Summary of Task Assignment DC030K
This is a Task Assignment Notification Form under Florida Department of Environmental Protection (FDEP) Contract No. HW560, issued to Tetra Tech, Inc. for operation and maintenance (O&M) services at the Village Cleaners site located at 2100 45th Street, West Palm Beach, Palm Beach County, Florida (ERIC_5205). The assignment was executed on December 9, 2021, with Dean Cox serving as the FDEP Contract Manager and Shawn Ouellette as the contractor representative. The task authorizes four months of O&M activities with a period of performance through June 30, 2022.
The scope of work encompasses four subtasks: project management (Subtask 1), system monitoring and sampling including monthly site visits from November 2021 through February 2022 (Subtask 2), system waste disposal including one carbon drum overpacking and disposal by Erwin Remediation for $450.00 (Subtask 3), and utility invoice services for four months of Florida Power & Light service at $1,400.00 (Subtask 4). The total task assignment value is $8,665.18, comprised of a fixed price of $7,265.18 and cost reimbursement of $1,400.00 plus a fixed fee of $80.00 for utility handling. Deliverables include O&M checklists, field documentation, laboratory reports, and system waste manifests, with final deliverables due by April 30, 2022. Payment is contingent upon FDEP approval of submitted documentation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW560
D000 NADC030K
Tetra Tech
Shawn Oullette
850-245-8969Dean Cox
ERIC_5205
Village Cleaners
2100 45th Street, West Palm Beach, Palm Beach County
Operation and Maintenance (O&M)
This Task Assignment authorizes four months of Tetra Tech O&M, including site visits & system sampling (Subtask 2), system waste disposal (Subtask 3), utilities (Subtask 4), and associated Project management (Subtask 1).
The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.
System waste manifest
04/30/2022
06/30/2022
$ 7,265.18 $ 0.00 $ 1,400.00 $ 0.00
$ 0.00
Dean Cox Digitally signed by Dean Cox Date: 2021.12.09 09:32:55 -05'00'
Dean Cox Digitally signed by Dean Cox Date: 2021.12.09 09:33:10 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.12.09 14:15:55 -05'00'
Shawn Ouellette Digitally signed by Shawn Ouellette Date: 2021.12.09 14:50:47 -05'00'
$ 8,665.18
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW560
O&M submittal, including checklists, field documentation, laboratory report, email recommendations & data tables (Subtask 2), and associated Project Management (Subtask1)
04/15/2022
System waste manifest (Subtask 3)
04/30/2022
FDEP approval of O&M submittal, including checklists, field documentation, laboratory report, email recommendations & data tables (Subtask 2), and associated Project Management (Subtask1)
$ 6,076.08
FDEP approval of system waste manifest (Subtask 3)
$ 1,109.10
FDEP receipt of utility invoices for 4 months (November 2021 - February 2022);
Utilities (Cost Plus Fixed Fee) = not to exceed $1400; Utilities Handling Fee $80 - Subtask 4 $ 1,480.00
$ 8,665.18
DC030K
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW560 Contract File FROM: Dean Cox, Contract Manager SUBJECT: Village Cleaners (ERIC_5205) O&M (4 months)
DATE: 12/8/2021
Task Assignment authorizes four months of Tetra Tech O&M, including site visits & system sampling (Subtask 2), system waste disposal (Subtask 3), utilities (Subtask 4), and associated Project management (Subtask 1).
FDEP COST ESTI MATEContractor: Tetra Tech
Date: October 28, 2021
Task #: HW560-DC030K SubTask 1 Project Management SubTask 6
Site: Village Cleaners, West Palm Beach SubTask 2 System Monitoring - (November 2021 - February 2022) SubTask 7
Activity/Phase: O&M SubTask 3 IDW Disposal Carbon Drum SubTask 8
Project Manager: Dean Cox SubTask 4 Utility Invoice Services - (November 2021- February 2022) SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$48.08 Project Manager (SO) 3 2.9 $34.86 Senior CADD Specialist (FM) 1 0 1 0 0 0 0 0 0 0 $32.19 Scientist II (JE) 20 20 0 0 0 0 0 0 0 0 $48.08 Scientist IV (SO) 3 0 3 0 0 0 0 0 0 0 $57.63 Engineer IV (MJ) 5 5.0 0 0.0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 32 3 25.0 4 0.0 0 0 0 0 0 0
Direct Labor $1,249.93 $138.88 $931.95 $179.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 143.00% $1,787.40 $198.60 $1,332.69 $256.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 12.20% $370.56 $41.17 $276.29 $53.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,407.89 $378.65 $2,540.93 $488.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $62.50 $6.94 $46.60 $8.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
REV: 02/03 Page 1
FDEP COST ESTI MATEContractor: Tetra Tech
Date: October 28, 2021
Task #: HW560-DC030K SubTask 1 Project Management SubTask 6
Site: Village Cleaners, West Palm Beach SubTask 2 System Monitoring - (November 2021 - February 2022) SubTask 7
Activity/Phase: O&M SubTask 3 IDW Disposal Carbon Drum SubTask 8
Project Manager: Dean Cox SubTask 4 Utility Invoice Services - (November 2021- February 2022) SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $456.00 $388.00 $68.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $456.00 $388.00 $68.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW (Erwin) $450.00 $0.00 $450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $1,400.00 $0.00 $0.00 $1,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $1,850.00 $0.00 $450.00 $1,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $125.00 $0.00 $45.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,975.00 $0.00 $495.00 $1,480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,066.00 $1,066.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $63.00 $63.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,129.00 $1,129.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $130.00 $130.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,164.00 $1,164.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,294.00 $1,294.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $8,324.39 $385.59 $5,398.53 $1,060.27 $1,480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $340.79 $37.87 $254.09 $48.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $8,665.18 $423.46 $5,652.62 $1,109.10 $1,480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Village Cleaners, West Palm Beach SUBTASK 2: System Monitoring - (November 2021- February 2022)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist II (JE) Monthly system performance 5 2 hrs round trip travel and 3 hrs on-site
Engineer V (MJ) Submit O&M checklist and email with recommendations 0.5
Scientist II (JE) Monthly system performance 5 2 hrs round trip travel and 3 hrs on-site
Engineer V (MJ) Submit O&M checklist via email with recommendations 0.5
Scientist II (JE) Monthly system performance / influent monitoring 4 VEWS Sampling 5 2 hrs round trip travel and 3 hrs on-site
Engineer V (MJ) Submit O&M checklist and lab data via email with recommendations 0.5
Scientist II (JE) Monthly system performance 5 Engineer V (MJ) Submit O&M checklist and lab data via email with recommendations 0.5
O&M Tables 6 Tables per visit (6 @0.5) 3
TOTAL LABOR 25
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Equipment O&M Kit $291.00 day 4 $1,164.00 Expendables $32.50 day 4 $130.00
TOTAL EQUIPMENT $1,294.00
VEHICLE TYPE RATE UNIT USAGE
Equipment Van $97.00 day 4 $388.00
TOTAL VEHICLE $388.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
HOTEL
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC
Organics Air TO15 $200.00 5 0 (influent - 4 VEWS January 2022) $1,000.00 Organics Soil 8260 partial Dry Clean Shortlist 1 Carbon Drum Removal $66.00 Shipping, FedEx, 5 lb @ 24 hrs $63.00 1 (from SVE) $63.00
TOTAL LAB $1,129.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
CEF DC030K LOE 2
CEF DC030K LOE 3
SUBTASK 3: IDW Disposal
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist IV (SO) Round trip travel and drum removal 3
Scientist IV (SO) Disposal profile review and approval, manifests for FDEP submittal 1
TOTAL LABOR 4
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
Car $68.00 Day 1 $68.00
TOTAL VEHICLE $68.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
NAME PURPOSE
IDW Disposal Dispose of 1 drum of non-hazardous IDW (estimated)
Erwin 1 drum of non-haz Carbon with Overpack $450.00 drum $450.00
TOTAL $450.00
SUBTASK 4: Utility Invoice Services - (Nov 2021 - February 2022)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Equipment
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
HOTEL
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
FPL 4 month of power (running 24 hrs/day) $350 month $1,400.00
TOTAL $1,400.00
The fixed handling charge associated with the utility procurement is broken down as follows:
$20/month processing fee for each utility for one month = $80
Total = $80
CEF DC030K LOE 4
CEF DC030K LOE 4
From: Ouellette, Shawn To: Cox, Dean Subject: FW: Overpak for Carbon Drum In West Palm Beach Date: Wednesday, December 8, 2021 11:48:03 AM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Dean, Not a formal quote but this is a response from the vendor.
Thanks, See Below Shawn Ouellette, P.G. | Sci.Geologist IV.
Direct +1 (772) 781-3412 | Business +1 (772) 781-3400 | Fax +1 772-781-3411 | Mobile +1 772-408-2959 | Shawn.Ouellette@tetratech.com
Tetra Tech | Complex World, Clear Solutions™ 759 S. Federal Hwy., Stuart, FL 34994-2936 | tetratech.com
From: Erwin Remediation <erwinremediation@gmail.com> Sent: Thursday, October 28, 2021 4:28 PM To: Ouellette, Shawn <Shawn.Ouellette@tetratech.com> Subject: Re: Overpak for Carbon Drum In West Palm Beach
⚠ CAUTION: This email originated from an external sender. Verify the source before opening links or attachments. ⚠
Hi Shawn, The overpack drum itself is $350 plus the base $100 drum disposal.
All in, it will be $450.00.
Thank you, Jonathan Erwin Erwin Remediation, Inc.
Office: (850) 292-6511|Email: ErwinRemediation@Gmail.com Erwin Remediation, Inc.|408 Ditmar Street Pensacola, FL 32503
On Thu, Oct 28, 2021 at 1:17 PM Ouellette, Shawn <Shawn.Ouellette@tetratech.com> wrote:
Jonathan, mailto:Shawn.Ouellette@tetratech.com mailto:Dean.Cox@floridadep.gov mailto:Shawn.Ouellette@tetratech.com http://www.tetratech.com/ tel:%28850%29%20292-6511 mailto:ErwinRemediation@gmail.com mailto:Shawn.Ouellette@tetratech.com
How much would you charge to overpak one carbon drum and dispose for the Village Cleaners site located In west Palm Beach Florida.
2100 45th Street West Palm Beach Florida 33407. Assume Non-HAZ
Shawn Ouellette, P.G. | Sci.Geologist IV.
Direct +1 (772) 781-3412 | Business +1 (772) 781-3400 | Fax +1 772-781-3411 | Mobile +1 772-408-2959 | Shawn.Ouellette@tetratech.com
Tetra Tech | Complex World, Clear Solutions™ 759 S. Federal Hwy., Stuart, FL 34994-2936 | tetratech.com mailto:Shawn.Ouellette@tetratech.com http://www.tetratech.com/
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Jay McGovern
Tetra Tech
759 South Federal Hwy, Suite 314
Stuart, FL 34994
February 13, 2020
Re: Drum Disposal – Non-Hazardous Material - Florida
Mr. McGovern:
The price for transportation and disposal of drums of either non-hazardous soil or groundwater located in the State of Florida (excluding the Florida Keys) will be $100.00 per drum for both transportation and disposal.
Please feel free to contact me on my direct line at 850-292-6511 if you have any questions.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
Tetra Tech, Inc.
759 South Federal Highway, Suite 314 Stuart, FL 34994
Tel 772.781.3400 Fax 772.781.3411 www.tetratech.com
October 28, 2021
TTST-HW560-21-078
Mr. Dean Cox Contract Manager Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
SUBJECT: TASK ASSIGNMENT REQUEST – SVE SYSTEM O&M
VILLAGE CLEANERS (FORMER)
2100 45TH STREET, UNIT B8
WEST PALM BEACH, FL 33407
ERIC_5205
Dear Mr. Cox:
Tetra Tech, Inc. is requesting a Task Assignment to continue the SVE system’s operation and maintenance (O&M) at the Village Cleaners site in West Palm Beach Florida. The following presents a scope of work (SOW) summary and the proposed schedule.
SOW – Field Activities The field activities associated with the proposed SOW will include travel to the site monthly for system operational measurement collection, system operation and routine maintenance.
The Task Assignment request also includes 4 months of Utility Invoice Services (November 2021 - February 2022) from Florida Power & Light to operate the SVE system, estimated at $350/month.
SOW – Reporting Following completion of quarterly field activities, the O&M checklists will be submitted via email. An interpretation of the results and recommendations for further courses of action will be provided.
The proposed deliverables and deliverable due dates are summarized below:
• Subtask 1 – Project Management
• Subtask 2 – Monthly System Monitoring - (November 2021 February 2022):
Deliverable (3 Monthly O&M checklists and quarterly O&M Report) due date.
March 21, 2022
Mr. Dean Cox October 28, 2021
Tetra Tech, Inc.
• Subtask 3 – Submittal of four months of paid utility invoices:
Deliverable due date March 31, 2022
Should you have any questions, please contact me at 772.781.3412.
Sincerely, Shawn Ouellette, P.G.
Project Manager c: File
Level of Effort/Cost Estimate Forms (submitted electronically)
| DC030K.pdf |
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
Pages from HW560 DC030K unsigned.pdf