This document is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) under Contract HW560. The assignment authorizes Tetra Tech EC, Inc. to perform soil vapor extraction (SVE) system shutdown evaluation services at the Palace Dry Cleaners site located at 733 S. Orange Blossom Trail, Apopka, Orange County, Florida. The task assignment was executed on October 1, 2020, with FDEP Contract Manager Walsta Jean-Baptiste and Tetra Tech representative Jay McGovern, P.G. managing the engagement.
The scope of work comprises three subtasks: Project Management, SVE Shutdown System Pulsing, and Utility Invoice Services for October through December 2020. The task involves conducting a one-month system pulsing shutdown procedure followed by collection and analysis of influent and three vapor extraction well air samples using EPA Method TO15, with results incorporated into a final SVE system O&M report and site path forward recommendations. The total task assignment value is $10,571.04, consisting of $9,971.04 in fixed price costs and $600.00 in cost-plus fixed fee for utilities (with a $60.00 handling fee). The period of performance extends from execution through March 31, 2021, with the final deliverable due date of December 31, 2020 for the SVE Shutdown Evaluation and Recommended Path Forward Report. Cost allocation includes 47 hours of labor from project managers, scientists, and engineers, along with equipment, travel, laboratory analysis, and field expenses. The only cost-plus fixed fee component is the payment of utilities estimated at $600.00 over three months. No retainage applies to this task assignment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW560
D000 NADC027i
Tetra Tech EC, Inc.
Jay McGover, PG
850-245-8705Walsta Jean-Baptiste
ERIC_5049
Palace Dry Cleaners
733 S Orange Blossom Trail, Apopka, Orange County
Operation and Maintenance
This Task Assignment authorizes Tetra Tech to complete soil vapor extraction system shutdown evaluation in accordance with the Tetra Tech scope of work, cost estimate form, and schedule received on September 30, 2020.
The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.
SVE Shutdown Evaluation and Recommended Path Forward Report (submitted electronically)
12/31/2020
03/31/2021
$ 9,971.04 $ 0.00 $ 600.00 $ 0.00
$ 0.00
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2020.10.01 12:41:56 -04'00'
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2020.10.01 12:42:03 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2020.10.01 15:18:46 -04'00'
Jay McGovern Digitally signed by Jay McGovern Date: 2020.10.05 08:44:51 -04'00'
$ 10,571.04
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
SVE Shutdown Evaluation and Recommended Path Forward Report (submitted electronically) 12/31/2020
FDEP approval of SVE Shutdown Evaluation and Recommended Path Forward Report (submitted electronically) - Subtasks 1 and 2 $ 9,911.04
FDEP receipt of utility invoices for 3 months (October - December 2020); Utilities (Cost Plus Fixed Fee) = not to exceed $600; Utilities Handling Fee = $60 - Subtask 3 $ 660.00
$ 10,571.04
HW560
DC027i
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: HW560 Contract File FROM: Walsta Jean-Baptiste, Contract Manager SUBJECT: DC027i Negotiation Summary Palace Dry Cleaners – SVE Shutdown Evaluation and Path Forward DATE: October 1, 2020
This Task Assignment authorizes Tetra Tech to complete soil vapor extraction system shutdown evaluation in accordance with the Tetra Tech scope of work, cost estimate form, and schedule received on September 30, 2020.
Changes to the costs include labor rate correction and increase in the level of effort to add the preparation of a site path forward. Previously, the SVE operation and maintenance and annual groundwater sampling were presented in separate reports resulting in conflicting path forwards for site closure.
This Task Assignment also authorizes three months of utilities from October through December 2020 to complete shutdown evaluation.
The cost related to this Task Assignment is $10,571.04 with 47 hours.
FDEP COST ESTI MATEContractor: Tetra Tech
Date: September 29, 2020
Task #: HW560-DC027i SubTask 1 Project Management SubTask 6
Site: Palace Dry Cleaners, Apopka SubTask 2 SVE Shutdown - System Pulsing SubTask 7
Activity/Phase: SVE Shutdown SubTask 3 Utility Invoice Services - (Oct - Dec 2020) SubTask 8
Project Manager: Walsta Jean-Baptiste, P.G. SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$69.35 Project Manager (JM) 4 4.2 $69.35 Scientist V (JM) 8 8 0 0 0 0 0 0 0 0 $42.78 Scientist IV (SO) 16 16 0 0 0 0 0 0 0 0 $69.35 Scientist V (JM) 0 0 0 0 0 0 0 0 0 0 $57.63 Engineer V (MJ) 19 19 0 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 47 4 43 0 0 0 0 0 0 0 0
Direct Labor $2,626.03 $291.78 $2,334.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 143.00% $3,755.23 $417.25 $3,337.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 12.20% $778.51 $86.50 $692.01 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,159.77 $795.53 $6,364.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $131.30 $14.59 $116.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTI MATEContractor: Tetra Tech
Date: September 29, 2020
Task #: HW560-DC027i SubTask 1 Project Management SubTask 6
Site: Palace Dry Cleaners, Apopka SubTask 2 SVE Shutdown - System Pulsing SubTask 7
Activity/Phase: SVE Shutdown SubTask 3 Utility Invoice Services - (Oct - Dec 2020) SubTask 8
Project Manager: Walsta Jean-Baptiste, P.G. SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $600.00 $0.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $600.00 $0.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $60.00 $0.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $660.00 $0.00 $660.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,000.00 $1,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $63.00 $63.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,063.00 $1,063.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $582.00 $582.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $647.00 $647.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $9,855.07 $810.12 $8,384.95 $660.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $715.97 $79.55 $636.42 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $10,571.04 $889.67 $9,021.37 $660.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Palace Dry Cleaners, Apopka SUBTASK 2: SVE Shutdown - System Pulsing
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Scientist V (JM) Prepare path forward recommendation for NFA 4 Technical review of Final SVE Report 4
Scientist IV (SO) 5 hrs round trip travel and 3 hr on-site 8 After the O&M checklist is completed, influent sample is collected, shut down the system to begin the one month of pulsing Confirmatory soil sampling is not required, no soil sample collected during the site assessment exceeded a SCTL
Scientist IV (SO) 5 hrs round trip travel and 3 hr on-site 8 After one month restart system, collect influent and 3 VEWs air samples, then leave system running until next O&M visit
Engineer V (MJ) Prepare Final SVE Report 16 Engineer V (MJ) O&M Tables (6 tables per site visit) 3
TOTAL LABOR 43
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Equipment O&M Kit $291.00 day 2 $582.00 Expendables $32.50 day 2 $65.00
TOTAL EQUIPMENT $647.00
VEHICLE TYPE RATE UNIT USAGE
Equipment Van $97.00 day 2 $194.00
TOTAL VEHICLE $194.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
$0.00
HOTEL
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC
Organics Air TO15 $200.00 5 0 (2 Influent & 3 VEWs at the end of pulse cycle) $1,000.00
Shipping, FedEx, 5 lb @ 24 hrs $63.00 1 $63.00
TOTAL LAB $1,063.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
HW560 Palace Dry Cleaners SVE Shutdown Oct 2020.xlsx LOE 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Palace Dry Cleaners, Apopka SUBTASK 3: Utility Invoice Services - (Oct - Dec 2020)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
Equipment
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE
MEALS
HOTEL
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Duke Energy 3 month of power $200 month $600.00
TOTAL $600.00
HW560 Palace Dry Cleaners SVE Shutdown Oct 2020.xlsx LOE 3
Tetra Tech, Inc.
759 South Federal Highway, Suite 314 Stuart, FL 34994
Tel 772.781.3400 Fax 772.781.3411 www.tetratech.com
September 30, 2020
TTST-HW560-20-045
Ms. Walsta Jean-Baptiste, P.G.
Contract Manager Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
SUBJECT: TASK ASSIGNMENT REQUEST – SVE SYSTEM SHUTDOWN
PALACE DRY CLEANERS
733 S. ORANGE BLOSSOM TRAIL
APOPKA, FL 32703
ERIC_5049
Dear Ms. Jean-Baptiste:
Tetra Tech, Inc. is requesting a Task Assignment to start the SVE System shutdown procedure at the Palace Dry Cleaners site in Apopka. The following presents a scope of work (SOW) summary and the proposed schedule.
SOW – Field Activities The field activities associated with the proposed SOW will include travel to the site and after the O&M checklist is completed, shut down the SVE system to begin the one month of pulsing per the Department’s SVE System Shutdown guidance. Confirmatory soil sampling is not required, no soil sample collected during the site assessment exceeded a SCTL. After one-month the SVE system will be restarted and influent and three VEWs air samples will be collected and analyzed by EPA Method TO- 15 for the drycleaning constituents of interest. The SVE system will be left running until the next O&M visit.
The Task Assignment request also includes three months of Utility Invoice Services (Oct - Dec 2020) from Duke Energy to operate the SVE system, estimated at $200/month.
SOW – Reporting Following completion of field activities and receipt of the analytical data, the data will be incorporated into a final SVE system O&M report. An interpretation of the results and recommendations for further courses of action will be provided.
Ms. Jean-Baptiste, P.G.
September 30, 2020
Tetra Tech, Inc.
The proposed deliverables and deliverable due dates are summarized below:
• Subtask 1 – Project Management
• Subtask 2 – Submittal of the Final SVE System O&M Report:
Deliverable due date December 4, 2020
• Subtask 3 – Submittal of three months of paid utility invoices:
Deliverable due date January 31, 2021
Should you have any questions, please contact me at 772.781.3409.
Sincerely, Jay McGovern, P.G.
Project Manager c: File Level of Effort/Cost Estimate Forms (submitted electronically)
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| Palace Cleaners SVE Shutdown TA Request.pdf |
| SUBJECT: TASK ASSIGNMENT REQUEST – SVE SYSTEM SHUTDOWN |
| HW560 Palace Dry Cleaners SVE Shutdown Oct 2020.pdf |
| CE |
| LOE 2 |
| LOE 3 |