This document is a Task Assignment Notification Form (TA BF562C) issued by the Florida Department of Environmental Protection (FDEP) under Contract No. HW556 with Cardno, Inc. (HSW Engineering, Inc.), a private environmental consulting firm. The task assignment pertains to site assessment activities at the Former Lamb's Recycling Facility located at 1067 North Highway 79 in Esto, Holmes County, Florida. The work is funded through the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The project is managed by Kelly Crain (FDEP Contract Manager) and Megan R. Johnson (FDEP Task Manager), with Bruce Moore serving as the contractor's representative.
The task assignment encompasses site assessment activities and preparation of a final Site Assessment Report (SAR) structured across five subtasks: Project Management ($1,301.05), QAPP/Work Plan and Health and Safety Plan preparation ($2,236.84), Site Assessment Activities including soil and groundwater sampling and laboratory analysis ($19,998.97), IDW disposal and monitoring well abandonment ($5,826.97), and Site Assessment Report preparation ($3,511.23), for a total contract value of $32,875.06. The scope includes installation of seven shallow monitoring wells, collection of 26 soil samples and seven groundwater samples analyzed for volatile organic compounds, polycyclic aromatic hydrocarbons, total recoverable petroleum hydrocarbons, and RCRA 8 metals via EPA-approved methods, with analysis performed by Advanced Environmental Laboratories of Tallahassee. Subcontractor costs include drilling services from Preferred Drilling Solutions, Inc. ($8,337.50 for well installation), IDW disposal from Irwin Remediation ($1,800.00), and laboratory analysis ($6,638.00). The final deliverable (Site Assessment Report) is due by October 23, 2020, with the task assignment execution period extending through November 23, 2020.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW556
SRPPM SRP18BF562C
Cardno
Bruce Moore, P.G. Phone#: (850) 385-8232
(850) 245-8953Kelly Crain
ERIC_7390
Former Lamb's Recycling Facility
1067 North Highway 79, Esto, Holmes County, Florida 32425
Site Assessment Activities and Report
The Department approves this Task Assignment (TA) based upon the Cost Proposal and Level of Effort (CP/LOE) for soil and groundwater assessment activities, submitted to the Department on June 16, 2020 (revised July 9, 2020 and July 27, 2020) by Cardno. The final deliverable will be a Site Assessment Report, received by the Department no later than October 23, 2020.
Site Assessment Report (SAR)
10/23/2020
11/23/2020
$ 32,875.06 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Megan R. Johnson Digitally signed by Megan R. Johnson Date: 2020.07.31 13:53:48 -04'00'
Kelly Crain Digitally signed by Kelly Crain Date: 2020.07.31 14:02:03 -04'00'
Digitally signed by Jennifer Farrell Date: 2020.07.31 14:41:54 -04'00'
Bruce Moore Digitally signed by Bruce Moore Date: 2020.07.31 15:43:45 -04'00'
$ 32,875.06
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
QAPP/Work Plan and HASP 08/21/2020
Field notes, photographic log, chain of custody, soil sampling logs 09/11/2020
Documentation of IDW disposal and monitoring well abandonment 10/09/2020
Site Assessment Report 10/23/2020
Department approval of QAPP/Work Plan and HASP (Subtask 2) $ 2,236.84
Department approval of field notes, photographic log, chain of custody, soil sampling logs (Subtask 3) $ 19,998.97
Department approval of IDW disposal and monitoring well abandonment documentation (Subtask 4) $ 5,826.97
Department approval of Site Assessment Report (Subtasks 1 & 5) $ 4,812.28
$ 32,875.06
HW556
BF562C
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: Cardno, HW556 Contract File
FROM: Kelly Crain, Contract Manager
DATE: July 31, 2020
SUBJECT: Negotiation Summary – SRP 18 Task Assignment (TA) BF562C
Town of Esto - Former Lamb’s Recycling Facility Facility ID # ERIC_7390 Site Assessment Activities and Report (SAR)
This TA is intended for conducting Site Assessment Activities at the Former Lamb’s Recycling Facility site, located at 1067 North Highway 79, Esto, Holmes County, Florida 32425. The scope of work builds upon the limited Phase II Environmental Site Assessment (ESA) activities conducted by Cardno in February 2020, and subsequent May 5, 2020 Phase II ESA Report conclusions and recommendations. The services are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, fringe and other direct costs. The agreed upon cost of this subtask is $1,301.05.
Subtask 2: QAPP/Work Plan, and Health and Safety Plan In accordance with an EPA directive, this subtask includes the completion of a Quality Assurance Project Plan (QAPP)/Work Plan, a Health and Safety Plan (HASP), and to coordinate utility location at the proposed soil boring and monitoring well locations. The QAPP/Work Plan will provide a brief summary of the scope of work, tables and figures showing the proposed sample locations, and laboratory and field quality assurance measures and procedures. The agreed upon cost of this subtask is $2,236.84.
Subtask 3: Site Assessment Activities Under this subtask, Cardno will install seven shallow monitoring wells and collect groundwater samples for analysis of volatile organic compounds (VOCs) via EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) via EPA Method 8270, total recoverable petroleum hydrocarbons (TRPHs) via FL PRO Method, and RCRA 8 metals via EPA Method 6010. Cardno will also collect 16 soil samples from eight soil borings at step out locations from previous Phase II ESA soil sample locations to analyze for lead and synthetic precipitation leaching procedure (SPLP) via EPA Method 1311. Ten additional soil samples will also be collected from five soil borings to be analyzed for VOCs, PAHs, TRPHs, and RCRA 8 metals via the methods listed above. Soil http://www.floridadep.gov/
Negotiation Summary – Task Assignment (TA) BF562C Former Lamb’s Recycling Facility
ERIC_7390
Holmes County Site Assessment Activities July 31, 2020 www.FloridaDEP.gov samples will be collected from soil borings advanced with hand augers from 0 to 0.5 and 0.5 to 2 feet below land surface intervals. The soil and groundwater samples will be analyzed by Advanced Environmental Laboratories (AEL) of Tallahassee, Florida. The agreed upon cost of this subtask is $19,998.97.
Subtask 4: IDW disposal and monitoring well abandonment Upon receipt of the analytical reports, IDW disposal will be scheduled after the licensed waste disposal facility approves the drums for transport. At that time, it is expected that the monitoring wells will also be abandoned. The agreed upon cost of this subtask is $5,826.97.
Subtask 5: Site Assessment Report A Site Assessment Report will be prepared detailing the field and laboratory results. This report will also include figures, tables, and conclusions and recommendations for any future work. The agreed upon cost of this subtask is $3,511.23.
Summary Cardno received three subcontractor quotes for the drilling work to be done on site, with the lowest coming from Betts. However, Betts submitted an incomplete quote, having not included the costs for well abandonment. Following multiple attempts by Cardno, requesting a complete quote, it was decided to use Preferred Drilling Solutions, Inc. for this project.
The Department’s SRP Contract Manager and Cardno’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $32,875.06.
Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) spreadsheets and CP/LOE letter provided by Cardno on June 16, 2020 (revised July 9, 2020 and July 27, 2020), as well as the Task Assignment Form for BF562C prepared by the Department.
The final deliverable must be received by the Department no later than October 23, 2020.
http://www.floridadep.gov/
2420 Lakeshore Drive Suite 100 Tallahassee, FL 32312
USA
Phone 850.385.8232 www.Cardno.com
July 27, 2020
Kelly Crain Environmental Manager Brownfields and CERCLA Site Screening Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4535 Tallahassee, FL 32399
RE: Technical Scope and Cost Proposal Assessment Activities and Site Assessment Report (SAR)
Town of Esto – Former Lamb’s Recycling Facility 1067 North Highway 79 North (FL ID 982145583 & ERIC_7390)
Esto, Holmes County, Florida 32425
Dear Ms. Crain:
Cardno is pleased to submit the following cost proposal for preparation of a site-specific quality assurance project work plan, an updated OSHA-compliant health and safety plan (HASP), soil assessment activities, monitor well installation, groundwater sampling and preparation of a final Site Assessment Report (SAR) for the above referenced property. The work plan will include the sampling and analysis plan, figures, subcontractor quotes, including laboratory and field quality assurance measures and procedures. The final report will summarize all of the findings and recommendations including, but not limited to tables, figures, field notes, laboratory analytical reports and professional certification. The cost estimate and level of effort spreadsheets are included as an attachment.
Subtask 1:
This subtask is designed for project management which calculates a percentage of the overall project fees as negotiated in the final approved contract rate schedule.
Subtask 2:
This subtask includes preparation of a site-specific quality assurance project plan (QAPP) and an updated OSHA-compliant health and safety plan (HASP). The QAPP and HASP plan will include the sampling and analysis plan, figures, including laboratory and field quality assurance measures and procedures. Cardno will deliver the QAPP and HASP within three (3) weeks upon receipt of the executed task assignment.
Subtask 3:
Services provided under this subtask includes the installation of seven (7) shallow monitoring wells and collection of groundwater samples for analysis of volatile organic compounds (VOCs) vis EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) via EPA Method 8270, total recoverable petroleum hydrocarbons (TRPH) via FL PRO method, and RCRA 8 metals via EPA Method 6010.
Eight (8) step out soil borings will be advanced with hand augers around SB-1 and SB-4 and sixteen (16) soil confirmatory samples will be collected from 0.0 to 0.5 and 0.5 to 2.0 feet below land surface (bls) intervals.
These soil samples will be analyzed for lead and synthetic precipitation leaching procedure (SPLP) via EPA Method 1311.
Five (5) additional soil borings will be advanced in the areas identified in historical aerial photographs to be collected at 0.0 to 0.5 and 0.5 to 2.0 foot depth intervals. The ten (10) soil samples will be analyzed for volatile organic compounds (VOCs) via EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) via EPA Method
Kelly Crain Page Two July 27, 2020
8270, total recoverable petroleum hydrocarbons (TRPH) via FL PRO method, and RCRA 8 metals via EPA Method 6010.
The samples will be transported to Advanced Environmental Laboratories (AEL) in Tallahassee for normal turnaround time delivery. All field documentation (field notes, sampling logs, etc.) will be submitted to the Department as an interim deliverable within seven (7) days upon completion of the field activities.
Subtask 4:
Upon receipt of the analytical reports, IDW disposal will be scheduled with the remediation contractor after the licensed waste disposal facility approves the drums for transport. In addition, it is expected that the monitor wells will be abandoned based on the results from the analytical data. Cardno anticipates that two (2) separate mobilizations will be required for these activities.
Subtask 5:
The final Site Assessment Report (SAR) will be submitted within forty-five (45) days upon completion of the field activities. The final report will summarize all of the findings and recommendations including, but not limited to tables, figures, field notes, laboratory analytical reports and professional certification.
Compensation:
The scope of services will be performed on a lump sum basis for $ 32,875.06 and in accordance with the Terms and Conditions of Contract No. HW556 between Cardno/HSW and the Florida Department of Environmental Protection (FDEP) dated December 27, 2010. Any variations to the schedule, scope of work, or site description may require a modification of the cost estimate. It is our understanding that authorization from FDEP to Cardno providing for the implementation of the proposed scope of work will be transmitted in the form of an executed Task Assignment (TA).
Schedule:
This work will commence upon receipt of the executed task assignment and the final work plan and HASP will be submitted to FDEP within three (3) calendar weeks and field activities within seven (7) workdays upon approval of the field activities outlined in the quality assurance work plan. In addition, you will find attached the cost estimate and level of effort spreadsheets included as Attachment A.
We appreciate your consideration of our firm for this work and look forward to working with you on this project.
If you have any questions or concerns, please do not hesitate to contact me at 850.629.2700 or via email at beth.norman@cardno.com.
Sincerely, Beth Norman Project Manager for Cardno cc: Megan R. Johnson, FDEP Justin L. Cross, FDEP
/brn: Attachments
COST ESTIMATE & LEVEL OF EFFORT
SPREADSHEETS
FDEP COST ESTIMATE
Cardno / HSW
Contract No. HW556
Contractor: CARDNO / HSW
Date: 27-Jul-20 Task #: BF562C SubTask 1 Project Management SubTask 6
Site: Former Lamb's Recycling Facility SubTask 2 Preparation/Submittal of QAPP & HASP SubTask 7 Activity/Phase: Site Assessment Report SubTask 3 Site Assessment Activities, Soil & GW Sampling & Laboratory Analysis SubTask 8
Project Manager: Beth Norman SubTask 4 Monitoring Well Abandonment Activities SubTask 9 SubTask 5 Report Preparation SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
CARDNO, Inc.
$38.43 Project Manager (BN) 3 3.0 $38.43 Project Engineer/Geologist (BN) 44 16 0 4 24 0 0 0 0 0 $42.31 Project Engineer/Geologist (EM) 5 3 0 0 2 0 0 0 0 0 $26.25 Staff Geologist (AS) 32 0 26 0 6 0 0 0 0 0 $15.42 Field Tech (RF) 46 0 26 20 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Hours 130 3 19 52 24 32 0 0 0 0 0
CARDNO, Inc.
Direct Labor $3,883.26 $431.47 $741.81 $1,083.42 $462.12 $1,164.44 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 169.58% $6,585.23 $731.69 $1,257.96 $1,837.26 $783.66 $1,974.66 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (CARDNO) $10,468.49 $1,163.16 $1,999.77 $2,920.68 $1,245.78 $3,139.10 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $10,468.49 $1,163.16 $1,999.77 $2,920.68 $1,245.78 $3,139.10 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $194.16 $21.57 $37.09 $54.17 $23.11 $58.22 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Vehicle Use - Truck $97.00 $0.00 $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem Meals Only $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem Hotel Only $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $388.00 $0.00 $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Laboratory Analysis (AEL) $6,638.00 $0.00 $6,638.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Driller (Preferred Drilling) $10,332.50 $0.00 $8,337.50 $1,995.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW Disposal (Irwin) $1,800.00 $0.00 $0.00 $1,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $18,770.50 $0.00 $14,975.50 $3,795.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,877.05 $0.00 $1,497.55 $379.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $20,647.55 $0.00 $16,473.05 $4,174.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Expendables $130.00 $0.00 $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $696.50 $0.00 $696.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling Related) $368.60 $0.00 $368.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical Related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW Related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $31,828.20 $1,184.73 $2,036.86 $19,706.90 $5,702.39 $3,197.32 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,046.86 $116.32 $199.98 $292.07 $124.58 $313.91 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $32,875.06 $1,301.05 $2,236.84 $19,998.97 $5,826.97 $3,511.23 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 1
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Lamb's Recycling Facility SUBTASK: 2 - Preparation of QAPP & HASP
DATE: 7/27/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE HOURS
Project Engineer/Geologist (BN) Preparation of QAPP & HASP (Figures Included) 16 Project Engineer/Geologist (EM) QAPP QA/QC Review 3
Figures To Be Included:
Figure 1: Site Vicinty Map
Figure 2: Proposed Soil Boring & Monitoring Well Locations Map
Figure 3: Abandoned Drum / Container Locations Map
TOTAL LABOR 19
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00
TOTAL LAB $0.00
SUBCONTRACTOR / SERVICES COSTS
NAME PURPOSE COST
TOTAL $0.00
FINAL --7/24/96
SITE : Former Lamb's Recycling Facility SUBTASK: 3- Site Assessment Activities (Soil & GW Sampling & Laboratory Analysis)
DATE: 7/27/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE HOURS
Staff Engineer (AS) Mobilization, Soil & GW Sampling & Field Documentation Advance Thirteen (13) Soil Borings via Hand Auger Collection of Twenty Six (26) Soil Samples & Record GPS Location(s) Collection of Seven (7) Groundwter Samples & Record GPS Locations Collection of Soil/Water Characterization Sample (8) Drums 26
Field Tech (RF) Mobilization, Soil & GW Sampling & Field Documentation Advance Thirteen (13) Soil Borings via Hand Auger Collection of Twenty Six (26) Soil Samples & Record GPS Location(s) Collection of Seven (7) Groundwter Samples & Record GPS Locations Collection of Soil/Water Characterization Sample (8) Drums 26
Total Mobilization - 90 miles and 1 hour and 15 minutes (one way) Total Hours for mobilization = 2 hours and 30 minutes TOTAL LABOR 52
EQUIPMENT RATE COSTING UNIT USEAGE TOTALS
Soil Assessment Kit $139.70 2 $279.40 Monitor Well Installation Kit $184.30 2 $368.60 Shallow Groundwater Kit $208.55 2 $417.10
TOTAL EQUIPMENT $1,065.10
VEHICLE TYPE RATE UNIT USEAGE
Cardno Vehicle Truck $97.00 1 2 $194.00
TOTAL VEHICLE $194.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
AEL Laboratory VOCS 8260 $66.00 7 GW $462.00 AEL Laboratory PAHs 8270 $100.00 7 GW $700.00 AEL Laboratory TRPH FL PRO $84.00 7 GW $588.00 AEL Laboratory RCRA 8 Metals 6010 $92.00 7 GW $644.00 AEL Laboratory Lead Only 6010 $11.50 16 Step Out SB $184.00 AEL Laboratory SPLP - Lead Only 1311 $40.00 16 Step Out SB $640.00 AEL Laboratory VOCS 8260 $66.00 10 Soil $660.00 AEL Laboratory PAHs 8270 $100.00 10 Soil $1,000.00 AEL Laboratory TRPH FL PRO $84.00 10 Soil $840.00 AEL Laboratory RCRA 8 Metals 6010 $92.00 10 Soil $920.00
SB Sample Depths 0.0-0.5 and 0.5-2.0 Depth Intervals
TOTAL LAB $6,638.00
EXPENDABLES
NAME PURPOSE RATE UNIT COST
Expendables (AS & RF) $32.50 2 $65.00
TOTAL $65.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Preferred Drilling Drillers / Installation of Monitor Wells $8,337.50
$0.00
TOTAL $8,337.50
SITE : Former Lamb's Recycling SUBTASK: 4 - Well Abandonment & IDW Disposal
DATE: 7/27/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Engineer/Geologist (BN) Driller /Remedial Contractor Coordination & Scheduling 4 Field Tech (RF) Field Activities & Oversight of IDW Disposal ** 8 Field Tech (RF) Field Activities & Oversight Well Abandonment Activities ** 12
** Assuming two (2) separate mobilizations; one for the IDW Contractor; and one for the Driller Well Abandonments
Total Mobilization - 90 miles and 1 hour and 15 minutes (one way)
Total Hours for mobilization = 2 hours and 30 minutes TOTAL LABOR 24
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USEAGE
Cardno Vehicle Truck $97.00 1 2 $194.00
** Assuming two (2) separate mobilizations; one for the IDW Contractor; and one for the Driller Well Abandonments
TOTAL VEHICLE $194.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE USEAGE
Irwin Remediation Inc. IDW Disposal * $100.00 18 $1,800.00 Preferred Drilling Well Abandonment Activities $1,995.00
* Assumes all Non-Hazardous Contents - 10 ea IDW (Soil/Water) and 8 ea Abandoned Drums TOTAL $3,795.00
EXPENDABLES
NAME PURPOSE RATE UNIT COST
Expendables (RF) $32.50 2 $65.00
** Assuming two (2) separate mobilizations; one for the IDW Contractor; and one for the Driller Well Abandonments
TOTAL $65.00
SITE : Former Lamb's Recycling SUBTASK: 5 - Report Preparation (Final Draft, Final)
DATE: 7/27/2020
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Engineer/Geologist (BN) Preparation of Final Site Assessment Report (SAR) 24 Project Engineer/Geologist (EM) Final Report QA/QC 2 Staff Geologist (AS) Tables, Sample Logs 6
TOTAL LABOR 32
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$0.00
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USEAGE
$0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00
TOTAL LAB $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
$0.00
TOTAL $0.00
Contractor: Cardno, Inc. (HSW Engineering, Inc.) February 5, 2020 Contract No. HW556
Cardno Direct Labor Rates Name Initials Classification Direct Labor Rate Miles Ballogg MB Principal $70.35 Rick Hagberg, PG RH Principal $76.06 Terry Griffin, PG TG Senior Engineer/Geologist $64.57 Bruce Moore BM Senior Engineer/Geologist $55.29 Greg Schultz, PE GS Senior Engineer/Geologist $54.57 Joel Carter JC Senior Scientist/Specialist $70.37 Eric Lalone EL Senior Scientist/Specialist $54.44 Dana Kress DK Project Engineer/Geologist $40.36 Shawn Lasseter SL Project Engineer/Geologist $41.94 Joe Marsh JM Project Engineer/Geologist $41.62 Eric Meyers EM Project Engineer/Geologist $42.31 Beth Norman BN Project Engineer/Geologist $38.43 Douglas Strait DS Project Engineer/Geologist $42.69 Thomas Causey TC Staff Engineer/Geologist $25.76 Katie Dobson KD Staff Engineer/Geologist $23.61 Enrico Gonzalez EG Staff Engineer/Geologist $24.89 Alex Jones AJ Staff Engineer/Geologist $20.10 Marleny Santana MS Staff Engineer/Geologist $27.69 Ashton Smithwick AS Staff Engineer/Geologist $26.25 Victor Urgiles VU Staff Engineer/Geologist $20.91 Katitlyn I. Woolard KW Project Surveyor $35.40 Robert Frizzell RF Field Technician $15.42 Gina Dykas GD Project Assistant $24.11 Michelle Rebmann MR Project Assistant $19.42 Phillip Brown PB CADD Technician $24.56 Frank Nolte FN CADD Technician $32.88 Tanya Camacho TC Senior GIS Specialist $43.13
HSW Direct Labor Rates Name Initials Classification Direct Labor Rate Fred Seguiti FAS Principal $74.52 Steven Folsom SDF Principal $66.35 Derek Huston DEH Principal $66.35 Zeke He ZH Senior Engineer $56.93 Cheryl Nichols CAN Senior Engineer $49.76 William Lais WGL Senior Engineer $55.29 Nicholas Barnes NSB Senior Engineer $45.20 Richard Poff RWP Senior Engineer/Geologist $51.45 Andy Lawn AML Senior Geologist $60.10 Cindy Westergard CLW Senior Scientist $45.68 Ravi Nalamothu RCN Project Engineer $44.24 Fabio Fortes FLF Project Engineer $29.81 Jason Chicchetti JPC Project Engineer $36.30 Benjamin Alex BLA Project Engineer $39.67 Jim Dozier JRD Project Geologist $43.27 Chad Thompson CMT Project Geologist $36.30 Joseph Bolich JAB Staff Engineer $33.66 Kyle Turner KMT Staff Geologist $25.97 Tim Easter TBE Senior Field Technician $30.75 Brittany Kinney BNK Project Assistant $15.00 Ken Badgley KCB GIS Technician $26.45
Harris_D Cross-Out
Figure 1 USGS/Site Vicinity
Map Not to Scale
Ins
Inset
Former Lamb’s Recycling Facility 1067 Highway 79 North Esto, Holmes County, Florida 32425 Parcel ID No. 0328.03-001-31S-007.000
FDEP HW556 - TA BF 562B
Approximate Location
Source:
EDR Report US Geological Survey (USGS)
Figure 2 Proposed Soil Boring and
Monitoring Well Locations Map 100 0 100
Former Lamb’s Recycling Facility 1067 Highway 79 North Esto, Holmes County, Florida 32425 Parcel ID No. 0328.03-001-31S-007.000
FDEP HW556 - TA BF 562B
Aerial Photograph Source:
Holmes County Property Appraiser
Notes:
1. Proposed step out soil borings (8 each) collected as confirmatory samples around SB-1 and SB-4 to be collected at 0.0 to 0.5 and 0.5 to 2.0 foot depth intervals and analyzed for lead and synthetic precipitation leaching procedure (SPLP) via EPA Method SW-846.
2. Proposed soil borings (5 each) collected in the areas identified in historical aerial photographs to be collected at 0.0 to 0.5 and 0.5 to 2.0 foot depth intervals and analyzed for volatile organic compounds (VOCs) via EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) via EPA Method 8270, total recoverable petroleum hydrocarbons (TRPHs) via FL PRO Method, and Resource Conservation and Recovery Act (RCRA) eight (8) metals (arsenic, barium, cadmium, chromium, lead, mercury, selenium, and silver) via EPA Method 6010.
3. Groundwater samples (7 each) collected will be analyzed for volatile organic compounds (VOCs) via EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) via EPA Method 8270, total recoverable petroleum hydrocarbons (TRPHs) via FL PRO Method, and Resource Conservation and Recovery Act (RCRA) eight (8) metals (arsenic, barium, cadmium, chromium, lead, mercury, selenium, and silver) via EPA Method 6010. Newly Installed monitor wells (MW-1 through MW-4) will be co-located with soil boring locations (SB-7 through SB-10).
LEGEND
Proposed Monitoring Well Location (7 each)
Proposed Soil Boring Location (13 each)
Soil Boring Location (February 2020)
Additional Areas of Concern (Identified in historical aerials and during the Phase II ESA field activities)
Area of Concern Boundary (Identified during the Phase I)
Approximate Site Boundary (For reference purposes only, not a surveyed boundary)
SB-5
MW-7
SB-3
SB-2
SB-1
MW-6
SB-6
SB-10 / MW-4
SB-7 / MW-1
SB-8 / MW-2
SB-9 / MW-3
SB-4
MW-5
SUBCONTRATOR QUOTES
(DRILLERS)
Preferred Drilling Solutions, Inc.
11747 87th St. North, Largo, FL 33773
Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
Contractor Name: Cardno
Site Name & Location: Former Lamb's Recycling Facility Date: 6/8/20 FAC ID#:
1067 Hwy 79 N, Esto, FL
PROPOSED SCOPE OF WORK:
Abandon 7-2" MW's 25' each, remove pads and manholes, restore with top soil, remove and dispose of debris
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Unit Unit Rate Number of Units Extended Price
Rig Type: Auger/Mud Rotary_____ Sonic_____ Other_____
Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation) (includes decon)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Borehole Grouting
4 - inch borehole diameter per foot $0.00 6 - inch borehole diameter per foot $0.00 8 - inch borehole diameter per foot $0.00
1" - 2" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
4" Well Installation (includes steamcleaning decon, screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Recovery Well Diameter: 4-6" per foot $0.00 Double Cased Wells $0.00
6" Surface Casing per foot $0.00 8" Surface Casing per foot $0.00 per well $0.00 and saw/jackhammer prep.)
1"- 2" Well Abandonment (includes grouting) per foot $6.00 175 $1,050.00 3"- 4" Well Abandonment (includes grouting) per foot $0.00 5"- 6" Well Abandonment (includes grouting) per foot $0.00 2' x 2' Well Pad Removal each $75.00 7 $525.00
Mobilization roundtrip $400.00 1 $400.00
Per Diem per crew $0.00 DOT Approved 55-gal Drum each $0.00 Permits (Drilling or abandonment only) each $20.00 1 $20.00
$0.00
$0.00
$0.00 Additional Development Time per hour $0.00 Additional Decontamination Time per hour $0.00 Standby/Delay/Difficult Access Time per hour $0.00
TOTAL QUOTE PRICE $1,995.00
Days to Complete Scope of Work: 1 Project No.:
Signature and Title of Person Submitting Quote: __________________________________Kevin Bonacum, Estimator Date: 6/8/20
Well Completion (includes 30 minute development, MH w/ cover, concrete pad, locking well cap, DRILLING
MISCELLANEOUS
Cardno, Former Lamb's Recycling Facility, Esto (abandonment)
Preferred Drilling Solutions, Inc.
11747 87th St. North, Largo, FL 33773 Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
DIRECT PUSH TECHNOLOGY QUOTE FORM
Consultant Name: Cardno
Site Name and Location: Former Lamb's Recycling Facility Date: 6/8/20 FAC ID#:
1067 Hwy 79 N, Esto, FL
PROPOSED SCOPE OF WORK:
(7) 2" x 25' MW's with 10' .010 screen, soil sampling as needed, pad and 8" manhole
Drum soil & water
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Unit Unit Rate Number of Units Extended Price
Equipment Type: Geoprobe 7822DT, Geoprobe 7720DT
Direct Push Daily Rate 1 - on-site day whole day $1,500.00 2 $3,000.00 Direct Push Half-Day Rate 1 - on-site half day half day $1,100.00 1 $1,100.00 Auger Attachment, 2" Well Install per foot $12.50 175 $2,187.50 Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5" each $75.00 $0.00 Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5" each $25.00 $0.00 Well Riser (includes all materials) ID 1" 5' Length each $15.00 $0.00 Well Completion (includes manhole w/ cover, concrete pad, and locking well cap) per well $100.00 7 $700.00
Mobilization roundtrip $500.00 1 $500.00 Per Diem per crew / per night $0.00 $0.00 DOT Approved 55-gal Drum each $50.00 16 $800.00 Permits each $50.00 1 $50.00 Other (specify) $0.00 Other (specify) $0.00 Other (specify) $0.00
TOTAL QUOTE PRICE $8,337.50
Notes:
1. Includes expendables, tubing, points, liners, caps, plugs, sawcuts, development, standby time, steamcleaning decon, and grouting.
Days to Complete Scope of Work: 2.5 Project No.:
Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477
Subcontract Mailing Address:8820 66th Street North, Pinellas Park, FL 33782
Signature and Title of Person Submitting Quote: ___________________________________Kevin Bonacum, Estimator Date: 6/8/20
DIRECT PUSH TECHNOLOGY
MISCELLANEOUS
Sonic Auger DPT Horizontal Directional Drilling
DATE: 6/5/2020
ESTIMATE #: 620025
ID QTY Unit Rate TOTAL
1 1 each 3,000.00$ 3,000.00$
2 2 night 300.00$ 600.00$
3 Daily Rate: Sonic Drill w/ crew 1 day 3,750.00$ 3,750.00$
4 Daily Rate: Sonic Drill w/ crew 1 1/2 day 2,500.00$ 2,500.00$
5 Materials: 2" Well Installations 175 foot 10.00$ 1,750.00$
6 8" Bolt Down Completion 7 each 100.00$ 700.00$
7 Well Development (Up to 1/2 Hour w/ Pump) 7 each 75.00$ 525.00$
8 Drums (Soil) Estimated 4 each 55.00$ 220.00$
9 Drums (Water) Estimated 1 each 55.00$ 55.00$
10 Permits: 1 each 30.00$ 30.00$
Completion: Subtotal 13,130.00$
David Boggs
David Boggs TOTAL 13,130.00$
Project Manager
THANK YOU FOR YOUR BUSINESS!
Per Diem (3 man crew)
***Damages to utilities on private property during borehole clearance are the responsibility of the client***
Beth Norman Cardno 2420 W. Lakeshore Drive Suite 100 Tallahassee, Florida 32303
(850) 629-2700
PROJECT DESCRIPTION:
Drum Soils & Water
Well Installations
1.5 Days
If you have any questions concerning this proposal contact David Boggs at (407) 426-7885 or David@drillprollc.com.
CUSTOMER
Esto, Florida
PROJECT
Former Lamb's Recycling 1067 Hwy 79 North
"Utility locates on Private Property are the responsibility of the client"
"Actual quantities used and days onsite will be invoiced"
DESCRIPTION
Mobilization / Demobilization
(7) 2" x 25' MW's w/10' of .010" Slotted Screen- 8" Boltdown Completions- No Soil Sampling
2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586
Sonic Auger DPT Horizontal Directional Drilling
DATE: 6/5/2020
ESTIMATE #: 620025 A
ID QTY Unit Rate TOTAL
1 1 each 1,750.00$ 1,750.00$
2 1 night 200.00$ 200.00$
3 Grout and abandon 2" Wells 175 foot 6.00$ 1,050.00$
4 Remove pads/manholes and patch surfaces w/concrete 7 each 95.00$ 665.00$
5 Well Development (Up to 1/2 Hour w/ Pump) 0 each 75.00$ -$
6 Permits: 7 each 10.00$ 70.00$
Completion: Subtotal 3,735.00$
David Boggs
David Boggs TOTAL 3,735.00$
Project Manager
Grout and abandon (7) 2" x 25' MW's - Remove pads/manholes and patch surfaces w/concrete
If you have any questions concerning this proposal contact David Boggs at (407) 426-7885 or David@drillprollc.com.
CUSTOMER
Esto, Florida
PROJECT
Former Lamb's Recycling 1067 Hwy 79 North
"Utility locates on Private Property are the responsibility of the client"
"Actual quantities used and days onsite will be invoiced"
DESCRIPTION
Mobilization / Demobilization
THANK YOU FOR YOUR BUSINESS!
Per Diem (2 man crew)
***Damages to utilities on private property during borehole clearance are the responsibility of the client***
Beth Norman Cardno 2420 W. Lakeshore Drive Suite 100 Tallahassee, Florida 32303
(850) 629-2700
PROJECT DESCRIPTION:
Well Abandonments
1/2 Day plus travel
2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586
From: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Sent: Wednesday, July 22, 2020 1:25 PM To: Beth Norman Cc: Crain, Kelly; Cross, Justin L.
Subject: RE: Response & Clarification ------ Cost Estimate - Lamb's Recycling SAR --- Direct
Push versus Sonic Costs Attachments: Former Lamb's Recycling CE 07 09 2020_DEP highlighted.pdf
Hi Beth, I’ve talked with Kelly and we both agree with your reasoning to stay with the current selected drillers. The only thing we need edited on the CP/LOE for the new Lamb’s TA is the removal of ice on both Subtask 3 and Subtask 4, since it is covered under the blanket expendables cost. Please let us know if you have any questions.
Thanks, Megan
From: Beth Norman <Beth.Norman@cardno.com> Sent: Tuesday, July 21, 2020 4:17 PM To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov>; Crain, Kelly <Kelly.Crain@dep.state.fl.us> Subject: Response & Clarification ‐‐‐‐‐‐ Cost Estimate ‐ Lamb's Recycling SAR ‐‐‐ Direct Push versus Sonic Costs
Megan, I checked in with DrillPro (aka Groundwater Protection) to see if they would provide a cost for the well installation via direct push rig versus the sonic rig. See below.
Todd, I just received notice that David is no longer with your firm. Can you please assist?
I am still working with FDEP on the Former Lamb’s Recycling field activities; they asked me to provide them with your well installation costs using direct push instead of sonic rig, to see if we could reduce the costs. I’ve attached your original estimate for your convenience.
To install a 2" well with DPT, we would have to drive the 4" casing and use 2" prepacked screens.
Not sure DPT could get to depth in the clay up there.
Plus, the prepacked screens and the 4" point would be an extra $255 per well.
Sonic is definitely the way to go up there, especially to make sure you get a good well.
With that said, it appears that they are unfamiliar with the geology in the area and Preferred Drilling (aka formerly Huss Drilling) and lowest bid is located in Bonifay.
In addition, we downloaded historical documents (SARs) from the “Friendly Mini Mart” which confirmed that general groundwater flow direction and Huss Drilling had installed the monitor wells and used direct push drill rig(s) with no apparent problem(s).
I’ve attached the email correspondence for your convenience. Feel free to contact me for questions.
Best regards, Norman
PROJECT MANAGER
PRINCIPAL - BROWNFIELDS
CARDNO
Direct +1 850 629 2700 Mobile +1 850 661 5475 Address 2420 W Lakeshore Drive Suite 100, Tallahassee, Florida 32303 Email beth.norman@cardno.com Web www.cardno.com
CONNECT WITH CARDNO
This email and its attachments may contain confidential and/or privileged information for the sole use of the intended recipient(s). All electronically supplied data must be checked against an applicable hardcopy version which shall be the only document which Cardno warrants accuracy. If you are not the intended recipient, any use, distribution or copying of the information contained in this email and its attachments is strictly prohibited. If you have received this email in error, please email the sender by replying to this message and immediately delete and destroy any copies of this email and any attachments. The views or opinions expressed are the author's own and may not reflect the views or opinions of Cardno.
Estimate
DATE
6/4/2020
Estimate NO.
BER204704
NAME / ADDRESS
Cardno TBE 2420 Lakeshore Dr., Ste. 100 Tallahassee, Fl. 32312 Attn: Beth Norman
Site Information:
Former Lambs Recycling Center Esto, FL
Betts Environmental Appreciates your bid request.
TOTAL
Atlanta | Adel | Jacksonville | Tallahassee
"In all thy ways acknowledge him, and he shall direct thy paths." Proverbs 3:6
DESCRIPTION QTY Unit Cost TOTAL
Scope of Work: Install (7) 2" x 25' PVC monitoring well, all with standard construction and 8" flush mount completion.
Wells are accessible to a CME Truck rig.
Mobilization / Demobilization CME Truck Rig w/Auto SPT Hammer 1 500.00 500.00
2" PVC Monitoring Well in Soil 0' - 50' 175 40.00 7,000.00
55 Gallon Drums 9 75.00 675.00
Well Completion 7 150.00 1,050.00
Well Permits 1 30.00 30.00
Abandonment of 2" Monitoring Well by Tremmie Grout per/ft 0 8.00 0.00
Utilities must be cleared and marked prior to starting work! Client listed above is responsible for 811 utility locate call and maintaining an active locate ticket.
Sonic! Sonic! Sonic! Betts is now in the Sonic drilling business and is the first Georgia Sonic drilling company. Call today and schedule your next Sonic drilling job.
$9,255.00
SUBCONTRACTOR QUOTES
(IDW DISPOSAL)
408 Ditmar Street
Pensacola, FL 32503
P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To:
Ms. Beth Norman
Cardno
2420 East Lakeshore Drive – Suite 100
Tallahassee, FL 32312
June 8, 2020
Re: Drum Disposal - Non-Hazardous VOH Impacted Soil or Water
Ms. Norman:
The price to dispose of a 55-gallon drum of non-hazardous soil or water impacted with VOHs, or dry-cleaning solvents, located within the State of Florida will be $100.00 per drum.
This price is a flat-rate that includes both the transportation and disposal for non-hazardous material and is valid for 12-months from the date of this letter. Pricing for the Florida Keys will be handled on a case by case basis.
If the soil or water is deemed to be hazardous additional charges will apply.
We appreciate the opportunity to work with you on this. Should you have any questions, please contact me directly at (850) 292-6511.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: Erwinremediation@gmail.com Phone: (850) 292-6511
1810 Industrial Drive, Panama City, FL 32405 Office: 850-571-3124
06/09/2020
Cardno 2420 W Lakeshore Drive Suite 100 Tallahassee, Florida 32312
Dear Beth, Hull's Environmental Services, Inc. (Hull's) is pleased to submit the enclosed Quote for the Scope of Work described, along with our Standard Terms & Conditions. We appreciate the opportunity to quote this work and are prepared to perform the work upon your approval.
Please do not hesitate to call me if you have any questions. To accept the quote, please sign and date the final page of the quote.
Sincerely, Christina Hiers Administrative Assistant Hull’s Environmental Services
QUOTE
Customer Cardno
Project Street Address 1067 N Highway 79
Project State Florida
Project City Esto
Project Zip 32425
Quote Number Q200356PC
Quote Date Jun 09, 2020 01:35:20 PM
Phone Number 850-661-5475
Email beth.norman@cardno.com
Hull's Rep Christina Hiers
SCOPE OF WORK
Hull's Environmental Services will provide personnel and equipment to transport and dispose of IDW liquid and solid drummed waste. Customer will provide current analytical if required for waste profiling.
Item description Quantity Unit Rate Amount
Stakebody Truck 1.00 Per Day $ 325.00 $ 325.00
Response Technician (actual times will be invoiced)
8.00 Per Hour $ 50.00 $ 400.00
Waste Profile 1.00 Each $ 65.00 $ 65.00
IDW Solid Drum Disposal 5.00 Each $ 70.00 $ 350.00
IDW Liquid Disposal 275.00 Gallon $ 0.65 $ 178.75
TOTAL $ 1,318.75
UNIT PRICING
Enhanced Environmental and Emergency Services 1682 Springridge Rd Raymond, MS 39154
24 Hour Emergency Number 1-844-333-0939 Office 601-897-4595 Fax 1-844-325-0511
6-9-2020
CARDNO
ATTETNION: Beth Norman
Subject: Drum Disposal from Esto FL
Enhanced Environmental & Emergency Services, Inc. (E3), appreciates your confidence in requesting this cost estimate for the above referenced project. Outlined below is our proposed scope of work for the project along with our “Budgetary Cost” for performing the outlined services. Our experienced personnel are 40-hour HAZWOPER trained with years of experience and will ensure your company a safe and timely completed project.
In accordance with OSHA, under 29 CFR 1910.120, all onsite personnel utilized on this project will be 40- Hour trained for working on remediation projects, in confined spaces, and in hazardous atmospheres and environments. As required by OSHA, in addition to the 40-Hour training, E3 will have certified “Confined Space Rescue Trained” personnel onsite. Job Safety Analysis are conducted and documented daily on all our projects.
Scope of work:
Pick up 10 drums of drilling mud and water and disposal of drums.
Compensation:
Pick up drums : $156.00
Trans to landfill: $208.00
Disposal per drum: $ 100.00 each
Empty drums $ 85.00 each
Stake body truck: $ 250.00
Again, E3 appreciates the opportunity to be of service to you and your company, should you have any further questions feel free to contact me at (850)-658-2486
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .