This document is a Task Assignment Change Order (TACO #1) for Contract HW560 between the Florida Department of Environmental Protection (FDEP) and Tetra Tech, Inc. The change order pertains to Task Assignment BF602C for targeted brownfield supplemental site assessment activities at the Port of Fort Pierce (formerly King Maritime Group), located at 101 Port Avenue A, Fort Pierce, Florida 34950, in St. Lucie County. The work is being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement administered by the FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The contract manager for FDEP is Megan Johnson, and the contractor representative is Misty Quandt of Tetra Tech.
The change order documents cost reductions resulting from scope changes that occurred during field work (Subtask 3) for soil and groundwater assessment activities. The original task amount was $50,164.34, which is reduced by $7,694.25 to a new task amount of $42,470.09. Cost reductions include: a $2,178.00 decrease in subcontracted drilling costs due to utilizing one pre-existing monitoring well instead of installing seven new wells; a $5,017.50 decrease in laboratory costs due to fewer soil and groundwater samples collected and reduced quality assurance samples; and a $498.75 decrease from eliminating the need for TerraCore kits for TPH-CWG sample analyses. The change order also extends the final deliverable due date for Subtask 4 (Targeted Brownfield Supplemental Site Assessment Report) from February 25, 2022 to April 15, 2022, and extends the overall period of performance from March 31, 2022 to May 13, 2022, representing a 43-day extension. The invoice schedule establishes three payment milestones: $10,014.85 upon FDEP approval of the QAPP/Work Plan and HASP; $25,371.71 upon approval of field notes and sampling logs; and $7,083.53 upon approval of the final report.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
HW560
1BF602C
Tetra Tech
Misty Quandt Phone #: (850) 536-8116
(850) 245-8994Megan Johnson
Port of Fort Pierce aka: Former King Maritime Group
ERIC_15269
The Department approves this Task Assignment Change Order (TACO) for changes in cost associated with scope changes that occurred during the field work (Subtask 3) These changes include: a decrease in subcontracted drilling cost; a decrease in laboratory cost; and a decrease in number of Encore samples needed. This TACO also serves as a time extension to the final deliverable due date for Subtask 4 - Targeted Brownfield Supplemental Site Assessment Report. This TACO is based upon the delta Level of Effort for soil and groundwater assessment activities, submitted to the Department on March 23, 2022 by Tetra Tech.
Targeted Brownfield Supplemental Site Assessment Report 04/15/2022
$ 50,164.34 $ 0.00 $ 0.00 $ 0.00
$ 50,164.34 $ 0.00 $ 0.00 $ 0.00 $ 50,164.34
($ 7,694.25) $ 0.00 $ 0.00 $ 0.00 ($ 7,694.25)
$ 42,470.09
03/31/2022
03/31/2022
43 days
05/13/2022
Megan R. Johnson Digitally signed by Megan R. Johnson Date: 2022.03.24 10:43:58 -04'00'
Megan R. Johnson Digitally signed by Megan R. Johnson Date: 2022.03.24 10:44:21 -04'00'
Digitally signed by Jennifer Farrell Date: 2022.03.25 11:29:11 -04'00'
Digitally signed by Misty L Quandt:A0109B300000173FC22014B0002F935 Date: 2022.03.28 15:35:40 -04'00'
$ 42,470.09 $ 0.00 $ 0.00 $ 0.00
$ 50,164.34
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
BWC TAFORM 2/03
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW560
BF602C
$ 42,470.09
QAPP/Work Plan and HASP
Field notes, photographic log, chain of custody, soil sampling logs, groundwater sampling logs
Project Management and Targeted Brownfield Supplemental Site Assessment Report
Department approval of QAPP/Work Plan and HASP (Subtask 2)
Department approval of Project Management and Targeted Brownfield Supplemental Site Assessment Report (Subtasks 1 and 4)
Department approval of field notes, photographic log, chain of custody, soil sampling logs, and groundwater sampling logs (Subtask 3)
12/27/2021
01/28/2022
04/15/2022
$ 25,371.71
$ 10,014.85
$ 7,083.53 www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Tetra Tech, Inc., HW560 Contract File
FROM: Megan Johnson, Contract Manager
DATE: March 24, 2022
SUBJECT: Negotiation Summary – SRP18 Grant
Task Assignment (TA) Change Order #1 – TA BF602CC1 Port of Fort Pierce aka: Former King Maritime Group Site ID # ERIC_15269 Targeted Brownfield Supplemental Site Assessment Activities
This Task Assignment Change Order (TACO) is for changes in cost associated with scope changes that occurred during the field work (Subtask 3) These changes include: a decrease in subcontracted drilling cost; a decrease in laboratory cost; and a decrease in number of Encore samples needed. This TACO also serves as a time extension to the final deliverable due date for Subtask 4 - Targeted Brownfield Supplemental Site Assessment Report and a time extension to the overall Period of Performance. This work was conducted at the Port of Fort Pierce aka: Former King Maritime Group site, located at 101 Port Avenue A, Fort Pierce, Florida 34950. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S.
Environmental Protection Agency (EPA).
Subtask 1: Project Management This TACO does not include any costs changes associated with this Subtask.
Subtask 2: QAPP/Work Plan and HASP This TACO does not include any costs changes associated with this Subtask.
Subtask 3: Targeted Brownfield Supplemental Site Assessment Activities Following the scoping site reconnaissance, it was decided to incorporate one pre-existing monitoring well into the groundwater monitoring network. This reduced the number of new monitoring wells from seven to six, reducing the subcontractor drilling costs, including the handling fee, by ($2,178.00).
Due to many areas of pavement which prevented the collection of surface soil samples and the presence of buried utilities or other obstructions at several of the pre-selected sampling locations, there was a reduction in soil samples collected. Due to a laboratory error, all samples for TPH-CWG analyses exceeded their holding time and were analyzed http://www.floridadep.gov/
Negotiation Summary – Task Assignment Change Order #1 TA BF602CC1 Port of Fort Pierce aka: Former King Maritime Group
ERIC_15269
March 24, 2022 www.FloridaDEP.gov by the laboratory at no cost. There were also fewer groundwater samples collected than originally scoped. Reductions in samples resulted in corresponding reductions in the number of QA samples required. This resulted in a decrease of ($5,017.50) for laboratory costs.
Previously TerraCore kits were needed for TPH-CWG samples. The laboratory no longer needs to use TerraCore kits for these analyses, therefore the cost of these kits, ($498.75), was removed.
The above changes resulted in a decrease of ($7,694.25) for this Subtask.
Subtask 4: Targeted Brownfield Supplemental Site Assessment Report Included in this TACO is a deliverable due date time extension for this Subtask. This TACO does not include any costs changes associated with this Subtask.
Summary The Department’s SRP Contract Manager and Tetra Tech’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost decrease of ($7,694.25). The changes were noted in the TACO Request received from Tetra Tech, Inc. on March 23, 2022. The final cost associated with this TA decreased from $50,164.34 to $42.470.09. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, the subcontractor invoice, the laboratory chains of custody and sample receipts, and the TACO Form for BF602CC1 prepared by the Department. The final deliverable for Subtask 4 – Targeted Brownfield Supplemental Site Assessment Report, must be received by the Department no later than April 15, 2022.
http://www.floridadep.gov/
Tetra Tech, Inc.
1558 Village Square Blvd., Ste. 2, Tallahassee, FL 32309-2478 Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com
TetraTech/TAL-22-06-112IC09660
March 22, 2022
Department of Environmental Protection Waste Cleanup Programs ATTN: Ms. Megan Johnson MS #4535 Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Reference: Florida Department of Environmental Protection (DEP) Waste
Cleanup Programs Consolidated Contract HW560
Subject: Change Order Request – Phase 3, Targeted Brownfield Assessment at Former King Maritime Group (AKA: Port of Fort Pierce), Fort Pierce, St. Lucie County, Florida
Dear Ms. Johnson:
Tetra Tech is providing this change order request to the Florida Department of Environmental Protection (FDEP) to document changes in cost associated with scope changes that occurred during the field work (Subtask 3) for the third phase of Targeted Brownfield Assessment activities at the Former King Maritime Group Site at 101 Port Avenue A, Fort Pierce, Florida. We are also requesting a time extension for completion of the final report (Subtask 4) in this change order.
The scope changes necessitating the change order are described below and in the attached Change Order and Change Order Delta workbooks.
Subtask 1 - Project Management: No changes.
Subtask 2 - Work Plan & Health and Safety Plan (HASP): No changes.
Subtask 3 – Soil Sampling, Well Installation, and Groundwater Sampling:
A. Decrease in subcontracted drilling cost. One pre-existing monitoring well was incorporated into the groundwater monitoring network, which reduced the number of new wells from seven (7) to six (6). This reduced the drilling cost by $1,980.00. The invoice from the drilling subcontractor is attached.
B. Decrease in laboratory cost. Fewer samples were collected than those included in the original cost proposal. This was due to a decrease in the number of soil, water and QA samples actually collected or analyses invoiced by the laboratory. The reduction in soil samples was due to the many areas of pavement which prevented the collection of surface soil samples and the presence of buried utilities or other obstructions at several of the pre-selected sampling locations. All samples for TPH-CWG analyses exceeded holding time due to a laboratory error and were analyzed at no cost. Also, fewer groundwater samples were collected than were included in the original TA cost proposal. Reductions in samples resulted in corresponding reductions in the number of QA samples required. The changes in numbers of samples and resulting cost difference are shown in the Change Order Delta LOE 3 Worksheet. Actual samples collected are documented in the attached copies of the sample “Chains of Custody and sample receipts.
C. Decrease in number of Encore samples needed. Previously TerraCore kits were needed for TPH-CWG samples. The laboratory no longer needs to use TerraCore kits for these analyses, therefore this cost was removed from the project.
Subtask 4 - Report: Due to drilling subcontractor scheduling issues, the field work was conducted approximately four weeks later than anticipated in the original schedule for the task assignment.
Tetra Tech requests a change in the final deliverable due date from February 25, 2022 to April 15, 2022. Tetra Tech requests a change in the period of performance date from March 31, 2022 to May 13, 2022.
Change Order Amount These changes result in a $7,694.25 reduction in cost for this task assignment. The requested new task assignment amount is $42,470.09
If you have any questions, please call myself or Richard Hicks (850) 385-9899.
Sincerely yours, Misty Quandt Project Manager rh/MLQ
Attachments c: Kelly Crain, FDEP Justin Cross, FDEP
Richard Hicks, Tetra Tech Shawn Oullette, Tetra Tech
Tallahassee File FDEP Contract HW560
Attachment A
Contract HW560 Cost Estimate Spreadsheets and Backup
Documentation
FDEP COST ESTIMATE
Contractor: Tetra Tech, Inc.
Date: March 22, 2022
Task #: HW560 BF602C TACO1 SubTask 1 Project Management
Site: Former King Maritime Group SubTask 2 Work Plan & HASP
Activity/Phase: Phase 3 Assessment SubTask 3 Fieldwork - Soil and Groundwater Assessment
Project Manager: M Johnson FDEP/R Hicks Tetra Tech SubTask 4 Report
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$61.82 Project Manager (GW) 0 0.0
$55.00 Scientist V (RH) 0 0 0 0 0
$48.08 Scientist IV (SO) 0 0 0 0 0
$32.19 Scientist II (JE) 0 0 0 0 0
$26.81 Engineer I (MQ) 0 0 0 0 0
$42.15 Sr GIS Specialist (LL) 0 0 0 0 0$0.00 Engineer I 0$0.00 Engineer II 0$0.00 Engineer III 0$0.00 Engineer V 0$0.00 00 0 0 0 0
Total Hours 0 0 0 0 0 0
Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 143.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Gen & Admin 12.20% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Transportation & Disposal $0.00 $0.00 $0.00 $0.00 $0.00
Drilling and Well Installation ($1,980.00) $0.00 ($1,980.00) $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal ($1,980.00) $0.00 ($1,980.00) $0.00 $0.00
Handling Fee ($198.00) $0.00 ($198.00) $0.00 $0.00
Total Subcontractor Cost ($2,178.00) $0.00 ($2,178.00) $0.00 $0.00
Laboratory
Laboratory ($5,017.50) $0.00 ($5,017.50) $0.00 $0.00
Encore Samplers ($498.75) $0.00 ($498.75) $0.00 $0.00
Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00
Total Laboratory ($5,516.25) $0.00 ($5,516.25) $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal ($7,694.25) $0.00 $0.00 ($7,694.25) $0.00 $0.00
Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost ($7,694.25) $0.00 $0.00 ($7,694.25) $0.00 $0.00
REV: 03/23/17 Page 1
Delta
SITE :
SUBTASK 2: Work Plan & HASP
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Tallahassee Office; Review Work Plan and HASP[2]; Coordination [3] 0
Scientist IV (SO) Stuart Office; Site visits (3, including mobe/demobe) [20], ROW permit [8] 0
Scientist II (JE) Stuart Office; Site visit (including mobe/demobe) [8] 0
Engineer I (MQ) Tallahassee Office; Prepare Draft, Final Work Plan [16], coordinate public utility locates [2], update HASP [2] 0
Sr GIS Specialist (LL) Figure preparation for work plan [4] 0
TOTAL LABOR 0
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Total GPS Station $141.65 Each 0 $0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 Stuart, 3 dys $0.00
Subtotal $0.00
Mileage Miles 0
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00
HOTEL 0
Scientist V (RH) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Subtotal $0.00 Unit Cost Quantity
Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
GeoTek utility locator $0.00
TOTAL $0.00
Former King Maritime Group
SUBTASK 3: Fieldwork - Soil and Groundwater Assessment
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Review field work deliverable [1] 0
Scientist IV (SO) Stuart Office; Field work mobilization (2=2hr/trip x 1), drilling oversight [8], field deliverable [4] 0
Scientist II (JE) Stuart Office; Field work (mobilization [14=2 hr/trip x 7], soil sampling [18], well instal and dev [12], groundwater sampling [14], 0 site restoration [2], water levels and survey [6], sample handling and shipping [2]
Engineer I (MQ) 0
Sr GIS Specialist (LL) 0
$0.00 0
TOTAL LABOR 0
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Soil Assessment Kit $208.55 Day 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00 Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00 Total Survey Station $41.75 Each 0 $0.00 Peristaltic Pump $29.10 Each 0 Extra pump for well purging $0.00 Hammer Drill $50.95 Each $0.00 MiniRae 3000 PID $87.30 Each 0 Included in MW and Soil kits $0.00 Total GPS Station $141.65 Each 0 Trimble GeoXH $0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $420.00 week 0 Staff members from Stuart (7 days) $0.00 Car $68.00 day 0 $0.00
Subtotal $0.00
Mileage Miles 0
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
Scientist V (RH) $36.00 Day 0 $0.00 Scientist $36.00 Day 0 $0.00 Engineer I $36.00 Day 0 $0.00
HOTEL
Scientist V (RH) $120.00 Day 0 $0.00 Scientist $120.00 Day 0 $0.00 Engineer I $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Metals Liquid 6010-As $11.50 -4 -4 based on actual samples collected ($92.00)
Metals Liquid 6010-Pb $11.50 $0.00
Volatile Organics Liquid 8260 $135.00 $0.00
TRPH Liquid Florida PRO $84.00 0 3 s eb $0.00
SVOC Liquid 8270 $100.00 $0.00
Mercury Liquid 7470 $23.00 $0.00
Pesticides Liquid 8081 $90.00 $0.00
Metals Soil 6010 -As $11.50 -20 -1 20 fewer samples collected, 1 fewer dup -$241.50
Metals Soil 6010- Pb $11.50 $0.00
Volatile Organics Soil 8260 $135.00 $0.00
TRPH Soil Florida PRO $84.00 -24 -2 24 fewer samples collected, 2 fewer dups ($2,184.00)
SVOC Soil 8270 $100.00 $0.00
TRPH Fractionation (see note) Soil TPH-CWG $250.00 -10 0 holding times exceeded, no charge for analysis ($2,500.00)
Pesticides Soil 8081 $90.00 $0.00 Subtotal ($5,017.50)
Unit Cost Quantity Sample Containers Lot $0.00 0 0 $0.00 Encore Samplers Each $8.75 -57 no Terracore kits needed ($498.75) Sample Shipping Coolers $104.00 0 priority overnight shipping FedEx $0.00
Subtotal ($498.75) Note: TRPH fractionation rate in attached lab quote. TOTAL LAB ($5,516.25)
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
Preferred Drilling Drilling $8,735.00 1 Fewer wells installed due to utilizing existing wells ($1,980.00)
TOTAL ($1,980.00)
LEVEL OF EFFORT/EXPENSE WORKSHEET
SUBTASK 4: Report
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Tallahassee Office; Document review and editing 0
Scientist IV (SO)
Scientist II (JE)
Engineer I (MQ) 0
Sr GIS Specialist (LL) Jacksonville Office; Process GPS data, figure preparation 0
TOTAL LABOR 0
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Site Reconnaissance Kit $81.48 Each 0 $0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00
Subtotal $0.00
Mileage Miles 0
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00
HOTEL
Scientist III (WO) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00
Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00
Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00
Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00
TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00
Lead Liquid 6010 $11.50 Standard Turn Around $0.00
Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00
COD Liquid SM5220 $25.00 Standard Turn Around $0.00
BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00
Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00
In-line Filter (0.45 Micron) Each $17.50 $0.00 Subtotal $0.00
Unit Cost Quantity Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
TOTAL $0.00
Former King Maritime Group
Tallahassee Office; Draft and Final report preparation; description of field activities, summary of results, tables of soil and groundwater results, figures showing soil and groundwater locations and results and groundwater flow direction
REV: 03/23/17 Page 2
FDEP COST ESTIMATE
Contractor: Tetra Tech, Inc.
Date: March 22, 2022
Task #: HW560 BF602C TACO1 SubTask 1 Project Management
Site: Former King Maritime Group SubTask 2 Work Plan & HASP
Activity/Phase: Phase 3 Assessment SubTask 3 Fieldwork - Soil and Groundwater Assessment
Project Manager: M Johnson FDEP/R Hicks Tetra Tech SubTask 4 Report
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$61.82 Project Manager (GW) 14 13.9
$55.00 Scientist V (RH) 10 5 1 4 0
$48.08 Scientist IV (SO) 42 28 14 0 0
$32.19 Scientist II (JE) 74 8 66 0 0
$26.81 Engineer I (MQ) 60 20 0 40 0
$42.15 Sr GIS Specialist (LL) 8 4 0 4 0$0.00 Engineer I 0$0.00 Engineer II 0$0.00 Engineer III 0$0.00 Engineer V 0$0.00 00 0 0 0 0
Total Hours 208 14 65 81 48 0
Direct Labor $7,759.37 $862.15 $2,583.56 $2,852.66 $1,461.00 $0.00
Overhead 143.00% $11,095.89 $1,232.87 $3,694.49 $4,079.30 $2,089.23 $0.00
Gen & Admin 12.20% $2,300.34 $255.59 $765.92 $845.70 $433.13 $0.00
Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $21,155.60 $2,350.61 $7,043.97 $7,777.66 $3,983.36 $0.00
Other Direct Costs $387.97 $43.11 $129.18 $142.63 $73.05 $0.00
Travel
Vehicle Rental $624.00 $204.00 $420.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $624.00 $204.00 $420.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Transportation & Disposal $0.00 $0.00 $0.00 $0.00 $0.00
Drilling and Well Installation $8,735.00 $0.00 $8,735.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $1,500.00 $1,500.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $10,235.00 $1,500.00 $8,735.00 $0.00 $0.00
Handling Fee $1,023.50 $150.00 $873.50 $0.00 $0.00
Total Subcontractor Cost $11,258.50 $1,650.00 $9,608.50 $0.00 $0.00
Laboratory
Laboratory $4,211.00 $0.00 $4,211.00 $0.00 $0.00
Encore Samplers $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $520.00 $0.00 $520.00 $0.00 $0.00
Total Laboratory $4,731.00 $0.00 $4,731.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $195.00 $0.00 $195.00 $0.00 $0.00
Equipment (Drilling related) $184.30 $0.00 $184.30 $0.00 $0.00
Equipment (Analytical related) $1,042.75 $0.00 $1,042.75 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) $775.40 $283.30 $492.10 $0.00 $0.00
Total Field Expenses $2,197.45 $283.30 $1,914.15 $0.00 $0.00
Subtotal $40,354.52 $2,393.72 $9,310.45 $24,593.94 $4,056.41 $0.00
Completion Fee $2,115.57 $235.06 $704.40 $777.77 $398.34 $0.00
Total Estimated Cost $42,470.09 $2,628.78 $10,014.85 $25,371.71 $4,454.75 $0.00
REV: 03/23/17 Page 1
Cost Actual
SUBTASK 2: Work Plan & HASP
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Tallahassee Office; Review Work Plan and HASP[2]; Coordination [3] 5
Scientist IV (SO) Stuart Office; Site visits (3, including mobe/demobe) [20], ROW permit [8] 28
Scientist II (JE) Stuart Office; Site visit (including mobe/demobe) [8] 8
Engineer I (MQ) Tallahassee Office; Prepare Draft, Final Work Plan [16], coordinate public utility locates [2], update HASP [2] 20
Sr GIS Specialist (LL) Figure preparation for work plan [4] 4
TOTAL LABOR 65
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Total GPS Station $141.65 Each 2 $283.30
TOTAL EQUIPMENT $283.30
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 3 Stuart, 3 dys $204.00
Subtotal $204.00
Mileage Miles 0
TOTAL VEHICLE $204.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
Scientist V (RH) $36.00 Day 0 $0.00 Engineer I (MQ) $36.00 Day 0 $0.00
HOTEL 0
Scientist V (RH) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Subtotal $0.00 Unit Cost Quantity
Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
GeoTek utility locator $1,500.00
TOTAL $1,500.00
SUBTASK 3: Fieldwork - Soil and Groundwater Assessment
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Review field work deliverable [1] 1
Scientist IV (SO) Stuart Office; Field work mobilization (2=2hr/trip x 1), drilling oversight [8], field deliverable [4] 14
Scientist II (JE) Stuart Office; Field work (mobilization [14=2 hr/trip x 7], soil sampling [18], well instal and dev [12], groundwater sampling [14], 66 site restoration [2], water levels and survey [6], sample handling and shipping [2]
Engineer I (MQ) 0
Sr GIS Specialist (LL) 0
$0.00 0
TOTAL LABOR 81
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Soil Assessment Kit $208.55 Day 3 $625.65 Monitoring Well Installation Kit $184.30 Day 1 $184.30 Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10 Expendables $32.50 Day 6 $195.00 Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00 Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00 Total Survey Station $41.75 Each 7 $292.25 Peristaltic Pump $29.10 Each 2 Extra pump for well purging $58.20 Hammer Drill $50.95 Each $0.00 MiniRae 3000 PID $87.30 Each 0 Included in MW and Soil kits $0.00 Total GPS Station $141.65 Each 1 Trimble GeoXH $141.65
TOTAL EQUIPMENT $1,914.15
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $420.00 week 1 Staff members from Stuart (7 days) $420.00 Car $68.00 day 0 $0.00
Subtotal $420.00
Mileage Miles 0
TOTAL VEHICLE $420.00
Scientist $36.00 Day 0 $0.00 Engineer I $36.00 Day 0 $0.00
HOTEL
Scientist V (RH) $120.00 Day 0 $0.00 Scientist $120.00 Day 0 $0.00 Engineer I $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Metals Liquid 6010-As $11.50 16 3 2 gw dups, 1 gw eb, 4 s ebs $218.50
Metals Liquid 6010-Pb $11.50 $0.00
Volatile Organics Liquid 8260 $135.00 $0.00
TRPH Liquid Florida PRO $84.00 3 3 s eb $252.00
SVOC Liquid 8270 $100.00 $0.00
Mercury Liquid 7470 $23.00 $0.00
Pesticides Liquid 8081 $90.00 $0.00
Metals Soil 6010 -As $11.50 49 6 7 dups $632.50
Metals Soil 6010- Pb $11.50 $0.00
Volatile Organics Soil 8260 $135.00 $0.00
TRPH Soil Florida PRO $84.00 33 4 6 dups $3,108.00
SVOC Soil 8270 $100.00 $0.00
TRPH Fractionation (see note) Soil TPH-CWG $250.00 0 0 69 spls collected, est 10 spls analyzed, no QA $0.00
Pesticides Soil 8081 $90.00 $0.00 Subtotal $4,211.00
Unit Cost Quantity Sample Containers Lot $0.00 0 0 $0.00 Encore Samplers Each $8.75 0 TerraCore kits (1 per TRPH CWG spl collected) $0.00 Sample Shipping Coolers $104.00 5 priority overnight shipping FedEx $520.00
Subtotal $520.00 Note: TRPH fractionation rate in attached lab quote. TOTAL LAB $4,731.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
Preferred Drilling Drilling $8,735.00
TOTAL $8,735.00
LEVEL OF EFFORT/EXPENSE WORKSHEET
SUBTASK 4: Report
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (RH) Tallahassee Office; Document review and editing 4
Scientist IV (SO)
Scientist II (JE)
Engineer I (MQ) 40
Sr GIS Specialist (LL) Jacksonville Office; Process GPS data, figure preparation 4
TOTAL LABOR 48
FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS
Equipment Hand Auger $8.25 Each 0 $0.00 Monitoring Well Installation Kit $184.30 Day 0 $0.00 Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00 Expendables $32.50 Day 0 $0.00 Personal Protection (Level D) $28.00 Day 0 $0.00 Site Reconnaissance Kit $81.48 Each 0 $0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
Air Fare $0.00 Each 0 $0.00 Van/Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00
Subtotal $0.00
Mileage Miles 0
TOTAL VEHICLE $0.00
Engineer I (MQ) $36.00 Day 0 $0.00
HOTEL
Scientist III (WO) $120.00 Day 0 $0.00 Engineer I (MQ) $120.00 Day 0 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER Media Method RATE # SAMPLES #QAQC Analysis
Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00
Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00
Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00
Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00
TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00
Lead Liquid 6010 $11.50 Standard Turn Around $0.00
Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00
COD Liquid SM5220 $25.00 Standard Turn Around $0.00
BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00
Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00
In-line Filter (0.45 Micron) Each $17.50 $0.00 Subtotal $0.00
Unit Cost Quantity Sample Containers Lot $0.00 0 $0.00 Encore Samplers Each $8.75 0 $0.00 Sample Shipping Coolers $104.00 0 $0.00
Subtotal $0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST Units
TOTAL $0.00
Tallahassee Office; Draft and Final report preparation; description of field activities, summary of results, tables of soil and groundwater results, figures showing soil and groundwater locations and results and groundwater flow direction
REV: 03/23/17 Page 2
)*+,-./01-+012341+Original
�Yí����b�íõ�S�ø���ðV���ñ �5��õ��öõ�̂ !��õí�T̂ !6 7�!̂ hY���íY���!�_bY!���#̂ !��õ�����!�̂ �'@FHH?@k@P' Z80I/(''50k7@k89 f8:0' �ò�î ï��ï�h�%!�& íñ��ñóñ��îî�̂���òîa�!î��îR���ðV���ñ �ñ "��õ��;ø<a����ð"� ñï�� �ò�î ï��ï�Yh�%�̂ & �ï�ñðï�̂���òîa���ïî�����ï��%� ò��"� ���� îô"î�� î&�;øû< �!̂ ���îð��ï�;]< ø] �ò�î ï��ï�YY�%��& �ï�ñðï�̂���òîa���ïî�����ï�%� ò��"� ���� îô"î�� î&�;]< ] îîð�Y�%�_& íñ��ñóñ��îî�̂���òîa��ðî�ñðî��ðñ�ï ñ����ðV���ñ �;ùú< �ò��ð"� ñïî��� ��ò��ï���ïU���òñïî��;ø< ���"ñïî��õ���;ø< øû �ð�TY����îò�ñ���ï�%öö& #���ðî��ðî�ñðñï�� ���ð�R�ðV���ñ
@8@FP/PFB80 ú�#Y�ö���������� k@'J 0F@' 58'@k9K/:9k@ :'FK' @8@FP'�X����î ï�ñ "�õ��îð �]�ø� �ñòó û �û�ûû�� �ï�ð� ���î���Y �ïñ��ñï�� �S�ï �ù]���û �ñU û �û�ûû�óñ���R�Tð�� "Rñïîð��ñ���� ��S�ï �øû]��� �ñU û �û�ûû�W�î "ñ �î� ��ø��û �ñU û �û�ûû�îð�� ñ���ð�ïîòï�� �%öî�î���& �ø]�ûû �ñU û �û�ûûí�ïñ��T����ïñï�� �ù�ù�ú� �ñòó ø �ø]���û@8@FP/'=:k7J'9@ �ø]���ûh��Y�ö� @>7' 0F@' :9k@ :'FK'õ�ð�#ñðî �û�ûû �ñòó û �û�ûûhñ ôíð�òV �$\�ûû "ñU û �û�ûû�ñð �ú]�ûû "ñU � �ï�ñðï ���"U� �øû��ûû�� ï�ïñ� �øû��ûû���îñ�î ���î� û @8@FP/?'fk5P' �øû��ûû��!��Y�� '@FHH 0F@' :9k@ :'FK' ��õö��ò�î ï��ï�h�%!�& ��ú�ûû �ñU û �û�ûû� îîð�Y�%�_& ��ú�ûû �ñU û �û�ûû�̂ í�ö û�ò�î ï��ï�h�%!�& �ùøû�ûû �ñU û �û�ûû� îîð�Y�%�_& �ùøû�ûû �ñU û �û�ûû
@8@FP/7'0/(k'J �û�ûûöõ�̂ !õí̂ !6��̂ �í�7F0FJ'@'0 J+42: J+-=64 0F@' @/'FJ7P'' @=F=5 FD:;Q323
�� ï�ïñ� �û�ûû:D2- 563- =(:D-2-Q�ñ���î��� ïñ� îð� ö�ï �û�ûû û �û�ûû� ò�ðî��ñ���îð� �ñòó �]�\� û �û�ûû�ñ���î��ó���� � ����îð� �ùû��ûû û �û�ûû�� ï�ïñ� �û�ûû@8@FP/PFB �û�ûû�b��̂ �í!õ�í̂ !��̂ �í�9FJ' 7:078'' 58'@ /:D2-3Tî�íîV �ï���ïU���òñï�ð �ù �ûû�ûû @8@FP �ù �ûû�ûû
#�ð�îð�S� ���ñð�ï��î�Tð��� ù
�Yí����b�íõ�S���#�î�"R�ðV�÷������ñ "�Tð�� "Rñïîð�õ��î���î ïöõ�̂ !��õí�T̂ !6 7�!̂ hY���íY���!�_bY!���#̂ !��õ�����!�̂ �'@FHH?@k@P' Z80I/(''50k7@k89 f8:0' �ò�î ï��ï�h�%!�& !î��îR���î�"�R�ðV�"î���îðñ �î�;ù< ù �ò�î ï��ï�Yh�%�̂ & �ï�ñðï�̂���òîa�#�î�"�R�ðV��� ��� ñï�� �%øAøóðôïð���W�ù& �"ð���� ����îð���óï�;]< ���î�"�"î���îðñ �î�;�< ù� �ò�î ï��ï�YY�%��& �ï�ñðï�̂���òîa�#�î�"�R�ðV�%�� ��� ñï�� �;ù�Aø�óðôïð���W�\< �������ñ���� ��;ù]< �Rî���� �ïñ��ñ "�"î��;ùø< ��ð�� "Rñïîð��ñ���� ��;ù�< úú��ïî�ðî�ï�ðñï�� �;ø< �Rñïîð��î�î���ñ "���ð�îU�;ú< ��ñ���î�óñ ��ñ "��ó���� ��;ø<� îîð�Y�%�_& û �ð�TY����îò�ñ���ï�%öö& û
�û�ûû û@8@FP/PFB80 ]ù#Y�ö���������� k@'J 0F@' 58'@k9K/:9k@ :'FK' @8@FP'�X����î ï�����õ��î���î ï�S�ï �øû]��� �ñU � �úø��ú��� �ï�ð� ���î���Y �ïñ��ñï�� �S�ï �ù]���û �ñU ù �ù]���û�óñ���R�Tð�� "Rñïîð��ñ���� ��S�ï �øû]��� �ñU ø ��ù\�ùû�W�î "ñ �î� ��ø��û �ñU ú �ù$��ûû�îð�� ñ���ð�ïîòï�� �%öî�î���& �ø]�ûû �îð��îð�� �W��ñU û �û�ûûíî��� �í� � ��%ùô�÷� òó�"�ñ�îïîð& �ù�$� #��ï û �û�ûûí�ïñ����ð�îU��ïñï�� ��ù�\� �ñòó \ �ø$ø�ø��îð��ïñ�ï�ò����� �ø$�ùû �ñòó ø �Wïðñ��������ð�Rî�����ð�� � ��]�øû�ñ��îð��ð��� ��û�$� �ñòó �û�ûû�� �!ñî��ûûû��Y� �]\��û �ñòó û Y ò��"î"�� �����ñ "�������V�ï� �û�ûûí�ïñ��T����ïñï�� �ù�ù�ú� �ñòó ù íð�� �î�Tî��� �ù�ù�ú�@8@FP/'=:k7J'9@ �ù $ù��ù�h��Y�ö� @>7' 0F@' :9k@ :'FK'õ�ð�#ñðî �û�ûû �ñòó û �û�ûûhñ ôíð�òV ��øû�ûû RîîV ù �ïñ����î� îð���ð����ï�ñðï�%\�"ñU�& ��øû�ûû�ñð �ú]�ûû "ñU û �û�ûû�� ï�ïñ� ��øû�ûû���îñ�î ���î� û @8@FP/?'fk5P' ��øû�ûû��!��Y�� '@FHH 0F@' :9k@ :'FK' ��õö��ò�î ï��ï�h�%!�& ��ú�ûû �ñU û �û�ûû�ò�î ï��ï� ��ú�ûû �ñU û �û�ûû� îîð�Y�� ��ú�ûû �ñU û �û�ûû�̂ í�ö�ò�î ï��ï�h�%!�& �ùøû�ûû �ñU û �û�ûû�ò�î ï��ï� �ùøû�ûû �ñU û �û�ûû� îîð�Y� �ùøû�ûû �ñU û �û�ûû
@8@FP/7'0/(k'J �û�ûûöõ�̂ !õí̂ !6��̂ �í�7F0FJ'@'0 J+42: J+-=64 0F@' @/'FJ7P'' @=F=5 FD:;Q323�îïñ�� ö�X��" úûùû÷õ� �ùù��û øû \ ø��R�"��� �ù��R�î
| �����î | � ��ùû��û�îïñ�� ö�X��" úûùû÷� | �ùù��û �û�ûûh��ñï��î�̂ð�ñ |
| �ò� ö�X��" ]øúû �ù���ûû �û�ûûí!��� ö�X��" #��ð�"ñ��!̂ �]��ûû � �����î | �ø�ø�ûû�ĥ � ö�X��" ]ø\û �ùûû�ûû �û�ûû�îðò�ðU ö�X��" \�\û �ø��ûû �û�ûû�î�ï�ò�"î� ö�X��" ]û]ù �$û�ûû �û�ûû�îïñ�� ���� úûùû�÷õ� �ùù��û ú$ \ \�"��� �]\��ûû�îïñ�� ���� úûùû÷�� | �ùù��û �û�ûûh��ñï��î�̂ð�ñ |
�ò� ���� ]øúû �ù���ûû �û�ûûí!��� ���� #��ð�"ñ��!̂ �]��ûû �\ ú ú�"��� �� ø$ø�ûû�ĥ � ���� ]ø\û �ùûû�ûû �û�ûûí!���#ðñòï�� ñï�� �%�îî� �ïî& ���� í��÷��T �ø�û�ûû ùû û ú$������ò���îòïî" �î�ï�ùû������ñ ñ�U î" ��_õ� �ø �ûû�ûû�î�ï�ò�"î� ���� ]û]ù �$û�ûû �û�ûû�� ï�ïñ� �$ øø]��û:D2- 563- =(:D-2-Q�ñ���î��� ïñ� îð� ö�ï �û�ûû û û �û�ûû� ò�ðî��ñ���îð� �ñòó �]�\� �\ íîððñ��ðî�V�ï��%ù��îð�í!�����T�����ò���îòïî"& ��$]�\��ñ���î��ó���� � ����îð� �ùû��ûû � �ð��ð�ïU���îð ��óï��ó���� ��#î"�W ��øû�ûû�� ï�ïñ� �ù ûù]�\���ïî��í!����ðñòï�� ñï�� �ðñïî�� �ñïïñòóî"��ñ �X��ïî� @8@FP/PFB �ùû ø�\�ø��b��̂ �í!õ�í̂ !��̂ �í�9FJ' 7:078'' 58'@ /:D2-3 �ðî�îððî"��ð���� � �ð���� � �ùû \ù��ûû
@8@FP �ùû \ù��ûû
#�ð�îð�S� ���ñð�ï��î�Tð��� ù
BCDCBEFGECGGFHIJCKLCMNCEOFHPNQCCI
RSTUVWRXYTZR[V\W]̂ _̀abcZYd]VeZTUfd]g hi]djSkUVTSlUV]UmXS]UkVnd]VUZeoViU]Rdpqrstturvrwx yz{|}~xq�{v�rvz� �z�{q
R��̂�b��bVjV�]o� T��������̂ V̂d����̂�Vk̀ ���̂ �bVâ��̂�V���V̂��b��� \ R��̂�b��bVSjV�Rd� R��̂�b��bVSSV��U� U����̂ âVSV�lm� \� RaVfSRVR_̂������bV�cc� �����̀�����̂Vd����̂�Vià�̂��VfiRV��b��V����âV_â_�a�b�̀�V \ rzrsw}ws�z{ \�nSUckVU�iUpRUR vrx� {srx �zqrv��}��vr �qs�x rzrswqU���_�̂ �bo���VZ��̂a �� ¡¢ U��� � �� ��l̀ ��b̀a���V£ �̂�VS��b����b�̀�V[�b �¤�\ ¥� k�¦ � �� ��R����̀�Vfà�����b̂aVR��_����V[�b �¡�� ¢¢ k�¦ � �� ��U§_̂���̈�̂� �¥¡ ¢� k�¦ � �� ��îa�̀���Viàb̂�b�̀�V�ĉ�̂�Vk� �¡� �� k�¦ � �� ��R�b̂V]̂ �̀���������̂V[�b ��¤ \� U��� � �� ��rzrsw}x©�v��x�r �� ��jUoSecU rª�x {srx ��vr �qs�xZ�aVn�â �� �� U��� � �� ��j��«Ta��� �¬ �� ��¦ � �� ��e�a �®� �� ��¦ � �� ��R�̈b̀b�� �� ��l��̂��̂ l��̂� � rzrsw}̄x�v�wx �� ��iU]VkSUl qrstt {srx ��vr �qs�x lUZcRR��̂�b��bVjV�]o� �¥® �� k�¦ � �� ��U����̂ âVSV�lm� �¥® �� k�¦ � �� ��odTUcR��̂�b��bVSSSV�£d� �¤¡� �� k�¦ � �� ��U����̂ âVSV�lm� �¤¡� �� k�¦ � �� �� rzrsw}�x{}~vx� �� ��cZYd]ZTd]gVedRTR�s{s�xrx{ �°±²³ �°́µ¶± {srx ·}qs��wxq ·©s©� ş ³¹º»²»j̀��b��̂� c����� �¡®� �¤¥¢ �� Rb����a�VT�a�VZà��� �� ��R̂���̀��b��̂� c����� �¡� �¤�� �� Rb����a�VT�a�VZà��� �� ��î�b����̂� c����� ���¤ �¬� �� Rb����a�VT�a�VZà��� �� ��ô ä����̂� c����� �¤¢¤ �¤¢� �� Rb����a�VT�a�VZà��� �� ��T]ioV c����� n�̀a���Vi]d ��\ �� Rb����a�VT�a�VZà��� �� ��ĉ�� c����� ®�¤� �¤¤ ¢� Rb����a�VT�a�VZà��� �� ��T̀b��Vk���̀��̂�Vn̂V���Vl� c����� ®�¤� �¡¥ �� Rb����a�VT�a�VZà��� �� ��edk c����� Rl¢¡¡� �¡¢ �� Rb����a�VT�a�VZà��� �� ��YdkV�¢V��¦� c����� Rl¢¡¤� �¡¢ �� Rb����a�VT�a�VZà��� �� ��l̂ b���̂«ed¡«�¡ c����� ¥�¤� �¤¤� �� Rb����a�VT�a�VZà��� �� ��S�¼���̂Vn��b̂aV�� \¢Vl��à�� U��� �¤ ¢� �� ��R�̈b̀b�� �� ���̧ ²́ �¶»́ ©½³̧ ²́́ºR��_�̂Vè �b���̂a� c̀b �� �� � �� ��U��̀âVR��_�̂a� U��� �� ¢ � �� ��R��_�̂VR��__��� è �̀̂a� �¤�\ �� � �� ��R�̈b̀b�� �� ��rzrsw}ws� �� ��RXYedpT]ZeTd]VedRTR�s�x ��{�zqx �zqr }�̧ ²́» rzrsw �� �� ǹa�̂ aV[���Vl�a�b��̂ Vfà�_
T��������̂ V̂d����̂�Vka��bV���Vn����Vâ_̀abV_â_�a�b�̀��V�̂��a�_b�̀�V̀�V��̂��V��b���b�̂��V�����a¦V̀�Vâ���b��Vb�̈�̂�V̀�V�̀��V���V�à�����b̂aVâ���b��V����â�V��̀����V�̀��V���V�à�����b̂aV�̀��b�̀��V���Vâ���b�V���V�à�����b̂aV��̀�V��â�b�̀�
¾¿ÀÁÂÃÄÅÆÄÅÇÈ ÉÊËÌÂÆ
±²³́µ¶³³·̧¹º»¹¼µ½¾¼·¿·À²¼·¾¹ÁÂò¹̧»µÄÅÆ»ÅǻȷɻŲÊÈ»³µ²¹ÆµË¹É¾·À»µÌÀûÆÍÈ»µ¶¼¼²Àú»¹¼
ÎÏÐÑÒÓÔÕÖ×ÑØÙÚÛØÜÝ
¾¹¼Å²À¼µ½ÍºÊ»ÅÞµ±²³́µ¶³³·̧¹º»¹¼µßÞµ ǻȷɻŲÊÈ»³Þ àáâãäáåæçâá àáâãäáåæçâáèàéáèàæêá
˹ɾ·À»µÌÀûÆÍÈ»Þ ëáìéãåáíáîêïèðñåèòîäñãóáèôéçíãêêæâ õíñéîêèêñèçáèòîäñãóáö
±Ä±¶÷µÂÄ̱ ø¤xxªr����x������¦�q¤vx z~ª~̄ª~u~z }���¦��������£�������£�������������������¢���¦���������� £��������������¢�¦¬������� £��������� uzª~{ª~u~~ x��ù����y����� ������¦��������¦�|��¬�����¦�v¢££�� ������v����¤����� ����w�£��� u~ª~sª~u~~
§�£��� �����££��¥������ø¤xxªr����x������¦�q¤vx��v¢̈�����~� ®�zu�uz��{s §�£��� �����££��¥����������¦��������£�������£�������������������¢���¦���������� £�������������¦����¢�¦¬������� £�����������v¢̈������� ®����uts��t §�£��� �����££��¥������x��ù����y����� ������¦��������¦�|��¬�����¦�v¢££�� ������v����¤����� ����w�£�����v¢̈������z�ú��� ®�̄�u{��s� ûüýþ������� qrstu|}tu~�
05/05/10 rev 2.0
Sample Login Acknowledgement
FDEP King Maritime Phase III SamplingClient Job Description:
10 DaysJob TAT:
3/4/2022Job Due Date:
Noel SavoieProject Manager:
Work Order #:
1187051Purchase Order #:
Report To:
Bill To:
Richard Hicks
1558 Village Square Blvd.
Suite 2
Tallahassee, FL 32309
Accounts Payable
Foster Plaza 7
661 Anderson Drive
Suite 200
Pittsburgh, PA 15220-2745
Tetra Tech, Inc.
Tetra Tech, Inc.
Job 660-117801-1
Max Deliverable Level:
Earliest Deliverable Due:
II
3/4/2022
Sample Receipt:
Method of Delivery:
Number of Coolers:
Cooler Temperature(s) (C°):
32/19/2022 9:10:00 AM
FedEx Priority Overnight 1.5; 4.8; 5.2;
Login 660-117801
Lab Sample #
Method
Client Sample ID
Method Description / Work Location
Date Sampled Matrix
Dry / Wet **Rpt Basis
660-117801-1 KMB09 SB1 (0.5-2) Solid2/15/2022 8:45:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-2 KMB09 SB2 (2-4) Solid2/15/2022 8:50:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-3 KMB10 SB1 Solid2/15/2022 9:00:00 AM
6010D TotalArsenic / In-Lab Dry
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-4 KMB10 SB1 DUP1 Solid2/15/2022 9:00:00 AM
6010D TotalArsenic / In-Lab Dry
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-5 KMB10 SB2 Solid2/15/2022 9:15:00 AM
6010D TotalArsenic / In-Lab Dry
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-6 KMB11 SB1 Solid2/15/2022 9:30:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-7 KMB11 SB2 Solid2/15/2022 9:40:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-8 KMB15 SB1 Solid2/15/2022 9:12:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-9 KMB15 SB2 Solid2/15/2022 9:45:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
* Method on-hold
** Wet/Dry indicates whether the reported results will be corrected for moisture content, and based on sample Wet weight or Dry weight .
Lab Sample #
Method
Client Sample ID
Method Description / Work Location
Date Sampled Matrix
Dry / Wet **Rpt Basis
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-10 KMB16 SB1 Solid2/15/2022 10:00:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-11 KMB16 SB2 Solid2/15/2022 10:05:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-12 KMB17 SB1 Solid2/15/2022 10:35:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-13 KMB17 SB1 Solid2/15/2022 10:40:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-14 KMB18 SB1 Solid2/15/2022 10:55:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-15 KMB18 SB1 Duplicate Solid2/15/2022 10:55:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-16 KMB18 SB2 Solid2/15/2022 11:00:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-17 KMB19 SB1 Solid2/15/2022 11:15:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-18 KMB19 SB2 Solid2/15/2022 11:20:00 AM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-19 KMC07 SB1 Solid2/15/2022 12:15:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-20 KMC07 SB2 Solid2/15/2022 12:20:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-21 KMC08 SB1 Solid2/15/2022 12:25:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-22 KMC08 SB2 Solid2/15/2022 12:30:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-23 KMC09 SB1 Solid2/15/2022 12:40:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
** Wet/Dry indicates whether the reported results will be corrected for moisture content, and based on sample Wet weight or Dry weight .
Method
Client Sample ID
Method Description / Work Location
Date Sampled Matrix
Dry / Wet **Rpt Basis
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-24 KMC09 SB2 Solid2/15/2022 12:45:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-25 KMC10 SB1 Solid2/15/2022 12:50:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-26 KMC10 SB2 Solid2/15/2022 12:55:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-27 KMC11 SB1 Solid2/15/2022 1:00:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-28 KMC11 SB2 Solid2/15/2022 1:05:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-29 KMC06 SB1 Solid2/15/2022 1:30:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-30 KMC06 SB1 DUP Solid2/15/2022 1:30:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-31 KMC06 SB2 Solid2/15/2022 1:35:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-32 KMC12 SB1 Solid2/15/2022 1:40:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-33 KMC12 SB2 Solid2/15/2022 1:45:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-34 KMC13 SS Solid2/15/2022 1:55:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-35 KMC13 SB1 Solid2/15/2022 1:58:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
660-117801-36 KMC13 SB1 DUP Solid2/15/2022 1:58:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-37 KMC13 SB2 Solid2/15/2022 2:00:00 PM
FL_PRO TotalTRPH / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
TPHCWG* TotalCLR-TPH-WG-FL / In-Lab Dry
** Wet/Dry indicates whether the reported results will be corrected for moisture content, and based on sample Wet weight or Dry weight .
Method
Client Sample ID
Method Description / Work Location
Date Sampled Matrix
Dry / Wet **Rpt Basis
660-117801-38 KMS EQB1 Water2/15/2022 2:30:00 PM
6010D Total
Recoverable
Arsenic / In-Lab Wet
FLPRO_Micro TotalTRPH / In-Lab Wet
660-117801-39 KMF04 SS- Solid2/15/2022 3:00:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-40 KMF04 SB1 Solid2/15/2022 3:05:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-41 KMF04 SB1 DUP Solid2/15/2022 3:05:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-42 KMF04 SB2 Solid2/15/2022 3:10:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-44 KMF05 SS Solid2/15/2022 3:15:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-45 KMF05 SB1 Solid2/15/2022 3:20:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-46 KMF05 SB2 Solid2/15/2022 3:25:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-47 KMF06 SS Solid2/15/2022 3:30:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-48 KMF06 SB1 Solid2/15/2022 3:35:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-49 KMF06 SB2 Solid2/15/2022 3:40:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-50 KMF07 SS Solid2/15/2022 3:42:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-51 KMF07 SB1 Solid2/15/2022 3:45:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-52 KMF07 SB2 Solid2/15/2022 3:47:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-53 KMF08 SS Solid2/15/2022 3:50:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-54 KMF08 SB1 Solid2/15/2022 3:52:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-55 KMF08 SB1 DUP Solid2/15/2022 3:52:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-56 KMF08 SB2 Solid2/16/2022 3:55:00 PM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-57 KMG04 SS Solid2/16/2022 8:15:00 AM
** Wet/Dry indicates whether the reported results will be corrected for moisture content, and based on sample Wet weight or Dry weight .
Method
Client Sample ID
Method Description / Work Location
Date Sampled Matrix
Dry / Wet **Rpt Basis
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-58 KMG04 SB1 Solid2/16/2022 8:20:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-59 KMG04 SB1 DUP Solid2/16/2022 8:20:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-60 KMG04 SB2 Solid2/16/2022 8:25:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-61 KMG06 SB1 Solid2/16/2022 8:30:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-62 KMG06 SB2 Solid2/16/2022 8:32:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-63 KMG07 SB1 Solid2/16/2022 8:50:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-64 KMG07 SB2 Solid2/16/2022 8:55:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-65 KMH 02 SB1 Solid2/16/2022 9:20:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-66 KMH 02 SB1 DUP Solid2/16/2022 9:20:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-67 KMH 02 SB2 Solid2/16/2022 9:25:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-68 KMH 04-SB1 Solid2/16/2022 10:15:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent Moisture / In-Lab Wet
660-117801-69 KMH 04-SB2 Solid2/16/2022 10:20:00 AM
6010D TotalArsenic / In-Lab Dry
Moisture TotalPercent…