This document is a Task Assignment Change Order (TACO #02) executed between the State of Florida Department of Environmental Protection (FDEP) and Wood Environment & Infrastructure Solutions, Inc. for work at the Ponte Vedra Cleaners site under Contract HW688. The change order amends Task Assignment DC002A and modifies the scope and schedule of operations and maintenance (O&M) activities. The authorized signatories are Geoff Schaefer, Project Manager for the contractor, and William E. Burns, Jr., Secretary or Designee for FDEP. The project is managed by Ginger Shirah for FDEP and Geoffrey Schaefer for Wood Environment & Infrastructure Solutions, Inc.

The change order authorizes a reduction in costs from Quarter 1 O&M activities due to system shutdown evaluation time, while adding subcontractor costs for one-year renewal of telemetry services and replacement of an hour meter for the system. The amended total task value decreased from $42,266.15 to $39,927.77, representing a net reduction of $2,338.38. The fixed unit rate component decreased from $32,516.15 to $30,177.77, while cost reimbursement remained at $9,750.00. The task completion date was extended by 60 days, from March 31, 2023, to May 30, 2023, to account for system shutdown and restart. Deliverables include quarterly O&M documentation, semi-annual and annual reports, laboratory analysis data, field notes, and paid utility invoices. The contract employs 189 total labor hours across multiple subtasks with various staff categories. Attachment 1 was replaced with Attachment 1-2 to reflect scope modifications.

View the file

Other files

File Type Posted
CN-370000-GC793-CMC1.pdf PDF
CN-370000-GC910.pdf PDF
CN-370000-HW688-A1.pdf PDF
CN-370000-HW688-BF01A.pdf PDF
CN-370000-HW688-FIL 3.pdf PDF
CN-370000-HW688-FIL1.pdf PDF
CN-370000-HW688-FIL2.pdf PDF
CN-370000-HW688-BF01B.pdf PDF
CN-370000-HW688-DC005A.pdf PDF
CN-370000-HW688-HW001A.pdf PDF
CN-370000-HW688-DC003A.pdf PDF
CN-370000-HW688-DC007A.pdf PDF
CN-370000-HW688-DC008A.pdf PDF
CN-370000-HW688-DC02ACO1.pdf PDF
CN-370000-HW688-DC001C.pdf PDF
CN-370000-HW688-DC004A.pdf PDF
CN-370000-HW688-DC005A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW688-DC006A.pdf PDF
CN-370000-HW688-DC01A.pdf PDF
CN-370000-HW688-DC01B.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC002A 02 HW688

This Task Assignment Change Order authorizes a reduction in costs in Quarter 1 of O&M along with the addition of subcontractor costs for telemetry service and a replacement hour meter for the system.

Ginger Shirah 850-245-8899 Contractor Contractor

Contractor Contractor

Contractor

Wood Environment & Infrastructure Solutions, Inc.

Geoffrey Schaefer 850-298-7707

ERIC_5404

Ponte Vedra Cleaners

✔ $ 30,177.77 $ 32,516.15 ✔ $ 9,750.00 $ 9,750.00

$ 39,927.77 $ 42,266.15 Completion

Completion✔ 03/31/2023 05/30/2023 60

✔ 1 1 2

Geoff Schaefer

Project Manager

8/22/2022

Geoff.Schaefer Digitally signed by Geoff.Schaefer Date: 2022.08.22 14:16:04 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.08.18 13:19:38 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW688

DC002A

$ 39,927.77

Documentation of completion of Year 4 Quarter 1 O&M activities including O&M logs, field notes, lab data (submitted electronically) and shutdown evaluation data with memo - Subtask 2

Semi-Annual Operation & Maintenance Report; Documentation of completion of Year 4 Quarter 2 O&M activities including O&M logs, field notes, waste manifest, lab data (submitted electronically) - Subtask 3

Documentation of completion of Year 4 Quarter 3 O&M activities including O&M logs, field notes, lab data (submitted electronically) - Subtask 4

Annual Operation & Maintenance Report; Documentation of Year 4 Quarter 4 O&M activities including O&M logs, field notes, waste manifest, lab data (submit electronically) and Project Management - Subtasks 1 & 5

Paid utility invoices (January through July 2022) - Subtasks 6 & 7

Paid utility invoices (August 2022 - January 2023) - Subtasks 8 & 9

Subtask 2 - FDEP approval of documentation of completion of Year 4 Quarter 1 O&M activities including O&M logs, field notes, lab data, and shutdown evaluation data with memo

Subtask 4 - FDEP approval of documentation of completion of Year 4 Quarter 3 O&M activities including O&M logs, field notes, lab data

Subtasks 1 & 5 - FDEP approval of Annual O&M Report, documentation of completion of Y4 Q4 O&M activities including O&M logs, field notes, lab data; and Project Management

Subtasks 8 & 9 - FDEP receipt & approval of paid utility invoices from August 2022 through January 2023 (Cost plus fixed fee not to exceed $4,500; Utilities handling fees $60+$60= $120)

Subtasks 6 & 7 - FDEP receipt & approval of paid utility invoices from January 2022 through July 2022 (Cost plus fixed fee not to exceed $5,250; Utilities handling fees $80+$60= $140)

Subtask 3 - FDEP approval of Semi-Annual O&M Report, documentation of completion of Y4 Q2 O&M activities including O&M logs, field notes, lab data

05/31/2022

10/28/2022

01/27/2023

03/28/2023

04/28/2023

10/28/2022

$ 11,188.48

$ 5,146.32

$ 3,781.13

$ 9,801.84

$ 5,390.00

$ 4,620.00

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To:

From:

Date:

HW688 Contract File

Ginger Shirah, Contract Manager

August 18, 2022

Subject: Task Assignment Change Order #02 Negotiation Summary HW688 Task Assignment DC002A Ponte Vedra Cleaners, ERIC_ 5404

This Task Assignment change order authorizes a decrease in cost from Quarter 1 of the annual O&M due to time off for the system shutdown evaluation, along with the addition of costs to account for one year renewal of Telemetry and a replacement hour meter for the system. Additionally, the deliverable due dates for each subtask and the TA period have been extended by sixty days to account for the system shutdown and restart. The Task specific cost changes are detailed below:

Subtask 2: Year 4 Quarter 1 O&M

This change order includes the removal of labor hours, equipment, vehicle costs, laboratory costs and expendables in Subtask 2. The change order also includes the addition of subcontractor costs in Subtask 2 for the one year renewal of Telemetry services and costs to replace the hour meter for the system.

Overall, these changes result in an overall decrease of $2,338.38. The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $39,927.77 with 189 labor hours.

FDEP COST ESTIMATE

Contractor: Wood Environment & Infrastructure Solutions, Inc.

Date: 8/16/2022

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$57.15 Project Manager GS 10 9.9 $57.15 Program Manager 0 0 0 0 0 0 0 0 0 0 $57.15 Project Manager GS 14 1 5 3 5 0 0 0 0 0 $33.00 Project Scientist NT 24 0 12 0 12 0 0 0 0 0 $19.23 Staff Scientist ZL 9 0 9 0 0 0 0 0 0 0 $19.25 Staff Engineer CP 32 7 17 0 8 0 0 0 0 0 $19.23 O&M Specialist ZL 94 22 24 24 24 0 0 0 0 0 $30.64 Drafter/GIS GB 6 0 3 0 3 0 0 0 0 0

Total Hours 189 10 30 70 27 52 0 0 0 0 0

Direct Labor $4,941.07 $568.44 $614.96 $1,735.51 $632.97 $1,389.19 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 127.30% $6,289.97 $723.62 $782.84 $2,209.30 $805.77 $1,768.44 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 6.81% $336.49 $38.71 $41.88 $118.19 $43.11 $94.60 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.50% $1,852.91 $213.17 $230.61 $650.82 $237.36 $520.95 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $13,420.44 $1,543.94 $1,670.29 $4,713.82 $1,719.21 $3,773.18 $0.00 $0.00 $0.00 $0.00 $0.00

HW688 - DC002A-Final TACO 2

REV: 02/03 CEF Wood Page 1

FDEP COST ESTIMATEContractor: Wood Environment & Infrastructure Solutions, Inc.

Date: 8/16/2022

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

HW688 - DC002A-Final TACO 2

Travel Vehicle Rental $1,560.00 $360.00 $480.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $728.00 $0.00 $728.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,288.00 $360.00 $1,208.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $450.00 $150.00 $150.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $9,750.00 $0.00 $0.00 $0.00 $0.00 $3,000.00 $2,250.00 $2,250.00 $2,250.00 $0.00 EOS Research (telemetry) $300.00 $0.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ENM Company (hour meter) $96.62 $0.00 $96.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $10,596.62 $150.00 $546.62 $0.00 $150.00 $3,000.00 $2,250.00 $2,250.00 $2,250.00 $0.00 Handling Fee $344.66 $15.00 $54.66 $0.00 $15.00 $80.00 $60.00 $60.00 $60.00 $0.00 Total Subcontractor Cost $10,941.28 $165.00 $601.28 $0.00 $165.00 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00

Laboratory Analytical Costs $5,557.00 $1,600.00 $2,134.00 $200.00 $1,623.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $850.00 $220.00 $260.00 $110.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $6,407.00 $1,820.00 $2,394.00 $310.00 $1,883.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $480.00 $120.00 $120.00 $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,049.00 $844.00 $1,680.00 $1,100.00 $1,425.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,529.00 $964.00 $1,800.00 $1,220.00 $1,545.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $38,585.72 $1,543.94 $4,979.29 $10,717.10 $3,609.21 $7,726.18 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00 Completion Fee $1,342.04 $154.39 $167.03 $471.38 $171.92 $377.32 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $39,927.77 $1,698.34 $5,146.32 $11,188.48 $3,781.13 $8,103.50 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00

REV: 02/03 CEF Wood Page 2

HW688 - DC002A - Final TACO 2

SITE : Ponte Vedra Cleaners

SUBTASK 2

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS 3 Staff Scientist CP 7 O&M Specialist ZL 24 O&M Specialist ZL 14

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Construct/O&M/Pilot Test Kit $1,440.00 week 0 $0.00

360 day 3 $1,080.00

PID/FID 500 week 0 $0.00

125 day 2 $250.00

Air Sampling Pump 108 week 0 $0.00

27 day 2 $54.00 Tedlar Bags 20 each 9 $180.00

$1,564.00

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00 $120.00 day 5 $600.00

$600.00

PER DIEM STAFF RATE UNIT USAGE

$0.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater Air $0.00 TO-15 $200.00 9 0 Dup $1,800.00

TOTAL LAB $1,800.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS air sample to lab $110.00 Overnight 3 $330.00

TOTAL SHIPPING $330.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Capitol Environmental Services GAC unit disposal $150.00

TOTAL $150.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day 5 $200.00

TOTAL SUPPLIES $200.00

TOTAL PER DIEM

TOTAL VEHICLE

TOTAL EQUIPMENT

Monthly O&M Deliverables (field notes, lab data)

TOTAL LABOR

Monthly O&M - Feb 22, Mar 22, Apr 22 SVE system evaluation air sampling (2 events)

SVE system evaluation air sampling (1 event)

13th Quarter O&M, SVE Evaluation

SUBTASK 3

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS 5 Project Engineer NT 12 O&M Specialist ZL 24 Staff Scientist CP 17 Staff Scientist ZL 9 Drafter GB 3

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Shallow GW Sampling Kit $1,160.00 week 0 $0.00 290 day 2 $580.00

Construct/O&M/Pilot Test Kit 1440 week 0 $0.00 360 day 3 $1,080.00

Tedlar Bags 20 each 1 $20.00

$1,680.00

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00

$120.00 day 4 $480.00 $480.00

PER DIEM STAFF RATE UNIT USAGE

hotel 2 Sampling $110.00 day 2 $440.00 meal 2 Sampling $36.00 day 4 $288.00

$728.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater

VOAs TCL (8260) $73.00 12 2 1 Dup / 1 Trip Blank $1,022.00 Total Iron (6010) MW-3S, MW-1I, MW-7I $13.50 3 0 Duplicate $40.50 Ferrous Iron (6010) MW-3S, MW-1I, MW-7I $13.50 3 0 Duplicate $40.50 Sulfate (375.2) MW-3S, MW-1I, MW-7I $21.00 3 0 Duplicate $63.00 Nitrate (353.2) MW-3S, MW-1I, MW-7I $23.00 3 0 Duplicate $69.00 Nitrite(353.2) MW-3S, MW-1I, MW-7I $23.00 3 0 Duplicate $69.00 Total Organic Carbon (9060) MW-3S, MW-1I, MW-7I $30.00 3 0 Duplicate $90.00 Methane, ethane & ethene (RSK175)MW-3S, MW-1I, MW-7I $180.00 3 0 Duplicate $540.00 Air TO-15 Influent $200.00 1 0 Duplicate $200.00

TOTAL LAB $2,134.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS air sample to lab $110.00 Overnight 1 $110.00 Large - 25 to 50 LBS Samples to lab $150.00 Overnight 1 $150.00 Ice $6.50 per cooler 0 $0.00

TOTAL SHIPPING $260.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Capitol Envrironmental Services IDW transport & disposal $150.00 EOS Research (telemetry) Telemetry $300.00 ENM Company (hour meter) Parts $96.62

TOTAL $546.62

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day 3 $120.00

TOTAL SUPPLIES $120.00

Semi-Annual O&M Report

Semi-Annual O&M Rpt figures

Monthly O&M Deliverables (field notes, lab data), O&M Rpt review

MW-1I, MW-2I, MW-3S,

MW-4I, MW-7I, MW-8D,

MW-9I, MW-10I, MW-13I,

MW-14I, MW-15I, MW-16D

14th Quarter O&M

TOTAL LABOR

GW Sampling 12 MWs for July 2022 after finishing July 2022 O&M y y , , y p g y GW Sampling 12 MWs for July 2022

TOTAL PER DIEM

TOTAL EQUIPMENT

TOTAL VEHICLE

SUBTASK 4

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS 3 O&M Specialist ZL 24

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Construct/O&M/Pilot Test Kit $1,440.00 week 0 $0.00

360 day 3 $1,080.00 Tedlar Bags 20 each 1 $20.00

$1,100.00

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00 $120.00 day 3 $360.00

$360.00

PER DIEM STAFF RATE UNIT USAGE

motel $110.00 day 0 $0.00 meal $36.00 day 0 $0.00

$0.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater VOAs TCL (8260) $73.00 1 Dup/TripBlk/EqBlk $0.00

TCLP/SPLP $0.00

Air $0.00 TO-15 $200.00 1 0 Dup $200.00

TOTAL LAB $200.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS $110.00 Overnight 1 $110.00 Large - 25 to 50 LBS Samples to lab $150.00 Overnight 0 $0.00 Ice $6.50 per cooler 0 $0.00

TOTAL SHIPPING $110.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day 3 $120.00 $0.00 per foot $0.00

TOTAL SUPPLIES $120.00

TOTAL EQUIPMENT

TOTAL VEHICLE

TOTAL PER DIEM

TOTAL LABOR

Monthly O&M Deliverables (field notes, lab data) Monthly O&M - Aug 22, Sept 22, Oct 22

15th Quarter O&M

SUBTASK 5

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS 5 Project Engineer NT 12 O&M Specialist ZL 24 Staff Scientist CP 8 Drafter GB 3

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

MW Installation Kit $1,300.00 week 0 $0.00 325 day 1 $325.00

Construct/O&M/Pilot Test Kit 1440 week 0 $0.00

360 day 3 $1,080.00

Tedlar Bags 20 each 1 $20.00

$1,425.00

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00 $120.00 day 3 $360.00

$360.00

PER DIEM STAFF RATE UNIT USAGE

motel 2 install $110.00 day 0 $0.00 meal 2 install $36.00 day 0 $0.00

$0.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater

VOAs TCL (8260) MW-1I, MW-2I, MW-3S, MW-4I, M $73.00 5 2 1 Dup / 1 Trip Blank $511.00 Total Iron (6010) MW-3S, MW-1I, MW-7I $13.50 3 0 Duplicate $40.50 Ferrous Iron (6010) MW-3S, MW-1I, MW-7I $13.50 3 0 Duplicate $40.50 Sulfate (375.2) MW-3S, MW-1I, MW-7I $21.00 3 0 Duplicate $63.00 Nitrate (353.2) MW-3S, MW-1I, MW-7I $23.00 3 0 Duplicate $69.00 Nitrite(353.2) MW-3S, MW-1I, MW-7I $23.00 3 0 Duplicate $69.00 Total Organic Carbon (9060) MW-3S, MW-1I, MW-7I $30.00 3 0 Duplicate $90.00 Methane, ethane & ethene (RSK175) MW-3S, MW-1I, MW-7I $180.00 3 0 Duplicate $540.00 Air TO-15 $200.00 1 0 Duplicate $200.00

TOTAL LAB $1,823.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS $110.00 2 Day 1 $110.00 Large - 25 to 50 LBS Samples to lab $150.00 Overnight 1 $150.00 Ice $6.50 per cooler 0 $0.00

TOTAL SHIPPING $260.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Capitol Envrironmental Services IDW transport & disposal $150.00

TOTAL $150.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day 3 $120.00

TOTAL SUPPLIES $120.00

TOTAL PER DIEM

TOTAL LABOR

TOTAL EQUIPMENT

TOTAL VEHICLE

Influent

16th Quarter O&M + Annual GW Sampling

Monthly O&M Deliverables (field notes, lab data), O&M Rpt review Annual O&M ReportMonthly O&M Nov 2022, Dec 2022, Jan 2023 GW Sampling in Jan GW Sampling 12 MWs for July 2022 Annual O&M Rpt figures

SUBTASK 6 Utilities 13th Quarter

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Beaches Energy Services Utilities - Jan 22, Feb 22, Mar 22, Apr 22 (~$750.00 x 4) $3,000.00 Beaches Energy Services Utility Handling Fee - Processing Fee ($20 x4) $80.00 EOS Research ProControl Wireless Data Service (4G) 1 Year $0.00

TOTAL $3,080.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $32.50 per day 0 $0.00

TOTAL SUPPLIES $0.00

TOTAL LABOR

SUBTASK 7 Utilities 14th Quarter

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Beaches Energy Services Utilities -May 22, June 22.July 22 (~$750.00 x3) $2,250.00 Beaches Energy Services Utility Handling Fee - Processing Fee ($20 x3) $60.00 EOS Research ProControl Wireless Data Service (4G) 1 Year $0.00

TOTAL $2,310.00

SUBTASK 8 Utilities 15th Quarter

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Beaches Energy Services Utilities - Aug 22, Sept 22, Oct 22 (~$750.00 x3) $2,250.00 Beaches Energy Services Utility Handling Fee - Processing Fee ($20 x3) $60.00 EOS Research ProControl Wireless Data Service (4G) 1 Year $0.00

TOTAL $2,310.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $32.50 per day 0 $0.00

TOTAL SUPPLIES $0.00

SUBTASK 9 Utilities 16th Quarter

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Beaches Energy Services Utilities - Nov 22, Dec 22, Jan 23 (~$750.00 x3) $2,250.00 Beaches Energy Services Utility Handling Fee - Processing Fee ($20 x3) $60.00 EOS Research ProControl Wireless Data Service (4G) 1 Year $0.00

TOTAL $2,310.00

Date: 8/16/2022

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$57.15 Project Manager GS -1 -1.0 $57.15 Program Manager 0 0 0 0 0 0 0 0 0 0 $57.15 Project Manager GS -2 -2 0 0 0 0 0 0 0 0 $33.00 Project Scientist NT 0 0 0 0 0 0 0 0 0 0 $28.85 Project Engineer 0 0 0 0 0 0 0 0 0 0 $19.23 Staff Scientist ZL 0 0 0 0 0 0 0 0 0 0 $19.25 Staff Engineer CP 0 0 0 0 0 0 0 0 0 0 $19.23 O&M Specialist ZL -16 -16 0 0 0 0 0 0 0 0 $30.64 Drafter/GIS GB 0 0 0 0 0 0 0 0 0 0

Total Hours -19 -1 -18 0 0 0 0 0 0 0 0

Direct Labor ($476.84) ($54.86) ($421.98) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 127.30% ($607.02) ($69.84) ($537.18) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 6.81% ($32.48) ($3.74) ($28.74) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.50% ($178.81) ($20.57) ($158.24) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor ($1,295.15) ($149.01) ($1,146.14) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

HW688 - DC002A-Final TACO 2 Delta

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

HW688 - DC002A-Final TACO 2 Delta

Travel Vehicle Rental ($240.00) ($240.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel ($240.00) ($240.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 EOS Research (telemetry) $300.00 $0.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ENM Company (hour meter) $96.62 $0.00 $96.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $396.62 $0.00 $396.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $39.66 $0.00 $39.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $436.28 $0.00 $436.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs ($200.00) ($200.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping ($110.00) ($110.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($310.00) ($310.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables ($80.00) ($80.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) ($720.00) ($720.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses ($800.00) ($800.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($2,208.87) ($149.01) ($2,496.14) $436.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee ($129.51) ($14.90) ($114.61) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($2,338.38) ($163.91) ($2,610.75) $436.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

HW688 - DC002A - Final TACO 2 Delta

SUBTASK 2

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS -2 Staff Scientist CP 0 O&M Specialist ZL -16 O&M Specialist ZL 0

-18

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Construct/O&M/Pilot Test Kit $1,440.00 week 0 $0.00

360 day -2 ($720.00)

PID/FID 500 week 0 $0.00

125 day 0 $0.00

Air Sampling Pump 108 week 0 $0.00

27 day 0 $0.00 Tedlar Bags 20 each 0 $0.00

($720.00)

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00 $120.00 day -2 ($240.00)

($240.00)

PER DIEM STAFF RATE UNIT USAGE

$0.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater Air $0.00 TO-15 $200.00 -1 0 Dup ($200.00)

TOTAL LAB ($200.00)

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS air sample to lab $110.00 Overnight -1 ($110.00)

TOTAL SHIPPING ($110.00)

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Capitol Environmental Services GAC unit disposal $0.00

TOTAL $0.00

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day -2 ($80.00)

TOTAL SUPPLIES ($80.00)

13th Quarter O&M, SVE Evaluation

Monthly O&M Deliverables (field notes, lab data)

TOTAL LABOR

Monthly O&M - Feb 22, Mar 22, Apr 22 SVE system evaluation air sampling (2 events)

SVE system evaluation air sampling (1 event)

TOTAL PER DIEM

TOTAL VEHICLE

TOTAL EQUIPMENT

HW688 - DC002A - Final TACO 2 Delta

SUBTASK 3

DATE: 8/16/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager GS 0 Project Engineer NT 0 O&M Specialist ZL 0 Staff Scientist CP 0 Staff Scientist ZL 0 Drafter GB 0

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Shallow GW Sampling Kit $1,160.00 week 0 $0.00 290 day 0 $0.00

Construct/O&M/Pilot Test Kit 1440 week 0 $0.00

360 day 0 $0.00 Tedlar Bags 20 each 0 $0.00

$0.00

PPE Level D H&S $35.00 (2 person x 2 days) TOTAL PPE $0.00

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $480.00 week 0 $0.00

$120.00 day 0 $0.00 $0.00

PER DIEM STAFF RATE UNIT USAGE

hotel 2 Sampling $110.00 day 0 $0.00 meal 2 Sampling $36.00 day 0 $0.00

$0.00

LABORATORY COSTS

Advanced Environmental Laboratory

PARAMETER RATE # SAMPLES #QAQC

Groundwater

VOAs TCL (8260) $73.00 0 0 1 Dup / 1 Trip Blank $0.00 Total Iron (6010) MW-3S, MW-1I, MW-7I $13.50 0 0 Duplicate $0.00 Ferrous Iron (6010) MW-3S, MW-1I, MW-7I $13.50 0 0 Duplicate $0.00 Sulfate (375.2) MW-3S, MW-1I, MW-7I $21.00 0 0 Duplicate $0.00 Nitrate (353.2) MW-3S, MW-1I, MW-7I $23.00 0 0 Duplicate $0.00 Nitrite(353.2) MW-3S, MW-1I, MW-7I $23.00 0 0 Duplicate $0.00 Total Organic Carbon (9060) MW-3S, MW-1I, MW-7I $30.00 0 0 Duplicate $0.00 Methane, ethane & ethene (RSK175 MW-3S, MW-1I, MW-7I $180.00 0 0 Duplicate $0.00 Air TO-15 Influent $200.00 0 0 Duplicate $0.00

TOTAL LAB $0.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS air sample to lab $110.00 Overnight 0 $0.00 Large - 25 to 50 LBS Samples to lab $150.00 Overnight 0 $0.00 Ice $6.50 per cooler 0 $0.00

TOTAL SHIPPING $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Capitol Envrironmental Services IDW transport & disposal $0.00 EOS Research Telemetry $300.00 EMN Company Hour Meter $96.62

TOTAL $396.62

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $40.00 per day 0 $0.00

TOTAL SUPPLIES $0.00

MW-1I, MW-2I, MW-3S,

MW-4I, MW-7I, MW-8D,

MW-9I, MW-10I, MW-13I,

MW-14I, MW-15I, MW-16D

14th Quarter O&M

TOTAL LABOR

GW Sampling 12 MWs for July 2022 after finishing July 2022 O&M o t y O& ay 0 , Ju e 0 , Ju y 0 G Sa p g Ju y GW Sampling 12 MWs for July 2022

TOTAL PER DIEM

TOTAL EQUIPMENT

TOTAL VEHICLE

Monthly O&M Deliverables (field notes, lab data), O&M Rpt review Semi-Annual O&M Report

Semi-Annual O&M Rpt figures

Date: 8/16/2022

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$57.15 Project Manager GS 11 10.9 $57.15 Program Manager 0 0 0 0 0 0 0 0 0 0 $57.15 Project Manager GS 16 3 5 3 5 0 0 0 0 0 $57.15 Consulting Eng/Sci 0 0 0 0 0 0 0 0 0 0 $49.56 Principal Eng/Sci 0 0 0 0 0 0 0 0 0 0 $45.00 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $45.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0 $33.00 Project Scientist NT 24 0 12 0 12 0 0 0 0 0 $28.85 Project Engineer 0 0 0 0 0 0 0 0 0 0 $19.23 Staff Scientist ZL 9 0 9 0 0 0 0 0 0 0 $19.25 Staff Engineer CP 32 7 17 0 8 0 0 0 0 0 $49.56 Technical Editor 0 0 0 0 0 0 0 0 0 0 $33.00 Construction Supervisor 0 0 0 0 0 0 0 0 0 0 $19.23 O&M Specialist ZL 110 38 24 24 24 0 0 0 0 0 $30.64 Drafter/GIS GB 6 0 3 0 3 0 0 0 0 0 $23.00 Senior Technician 0 0 0 0 0 0 0 0 0 0 $26.09 Engineering Tech 0 0 0 0 0 0 0 0 0 0 $20.00 Project Assistant 0 0 0 0 0 0 0 0 0 0 $19.23 Field Technician 0 0 0 0 0 0 0 0 0 0 $39.27 Project Accountant 0 0 0 0 0 0 0 0 0 0 $21.94 Contracts/Purchasing 0 0 0 0 0 0 0 0 0 0 $25.82 Clerical 0 0 0 0 0 0 0 0 0 0 $85.84 Surveyor 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 208 11 48 70 27 52 0 0 0 0 0

Direct Labor $5,417.91 $623.30 $1,036.94 $1,735.51 $632.97 $1,389.19 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 127.30% $6,896.99 $793.46 $1,320.02 $2,209.30 $805.77 $1,768.44 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 6.81% $368.97 $42.45 $70.62 $118.19 $43.11 $94.60 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.50% $2,031.72 $233.74 $388.85 $650.82 $237.36 $520.95 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $14,715.59 $1,692.95 $2,816.43 $4,713.82 $1,719.21 $3,773.18 $0.00 $0.00 $0.00 $0.00 $0.00

HW688 - DC002A-Final TACO 2 Original

Task #: SubTask 1 Project Management SubTask 6 Utilities 13th Quarter

Site: Ponte Vedra Cleaners SubTask 2 13th Quarter O&M, SVE Evaluation SubTask 7 Utilities 14th Quarter

Activity/Phase: O&M February 2022 - January 2023 SubTask 3 14th Quarter O&M SubTask 8 Utilities 15th Quarter

Project Manager: G. Shirah (FDEP)/G. Schaefer (Wood) SubTask 4 15th Quarter O&M SubTask 9 Utilities 16th Quarter

Wood Project # 67832270XX SubTask 5 16th Quarter O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

HW688 - DC002A-Final TACO 2 Original

Travel Vehicle Rental $1,800.00 $600.00 $480.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $728.00 $0.00 $728.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,528.00 $600.00 $1,208.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $450.00 $150.00 $150.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $9,750.00 $0.00 $0.00 $0.00 $0.00 $3,000.00 $2,250.00 $2,250.00 $2,250.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $10,200.00 $150.00 $150.00 $0.00 $150.00 $3,000.00 $2,250.00 $2,250.00 $2,250.00 $0.00 Handling Fee $305.00 $15.00 $15.00 $0.00 $15.00 $80.00 $60.00 $60.00 $60.00 $0.00 Total Subcontractor Cost $10,505.00 $165.00 $165.00 $0.00 $165.00 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00

Laboratory Analytical Costs $5,757.00 $1,800.00 $2,134.00 $200.00 $1,623.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $960.00 $330.00 $260.00 $110.00 $260.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $6,717.00 $2,130.00 $2,394.00 $310.00 $1,883.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $560.00 $200.00 $120.00 $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,769.00 $1,564.00 $1,680.00 $1,100.00 $1,425.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $6,329.00 $1,764.00 $1,800.00 $1,220.00 $1,545.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $40,794.59 $1,692.95 $7,475.43 $10,280.82 $3,609.21 $7,726.18 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00 Completion Fee $1,471.56 $169.30 $281.64 $471.38 $171.92 $377.32 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $42,266.15 $1,862.25 $7,757.07 $10,752.20 $3,781.13 $8,103.50 $3,080.00 $2,310.00 $2,310.00 $2,310.00 $0.00

Description

CURRENT BALANCE

PREVIOUS BALANCE

TOTAL THIS INVOICE

INVOICE

Invoice Number:

Date:

Project:

159 Walnut Street Rochester, New Hampshire 03867

Bill To:

Price Quantity Total

Work Performed

$300.00 $300.00

$300.00

$300.00

Phone (603) 332-2099, Fax (603) 332-2727

We are proud of the promptness with which we attend to our customers' needs and ask that you reciprocate by promptly remitting payment in full within 30 days. Any outstanding balances will be subject to an additional finance charge, computed at an annual rate of 18%. If an account remains unpaid, we reserve the right to place the account on hold until it is current.

Terms

Attn:

20387

07/29/2022

Wood PLC 1441 Maclay Commerce Drive Suite 102

Ronald White/AP

Tallahassee FL 32312

Net 30 Days

Annual Renewal of ProControl Wireless Data Service ProControl Series 2Plus Model B1

IP Address: 166.252.22.252

*Failure to submit payment within 30 days may lead to cancellation of cell service as well as additional reactivation charges

ProControl Wireless Data Service (4G) - 1 Year 1.00

Shirah, Ginger K

From: Schaefer, Geoff D. <geoff.schaefer@woodplc.com> Sent: Tuesday, August 16, 2022 4:41 PM To: Shirah, Ginger K Subject: RE: Ponte Vedra Cleaners, ERIC_5404, HW688 DC002A Deliverable 1 Attachments: Ponte Vedra - O&M - SVE Sampling - Final After TACO 2.xlsm; Ponte Vedra - O&M - SVE Sampling -

Final After TACO 2.pdf; Ponte Vedra - O&M - SVE Sampling - Delta TACO 2.xlsm; Ponte Vedra - O&M - SVE Sampling - Delta TACO 2.pdf; Ponte Vedra - O&M - SVE Sampling - Original After TACO 1.xlsm; Ponte Vedra - O&M - SVE Sampling - Original After TACO 1.pdf; ENM Company.pdf; EOS Telemetry Quote.pdf

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Ginger, Just realizing that I never sent you a TACO to reduce the costs from Q1 of the O&M.

Attached are the Original (after TACO 1), Delta, and Final (after TACO2) CEF/LOE workbooks.

We have removed the following form ST2:

2 hours for me to for the monthly O&M deliverables, 16 hours to do 2 months of O&M, 2 days of O&M kit, 2 Vans, 1 air sample, 1 sample shipping, 2 days of expendables

We have added the following to ST3:

1 year renewal of Telemetry

Replacement hour meter for the system v/r, Geoff Schaefer +01 850 298 7707 (d) +01 850 591 9249 (m)

From: Shirah, Ginger K <Ginger.K.Shirah@FloridaDEP.gov> Sent: Tuesday, June 21, 2022 11:29 AM To: Schaefer, Geoff D. <geoff.schaefer@woodplc.com> Subject: FW: Ponte Vedra Cleaners, ERIC_5404, HW688 DC002A Deliverable 1

CAUTION: External email. Please do not click on links/attachments unless you know the content is genuine and safe.

Geoff, Shirah, Ginger K

From: Schaefer, Geoff D. <geoff.schaefer@woodplc.com> Sent: Thursday, August 18, 2022 12:47 PM To: Shirah, Ginger K Cc: White, Ron D.; Peck, Renee L Subject: Ponte Vedra Cleaners O&M Deliverable date changes

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Ginger, Since we halted and then restarted the O&M at PVC, I propose the below new deliverable dates. The Semi‐Annual GW sampling is scheduled for mid September.

Deliverable Orig Date New Date Semi‐Annual O&M Report 8/31/22 10/28/22 Documentation for completion of Y4Q3 O&M 11/30/22 1/27/23 Annual O&M Report 2/28/23 4/28/23 Paid Utility Invoices 8/31/22 10/28/22 Paid Utility Invoices 2/258/23 4/28/23

Geoffrey D Schaefer, PE Senior Engineer Wood Environment & Infrastructure Solutions 1441 Maclay Commerce Drive, Suite 102 Tallahassee, Florida 32312 Direct: +01 850 298 7707 Mobile: +01 850 591 9249 www.woodplc.com

This message is the property of John Wood Group PLC and/or its subsidiaries and/or affiliates and is intended only for the named recipient(s). Its contents (including any attachments) may be confidential, legally privileged or otherwise protected from disclosure by law. Unauthorized use, copying, distribution or disclosure of any of it may be unlawful and is strictly prohibited. We assume no responsibility to persons other than the intended named recipient(s) and do not accept liability for any errors or omissions which are a result of email transmission. If you have received this message in error, please

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

DC002A 01 HW688

This change order will add costs to conduct an SVE system shutdown evaluation sampling event per attached review memo dated 2/17/2022.

Ginger Shirah (850) 245-8899 Contractor Wood Environment & Infrastructure Solutions, Inc. Contractor

Contractor Geoffrey Schaefer Contractor (850) 298-7707

ERIC_5404

Ponte Vedra Cleaners

✔ $ 32,516.15 $ 28,548.28 ✔ $ 9,750.00 9750

$ 42,266.15 $ 38,298.28 ✔ Completion

Completion 0

✔ 1 1 1

Contractor Geoffrey Schaefer

Geoff.Schaefer Digitally signed by Geoff.Schaefer Date: 2022.03.08 14:09:02 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2022.03.08 12:00:41 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW688

DC002A

$ 42,266.15

Documentation of completion of Year 4 Quarter 1 O&M activities including O&M logs, field notes, lab data (submitted electronically) and shutdown evaluation data with memo - Subtask 2

Semi-Annual Operation & Maintenance Report; Documentation of completion of Year 4 Quarter 2 O&M activities including O&M logs, field notes, waste manifest, lab data (submitted electronically) - Subtask 3

Documentation of completion of Year 4 Quarter 3 O&M activities including O&M logs, field notes, lab data (submitted electronically) - Subtask 4

Annual Operation & Maintenance Report; Documentation of Year 4 Quarter 4 O&M activities including O&M logs, field notes, waste manifest, lab data (submit electronically) and Project Management - Subtasks 1 & 5

Paid utility invoices (January through July 2022) - Subtasks 6 & 7

Paid utility invoices (August 2022 - January 2023) - Subtasks 8 & 9

Subtask 2 - FDEP approval of documentation of completion of Year 4 Quarter 1 O&M activities including O&M logs, field notes, lab data, and shutdown evaluation data with memo

Subtask 4 - FDEP approval of documentation of completion of Year 4 Quarter 3 O&M activities including O&M logs, field notes, lab data

Subtasks 1 & 5 - FDEP approval of Annual O&M Report, documentation of completion of Y4 Q4 O&M activities including O&M logs, field notes, lab data; and Project Management

Subtasks 8 & 9 - FDEP receipt & approval of paid utility invoices from August 2022 through January 2023 (Cost plus fixed fee not to exceed $4,500; Utilities handling fees $60+$60= $120)

Subtasks 6 & 7 - FDEP receipt & approval of paid utility invoices from January 2022 through July 2022 (Cost plus fixed fee not to exceed $5,250; Utilities handling fees $80+$60= $140)

Subtask 3 - FDEP approval of Semi-Annual O&M Report, documentation of completion of Y4 Q2 O&M activities including O&M logs, field notes, lab data

05/31/2022

08/31/2022

11/30/2022

02/28/2023

02/28/2023

08/31/2022

$ 10,752.20

$ 7,757.07

$ 3,781.13

$ 9,965.75

$ 5,390.00

$ 4,620.00