CN-370000-HW560-DC038C.pdf
PDF 634 KB Posted
- Contract number
- HW560
- Issued by
- Florida
About this file
This Task Assignment Notification Form (WCP TAFORM 01-18) is issued by the Florida Department of Environmental Protection (FDEP) to Tetra Tech EC, Inc. for work at Davidson's Dry Cleaners, a contaminated site in LaBelle, Hendry County, Florida (ERIC_4673). The task assignment is executed under FDEP Contract No. HW560 and is designated as Task Assignment DC038C within Module D000. Key personnel include DEP Contract Manager Walsta Jean-Baptiste, DEP Task Manager Walsta Jean-Baptiste, Tetra Tech's Contractor Representative Jay McGovern, PG, and Project Manager John Sykes III. The contractual authority is William E. Burns, Jr., and the work is categorized as a "Deletion" phase of site rehabilitation.
This task assignment authorizes Tetra Tech to complete monitoring well abandonment activities in accordance with their scope of work, cost estimate form, and bid documentation, with timelines aligned to the approved Site Rehabilitation Completion Order dated September 15, 2020. The primary deliverable is a Well Abandonment Report including photographic documentation of final site conditions, due November 30, 2020 (extended to February 1, 2021), with payment contingent upon FDEP approval. The task is structured as a fixed-price engagement totaling $4,610.33 with no retainage. This cost encompasses 15 labor hours, including project management and abandonment of seven monitoring wells (118 total feet), drilling services procured from Preferred Drilling Solutions at $2,096.00, vehicle rental at $68.00, and a completion fee of $200.00. No cost reimbursement or additional fixed fees apply. The period of performance extends from execution through February 1, 2021.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW560
D000 NADC038C
Tetra Tech EC, Inc.
Jay McGovern, PG
850-245-8705Walsta Jean-Baptiste
ERIC_4673
Davidson's Dry Cleaners
325 N Bridge Street, Labelle, Hendry County
Deletion
This Task Assignment authorizes Tetra Tech to complete monitoring well abandonment in accordance with the Tetra Tech scope of work, cost estimate form, and bid documentation. The schedule will coincide with the time frames specified in the approved Site Rehabilitation Completion Order dated September 15, 2020.
Well Abandonment Report including photographic log of final site conditions (submitted electronically)
11/30/2020
02/01/2021
$ 4,610.33 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2020.09.21 12:23:20 -04'00'
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2020.09.21 12:23:29 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2020.09.21 14:12:03 -04'00'
Jay McGovern Digitally signed by Jay McGovern Date: 2020.09.21 14:18:56 -04'00'
$ 4,610.33
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Well Abandonment Report including photographic log of final site conditions (submitted electronically) 11/30/2020
FDEP approval of Well Abandonment Report including photographic log of final site conditions (submitted electronically) - Subtasks 1 and 2 $ 4,610.33
$ 4,610.33
HW560
DC038C
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: HW556 Contract File FROM: Walsta Jean-Baptiste, Contract Manager SUBJECT: Davidson’s Dry Cleaners; Well Abandonment and Site Restoration DATE: September 21, 2020
This Task Assignment authorizes Tetra Tech to complete monitoring well abandonment in accordance with the Tetra Tech scope of work, cost estimate form, and bid documentation. The schedule will coincide with the time frames specified in the approved Site Rehabilitation Completion Order dated September 15, 2020.
There were no changes to the proposed costs.
The cost related to this Task Assignment is $4,610.33 with 15 hours.
FDEP COST ESTI MATEContractor: Tetra Tech
Date: June 1, 2020
Task #: HW560-DC019J SubTask 1 Project Management SubTask 6
Site: Davidsons Dry Cleaners, LaBelle (ERIC_4673) SubTask 2 Abandonment of the Monitor Well Network SubTask 7
Activity/Phase: Site Closure SubTask 3 SubTask 8
Project Manager: John Sykes III SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$69.35 Project Manager (JM) 1 1.2 $34.50 Senior CADD Specialist (FM) 0 0 0 0 0 0 0 0 0 0 $42.78 Scientist IV (SO) 12 12 0 0 0 0 0 0 0 0 $69.35 Scientist V (JM) 2 2 0 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 15 1 14 0 0 0 0 0 0 0 0
Direct Labor $733.57 $81.51 $652.06 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 143.00% $1,049.01 $116.56 $932.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 12.20% $217.47 $24.16 $193.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $2,000.05 $222.23 $1,777.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $36.68 $4.08 $32.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $68.00 $68.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $68.00 $68.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTI MATEContractor: Tetra Tech
Date: June 1, 2020
Task #: HW560-DC019J SubTask 1 Project Management SubTask 6
Site: Davidsons Dry Cleaners, LaBelle (ERIC_4673) SubTask 2 Abandonment of the Monitor Well Network SubTask 7
Activity/Phase: Site Closure SubTask 3 SubTask 8
Project Manager: John Sykes III SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $2,096.00 $2,096.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,096.00 $2,096.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $209.60 $209.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,305.60 $2,305.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,410.33 $226.31 $4,184.02 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $200.00 $22.22 $177.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $4,610.33 $248.53 $4,361.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT WORKSHEET
SITE : Davidsons Dry Cleaners, LaBelle (ERIC_4673) SUBTASK 2: Abandonment of the Monitor Well Network
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Perform Site Closure:
Scientist IV (SO) Oversee MW abandonments (7 Monitor Wells), photo document 12
Includes round trip travel (6 hrs)
Scientist V (JM) Prepare Letter Report documenting MW Abandonment 2
TOTAL LABOR 14
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
car $68.00 1 day $68.00
TOTAL VEHICLE $68.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
HOTEL
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Preferred Abandon 7 MWs (118 ft) $2,096.00 $2,096.00
TOTAL $2,096.00
Davidsons Dry Cleaners MW Abandonments.xlsx LOE 2
Tetra Tech, Inc.
759 South Federal Highway, Suite 314 Stuart, FL 34994
Tel 772.781.3400 Fax 772.781.3411 www.tetratech.com
September 21, 2020
TTST-HW560-20-043
Ms. Walsta Jean-Baptiste, P.G.
Contract Manager Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
SUBJECT: MONITOR WELL ABANDONMENT TASK ASSIGNMENT REQUEST
DAVIDSONS DRY CLEANERS
345 N. BRIDGE STREET
LABELLE, FL 33935
ERIC_4673
Dear Ms. Jean-Baptiste:
Tetra Tech is requesting a Task Assignment to abandon the monitor well network at the Davidsons Dry Cleaners site in LaBelle, FL as part of the Site Rehabilitation Completion Order. The proposed activities include oversight for the abandonment of all site groundwater monitoring wells by a licensed water well contractor.
The proposed deliverables and deliverable due dates are summarized below:
• Subtask 1 – Project Management
• Subtask 2 – Submittal of a Letter Report documenting MW Abandonment:
Deliverable due date November 20, 2020
Should you have any questions, please contact me at 772.781.3409.
Sincerely, Jay McGovern, P.G.
Project Manager
Enclosures c: File
Preferred Drilling Solutions, Inc.
11747 87th St. North, Largo, FL 33773
Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
Contractor Name: Tetra Tech
Site Name & Location: Davidson Dry Cleaners Date: 5/29/20 FAC ID#:
345 N Bridge St, Labelle, FL
PROPOSED SCOPE OF WORK:
Abandon 7-1" MW's, 6 wells 13' and 1 well 40' in depth, remove pads and manholes and restore grade at 6 location, concrete 1 interior location in place
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Unit Unit Rate Number of Units Extended Price
Rig Type: Auger/Mud Rotary_____ Sonic_____ Other_____
Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation) (includes decon)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Borehole Grouting
4 - inch borehole diameter per foot $0.00 6 - inch borehole diameter per foot $0.00 8 - inch borehole diameter per foot $0.00
1" - 2" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
4" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Recovery Well Diameter: 4-6" per foot $0.00 Double Cased Wells $0.00
6" Surface Casing per foot $0.00 8" Surface Casing per foot $0.00 per well $0.00 and saw/jackhammer prep.)
1"- 2" Well Abandonment (includes grouting) per foot $7.00 118 $826.00 3"- 4" Well Abandonment (includes grouting) per foot $0.00 5"- 6" Well Abandonment (includes grouting) per foot $0.00 2' x 2' Well Pad Removal and Patch each $95.00 6 $570.00
Mobilization roundtrip $575.00 1 $575.00
Per Diem per crew $0.00 DOT Approved 55-gal Drum each $0.00 Permits (Drilling or abandonment only) each $125.00 1 $125.00
$0.00
$0.00
$0.00 Additional Development Time per hour $0.00 Additional Decontamination Time per hour $0.00 Standby/Delay/Difficult Access Time per hour $0.00
TOTAL QUOTE PRICE $2,096.00
Days to Complete Scope of Work: .5 Project No.:
Signature and Title of Person Submitting Quote: __________________________________Kevin Bonacum, Estimator Date: 5/29/20
Well Completion (includes 30 minute development, MH w/ cover, concrete pad, locking well cap, DRILLING
MISCELLANEOUS
Tetra Tech, Davidson Dry Cleaners, Labelle
EARTH TECH DRILLING
2703 NW 19TH STREET, POMPANO BEACH, FL 33069
954.974.2424 FAX:954.9742423
Date: 5/28/2020
FAC ID#:
PROPOSED SCOPE OF WORK:
Unit Unit Rate Number of Units Extended Price
Rig Type: Auger/Mud Rotary____ Sonic_____ Other_x Abandonment
Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation) (includes decon)
HAND CLEARING to 5' BLS per foot $0.00
<50 foot boring depth per foot $0.00
50 foot to 100 foot boring depth per foot $0.00
>100 foot boring depth per foot $0.00
Borehole Grouting
4 - inch borehole diameter per foot $0.00
6 - inch borehole diameter per foot $0.00
8 - inch borehole diameter per foot $0.00
1" - 2" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00
50 foot to 100 foot boring depth per foot $0.00
>100 foot boring depth per foot $0.00
4" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00
50 foot to 100 foot boring depth per foot $0.00
>100 foot boring depth per foot $0.00
Recovery Well Diameter: ______ per foot
Double Cased Wells
4" Surface Casing per foot $0.00
6" Surface Casing per foot $0.00
8" Surface Casing per foot $0.00 per well $0.00
1"- 2" Well Abandonment (includes grouting) per foot $12.00 118 $1,416.00
3"- 4" Well Abandonment (includes grouting) per foot $0.00
5"- 6" Well Abandonment (includes grouting) per foot $0.00
2' x 2' Well Pad Removal and Patch each $95.00 6 $570.00
Mobilization roundtrip $575.00 1 $575.00
Per Diem per crew / per night $0.00
DOT Approved 55-gal Drum each $0.00
Permits (Drilling or abandonment only; cost according to WMD & Local Municipalities) each $175.00 1 $175.00 each $25.00 1 $25.00 ls $75.00 1 $75.00
$0.00
$0.00
Standby/Delay/Difficult Access Time per hour $375.00 $0.00
TOTAL QUOTE PRICE $2,836.00
Project No.: ________________________
Date: 5/28/2020
Well Completion (includes 30 minute development, manhole, concrete pad, locking well cap, DRILLING
MISCELLANEOUS
Site Name: Davidsons Dry Cleaners / 345 N Bridge Street Labelle, FL
Contractor Name: Tetra Tech / Jay McGovern / 772 781-3409
Grout Abandon (6) 1" x 13' MW's = 78' Total
Grout Abandon (1) 1" x 40' MW = 40' Total
Remove (6) Pad/Manhole & Resod
Dispose of all debris offsite
1 well is inside drycleaner and manhole needs filled with concrete
Days to Complete Scope of Work: 1 Day
Subcontract Company Name: EARTH TECH DRILLING 954.974.2424
Subcontract Mailing Address: 2703 NW 19th St., Pompano Bch. FL 33069
Signature and Title of Person Submitting Quote: Charles Bucher
Fill Manhole with concrete
Debris disposal offsite
Monitoring Wells Sparge Wells Horizontal and Vertical Vapor Extraction Wells Geotechnical Drilling Direct Push
Sonic Auger DPT Horizontal Directional Drilling
DATE: 5/29/2020
ESTIMATE #: 520092
ID QTY Unit Rate TOTAL
1 1 ls 1,000.00$ 1,000.00$
2 0 night 200.00$ -$
3 118 foot 6.00$ 708.00$
4 Remove manhole lid and ring. Fill w/concrete 1 each 75.00$ 75.00$
5 Remove pads/manholes and patch w/sod 6 each 95.00$ 570.00$
6 Debris disposal offsite 1 ls 75.00$ 75.00$
7 Permits: Hendry County 2 each 100.00$ 200.00$
Completion: Subtotal 2,628.00$
David Boggs David Boggs TOTAL 2,628.00$ Project Manager
If you have any questions concerning this proposal contact David Boggs at 407-426-7885 or at David@drillprollc.com.
Well Abandonments
DESCRIPTION
Mobilization / Demobilization
Per Diem
THANK YOU FOR YOUR BUSINESS!
PROJECT DESCRIPTION:
Dispose of debris offsite
Grout and abandon 1" wells
"Private utility locates are the responsibility of the client"
(772) 781-3409
"Actual quantities used and days on site will be invoiced"
1/2 Day
Grout and abandon (7) 1" Wells- Total LF is 118'- Remove pads/manholes and patch w/sod (1 is inside and manhole will be filled w/concrete)
CUSTOMER
Labell, Florida
PROJECT
Davidson's Dry Cleaners 345 N Bridge Street
Jay McGovern Tetra Tech 759 South Federal Highway, Ste 314 Stuart, FL 34994
2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| Combined MW Abandon Quotes.pdf |
| Tetra Tech, Davidson Dry Cleaners, Labelle.pdf |
| Drilling |
| Davidsons Dry Cleaners MW Abandonments.pdf |
| CE |
| LOE 2 |
| Davidsons TA Request.pdf |
| 20_043CL |
| Combined MW Abandon Quotes |
| Tetra Tech, Davidson Dry Cleaners, Labelle.pdf |
| Drilling |
File details come from the government source that posted it. Updated .