This is a Task Assignment Notification Change Order Form (Change Order #1) for DEP Contract No. HW560 between the Florida Department of Environmental Protection (FDEP) and Tetra Tech, Inc. The contract pertains to supplemental site assessment activities at the Port of Fort Pierce, also known as the Former King Maritime Group, located in Fort Pierce, Florida (Site ID ERIC_15269). The change order was processed by DEP Contract Manager Kelly Crain and DEP Task Manager Megan R. Johnson, with contractor representative Gerry Walker, P.G., and was executed in January 2021.

The change order modifies Task Assignment BF602B for supplemental site assessment activities funded through the State & Tribal Response Program (SRP18 Grant), a federal cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency. The modification reflects actual field conditions encountered during Phase II assessment work and includes the following adjustments: an increase of 8 hours for a Scientist IV to coordinate onsite sampling activities (Subtask 3), resulting in a net cost increase of $342.24; a decrease in subcontracted drilling costs of $550.00 due to incorporation of two pre-existing monitoring wells, reducing new well installations from four to two; and a decrease in laboratory costs of $1,084.00 due to fewer samples collected than originally proposed. The overall result is a cost decrease of $491.54, reducing the total task amount from $36,372.08 to $35,880.54. The final deliverable due date for Subtask 4 (Supplemental Site Assessment Report) was extended from January 15, 2021 to February 5, 2021, with the overall period of performance extended by 18 days to March 5, 2021.

View the file

Other files

File Type Posted
CN-370000-HW560-A12.pdf PDF
CN-370000-HW560-A2.pdf PDF
CN-370000-HW560-A7.pdf PDF
CN-370000-HW560-A8.pdf PDF
CN-370000-HW560-BF02B.pdf PDF
CN-370000-HW560-BF03B.pdf PDF
CN-370000-HW560-BF04A.pdf PDF
CN-370000-HW560-BF04ACO1.pdf PDF
CN-370000-HW560-BF04D.pdf PDF
CN-370000-HW560-BF05.pdf PDF
CN-370000-HW560-BF05ACO4.pdf PDF
CN-370000-HW560-BF06.pdf PDF
CN-370000-HW560-BF06CO1.pdf PDF
CN-370000-HW560-BF07BCO1.pdf PDF
CN-370000-HW560-BF602A.pdf PDF
CN-370000-HW560-BF62CCO1.pdf PDF
CN-370000-HW560-BF62CCO2.pdf PDF
CN-370000-HW560-CO4.pdf PDF
CN-370000-HW560-CO5.pdf PDF
CN-370000-HW560-CS19ACO1.pdf PDF
CN-370000-HW560-CSS-19A.pdf PDF
CN-370000-HW560-CSS-31A.pdf PDF
CN-370000-HW560-CSS-32A.pdf PDF
CN-370000-HW560-CSS3ACO1.pdf PDF
CN-370000-HW560-DC006I.pdf PDF
CN-370000-HW560-DC007P.pdf PDF
CN-370000-HW560-DC008R.pdf PDF
CN-370000-HW560-DC009A.pdf PDF
CN-370000-HW560-DC010O.pdf PDF
CN-370000-HW560-DC01ACO1.pdf PDF
CN-370000-HW560-DC01ACO5.pdf PDF
CN-370000-HW560-DC01ACO6.pdf PDF
CN-370000-HW560-DC01ACO9.pdf PDF
CN-370000-HW560-DC021C.pdf PDF
CN-370000-HW560-DC025A.pdf PDF
CN-370000-HW560-DC025D.pdf PDF
CN-370000-HW560-DC027J.pdf PDF
CN-370000-HW560-DC030K.pdf PDF
CN-370000-HW560-DC031B.pdf PDF
CN-370000-HW560-DC032B.pdf PDF
CN-370000-HW560-DC035B.pdf PDF
CN-370000-HW560-DC036F.pdf PDF
CN-370000-HW560-DC03CCO1.pdf PDF
CN-370000-HW560-DC03I.pdf PDF
CN-370000-HW560-DC04CCO1.pdf PDF
CN-370000-HW560-DC04CCO2.pdf PDF
CN-370000-HW560-DC04D.pdf PDF
CN-370000-HW560-DC04E.pdf PDF
CN-370000-HW560-DC05D.pdf PDF
CN-370000-HW560-DC05H.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

BWC TAFORM 2/03

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW560

BF602B

$ 35,880.54

QAPP/Work Plan and HASP

Field notes, photographic log, chain of custody, soil sampling logs, groundwater sampling logs

Supplemental Site Assessment Report

Department approval of QAPP/Work Plan and HASP (Subtask 2)

Department approval of Supplemental Site Assessment Report (Subtasks 1 and 4)

Department approval of field notes, photographic log, chain of custody, soil sampling logs, and groundwater sampling logs (Subtask 3)

11/16/2020

12/29/2020

02/05/2021

$ 24,924.40

$ 4,354.99

$ 6,601.15 www.FloridaDEP.gov

FFLORIDA DEPARTMENT OFF

EEnvironmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette NNuñez

Lt. Governor

NNoah Valenstein Secretary

Memorandum TO: Tetra Tech, Inc., HW560 Contract File

FROM: Kelly Crain, Contract Manager

DATE: January 20, 2021

SUBJECT: Negotiation Summary – SRP18 Grant

Task Assignment (TA) Change Order #1 – TA BF602BC1 Port of Fort Pierce aka: Former King Maritime Group Site ID # ERIC_15269 Supplemental Site Assessment Activities

This Task Assignment Change Order (TACO) is for an increase of 8 hours for a Scientist IV, a decrease in subcontracted drilling cost, and a decrease in laboratory cost, resulting in an overall decrease of costs for Subtask 3 – Field Activities; this led to a slight increase of 0.7 hours to Subtask 1 – Project Management; and a time extension to the deliverable due date for Subtask 4

– Supplemental Site Assessment Report. A time extension to the overall Period of Performance was given, as well. This work was conducted at the Port of Fort Pierce aka: Former King Maritime Group site, located at 101 Port Avenue A, Fort Pierce, Florida 34950. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S.

Environmental Protection Agency (EPA).

Subtask 1: Project Management An increase in labor expended increased the number of project management hours by 0.7 hours. This resulted in an increase of $131.94 for this Subtask.

Subtask 2: QAPP/Work Plan, and HASP This TACO does not include any costs changes associated with this Subtask.

Subtask 3: Supplemental Site Assessment Activities On November 30, 2020, Tetra Tech sought Department approval to include eight (8) hours of time for a Scientist IV to assist in the coordination of onsite sampling activities due to this individual’s prior knowledge of the site. The Department approved this request on December 2, 2020, and that approval email is attached.

Two pre-existing monitoring wells were incorporated into the groundwater monitoring network, which reduced the number of new wells from four (4) to two (2), reducing the subcontracted drilling cost. In addition, fewer samples were collected than those included in the original cost proposal due to an overestimation of number of TRPH samples needed prior to workplan development.

Negotiation Summary – Task Assignment Change Order #1 TA BF602BC1 Port of Fort Pierce aka: Former King Maritime Group

ERIC_15269

January 20, 2021 www.FloridaDEP.gov

This resulted in a decrease in laboratory costs These changes resulted in an overall decrease of ($623.48) for this Subtask.

Subtask 4: Supplemental Site Assessment Report Included in this TACO is a deliverable due date time extension for this Subtask. This TACO does not include any costs changes associated with this Subtask.

Summary The Department’s SRP Contract Manager and Tetra Tech’s Contract Manager have both agreed to the above changes. Due to a rounding error in Excel, the Cost Actual LOE spreadsheet states an overall project cost of $35,880.56, a decrease of ($491.52), when it is actually $35,880.54, a decrease of ($491.54), as shown in the Delta LOE spreadsheet. Therefore, all changes noted above represent a total overall cost decrease of ($491.54). The changes were noted in the TACO Request received from Tetra Tech, Inc. on January 12, 2021. The final cost associated with this TA decreased from $36,372.08 to $35,880.54. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet, and the Cost Actual LOE spreadsheet, the TACO Form for BF602BC1 prepared by the Department, and the December 2, 2020 Department approval of additional field hours email. The final deliverable for Subtask 4 – Supplemental Site Assessment Report, must be received by the Department no later than February 5, 2021.

Tetra Tech, Inc.

1558 Village Square Blvd., Ste. 2, Tallahassee, FL 32309-2478 Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

TetraTech/TAL-21-02-112IC09330

January 12, 2021

Department of Environmental Protection Waste Cleanup Programs ATTN: Ms. Megan Johnson MS #4535 Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Reference: Florida Department of Environmental Protection (DEP) Waste

Cleanup Programs Consolidated Contract HW560

Subject: Change Order Request – Phase 2, Targeted Brownfield Assessment at Former King Maritime Group (AKA: Port of Fort Pierce), Fort Pierce, St. Lucie County, Florida

Dear Ms. Johnson:

Tetra Tech is providing this change order request to the Florida Department of Environmental Protection (FDEP) to document changes in cost associated with scope changes that occurred during the field work (Subtask 3) for the second phase of Targeted Brownfield Assessment activities at the Former King Maritime Group Site at 101 Port Avenue A, Fort Pierce, Florida. We are also requesting a time extension for completion of the final report (Subtask 4) in this change order.

The scope changes necessitating the change order are described below and in the attached Change Order and Change Order Delta workbooks.

Subtask 1 - Project Management: Increase (0.7 hour) due to Subtask 3 labor increase.

Subtask 2 - Work Plan & Health and Safety Plan (HASP): No changes.

Subtask 3 – Soil Sampling, Well Installation, and Groundwater Sampling:

A. Increase in LOE cost. FDEP approved the inclusion of LOE for a Scientist IV (SO) to assist in the coordination of onsite sampling activities with the onsite representative from Derector and the Tetra Tech Field Operations Lead. Mr. Sean Ouellette led the previous sampling effort and his coordination greatly facilitated access to the site and locating the sampling stations. This request includes eight (8) hours of his time that were not included in the original cost proposal.

B. Decrease in subcontracted drilling cost. Two pre-existing monitoring wells were incorporated into the groundwater monitoring network, which reduced the number of new wells from four (4) to two (2). This reduced the drilling cost by $550.00. The invoice from the drilling subcontractor is attached.

C. Decrease in laboratory cost. Fewer samples were collected than those included in the original cost proposal. This was due to an overestimate of number of TRPH samples needed in the original scoping prior to workplan development. Fewer surface soil samples were also collected from the 0 to 6-inch below land surface soil interval at some locations due to concrete pavement and pavement base material that occurred in Site Areas B and C. The changes in numbers of samples and resulting cost difference are shown in the Change Order Delta LOE 3 Worksheet. Actual samples collected are documented in the attached copies of the sample “Chains of Custody and sample receipts.

Subtask 4 - Report: Due to several factors, the field work was conducted approximately three weeks later than anticipated in the original schedule for the task assignment. The original schedule did not account for time needed to obtain a right of way permit from the City of Fort Pierce for background sampling or scheduling weekend work with the driller to work around ongoing construction work on the former port site. Tetra Tech requests a change in the final deliverable due date from January 15, 2021 to February 5, 2021.

Change Order Amount These changes result in a $491.54 reduction in cost for this task assignment. The requested new task assignment amount is $35,880.56.

If you have any questions, please call myself or Richard Hicks (850) 385-9899.

Sincerely yours, Gerald Walker, P.G.

Brownfields Program Manager rh/GAW

Attachments c: Kelly Crain, FDEP Justin Cross, FDEP Richard Hicks, Tetra Tech Jay McGovern, Tetra Tech Tallahassee File FDEP Contract HW560

Due to a rounding error in Excel, the Cost Actual LOE spreadsheet states an overall project cost of $35,880.56, a decrease of ($491.52), when it is actually $35,880.54, a decrease of ($491.54), as shown in the Delta LOE spreadsheet.

Attachment A

Contract HW560 Cost Estimate Spreadsheets and Backup

Documentation

FDEP COST ESTIMATE

Contractor: Tetra Tech, Inc.

Date: January 11, 2021

Task #: HW560 TA SubTask 1 Project Management

Site: Former King Maritime Group SubTask 2 Phase II Work Plan

Activity/Phase: Phase II Change Order Delta SubTask 3 Fieldwork - Soil and Groundwater Assessment

Project Manager: Megan Johnson SubTask 4 Report

SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$61.82 Project Manager (GW) 1 0.7 0 0 $55.00 Scientist V (RH) 0 0 0 0 0 $43.27 Scientist IV (CA) 0 0 0 0 0 $42.78 Scientist IV (SO) 8 0 8 $23.41 Scientist I (DH) 0 0 0 0 0 $26.81 Engineer I (MQ) 0 0 0 0 0 $37.54 Staff GIS Specialist (JM) 0 0 0 0 0

Total Hours 9 1 0 8 0 0

Direct Labor $385.51 $43.27 $0.00 $342.24 $0.00 $0.00

Overhead 143.00% $551.28 $61.88 $0.00 $489.40 $0.00 $0.00 Gen & Admin 12.20% $114.29 $12.83 $0.00 $101.46 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $1,051.08 $117.98 $0.00 $933.10 $0.00 $0.00

Other Direct Costs $19.27 $2.16 $0.00 $17.11 $0.00 $0.00 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Transportation & Disposal $0.00 $0.00 $0.00 $0.00 $0.00 Drilling and Well Installation ($530.00) $0.00 ($530.00) $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal ($530.00) $0.00 ($530.00) $0.00 $0.00 Handling Fee ($53.00) $0.00 ($53.00) $0.00 $0.00 Total Subcontractor Cost ($583.00) $0.00 ($583.00) $0.00 $0.00

Laboratory Laboratory ($1,084.00) $0.00 ($1,084.00) $0.00 $0.00 Encore Samplers $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($1,084.00) $0.00 ($1,084.00) $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($596.65) $120.14 $0.00 ($716.79) $0.00 $0.00 Completion Fee $105.11 $11.80 $0.00 $93.31 $0.00 $0.00

Total Estimated Cost ($491.54) $131.94 $0.00 ($623.48) $0.00 $0.00

REV: 03/23/17 Page 1

Due to a rounding error in Excel, the Cost Actual LOE spreadsheet states an overall project cost of $35,880.56, a decrease of ($491.52), when it is actually $35,880.54, a decrease of ($491.54), as shown in the Delta LOE spreadsheet.

SITE :

SUBTASK 2: Phase II Work Plan

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) 0 Scientist V (RH) Tallahassee Office; Develop/review Work Plan [4]; Coordination, teleconference with staff, County and FDEP [3] 0

Scientist IV (CA) Site Recon to identify, mark proposed locations [8], coordinate with County, City and Derecktor on access to site and rights of way [4] 0 Scientist IV (SO) 0 Scientist I (DH) Tallahassee Office; Work plan preparation, draft figures, text and tables [12] 0

Engineer I (MQ) Tallahassee Office; Revise, recertify HASP [2] 0

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation, approximately 6 figures with proposed locations and previous results shown [2] 0

TOTAL LABOR 0

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Total GPS Station $141.65 Each 0 $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 Cocoa to Ft. Pierce, 1 dy $0.00

Subtotal $0.00 Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL 0

Scientist V (RH) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Tallahassee Office; Review Work Plan [1]

SUBTASK 3: Fieldwork - Soil and Groundwater Assessment

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (RH) Coordination with Subs, Review field work deliverable [2] 0

Scientist IV (CA) Cocoa Office; ROW permits [4]; Field work (mobs [3 times, 12], uti loc [8], soil borings/splng [20], GPS/TOC svy [4]; 0 well instal [6]; gw splng [12]; gw level meas in all mon wells [2]; field prep, documentation, shipping [4])

Scientist IV (SO) Stuart Office; assist in coordinating access to onsite locations and site visit to help mark sampling locations [8] 8 Scientist I (DH) Tallahassee office; Field deliverable prep [4] 0

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

TOTAL LABOR 8

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Soil Assessment Kit $208.55 Day 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00 Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00 Total Survey Station $41.75 Each 0 $0.00 Peristaltic Pump $29.10 Each 0 Extra pump for well purging $0.00 Hammer Drill $50.95 Each $0.00 MiniRae 3000 PID $87.30 Each Included in MW and Soil kits $0.00 Total GPS Station $141.65 Each 0 Trimble GeoXH $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $420.00 week 0 Staff from Cocoa for field work (6 days) $0.00 Car $68.00 day 0 Staff from Cocoa for utility location and ROW permittin $0.00

Subtotal $0.00 Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V $36.00 Day 0 $0.00 Scientist IV (CA) $36.00 Day 0 $0.00 Engineer I $36.00 Day 0 $0.00

HOTEL

Scientist V $120.00 Day 0 $0.00 Scientist IV (CA) $120.00 Day 0 $0.00 Engineer I $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Metals Liquid 6010-As $11.50 1 0 based on actual samples collected $11.50 Nitrate Liquid 353.2 $20.00 0 0 based on actual samples collected $0.00 Ammonia Liquid 350.2 $20.00 0 0 based on actual samples collected $0.00 TRPH Liquid Florida PRO $84.00 0 -3 based on actual samples collected ($252.00) SVOC Liquid 8270 $100.00 $0.00 Mercury Liquid 7470 $23.00 $0.00 Pesticides Liquid 8081 $90.00 $0.00 Metals Soil 6010 -As $11.50 6 1 based on actual samples collected $80.50 Metals Soil 6010- Pb $11.50 $0.00 Volatile Organics Soil 8260 $135.00 $0.00 TRPH Soil Florida PRO $84.00 -11 0 based on actual samples collected ($924.00) SVOC Soil 8270 $100.00 $0.00 TRPH Fractionation (see note) Soil TPH-CWG $250.00 $0.00 Pesticides Soil 8081 $90.00 $0.00

Subtotal ($1,084.00) Unit Cost Quantity

Sample Containers Lot $0.00 $0.00 Encore Samplers Each $8.75 $0.00 Sample Shipping Coolers $104.00 $0.00

Subtotal $0.00

TOTAL LAB ($1,084.00)

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

Preferred Drilling Solutions Drilling ($530.00) 1 fewer wells installed, resulted in reduction ($530.00) GeoTek Utility Locate $0 1 $0.00

TOTAL ($530.00)

LEVEL OF EFFORT/EXPENSE WORKSHEET

SUBTASK 4: Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) Tallahassee Office; Document review and seal 0 Scientist V (RH) Tallahassee Office; Document review and editing 0

Scientist IV (CA)

Scientist I (DH) 0

Engineer I (MQ)

Staff GIS Specialist (JM) Jacksonville Office; Process GPS data, figure preparation 0

TOTAL LABOR 0

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Site Reconnaissance Kit $81.48 Each 0 $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00

Subtotal $0.00 Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00 Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00 Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00 Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00 TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00 Lead Liquid 6010 $11.50 Standard Turn Around $0.00 Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00 COD Liquid SM5220 $25.00 Standard Turn Around $0.00 BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00 Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00 In-line Filter (0.45 Micron) Each $17.50 $0.00

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Compare onsite and offsite data, calculate background reference levels [20], report prep, tables and draft figs [16]

REV: 03/23/17 Page 2

Date: January 11, 2021

SubTask 1 Project Management

SubTask 2 Phase II Work Plan

SubTask 3 Fieldwork - Soil and Groundwater Assessment

Task #: HW560 TA

Site: Former King Maritime Group

Activity/Phase: Phase II Change Order

Project Manager: Megan Johnson SubTask 4 Report

SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$61.82 Project Manager (GW) 13 13.4 1 2 $55.00 Scientist V (RH) 15 7 4 4 0 $43.27 Scientist IV (CA) 88 12 76 0 0 $42.78 Scientist IV (SO) 0 8 $23.41 Scientist I (DH) 52 12 4 36 0 $26.81 Engineer I (MQ) 1 1 0 0 0 $37.54 Staff GIS Specialist (JM) 6 2 0 4 0

Total Hours 186 13 35 92 46 0

Direct Labor $7,458.22 $828.39 $1,348.87 $3,944.40 $1,336.56 $0.00

Overhead 143.00% $10,665.25 $1,184.60 $1,928.88 $5,640.49 $1,911.28 $0.00 Gen & Admin 12.20% $2,211.07 $245.58 $399.89 $1,169.36 $396.24 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $20,334.54 $2,258.57 $3,677.64 $10,754.25 $3,644.08 $0.00

Other Direct Costs $372.91 $41.42 $67.44 $197.22 $66.83 $0.00 Travel

Vehicle Rental $624.00 $68.00 $556.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $660.00 $0.00 $660.00 $0.00 $0.00 Total Travel $1,284.00 $68.00 $1,216.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Transportation & Disposal $0.00 $0.00 $0.00 $0.00 $0.00 Drilling and Well Installation $4,575.00 $0.00 $4,575.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $1,500.00 $0.00 $1,500.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $6,075.00 $0.00 $6,075.00 $0.00 $0.00 Handling Fee $607.50 $0.00 $607.50 $0.00 $0.00 Total Subcontractor Cost $6,682.50 $0.00 $6,682.50 $0.00 $0.00

Laboratory Laboratory $3,189.50 $0.00 $3,189.50 $0.00 $0.00 Encore Samplers $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $416.00 $0.00 $416.00 $0.00 $0.00 Total Laboratory $3,605.50 $0.00 $3,605.50 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $195.00 $32.50 $162.50 $0.00 $0.00 Equipment (Drilling related) $184.30 $0.00 $184.30 $0.00 $0.00 Equipment (Analytical related) $834.20 $0.00 $834.20 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $354.15 $141.65 $212.50 $0.00 $0.00 Total Field Expenses $1,567.65 $174.15 $1,393.50 $0.00 $0.00

Subtotal $33,847.10 $2,299.99 $3,987.23 $23,848.97 $3,710.91 $0.00 Completion Fee $2,033.46 $225.86 $367.76 $1,075.43 $364.41 $0.00

Total Estimated Cost $35,880.56 $2,525.85 $4,354.99 $24,924.40 $4,075.32 $0.00

REV: 03/23/17 Page 1

Due to a rounding error in Excel, the Cost Actual LOE spreadsheet states an overall project cost of $35,880.56, a decrease of ($491.52), when it is actually $35,880.54, a decrease of ($491.54), as shown in the Delta LOE spreadsheet.

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) 1 Scientist V (RH) Tallahassee Office; Develop/review Work Plan [4]; Coordination, teleconference with staff, County and FDEP [3] 7

Scientist IV (CA) Site Recon to identify, mark proposed locations [8], coordinate with County, City and Derecktor on access to site and rights of way [4] 12 Scientist IV (SO) Scientist I (DH) Tallahassee Office; Work plan preparation, draft figures, text and tables [12] 12

Engineer I (MQ) Tallahassee Office; Revise, recertify HASP [2] 1

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation, approximately 6 figures with proposed locations and previous results shown [2] 2

TOTAL LABOR 34

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 1 $32.50 Personal Protection (Level D) $28.00 Day 0 $0.00 Total GPS Station $141.65 Each 1 $141.65

TOTAL EQUIPMENT $174.15

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 1 Cocoa to Ft. Pierce, 1 dy $68.00

Subtotal $68.00 Mileage Miles 0

TOTAL VEHICLE $68.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL 0

Scientist V (RH) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (RH) Coordination with Subs, Review field work deliverable [2] 4

Scientist IV (CA) Cocoa Office; ROW permits [4]; Field work (mobs [3 times, 12], uti loc [8], soil borings/splng [20], GPS/TOC svy [4]; 76 well instal [6]; gw splng [12]; gw level meas in all mon wells [2]; field prep, documentation, shipping [4])

Scientist IV (SO) Stuart Office; coordinate logistics for onsite sampling with site manager, site visit to help mark sampling locations 8 Scientist I (DH) Tallahassee office; Field deliverable prep [4] 4

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

TOTAL LABOR 92

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Soil Assessment Kit $208.55 Day 2 $417.10 Monitoring Well Installation Kit $184.30 Day 1 $184.30 Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10 Expendables $32.50 Day 5 $162.50 Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00 Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00 Total Survey Station $41.75 Each 1 $41.75 Peristaltic Pump $29.10 Each 1 Extra pump for well purging $29.10 Hammer Drill $50.95 Each $0.00 MiniRae 3000 PID $87.30 Each Included in MW and Soil kits $0.00 Total GPS Station $141.65 Each 1 Trimble GeoXH $141.65

TOTAL EQUIPMENT $1,393.50

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $420.00 week 1 Staff from Cocoa for field work (6 days) $420.00 Car $68.00 day 2 Staff from Cocoa for utility location and ROW permittin $136.00

Subtotal $556.00 Mileage Miles 0

TOTAL VEHICLE $556.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V $36.00 Day 0 $0.00 Scientist IV (CA) $36.00 Day 5 $180.00 Engineer I $36.00 Day 0 $0.00

HOTEL

Scientist V $120.00 Day 0 $0.00 Scientist IV (CA) $120.00 Day 4 $480.00 Engineer I $120.00 Day 0 $0.00

TOTAL PER DIEM $660.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Metals Liquid 6010-As $11.50 13 4 QA includes 2 GW dup, GW EB, Soil EB $195.50 Nitrate Liquid 353.2 $20.00 1 2 QA includes GW dup, GW EB $60.00 Ammonia Liquid 350.2 $20.00 1 2 QA includes GW dup, GW EB $60.00 TRPH Liquid Florida PRO $84.00 2 2 Based on actual samples collected $336.00 SVOC Liquid 8270 $100.00 $0.00 Mercury Liquid 7470 $23.00 $0.00 Pesticides Liquid 8081 $90.00 $0.00 Metals Soil 6010 -As $11.50 54 6 Based on actual samples collected $690.00 Metals Soil 6010- Pb $11.50 $0.00 Volatile Organics Soil 8260 $135.00 $0.00 TRPH Soil Florida PRO $84.00 19 3 Based on actual samples collected $1,848.00 SVOC Soil 8270 $100.00 $0.00 TRPH Fractionation (see note) Soil TPH-CWG $250.00 $0.00 Pesticides Soil 8081 $90.00 $0.00

Subtotal $3,189.50 Unit Cost Quantity

Sample Containers Lot $0.00 $0.00 Encore Samplers Each $8.75 $0.00 Sample Shipping Coolers $104.00 4 $416.00

Subtotal $416.00 Note: TRPH fractionation rate in attached lab quote. TOTAL LAB $3,605.50

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

Preferred Drilling Solutions Drilling $4,575.00 $4,575.00 GeoTek Utility Locate $1,500 1 $1,500.00

TOTAL $6,075.00

SUBTASK 4: Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) Tallahassee Office; Document review and seal 2 Scientist V (RH) Tallahassee Office; Document review and editing 4

Scientist IV (CA)

Scientist I (DH) 36

Engineer I (MQ)

Staff GIS Specialist (JM) Jacksonville Office; Process GPS data, figure preparation 4

TOTAL LABOR 44

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Site Reconnaissance Kit $81.48 Each 0 $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00

Subtotal $0.00 Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00 Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00 Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00 Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00 TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00 Lead Liquid 6010 $11.50 Standard Turn Around $0.00 Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00 COD Liquid SM5220 $25.00 Standard Turn Around $0.00 BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00 Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00 In-line Filter (0.45 Micron) Each $17.50 $0.00

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Compare onsite and offsite data, calculate background reference levels [20], report prep, tables and draft figs [16]

Date: October 8, 2020

Task #: HW560 TA SubTask 1 Project Management

SubTask 2 Phase II Work Plan

SubTask 3 Fieldwork - Soil and Groundwater Assessment Site: Former King Maritime Group

Activity/Phase: Supplemental Assessment

Project Manager: Megan Johnson SubTask 4 Report

SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$61.82 Project Manager (GW) 13 12.7 1 2 $55.00 Scientist V (RH) 15 7 4 4 0 $43.27 Scientist IV (CA) 88 12 76 0 0 $23.41 Scientist I (DH) 52 12 4 36 0 $26.81 Engineer I (MQ) 1 1 0 0 0 $37.54 Staff GIS Specialist (JM) 6 2 0 4 0

Total Hours 178 13 35 84 46 0

Direct Labor $7,072.70 $785.11 $1,348.87 $3,602.16 $1,336.56 $0.00

Overhead 143.00% $10,113.96 $1,122.71 $1,928.88 $5,151.09 $1,911.28 $0.00 Gen & Admin 12.20% $2,096.78 $232.75 $399.89 $1,067.90 $396.24 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $19,283.44 $2,140.57 $3,677.64 $9,821.15 $3,644.08 $0.00

Other Direct Costs $353.64 $39.26 $67.44 $180.11 $66.83 $0.00 Travel

Vehicle Rental $624.00 $68.00 $556.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $660.00 $0.00 $660.00 $0.00 $0.00 Total Travel $1,284.00 $68.00 $1,216.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Transportation & Disposal $0.00 $0.00 $0.00 $0.00 $0.00 Drilling and Well Installation $5,105.00 $0.00 $5,105.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $1,500.00 $0.00 $1,500.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $6,605.00 $0.00 $6,605.00 $0.00 $0.00 Handling Fee $660.50 $0.00 $660.50 $0.00 $0.00 Total Subcontractor Cost $7,265.50 $0.00 $7,265.50 $0.00 $0.00

Laboratory Laboratory $4,273.50 $0.00 $4,273.50 $0.00 $0.00 Encore Samplers $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $416.00 $0.00 $416.00 $0.00 $0.00 Total Laboratory $4,689.50 $0.00 $4,689.50 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $195.00 $32.50 $162.50 $0.00 $0.00 Equipment (Drilling related) $184.30 $0.00 $184.30 $0.00 $0.00 Equipment (Analytical related) $834.20 $0.00 $834.20 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $354.15 $141.65 $212.50 $0.00 $0.00 Total Field Expenses $1,567.65 $174.15 $1,393.50 $0.00 $0.00

Subtotal $34,443.73 $2,179.83 $3,987.23 $24,565.76 $3,710.91 $0.00 Completion Fee $1,928.35 $214.06 $367.76 $982.12 $364.41 $0.00

Total Estimated Cost $36,372.08 $2,393.89 $4,354.99 $25,547.88 $4,075.32 $0.00

REV: 03/23/17 Page 1

Original Cost Proposal/Level of Effort

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) 1 Scientist V (RH) Tallahassee Office; Develop/review Work Plan [4]; Coordination, teleconference with staff, County and FDEP [3] 7

Scientist IV (CA) Site Recon to identify, mark proposed locations [8], coordinate with County, City and Derecktor on access to site and rights of way [4] 12

Scientist I (DH) Tallahassee Office; Work plan preparation, draft figures, text and tables [12] 12

Engineer I (MQ) Tallahassee Office; Revise, recertify HASP [2] 1

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation, approximately 6 figures with proposed locations and previous results shown [2] 2

TOTAL LABOR 34

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 1 $32.50 Personal Protection (Level D) $28.00 Day 0 $0.00 Total GPS Station $141.65 Each 1 $141.65

TOTAL EQUIPMENT $174.15

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 1 Cocoa to Ft. Pierce, 1 dy $68.00

Subtotal $68.00 Mileage Miles 0

TOTAL VEHICLE $68.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL 0

Scientist V (RH) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (RH) Coordination with Subs, Review field work deliverable [2] 4

Scientist IV (CA) Cocoa Office; ROW permits [4]; Field work (mobs [3 times, 12], uti loc [8], soil borings/splng [20], GPS/TOC svy [4]; 76 well instal [6]; gw splng [12]; gw level meas in all mon wells [2]; field prep, documentation, shipping [4])

Scientist I (DH) Tallahassee office; Field deliverable prep [4] 4

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

TOTAL LABOR 84

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Soil Assessment Kit $208.55 Day 2 $417.10 Monitoring Well Installation Kit $184.30 Day 1 $184.30 Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10 Expendables $32.50 Day 5 $162.50 Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00 Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00 Total Survey Station $41.75 Each 1 $41.75 Peristaltic Pump $29.10 Each 1 Extra pump for well purging $29.10 Hammer Drill $50.95 Each $0.00 MiniRae 3000 PID $87.30 Each Included in MW and Soil kits $0.00 Total GPS Station $141.65 Each 1 Trimble GeoXH $141.65

TOTAL EQUIPMENT $1,393.50

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $420.00 week 1 Staff from Cocoa for field work (6 days) $420.00 Car $68.00 day 2 Staff from Cocoa for utility location and ROW permittin $136.00

Subtotal $556.00 Mileage Miles 0

TOTAL VEHICLE $556.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V $36.00 Day 0 $0.00 Scientist IV (CA) $36.00 Day 5 $180.00 Engineer I $36.00 Day 0 $0.00

HOTEL

Scientist V $120.00 Day 0 $0.00 Scientist IV (CA) $120.00 Day 4 $480.00 Engineer I $120.00 Day 0 $0.00

TOTAL PER DIEM $660.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Metals Liquid 6010-As $11.50 12 4 QA includes 2 GW dup, GW EB, Soil EB $184.00 Nitrate Liquid 353.2 $20.00 1 2 QA includes GW dup, GW EB $60.00 Ammonia Liquid 350.2 $20.00 1 2 QA includes GW dup, GW EB $60.00 TRPH Liquid Florida PRO $84.00 2 5 QA includes 1 GW dup, 1 GW EB, 3 Soil EB $588.00 SVOC Liquid 8270 $100.00 $0.00 Mercury Liquid 7470 $23.00 $0.00 Pesticides Liquid 8081 $90.00 $0.00 Metals Soil 6010 -As $11.50 48 5 QA includes 6 soil dups $609.50 Metals Soil 6010- Pb $11.50 $0.00 Volatile Organics Soil 8260 $135.00 $0.00 TRPH Soil Florida PRO $84.00 30 3 QA includes 3 soil dups $2,772.00 SVOC Soil 8270 $100.00 $0.00 TRPH Fractionation (see note) Soil TPH-CWG $250.00 $0.00 Pesticides Soil 8081 $90.00 $0.00

Subtotal $4,273.50 Unit Cost Quantity

Sample Containers Lot $0.00 $0.00 Encore Samplers Each $8.75 $0.00 Sample Shipping Coolers $104.00 4 priority overnight shipping FedEx $416.00

Subtotal $416.00 Note: TRPH fractionation rate in attached lab quote. TOTAL LAB $4,689.50

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

Preferred Drilling Solutions Drilling $5,105.00 $5,105.00 GeoTek Utility Locate $1,500 1 $1,500.00

TOTAL $6,605.00

SUBTASK 4: Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) Tallahassee Office; Document review and seal 2 Scientist V (RH) Tallahassee Office; Document review and editing 4

Scientist IV (CA)

Scientist I (DH) 36

Engineer I (MQ)

Staff GIS Specialist (JM) Jacksonville Office; Process GPS data, figure preparation 4

TOTAL LABOR 44

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Site Reconnaissance Kit $81.48 Each 0 $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00

Subtotal $0.00 Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00 Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00 Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00 Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00 TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00 Lead Liquid 6010 $11.50 Standard Turn Around $0.00 Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00 COD Liquid SM5220 $25.00 Standard Turn Around $0.00 BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00 Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00 In-line Filter (0.45 Micron) Each $17.50 $0.00

Subtotal $0.00 Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Compare onsite and offsite data, calculate background reference levels [20], report prep, tables and draft figs [16]

From: Johnson, Megan R To: Hicks, Richard Cc: Walker, Gerry; Crain, Kelly Subject: RE: Update on Port of Fort Pierce/King Maritime upcoming field work Date: Wednesday, December 02, 2020 11:00:00 AM Attachments: image001.png

Good morning Rick, Thanks so much for the updates and for checking on adding some hours for Shawn. I spoke with Kelly and that is no problem, we appreciate Shawn’s knowledge of the site and relationship with the site manager. Looking forward to seeing the ROW permit package and hearing any feedback that comes from the Friday site visit. Hope you all had a great Thanksgiving!

Thanks, Megan

Megan R. Johnson Environmental Consultant Brownfields and CERCLA Site Screening Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4535 Tallahassee, FL 32399

Megan.R.Johnson@floridadep.gov Office: 850-245-8994

From: Hicks, Richard <Richard.Hicks@tetratech.com> Sent: Monday, November 30, 2020 12:46 PM To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Cc: Walker, Gerry <Gerry.Walker@tetratech.com>; Crain, Kelly <Kelly.Crain@dep.state.fl.us> Subject: Update on Port of Fort Pierce/King Maritime upcoming field work

Hi Megan. I just wanted to give you a brief update on what’s going on.

-We have a schedule for doing the drilling and sampling work. Drilling and soil sampling will occur on 12/18-19 and we will do the groundwater sampling and surveying early in the following week, week of 12/21.

-Our folks will be onsite this Friday to meet with the site rep at Derektor and do the utility locate work. Chris Adkison of our Cocoa office is going to oversee/conduct the drilling/sampling but I asked Shawn Ouellette from Stuart who did the last phase of sampling to go with Chris for the site visit, to help locate the onsite soil borings and coordinate with the site rep at Derektor. Shawn has a good relationship with the site manager and I didn’t want any hitches to occur in communication when we go into the site to do our work in the construction area. With your permission, I may request adding a few hours for Shawn.

-We will submit our ROW permit package to the City Engineer for locations on City ROW after the utility locate and be ready to go with work on ROWs by 12/18. I will send you a copy of the permit package.

-Also, there are two existing wells at the site that we discovered in a visit a couple of weeks ago that may serve our purposes and allow us to eliminate one of the wells we were planning to install, which would reduce some cost.

Let me know if you have any questions or need other information. Thanks. Have a great week.

Richard Hicks, P. G.

Senior Geoscientist Tetra Tech Inc.

1558 Village Square Boulevard Suite 2 Tallahassee, FL 32309 Office: 850/385-9897 Mobile: 850/509-2720 richard.hicks@tetratech.com