CN-370000-HW556-DC022E.pdf
PDF 1 MB Posted
- Contract number
- HW556
- Issued by
- Florida
About this file
This is a Task Assignment Notification Form (Task Assignment DC022E) issued by the Florida Department of Environmental Protection (FDEP) under DEP Contract No. HW556 with contractor Cardno, Inc. (operating as HSW Consulting, LLC). The task assignment authorizes operation and maintenance activities at the Touch of Class Cleaners site located at 6402 US Highway 41 North, Apollo Beach, Hillsborough County, Florida (FDEP Site No. ERIC_4697). The contract manager is Walsta Jean-Baptiste, and the contractor representative is Eric Meyers. The task assignment was executed on March 4, 2021, with a period of performance extending through August 31, 2022.
The task assignment authorizes six months of soil vapor extraction system operation and maintenance, groundwater performance monitoring, annual groundwater sampling, and investigation-derived waste disposal in accordance with the approved remedial action plan for bioremediation. The contract employs a mixed compensation structure consisting of a fixed price component of $26,253.83 and a cost-plus-fixed-fee component for utility payments not to exceed $4,200.00, with a utilities handling fee of $140.00, resulting in a total task assignment value of $30,453.83. Deliverables include a Quarterly O&M Submittal due February 8, 2022, and a Semi-Annual Remedial Action Status Report due May 9, 2022. Payment is contingent upon FDEP approval of the quarterly O&M submittal and receipt of utility invoices for seven months. The subcontractor Petrotech was selected as the lowest responsive bidder for investigation-derived waste disposal services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW556
D000 NADC022E
Cardno, Inc.
Eric Meyers
850-245-8705Walsta Jean-Baptiste
ERIC_4697
Touch of Class
6402 US Highway 41 North, Apollo Beach, Hillsborough
Operation and Maintenance
This Task Assignment authorizes HSW to conduct six months of operation and maintenance in accordance with the HSW scope of work, schedule, and cost estimate received on February 23, 2021.
The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.
Semi-Annual Remedial Action Status Report
05/09/2022
08/31/2022
$ 26,253.83 $ 0.00 $ 4,200.00 $ 0.00
$ 0.00
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.03.04 14:36:15 -05'00'
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.03.04 14:36:22 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.03.05 09:02:18 -05'00'
Eric Meyers Digitally signed by Eric Meyers Date: 2021.03.05 10:01:34 -05'00'
$ 30,453.83
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Quarterly O&M submittal including field documentation, laboratory reports and tables (submitted electronically) - Subtask 2 02/08/2022
Semi-Annual Remedial Action Status Report (submitted electronically) - Subtask 3 05/09/2022
FDEP approval of quarterly O&M submittal including field documentation, laboratory reports and tables (submitted electronically) - Subtask 2; AND FDEP approval of Semi-Annual Remedial Action Status Report (submitted electronically) - Subtask 3
$ 26,113.83
FDEP receipt of utility invoices for 7 months; Utilities (Cost Plus Fixed Fee) = not to exceed $4,200; Utilities Handling Fee = $140 - Subtask 4 $ 4,340.00
$ 30,453.83
HW556
DC022E
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: HW556 Contract File FROM: Walsta Jean-Baptiste, Contract Manager SUBJECT: Touch of Class Apollo Beach; DC022E Operation and Maintenance DATE: March 4, 2021
This Task Assignment authorizes HSW to conduct operation and maintenance in accordance with the HSW scope of work, cost estimate form, and bid documentation received on February 23, 2021.
Operation and maintenance includes groundwater performance monitoring, annual groundwater sampling, and soil vapor extraction in accordance with the approved remedial action plan for bioremediation. The soil vapor extraction system needs to run continuously for methane mitigation purposes.
Subcontractor costs include investigation derived waste disposal. HSW selected Petrotech as the lowest responsive bidder.
The cost related to this Task Assignment is $30,453.83 with 154 hours.
FDEP COST ESTI MATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: TBD
Task #: TBD SubTask 1 Project Management SubTask 6 Utilities (quarterly)
Site: Touch of Class Cleaners SubTask 2 O&M - Quarter 1 SubTask 7
Activity/Phase: O&M SubTask 3 O&M - Quarter 2 , Semi-Annual Status Report SubTask 8
Project Manager: Steven Folsom SubTask 4 O&M - Quarter 3 SubTask 9
SubTask 5 O&M - Quarter 4, Annual Status Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
HSW Engineering, Inc.
$66.35 Project Manager SDF 10 10.2
Principal 0 0 0 0 0 0 0 0 0 0 $66.35 Project Manager SDF 14 4 10 0 0 0 0 0 0 0
Senior Geologist 0 0 0 0 0 0 0 0 0 0 Senior Engineer 0 0 0 0 0 0 0 0 0 0 Project Geologist 0 0 0 0 0 0 0 0 0 0
$45.20 Senior Engineer NSB 42 10 32 0 0 0 0 0 0 0 $45.68 Senior Scientist CLW 2 0 2 0 0 0 0 0 0 0
Staff Engineer/Geologist 0 0 0 0 0 0 0 0 0 0 $28.43 Staff Scientist WJT 82 42 40 0 0 0 0 0 0 0
Field Technician 0 0 0 0 0 0 0 0 0 0 $45.68 Senior Scientist CLW 0 0 0 0 0 0 0 0 0 0 $39.67 CADD Technician BLA 4 0 4 0 0 0 0 0 0 0 $15.00 Project Assistant BNK 0 0 0 0 0 0 0 0 0 0
$0.00 CADD Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Surveyor (PLS) 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Party chief 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Crew 0 0 0 0 0 0 0 0 0 0 $0.00 Subsurface Utility Location (SUE) Tech 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 154 10 56 88 0 0 0 0 0 0 0
HSW Engineering, Inc.
Direct Labor $6,084.68 $676.08 $1,911.46 $3,497.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 170.00% $10,343.96 $1,149.34 $3,249.48 $5,945.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (HSW) $16,428.64 $1,825.42 $5,160.94 $9,442.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $16,428.64 $1,825.42 $5,160.94 $9,442.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $304.23 $33.80 $95.57 $174.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 1
FDEP COST ESTI MATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: TBD
Task #: TBD SubTask 1 Project Management SubTask 6 Utilities (quarterly)
Site: Touch of Class Cleaners SubTask 2 O&M - Quarter 1 SubTask 7
Activity/Phase: O&M SubTask 3 O&M - Quarter 2 , Semi-Annual Status Report SubTask 8
Project Manager: Steven Folsom SubTask 4 O&M - Quarter 3 SubTask 9
SubTask 5 O&M - Quarter 4, Annual Status Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $679.00 $388.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $679.00 $388.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $115.00 $0.00 $115.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $4,200.00 $0.00 $0.00 $0.00 $0.00 $4,200.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $4,315.00 $0.00 $115.00 $0.00 $0.00 $4,200.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $151.50 $0.00 $11.50 $0.00 $0.00 $140.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $4,466.50 $0.00 $126.50 $0.00 $0.00 $4,340.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $5,403.00 $2,566.00 $2,837.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $416.00 $208.00 $208.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $5,819.00 $2,774.00 $3,045.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $260.00 $130.00 $130.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $417.10 $208.55 $208.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $58.20 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $378.30 $189.15 $189.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,113.60 $585.90 $527.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $28,810.97 $1,859.22 $9,004.41 $13,607.34 $0.00 $0.00 $4,340.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,642.86 $182.54 $516.09 $944.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $30,453.83 $2,041.76 $9,520.50 $14,551.57 $0.00 $0.00 $4,340.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 2
SITE : Touch of Class Cleaners
FDEP NO: ERIC_4697
SUBTASK: O&M - Quarter 1
DATE: 3/4/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager SDF System Operation Review 4
Senior Engineer NSB Field Correspondence 4 Documentation of O&M Preparation 6
Staff Scientist WJT Mobilization/Demobilization - Month 1, Month 2, Month 3 8 System O&M, Field Measurements, Sample Collection 24 Groundwater sampling 10
TOTAL LABOR 56
TRAVEL
TYPE RATE UNIT USEAGE Miles Free Truck $97.00 day 4 $388.00
TOTAL VEHICLE $388.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
TOTAL SUBS $0.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 4 $800.00
TRPH (aqueous) FL-PRO Quarter 1 $84.00 4 $336.00 Nitrate (aqueous) Quarter 1 $20.00 4 $80.00 TDS (aqueous) Quarter 1 $11.50 4 $46.00 Sodium (aqueous) EPA 6010 Quarter 1 $11.50 4 $46.00 Sulfate (aqueous) Quarter 1 $16.00 4 $64.00 Chloride (aqueous) Quarter 1 $14.00 4 $56.00 Ammonia (aqueous) Quarter 1 $21.00 4 $84.00 pH Quarter 1 $8.00 4 $32.00 Molybdenum (aqueous) EPA 6010 Quarter 1 $11.50 4 $46.00 Iron (aqueous) EPA 6010 Quarter 1 $11.50 4 $46.00 TOC (aqueous) Quarter 1 $26.00 5 $130.00 Methane/Ethane/Ethene (aqueouRSK 175 Quarter 1 $160.00 5 $800.00 Sample Shipment/Preparation Large (25 to 50 lbs), Overnight $104.00 2 $208.00
TOTAL LAB $2,774.00
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Construction/O&M Supplies $63.05 day 3 $189.15 Shallow Groundwater Sampling Kit $208.55 day 1 $208.55 Drum $58.20 each 1 $58.20
Sub-Total $455.90
Expendables $32.50 day 4 $130.00
Sub-Total $130.00
Total Equipment $585.90
SUBTASK: O&M - Quarter 2
DATE: 3/4/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager SDF System Operation Review 4 Senior Review 6
Senior Engineer NSB Field Correspondence 4 Semi-Annual Status Report 28
CAD Technician BLA Figures 4
Staff Scientist WJT Mobilization/Demobilization - Month 4, Month 5, Month 6 6 System O&M, Field Measurements, Sample Collection 24 Groundwater Sampling 10
Senior Scientist CLW Data Validation 2
TOTAL LABOR 88
TRAVEL
TYPE RATE UNIT USEAGE Miles Free Truck $97.00 day 3 $291.00
TOTAL VEHICLE $291.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
Petrotech IDW Disposal $115.00 each 1 $115.00
TOTAL SUBS $115.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 2 $400.00
Halocarbons (aqueous) EPA 8260 Quarter 2 $66.00 6 1 $462.00 TRPH (aqueous) FL-PRO Quarter 2 $84.00 5 $420.00 Nitrate (aqueous) Quarter 2 $20.00 5 $100.00 TDS (aqueous) Quarter 2 $11.50 5 $57.50 Sodium (aqueous) EPA 6010 Quarter 2 $11.50 5 $57.50 Sulfate (aqueous) Quarter 2 $16.00 5 $80.00 Chloride (aqueous) Quarter 2 $14.00 5 $70.00 Ammonia (aqueous) Quarter 2 $21.00 5 $105.00 pH Quarter 2 $8.00 5 $40.00 Molybdenum (aqueous) EPA 6010 Quarter 2 $11.50 5 $57.50 Iron (aqueous) EPA 6010 Quarter 2 $11.50 5 $57.50 TOC (aqueous) Quarter 2 $26.00 5 $130.00 Methane/Ethane/Ethene (aqueouRSK 175 Quarter 2 $160.00 5 $800.00 Sample Shipment/Preparation Large (25 to 50 lbs), Overnight $104.00 2 $208.00
TOTAL LAB $3,045.00
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Shallow Groundwater Sampling Kit $208.55 day 1 $208.55 Construction/O&M Supplies $63.05 day 3 $189.15
Sub-Total $397.70
Expendables $32.50 day 4 $130.00
Sub-Total $130.00
Total Equipment $527.70
SUBTASK: O&M - Utilities
DATE: 3/4/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
O&M Quarter 1 Utilities Four Months
Utility Charges (Electric) $600.00 month 4 $2,400.00 Utility Handling Fee $20.00 month 4 $80.00
Sub-Total $2,480.00 O&M Quarter 2 Utilities Three Months
Utility Charges (Electric) $600.00 month 3 $1,800.00 Utility Handling Fee $20.00 month 3 $60.00
Sub-Total $1,860.00
O&M Quarter 3 Utilities Three Months Utility Charges (Electric) $600.00 month $0.00 Utility Handling Fee $20.00 month $0.00
Sub-Total $0.00
O&M Quarter 3 Utilities Three Months Utility Charges (Electric) $600.00 month $0.00 Utility Handling Fee $20.00 month $0.00
Sub-Total $0.00 Total Equipment $4,340.00
(813) 968-7722 ■ 15711 Mapledale Blvd., Suite B ■ Tampa, FL 33624 ■ www.hsweng.com Innovative Solutions Within Your Reach…
P:\1CB6 Cardno\1CB602001 Touch of Class Cleaners\01 Proposals\RAP Implementation\TA Request_O&M.docx
February 23, 2021 Sent via Electronic Mail
Ms. Walsta Jean-Baptiste, P.G.
Florida Department of Environmental Protection Waste Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Re: Task Assignment Request – SVE Operation & Maintenance and Groundwater Monitoring Touch of Class Cleaners 6402 US Highway 41, Apollo Beach, FL
ERIC_4697
Dear Walsta:
HSW Consulting, LLC (HSW) is pleased to submit this Task Assignment request for soil vapor extraction system operation and maintenance (SVE O&M) and groundwater injection monitoring activities at the Touch of Class Cleaners site (Site) in accordance with the approved RAP. The following presents a proposed schedule and associated cost estimate for implementation of the activities described above.
Subtask 1: Project Management;
Subtask 2: Quarter One; submittal of Quarterly O&M Documentation.
Deliverable Date: February 8, 2022
Subtask 3: Quarter Two; Submittal of Semiannual Remedial Action Status Report, including updated tables, figures and laboratory data.
Deliverable Date: May 9, 2022
Touch of Class Cleaners Task Assignment Request
HSW Consulting ■ www.hsweng.com 2 Innovative Solutions Within Your Reach…
P:\1CB6 Cardno\1CB602001 Touch of Class Cleaners\01 Proposals\RAP Implementation\TA Request_O&M.docx
Sincerely, HSW ENGINEERING, INC.
Nicholas Barnes, P.E.
Senior Engineer
Attachments: Subcontractor Quotes Level of Effort/Cost Estimate Forms (native file attached)
October 25, 2017
Nick Barnes HSW Enginering 15711 Mapledale Blvd Suite B Tampa Fl 33624 813-549-1016
RE: Drum disposal
Dear Nick:
Petrotech Southeast, Inc. would like to take this opportunity to thank you for your interest in our services. Per your request, please find our proposal for the services you require.
Description of work: Petrotech Southeast, Inc. proposes to provide the equipment and personnel to remove IDW drums from sites in Central Fl. Drums must be placed on hard surface, IE concrete or asphalt. Additional loading charge may apply. All non-hazardous waste material will be recycled and/or disposed of according to Florida’s Department of Environmental Protection’s regulations. All rates are based upon standard working hours 8 AM to 5 PM Monday through Friday.
Product / Service Unit Type Unit Price Non Haz, Solid Drum Disposal with Trans and fuel charge Per Drum $125.00
Non Hazardous Waters W/ T&D Per Drum $115.00 With approved Analytical / profile. Water 8260 Volatiles, Solids 8 RCRA metals & Volatiles.
Estimate is for budgetary purpose only actual Quantities invoiced.
Payment Terms: Net 30 days.
All other Petrotech Southeast, Inc. standard terms and conditions shall apply. Any applicable taxes and fuel surcharges shall be invoiced accordingly. Quoted pricing is good for 90 days.
If you have any questions regarding this service agreement, please do not hesitate to call me 407-656-8114. Otherwise, please return a signed copy.
Best regards, PETROTECH SOUTHEAST, INC. HSW Engineering
Mike Anderson Mike Anderson Date Signature Date Sales Title nbarnes Text Box Price Confirmed nbarnes Text Box 1 drum Purge Water $30 + $60 = $90 Stop Fee = $50 Total = $140
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| 2021_01 SVE OM.pdf |
| Cost Estimate |
| sub 2 |
| sub 3 |
| sub 4 |
| LOE_CEF-O&M.pdf |
| Cost Estimate |
| sub 2 |
| sub 3 |
| sub 6 |
File details come from the government source that posted it. Updated .