CN-370000-HW688-HW001A.pdf
PDF 2 MB Posted
- Contract number
- HW688
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Wood Environment & Infrastructure Solutions, Inc. The task assignment is identified as HW001A under Contract Number HW688 and pertains to environmental site assessment work at the Former Adams Packing/Callaway Drum Recycling site located at 0 Berkley Road, Auburndale, Polk County, Florida (ERIC_13376). The document was signed by Geoffrey Schaefer, Contract Manager for Wood, and William E. Burns, Jr., Secretary or Designee for FDEP, with an effective date of February 18, 2022.
Wood Environment & Infrastructure Solutions, Inc. is contracted to prepare a Site Assessment Work Plan for the subject property, with all work conducted according to the scope of work and cost proposal submitted February 11, 2022. The task is divided into three subtasks: Project Management (13% of direct labor costs), File Review & Site Recon (including review of 76 available documents and a site walkover with travel costs), and Site Assessment Work Plan (including preparation of a comprehensive work plan with historical summary, sampling plan, Health and Safety Plan, and project schedule). The total task assignment value is $7,117.09 on a fixed unit rate basis. The primary deliverable, due April 15, 2022, consists of documentation of site reconnaissance, project management, and the Site Assessment Work Plan and HASP, with final task completion scheduled for May 31, 2022. Invoice payment of $7,117.09 is contingent upon FDEP approval of all deliverables.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW688
HW001A Completion May 31, 2022
Wood Environment & Infrastructure Solutions, Inc. will prepare a Site Assessment Work Plan at the Former Adams Packing Site. All work will be conducted in accordance with the scope of work and cost proposal submitted February 11, 2022.
Ginger Shirah (850) 245-8899 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Wood Environment & Infrastructure Solutions, Inc.
Wood Environment & Infrastructure Solutions, Inc.
Geoffrey Schaefer (850) 298-7707
ERIC_13376
0 Berkley Rd, Auburndale, Polk County, Florida
Former Adams Packing/Callaway Drum Recycling
✔ $ 7,117.09
$ 7,117.09
Scope of Work
Geoffrey Schaefer
Contract Manager
Geoff.Schaefer Digitally signed by Geoff.Schaefer Date: 2022.02.18 09:11:22 -05'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.02.16 11:53:40 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Documentation of site recon, Site Assessment Work Plan/HASP & project management: Subtasks 1 - 3 04/15/2022
FDEP approval of documentation of site recon, project management, and the Site Assessment Work Plan and HASP: Subtasks 1-3 $ 7,117.09
$ 7,117.09
HW688
HW001A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
To:
From:
Date:
HW688 Contract File
Ginger Shirah, Contract Manager
February 15, 2022
Subject: Task Assignment Negotiation Summary HW688 Task Assignment HW001A Site Assessment Work Plan Former Adams Packing, ERIC_ 13376
This Task Assignment authorizes Wood Environment & Infrastructure Solutions, Inc.
to prepare a Site Assessment Work Plan for the above referenced site. All work will be conducted in accordance with the scope of work and cost proposal submitted on February 11, 2022. Specific subtasks are detailed below:
Subtask 1: Project Management
Project management is calculated at 13% of the direct labor costs.
Subtask 2: File Review & Site Recon
This subtask includes labor and related costs for review of site-specific data and historical documents, as well as travel costs to perform a site reconnaissance. The deliverable for this subtask will include field notes and photo documentation.
Subtask 3: Site Assessment Work Plan
This subtask includes labor costs associated with prearing the final deliverable, the Site Assessment Work Plan, which shall include a site/historical summary, details of the site recon, project approach, sampling plan, HASP, project schedule and Cost Estimate/ Level of Effort worksheets.
Documentation of the costs is included in the attached CEF, Level of Effort worksheets, and the contractor’s proposal. The final deliverable due date is April 15, 2022 and the completion date for the task assignment is May 31, 2022. The total cost for Task Assignment HW001A is $7,117.09
FDEP COST ESTI MATEContractor: Wood Environment & Infrastructure Solutions, Inc.
Date: February 11, 2022
Task #: HW688 - HW001A SubTask 1 Project Management SubTask 6
Site: Adam's Packing/Callaway Drum Recycling SubTask 2 File Review & Site Recon SubTask 7
Activity/Phase: File Review, Recon, Assessment Work Plan SubTask 3 Site Assessment Work Plan SubTask 8
Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 SubTask 9
Wood Project # 67832270XX SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$57.15 Project Manager GS 5 4.5 $57.15 Program Manager 0 0 0 0 0 0 0 0 0 0 $57.15 Project Manager GS 2 0 2 0 0 0 0 0 0 0 $49.56 Consulting Eng/Sci RW 29 13 16 0 0 0 0 0 0 0 $45.00 Principal Eng/Sci JM 6 4 2 0 0 0 0 0 0 0 $45.00 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $45.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0 $33.00 Project Scientist 0 0 0 0 0 0 0 0 0 0 $28.85 Project Engineer 0 0 0 0 0 0 0 0 0 0 $19.23 Staff Scientist 0 0 0 0 0 0 0 0 0 0 $19.25 Staff Engineer 0 0 0 0 0 0 0 0 0 0 $49.56 Technical Editor 0 0 0 0 0 0 0 0 0 0 $33.00 Construction Supervisor 0 0 0 0 0 0 0 0 0 0 $19.23 O&M Specialist 0 0 0 0 0 0 0 0 0 0 $30.64 Drafter/GIS GB 4 0 4 0 0 0 0 0 0 0 $23.00 Senior Technician 0 0 0 0 0 0 0 0 0 0 $26.09 Engineering Tech 0 0 0 0 0 0 0 0 0 0 $20.00 Project Assistant 0 0 0 0 0 0 0 0 0 0 $19.23 Field Technician 0 0 0 0 0 0 0 0 0 0 $39.27 Project Accountant 0 0 0 0 0 0 0 0 0 0 $21.94 Contracts/Purchasing 0 0 0 0 0 0 0 0 0 0 $21.94 Clerical RP 1 0 1 0 0 0 0 0 0 0 $85.84 Surveyor 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 47 5 17 25 0 0 0 0 0 0 0
Direct Labor $2,221.63 $255.59 $824.28 $1,141.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 127.30% $2,828.14 $325.37 $1,049.31 $1,453.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 6.81% $151.29 $17.41 $56.13 $77.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.50% $833.12 $95.85 $309.11 $428.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,034.18 $694.22 $2,238.83 $3,101.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
FDEP COST ESTI MATEContractor: Wood Environment & Infrastructure Solutions, Inc.
Date: February 11, 2022
Task #: HW688 - HW001A SubTask 1 Project Management SubTask 6
Site: Adam's Packing/Callaway Drum Recycling SubTask 2 File Review & Site Recon SubTask 7
Activity/Phase: File Review, Recon, Assessment Work Plan SubTask 3 Site Assessment Work Plan SubTask 8
Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 SubTask 9
Wood Project # 67832270XX SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $182.00 $182.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $422.00 $422.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) (ODCs not covered by G&A) $17.50 $7.00 $10.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $57.50 $47.00 $10.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,513.68 $694.22 $2,707.83 $3,111.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $603.41 $69.42 $223.88 $310.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $7,117.09 $763.64 $2,931.71 $3,421.74 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Adam's Packing/Callaway Drum Recycling SUBTASK: File Review & Site Recon
DATE: 2/11/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE STAFF WORK DESCRIPTION HOURS
Consulting Eng/Sci RW 13 Principal Eng/Sci JM 4
TOTAL LABOR 17
VEHICLE RATE UNIT USEAGE
$480.00 week 0 $0.00 $120.00 day 2 $240.00
TOTAL VEHICLE $240.00
PER DIEM RATE UNIT USEAGE
motel $110.00 day 1 $110.00 meal $36.00 day 2 $72.00
TOTAL PER DIEM $182.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL SUBS $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
Fast Turn-Around
TOTAL FAST TURN $0.00
SHIPPING RATE COSTING UNIT USEAGE TOTALS
TOTAL SHIPPING $0.00
EQUIPMENT RATE COSTING UNIT USEAGE TOTALS
$600.00 week 0 $0.00 $150.00 day 1 $150.00
TOTAL EQUIPMENT $150.00
FIELD EXPENSES RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables $40.00 day 1 $40.00
SUBTOTAL $40.00
Equipment (Other) ODCs not covered by G&A copies, printing, computer, etc $3.50 Man-Day 2 $7.00
SUBTOTAL $7.00
TOTAL FIELD EXPENSES $47.00
TYPE
Truck
ITEM
Site Recon Kit
ITEM
Perform site recon & review files File review
RW
ITEM
STAFF
RW
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Adam's Packing/Callaway Drum Recycling SUBTASK: Assessment Work Plan & HASP
DATE: 2/11/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE STAFF WORK DESCRIPTION HOURS
Project Manager GS 2 Consulting Eng/Sci RW 16 Principal Eng/Sci JM 2 Drafter/GIS GB 4 Clerical RP 1
TOTAL LABOR 25
VEHICLE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL SUBS $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
Fast Turn-Around
TOTAL FAST TURN $0.00
SHIPPING RATE COSTING UNIT USEAGE TOTALS
TOTAL SHIPPING $0.00
EQUIPMENT RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
FIELD EXPENSES RATE COSTING UNIT USEAGE TOTALS
Equipment (Other) Office ODCs copies, printing, computer, etc. $3.50 Man-Day 3 $10.50
SUBTOTAL $10.50
TOTAL FIELD EXPENSES $10.50
WP/HASP review Prepare Worplan & HASP Prepare file review summary Draft Site WP Figures WP Formating
TYPE
STAFF
ITEM
ITEM
ITEM
FINAL --7/24/96
Wood’ is a trading name for John Wood Group PLC and its subsidiaries
Wood Environment & Infrastructure Solutions, Inc.
1441 McClay Commerce Drive, Suite 102 Tallahassee, Florida 32312
USA
T: 850-656-1293
February 11, 2022
Ms. Ginger Shirah Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road Tallahassee, FL 32399-2400
RE: Proposal to Conduct a File Review, Site Recon, and a Site Assessment Work Plan Former Adam’s Packing / Callaway Drum Recycling County Road (CR) 655 (aka Berkley Road), Auburndale, Polk County, Florida
EPA ID: FLN000407303, ERIC_13376, COM_19648
HW688 Task Assignment No: HW001A (tentative)
Dear Ms. Shirah, Wood Environment & Infrastructure Solutions, Inc., (Wood) is pleased to provide this cost proposal and scope of work to conduct a site recon, file review and prepare a Site Assessment Work Plan for the Adam’s Packing / Callaway Drum Recycling site in Auburndale, Florida.
Please find attached the Cost Estimate and related Level of Effort Spreadsheets to conduct the referenced activities. The scope of work is discussed below. The scope of work for this includes travel to Auburndale for the file review, site reconnaissance, scoping meetings and development of a Site Assessment Work Plan and Health & Safety Plan (HASP). The site reconnaissance will include a site visit and walkover of the site and a surrounding area survey.
Wood assumes that FDEP will provide access to the site. Travel will be by automobile and will take 2 days including travel to the site. The recon can be conducted within 2 weeks of the receipt of authorization from FDEP.
Subtask 1 – Project Management This subtask includes all tasks associated with managing and scheduling the site recon and workplan deliverables.
Subtask 2 – File Review and Site Recon This subtask includes the level of effort for review of the 76 available documents in the FDEP Nexus data base (https://prodenv.dep.state.fl.us/DepNexus/public/electronic-documents/ERIC_13376/facility!search), and travel to/from the site in Auburndale to conduct a site reconnaissance. After the site reconnaissance, Wood will provide field notes and photographic documentation as needed for the deliverable. The file review will be summarized in the Subtask 3 deliverable.
https://prodenv.dep.state.fl.us/DepNexus/public/electronic-documents/ERIC_13376/facility!search https://prodenv.dep.state.fl.us/DepNexus/public/electronic-documents/ERIC_13376/facility!search
Subtask 3 – Site Assessment Work Plan This subtask includes the level of effort for preparing the site assessment Work Plan including a file review/historical summary, details of the site recon, project approach, sampling plan, HASP, and project schedule.
Deliverables
The total estimated costs for conducting the referenced activities is $7,117.09. Wood is prepared to initiate the activities as scheduled after receiving a signed task assignment. Please let me know if you have any questions concerning this proposal.
Sincerely, Wood Environment & Infrastructure Solutions, Inc.
Geoff Schaefer, P.E. Ron White, P.G.
Associate Engineer Senior Geologist
Deliverable Schedule
SubTask Proposed
Field/Office Date
Samples Deliverable Proposed
Deliverable Due Date
2 Mar 2022 NA Field notes, photos, misc.
documentation
Mar 31, 2022
3 Mar/Apr 2022 NA Site Assessment Work Plan with
HASP
Apr 15, 2022
2 & 3 May 2022 NA Invoice May 16, 2022
ID Task Mode
Task Name Start Finish
1 Project Setup Mon 2/28/22 Tue 3/1/22
2 Subtask 2 Mon 2/28/22 Thu 3/31/22
3 File Review Mon 2/28/22 Fri 3/11/22
4 Site Recon Mon 3/14/22 Tue 3/15/22
5 Deliverable (field notes) Thu 3/31/22 Thu 3/31/22
6 Subtask 3 Wed 3/16/22 Fri 5/20/22
7 Site Assessment Work Plan Wed 3/16/22 Fri 4/15/22
8 Invoice Mon 5/16/22 Mon 5/16/22
GS,RP,RW
GS,JM,RW
RW
GS,RW,RP
GS,RW,JM
5/16
25272931 2 4 6 8 10121416182022242628 2 4 6 8 1012141618202224262830 1 3 5 7 9 11131517192123252729 1 3 5 7 9 11131517192123 February 2022 March 2022 April 2022 May 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Adam's Packing Date: Wed 2/11/22