Task Assignment BF562E Summary
This is a Task Assignment Notification Form executed under Florida Department of Environmental Protection (FDEP) Contract No. HW556, administered through the State & Tribal Response Program (SRP18) cooperative agreement with the U.S. Environmental Protection Agency (EPA). The primary parties are FDEP, the contractor Cardno, Inc. (operating as HSW Consulting, LLC), and the site location is the Former Lamb's Recycling Facility in Esto, Holmes County, Florida (Facility ID ERIC_7390). The task assignment was signed and approved on April 9, 2021, with contract manager Kelly Crain representing FDEP and Eric Meyers representing the contractor.
The scope of work consists of two subtasks: Subtask 1 covers project management at a cost of $213.33, and Subtask 2 encompasses waste disposal oversight activities including removal of eight 55-gallon drums and nine 5-gallon buckets containing liquid, plus twenty-five drums of soil and groundwater investigation-derived waste (IDW), with an agreed cost of $7,770.61. The total task assignment value is $7,983.94 on a fixed-price basis with no retainage. The final deliverable—a waste disposal oversight summary including field notes, photographic log, and waste manifests—is due to FDEP by June 4, 2021, with the period of performance extending through June 30, 2021. Invoice payment is contingent upon FDEP's approval of all deliverables, and the cost estimate incorporates subcontractor waste disposal services procured through competitive quotes from Capitol Environmental Services, Erwin Remediation, and US Ecology.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW556
SRPPM SRP18BF562E
Cardno, Inc.
Eric Meyers Phone #: (850) 629-2702
(850) 245-8953Kelly Crain
ERIC_7390
Former Lamb's Recycling Facility
1067 North Highway 79, Esto, Holmes County, Florida 32425
Waste Disposal activities
The Department approves this Task Assignment (TA) based upon the Cost Proposal and Level of Effort (CP/LOE) for waste disposal activities, including removal of the abandoned eight (8) 55-gallon drums and nine (9) 5-gallon buckets containing liquid, and the twenty-five (25) drums of soil and groundwater investigation derived waste (IDW), submitted to the Department on April 6, 2021 by HSW Consulting, LLC. The final deliverable will be a waste disposal oversight summary including field notes, photographic log, and waste manifests, received by the Department no later than June 4, 2021.
Waste Disposal Oversight Summary
06/04/2021
06/30/2021
$ 7,983.94 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Megan R. Johnson Digitally signed by Megan R. Johnson Date: 2021.04.09 14:45:37 -04'00'
Kelly Crain Digitally signed by Kelly Crain Date: 2021.04.09 14:56:30 -04'00'
Digitally signed by Jennifer Farrell Date: 2021.04.09 15:50:17 -04'00'
Eric Meyers Digitally signed by Eric Meyers Date: 2021.04.12 14:40:34 -04'00'
$ 7,983.94
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Waste Disposal Oversight Summary; field notes, photographic log, and waste manifests. 06/04/2021
Department approval of Waste Disposal Oversight Summary; field notes, photographic log, and waste manifests (Subtasks 1 & 2) $ 7,983.94
$ 7,983.94
HW556
BF562E
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: HSW Consulting, LLC, HW556 Contract File
FROM: Kelly Crain, Contract Manager
DATE: April 9, 2021
SUBJECT: Negotiation Summary – SRP 18 Task Assignment (TA) BF562E
Town of Esto - Former Lamb’s Recycling Facility Facility ID # ERIC_7390 Waste Disposal activities
This TA is intended for conducting Waste Disposal activities at the Former Lamb’s Recycling Facility site, located at 1067 North Highway 79, Esto, Holmes County, Florida 32425. The scope of work is to complete and build upon the Site Assessment Report activities that were conducted in September and October 2020, and Site Reconnaissance and Waste Analysis activities conducted in March 2021. The services are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, fringe and other direct costs. The agreed upon cost of this subtask is $213.33.
Subtask 2: Waste Disposal Oversight Under this subtask, HSW will conduct waste disposal oversight activities at the site, including removal of the abandoned eight (8) 55-gallon drums and nine (9) 5-gallon buckets containing liquid, and the twenty-five (25) drums of soil and groundwater investigation derived waste (IDW).
The final deliverable will be a waste disposal oversight summary including field notes, photographic log, and waste manifests. The agreed upon cost of this subtask is $7,770.61.
Summary The Department’s SRP Contract Manager and HSW’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $7,983.94.
Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) spreadsheets and CP/LOE letter provided by HSW on April 6, 2021, as well as the Task Assignment Form for BF562E prepared by the Department. The final deliverable must be received by the Department no later than June 4, 2021.
http://www.floridadep.gov/
(813) 968-7722 ■ 15711 Mapledale Blvd., Suite B ■ Tampa, FL 33624 ■ www.hsweng.com Innovative Solutions Within Your Reach…
P:\1CB6 Cardno\1CB603401 Former Lamb's Recycling\01 Proposals\Disposal\TA Request-ERIC_7390.docx
April 6, 2021
Sent via Electronic Mail
Ms. Megan R. Johnson Florida Department of Environmental Protection Brownfields and CERCLA Site Screening Section 2600 Blair Stone Road, MS 4535 Tallahassee, FL 32399-2400
Re: Task Assignment Request Former Lamb’s Recycling Facility
1067 North Highway 79 Esto, Holmes County, Florida Facility ID ERIC_7390
Dear Megan:
HSW Consulting, LLC (HSW) is pleased to submit this Task Assignment Request activities related to the subject site. The scope of work, proposed deliverables, and deliverable schedule are summarized below.
Project Background During the course of prior assessment activities, eight (8) abandoned 55-gallon drums containing liquids were discovered, along with additional abandoned drums determined to be empty or containing household garbage. Nine (9) 5-gallon buckets containing liquids were also determined to be present. In addition, a total of twenty-five (25) drums were generated during monitoring well installation and sampling activities, with nineteen (19) drums containing soil cuttings and six (6) drums containing monitoring well development and purge water. During a prior site visit, HSW collected additional samples and provided analytical data and site information to applicable disposal companies in order to remove and dispose of the abandoned liquid-holding containers and the drums generated during monitoring well installation and sampling.
Scope of Work The proposed scope of work for this Task Assignment includes the following elements:
• HSW will coordinate and oversee the removal of the abandoned eight (8) 55-gallon drums and nine (9) 5-gallon buckets containing liquid and the twenty-five (25) drums of soil and groundwater IDW.
Subtask 1: Project Management $213.33
Subtask 2: Waste disposal oversight; submittal of letter summary including field notes, photographs, and waste manifests.
Deliverable Date: June 4, 2021
$7,770.61
TOTAL $7,983.94
Former Lamb’s Recycling Task Assignment Request
HSW Consulting ■ www.hsweng.com 2 Innovative Solutions Within Your Reach…
P:\1CB6 Cardno\1CB603401 Former Lamb's Recycling\01 Proposals\Disposal\TA Request-ERIC_7390.docx
Sincerely, HSW Consulting, Nicholas S. Barnes, P.E.
Senior Engineer
Attachment: Subcontractor Quotes
Level of Effort/Cost Estimate Forms (native file attached)
Capitol 200 Biddle Ave, Suite 205 Environmental Newark, DE 19702 Services, Inc. 302-380-3737 www.capitolenv.com
EXPERTISE SUSTAINABILITY SOLUTIONS
Nick Barnes 3-31-2021 H S W 15711 Mapledale Blvd Tampa FL 33624
Dear, Nick
RE: Cleanup activity at Lamp recycling Esto FL
Capitol Environmental Services, Inc. (CESI) is pleased to present the following disposal, and cleaning prices.
Capitol Environmental services, Inc. will provide Vacuum truck / operator, Box truck, and trained tech to remove pump and dispose of various drums. Capitol will provide disposal manifest.
DESCRIPTION Estimated
UM Unit Rate $ Total $
Vacuum truck & Operator 8 Hour Per Hour 130.00 $1040.00
Trained tech 8 Hour Per Hour 50.00 $400.00
Oily waters disposal bulk 485 Per Gallon .65 $130.00
PPE safety equipment Pressure washer
Per job Per day
55.00 135.00
$55.00 $135.00
Waters disposal
6 Per Drum 125.00 $750.00
Solids disposal 19 Per Drum 135.00 $2565.00
Empty drum recycling 8 est Per drum 40.00 $320.00
Estimate two trips to site
Tax and fuel charge billed. Actual time billed. Personnel & Equipment billed Portal to Portal.
Print Title:
Authorized Signature:
Date:
Mike Anderson
NBarnes Text Box Total: $5,395.00
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Nicholas Barnes, PE
HSW Consulting, LLC
15711 Mapledale Blvd., Suite B
Tampa, FL 33624
March 24, 2021
Re: Vacuum Truck Service and Drum Disposal - Esto, FL
Mr. Barnes:
The price for Vacuum Truck and Drum Disposal Service located at your jobsite in Esto, FL is itemized below.
Scope of Work
• Mobilize 3,000-gallon vacuum truck to Esto, FL.
• Pump out approximately 7-10 steel 55-gallon drums containing non-hazardous oil and water.
• Provide overpack drums for older damaged drums as needed.
• Provide transport and disposal for twenty five (25) drums of IDW, eight (8) older abandoned drums and seven (7) 5-gallon buckets.
Description Qty Rate Unit Sub Total
Vacuum Truck Service 1 $ 900.00 Ea. $ 900.00
Oil/Water/Liquid Disposal 550 $ 0.40 Gallon $ 220.00
Drum Disposal (Abandoned Drums) 8 $ 100.00 Ea. $ 800.00
Overpack Drums 8 $ 300.00 Ea. $ 2,400.00
5-Gallon Bucket Disposal 9 $ 20.00 Ea. $ 180.00
Drum Disposal (IDW drums of soil/water) 25 $ 100.00 Ea. $ 2,500.00
Total
Estimate:
$ 7,000.00 mailto:Remediation@Gmail.com NBarnes Line
NBarnes Text Box
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
All work will be performed on the approved unit rates as shown. Any additional work authorized by HSW Consulting will be billed based on Erwin Remediation’s standard unit costs. This estimate is based on approximate quantities. The final invoice will reflect actual work performed on approved tasks.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
PC01875 (Revised 3/31/2021)
Description Rate Quantity Unit Total
Site Address: 1067 North Highway 79, Esto (Holmes County), FL
Job Summary
$12,415.25Total:
March 31, 2021
FAX
Nicholas Barnes, PE
HSW Engineering, Inc.
Dear Mr. Barnes
US Ecology is pleased to submit the following proposal for the Scope of Work described herein, along with our standard Terms & Conditions. We appreciate the opportunity to bid on this project and are prepared to perform the work upon your approval of the Proposal.')
15711 Mapledale Blvd.
Suite B
Scope of Work :Tampa, FL 33624-
RE: Waste Overpack, Vacuum Truck & Waste T&D Services
1736 Bayview Avenue
Panama City, FL 32405
850-563-0822 850-563-0827
Scope of Work
$3,329.00 DayLabor & Equipment (Vac Svcs & Overpack Svcs) $3,329.001
$1,260.00 LoadWaste Transportation (Non-Haz IDW Liquid Waste), Estimate $1,260.001
$0.46 GallonDisposal, Non-Haz IDW Groundwater, Estimate $356.50775
$715.00 LoadWaste Transportation (Non-Haz IDW Soil Drums), Estimate $715.001
$108.75 DrumDisposal, Non-Haz IDW Soil, Estimate $2,066.2519
$1,596.00 LoadWaste Transportation (Haz Waste & Empty Drums) -> TPA, Estimate
$1,596.001
$365.00 DrumDisposal, Hazardous Waste (Organics / Overpacks), Estimate $1,825.005
$48.75 EachDisposal, DOT Empty Drums $1,267.5026
• US Ecology (USE) will mobilize labor and equipment to 1067 North Highway 79 in Esto (Holmes County), FL. USE will vacuum extract all the IDW groundwater from 6 groundwater drums as well as the 8 abandon drums containing Non-Haz Petroleum Contaminated Water (PCW). USE will collect and dispose of 26 DOT empty drums. The 19 IDW soil drums will be loaded on to a box truck and the 9 5/gal buckets will be overpacked into 55/gal poly drums and loaded on to a box truck with 26 empty drums.
• USE will transport the bulk Non-Haz Petroleum Contaminated Water (PCW) mixed with IDW Groundwater to a disposal facility in Mobile, AL. The 19 IDW soil drums will be transported to the Springhill landfill in
Campbellton, FL. The 9 hazardous waste 5/gal buckets overpacked in 55/gal drums & 26 DOT empty drums will be transpoted to the US Ecology Treatment Storage Disposal Facility (TSDF) in Tampa, FL.
• Note: This quote is based on a single mobilization to the site. All work will be scheduled and completed during normal business hours, Monday - Friday. Nights, weekends and holidays are not included. Drums must be in DOT shippable containers before being transported. All waste must be profiled and acknowledged by the customer. Pricing for waste is upon disposal facility acceptance. Off-spec charges and/or surcharges will be priced accordingly. Waste surcharges apply if the bulk stream does not meet the approved discharge criteria.
Customer acknowledges that invoicing will consist of actual quantities incurred at the provided rates. Any additional resources required, other than those identified herein, will be invoiced in accordance with US Ecology's
HSW Engineering, Inc.
PC01875 (Revised 3/31/2021)
March 31, 2021
US Ecology customary work hours are 7:00 a.m. to 3:00 p.m.
A fuel recovery charge has been incorporated into this lump sum/fixed price quote. We reserve the right to adjust pricing for services provided beyond thirty (30) days from quote date if the cost of fuel varies significantly.
Drums must be in DOT shippable containers before being transported.
All waste must be profiled and acknowledged by the customer.
Pricing for waste is upon disposal facility acceptance. Off-spec charges and/or surcharges will be priced accordingly.
Waste surcharges apply if the bulk stream does not meet the approved discharge criteria.
current time and materials rates. If the Customer issues a Purchase Order for an estimated amount, Customer acknowledges that invoicing will still be based on actual quantities incurred at the provided rates regardless if the
Purchase Order amount is exceeded. Any terms proposed in Customer's acceptance of this proposal which add to, vary from, or conflict with this proposal or US Ecology’s Standard Terms and Conditions, are hereby rejected.
Any such proposed terms shall be void and the terms in this proposal and US Ecology's Standard Terms and
Conditions shall constitute the complete and exclusive statement of the terms and conditions of the contract between US Ecology and Customer.
We appreciate the opportunity to submit this proposal. If you have any questions or require additional information, please contact me at the phone number or address below. If you accept this proposal, please sign and return to US Ecology.
Cc: SRV CTR, Bus Dev Rep
AGREED: HSW Engineering, Inc.
By:_______________________
Date: ____/____/____
Nick Soucy
Respectfully, Regional Estimator
1736 Bayview Avenue
Panama City, FL 32405
850-563-0822
Nick SoucyNick SoucyNick SoucyNick Soucy
Cc: Gary Jones, Branch Manager
FDEP COST ESTIMATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: 6-Apr-21
Task #: BF562E SubTask 1 Project Management SubTask 6
Site: SubTask 2 Waste Disposal Oversight SubTask 7
Activity/Phase: Waste Disposal SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
HSW Engineering, Inc.
$66.35 Project Manager SDF 1 1.1
Senior Geologist 0 0 0 0 0 0 0 0 0 0 $66.35 Project Manager SDF 2 2 0 0 0 0 0 0 0 0
Staff Geologist 0 0 0 0 0 0 0 0 0 0 $45.20 Senior Engineer NSB 2 2 0 0 0 0 0 0 0 0
Project Geologist 0 0 0 0 0 0 0 0 0 0 Senior Engineer 0 0 0 0 0 0 0 0 0 0 Project Scientist 0 0 0 0 0 0 0 0 0 0 Staff Engineer/Geologist 0 0 0 0 0 0 0 0 0 0 Project Engineer 0 0 0 0 0 0 0 0 0 0
$28.50 Staff Scientist CO 12 12 0 0 0 0 0 0 0 0 Senior GIS Technician 0 0 0 0 0 0 0 0 0 0 CADD Technician 0 0 0 0 0 0 0 0 0 0 Project Assistant 0 0 0 0 0 0 0 0 0 0
$0.00 CADD Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Surveyor (PLS) 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Party chief 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Crew 0 0 0 0 0 0 0 0 0 0 $0.00 Subsurface Utility Location (SUE) Tech 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 17 1 16 0 0 0 0 0 0 0 0
HSW Engineering, Inc.
Direct Labor $635.74 $70.64 $565.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 170.00% $1,080.76 $120.09 $960.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (HSW) $1,716.50 $190.73 $1,525.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $1,716.50 $190.73 $1,525.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $31.79 $3.53 $28.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Town of Esto - Lamb's Recycling
Steven Folsom/Megan Johnson
REV: 05/2015 CEF: CARDNO HSW Page 1
FDEP COST ESTIMATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: 6-Apr-21
Task #: BF562E SubTask 1 Project Management SubTask 6
Site: SubTask 2 Waste Disposal Oversight SubTask 7
Activity/Phase: Waste Disposal SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Town of Esto - Lamb's Recycling
Steven Folsom/Megan Johnson
Travel Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $5,395.00 $5,395.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities (sewer) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $5,395.00 $5,395.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $539.50 $539.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $5,934.50 $5,934.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $7,812.29 $194.26 $7,618.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $171.65 $19.07 $152.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $7,983.94 $213.33 $7,770.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 2
SITE : Town of Esto - Lamb's Recycling
FDEP NO: ERIC_7390
SUBTASK: 2 - Waste Disposal Oversight
DATE: 4/9/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager SDF Technical Assistance 2
Senior Engineer NSB Field Documentation Submittal Prepration 2
Staff Scientist CO Mobilization 4 Disposal Pickup Oversight 8
TOTAL LABOR 16
TRAVEL TYPE RATE UNIT USEAGE Miles Free
Truck $97.00 day 1 $97.00 $0.00 $0.00
TOTAL VEHICLE $97.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
Capitol Environmental Waste Disposal $5,395.00 LS 1 $5,395.00 $0.00 $0.00
TOTAL SUBS $5,395.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Expendables $32.50 day 1 $32.50 Sub-Total $32.50
$0.00 Sub-Total $0.00
TOTAL EQUIPMENT $32.50
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .