat, gauge or building automation system, is within the tolerances in the table below of the instrument-measured value.
3. If not, install offset, calibrate or replace sensor.
E. Sensors With Transmitters - Standard Application.
1. Disconnect sensor.
2. Connect a signal generator in place of sensor.
3. Connect ammeter in series between transmitter and building automation system control panel.
4. Using manufacturer’s resistance-temperature data, simulate minimum desired temperature.
5. Adjust transmitter potentiometer zero until 4 mA is read by the ammeter.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
6. Repeat for the maximum temperature matching 20 mA to the potentiometer span or maximum and verify at the building automation system.
7. Record all values and recalibrate controller as necessary to comply with specified control ramps, reset schedules, proportional relationship, reset relationship and P/I reaction.
8. Reconnect sensor.
9. Make a reading with a calibrated test instrument within 6 inches of the site sensor.
10. Verify that the sensor reading, via the permanent thermostat, gauge or building automation system, is within the tolerances in the table below of the instrument-measured value.
11. If not, replace sensor and repeat.
12. For pressure sensors, perform a similar process with a suitable signal generator.
F. Sensor Tolerances for Standard Applications: Plus/minus the following maximums:
1. Watthour, Voltage, Amperage: 1 percent of design.
2. Pressure, Air, Water, Gas: 3 percent of design.
3. Air Temperatures (Outside Air, Space Air, Duct Air): 0.4 degrees F.
4. Relative Humidity: 4 percent of design.
5. Barometric Pressure: 0.1 inch of Hg.
6. Flow Rate, Air: 10 percent of design.
7. Flow Rate, Water: 4 percent of design.
8. AHU Wet Bulb and Dew Point: 2.0 degrees F.
G. Critical Applications: For some applications more rigorous calibration techniques may be required for selected sensors. Describe any such methods used on an attached sheet.
H. Valve/Damper Stroke Setup and Check:
1. For all valve/damper actuator positions checked, verify the actual position against the control system readout.
2. Set pump/fan to normal operating mode.
3. Command valve/damper closed; visually verify that valve/damper is closed and adjust output zero signal as required.
4. Command valve/damper to open; verify position is full open and adjust output signal as required.
5. Command valve/damper to a few intermediate positions.
6. If actual valve/damper position does not reasonably correspond, replace actuator or add pilot positioner (for pneumatics).
I. Isolation Valve or System Valve Leak Check: For valves not associated with coils.
1. With full pressure in the system, command valve closed.
2. Use an ultra-sonic flow meter to detect flow or leakage.
3.6 TEST PROCEDURES - GENERAL
A. Provide skilled technicians to execute starting of equipment and to execute the Functional
Tests. Ensure that they are available and present during the agreed upon schedules and for sufficient duration to complete the necessary tests, adjustments and problem-solving.
B. Provide all necessary materials and system modifications required to produce the flows, pressures, temperatures, and conditions necessary to execute the test according to the specified conditions. At completion of the test, return all affected equipment and systems to their pre-test condition.
C. Sampling: Where Functional Testing of fewer than the total number of multiple identical or near-identical items is explicitly permitted, perform sampling as follows:
1. Identical Units: Defined as units with same application and sequence of operation; only minor size or capacity difference.
2. Sampling is not allowed for:
a. Major equipment.
b. Life-safety-critical equipment.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 13
GENERAL COMMISSIONING REQUIREMENTS
c. Prefunctional Checklist execution.
3. XX = the percent of the group of identical equipment to be included in each sample;
defined for specific type of equipment.
4. YY = the percent of the sample that if failed will require another sample to be tested;
defined for specific type of equipment.
5. Randomly test at least XX percent of each group of identical equipment, but not less than three units. This constitutes the "first sample."
6. If YY percent of the units in the first sample fail, test another XX percent of the remaining identical units.
7. If YY percent of the units in the second sample fail, test all remaining identical units.
8. If frequent failures occur, the Commissioning Provider may stop the testing and require
Contractor to perform and document a checkout of the remaining units prior to continuing testing.
D. Manual Testing: Use hand-held instruments, immediate control system readouts, or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the “observation”).
E. Simulating Conditions: Artificially create the necessary condition for the purpose of testing the response of a system; for example apply hot air to a space sensor using a hair dryer to see the response in a VAV box.
F. Simulating Signals: Disconnect the sensor and use a signal generator to send an amperage, resistance or pressure to the transducer and control system to simulate the sensor value.
G. Over-Writing Values: Change the sensor value known to the control system in the control system to see the response of the system; for example, change the outside air temperature value from 50 degrees F to 75 degrees F to verify economizer operation.
H. Indirect Indicators: Remote indicators of a response or condition, such as a reading from a control system screen reporting a damper to be 100 percent closed, are considered indirect indicators.
I. Monitoring: Record parameters (flow, current, status, pressure, etc.) of equipment operation using dataloggers or the trending capabilities of the relevant control systems; where monitoring of specific points is called for in Functional Test Procedures:
1. All points that are monitored by the relevant control system shall be trended by Contractor;
at the Commissioning Provider's request, Contractor shall trend up to 20 percent more points than specified at no extra charge.
2. Other points will be monitored by the Commissioning Provider using dataloggers.
3. At the option of the Commissioning Provider, some control system monitoring may be replaced with datalogger monitoring.
4. Provide hard copies of monitored data in columnar format with time down left column and at least 5 columns of point values on same page.
5. Graphical output is desirable and is required for all output if the system can produce it.
6. Monitoring may be used to augment manual testing.
3.7 OPERATION AND MAINTENANCE MANUALS
A. See Section 01 78 00 - Closeout Submittals for additional requirements.
B. Add design intent documentation furnished by Architect to manuals prior to submission to
Owner.
C. Submit manuals related to items that were commissioned to Commissioning Provider for review; make changes recommended by Commissioning Provider.
D. Commissioning Provider will add commissioning records to manuals after submission to Owner.
A/E PROJECT 100168
Copyright GMB 2026 SECTION 01 91 14
COMMISS…