This document is a Task Assignment Change Order (Change Order No. 1) issued under Florida Department of Environmental Protection (FDEP) Contract No. HW554 between FDEP and APTIM Environmental & Infrastructure, Inc. The task assignment pertains to biennial groundwater monitoring and project management services at the Altamonte Springs Dry Cleaners facility (Site ID ERIC_5459) located in Altamonte Springs, Seminole County, Florida. The contract manager is Melissa A Walsh, and the contractor representative is Eric Kramer, P.E.

The change order decreases the original task assignment amount by $234.20, reducing the fixed price contract value from $6,760.53 to $6,526.33. The cost reduction results from the elimination of expenses associated with passive diffusion bag sampling methodology, specifically the removal of drum characterization analytical costs, drum disposal costs, and related pickup and disposal fees. The task assignment is extended by 31 days to allow sufficient time for invoicing, with the new completion date established as February 14, 2022. The final deliverable is a Biennial Groundwater Monitoring Report with a due date of September 30, 2021. The contract work includes two subtasks: Subtask 1 (Project Management) and Subtask 2 (Biennial Groundwater Sampling), performed in accordance with the scope of work dated September 9, 2021. Invoice requirements specify that the full contract amount of $6,526.33 is due upon submittal and FDEP approval of the Biennial Groundwater Monitoring Report.

View the file

Other files

File Type Posted
CN-370000-HW554-A10.pdf PDF
CN-370000-HW554-A5.pdf PDF
CN-370000-HW554-A6.pdf PDF
CN-370000-HW554-CO1.pdf PDF
CN-370000-HW554-CO2.pdf PDF
CN-370000-HW554-CO3.pdf PDF
CN-370000-HW554-DC003J.pdf PDF
CN-370000-HW554-DC004F.pdf PDF
CN-370000-HW554-DC007F.pdf PDF
CN-370000-HW554-DC007G.pdf PDF
CN-370000-HW554-DC008I.pdf PDF
CN-370000-HW554-DC009G.pdf PDF
CN-370000-HW554-DC010G.pdf PDF
CN-370000-HW554-DC010I.pdf PDF
CN-370000-HW554-DC010K.pdf PDF
CN-370000-HW554-DC012I.pdf PDF
CN-370000-HW554-DC012J.pdf PDF
CN-370000-HW554-DC014F.pdf PDF
CN-370000-HW554-DC014H.pdf PDF
CN-370000-HW554-DC01ACO4.pdf PDF
CN-370000-HW554-DC01ACO5.pdf PDF
CN-370000-HW554-DC01ACO8.pdf PDF
CN-370000-HW554-DC01C.pdf PDF
CN-370000-HW554-DC01G.pdf PDF
CN-370000-HW554-DC01i.pdf PDF
CN-370000-HW554-DC021C.pdf PDF
CN-370000-HW554-DC022C.pdf PDF
CN-370000-HW554-DC024C.pdf PDF
CN-370000-HW554-DC02BCO1.pdf PDF
CN-370000-HW554-DC02BCO7.pdf PDF
CN-370000-HW554-DC02BCO8.pdf PDF
CN-370000-HW554-DC02F.pdf PDF
CN-370000-HW554-DC02FCO2.pdf PDF
CN-370000-HW554-DC02ICO3.pdf PDF
CN-370000-HW554-DC02L.pdf.crdownload CRDOWNLOAD file
CN-370000-HW554-DC02LCO1.pdf PDF
CN-370000-HW554-DC03D.pdf PDF
CN-370000-HW554-DC03DCO1.pdf PDF
CN-370000-HW554-DC03E.pdf PDF
CN-370000-HW554-DC03ECO2.pdf PDF
CN-370000-HW554-DC03FCO2.pdf PDF
CN-370000-HW554-DC03FCO3.pdf PDF
CN-370000-HW554-DC03L.pdf PDF
CN-370000-HW554-DC04D.pdf PDF
CN-370000-HW554-DC05C.pdf PDF
CN-370000-HW554-DC05CCO1.pdf PDF
CN-370000-HW554-DC05CCO4.pdf PDF
CN-370000-HW554-DC05E.pdf PDF
CN-370000-HW554-DC05HCO1.pdf PDF
CN-370000-HW554-DC07B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Change Order No.:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

Site Name:

Site ID / Facility ID::

Description of Change [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverable:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

Cost Reimbursement Fixed Fee

Original Task Amount

Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00

Original Task Completion Date:

Completion Date Prior to this Change:

Net Increase/Decrease in Task Period:

Completion Date with all Change Orders:

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

FIXED PRICE

TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM

ITEM

$0.00

$0.00

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Final Deliverable Due Date:

$0.00

$0.00

CHANGE IN TASK TIME

FEE SCHEDULE

COST PLUS FIXED FEE

TOTAL

WCP TAFORM 01_18

HW554

1DC004F

APTIM

Eric Kramer, P.E.

(850)-245-8960Melissa A Walsh

Altamonte Springs Dry Cleaners

ERIC_5459

This Task Assignment Change Order is for a decrease of $234.20 because of the use of passive diffusion bags under subtask 2 and removal cost of the drum. The Task Assignment will be extended by one month to allow sufficient time for invoicing. Work will be done according to the attached scope of work dated September 9, 2021.

Biennial Groundwater Monitoring Report & Project Management 09/30/2021

$ 6,760.53 $ 0.00 $ 0.00 $ 0.00

$ 6,760.53 $ 0.00 $ 0.00 $ 0.00 $ 6,760.53

($ 234.20) $ 0.00 $ 0.00 $ 0.00 ($ 234.20)

$ 6,526.33

01/13/2022

01/13/2022

31 days

02/14/2022

Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.11.04 09:29:26 -04'00'

Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.11.04 09:29:35 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.11.04 09:40:50 -04'00'

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2021.11.04 09:50:31 -04'00'

$ 6,526.33 $ 0.00 $ 0.00 $ 0.00

$ 6,760.53

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

BWC TAFORM 2/03

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW554

DC004F

$ 6,526.33

Biennial Groundwater Monitoring Report & Project Managment

Submittal and FDEP approval of Biennial Groundwater Monitoring Report & Project Management

09/30/2021

$ 6,526.33

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

Memorandum TO: APTIM Contract File

Contract No. HW554

FROM: Melissa A Walsh, Project Manager

SUBJECT: Altamonte Springs Dry Cleaners

FAC # ERIC_5459

Task Assignment #DC004F Monitoring

DATE: November 2, 2021

Under this Task Assignment Change Order, APTIM will collect samples for groundwater as required for closure of the site. This Change Order is for a decrease of $234.20 because of the use of passive diffusion bags under subtask 2 and the has removal the cost of a drum. The Task Assignment will be extended by one month to allow sufficient time for invoicing. Work will be done according to the attached scope of work dated September 9, 2021.

Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate.

Subtask 2: Annual Groundwater Sampling Report APTIM and DEP agreed to the proposed scope of work and level of effort. This is task allows for groundwater sampling for a Biennial Groundwater Monitoring Report.

The Final Task Assignment value is for the fixed price $6,526.33

FDEP COST ESTI MATE

Contractor: APTIM Environmental & Infrastructure, Inc.

Date: 9/15/2021

Task #: HW554-DC004F TACO #1 ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$63.32 Client Program Manager 1 E. Kramer 3 3.3 $63.32 Engineer/Scientist 5 E. Kramer 2 2 0 0 0 0 0 0 0 0 $60.61 Engineer/Scientist 5 G. Roberts 16 16 0 0 0 0 0 0 0 0 $32.77 Engineer/Scientist 2 K. Howard 14 14 0 0 0 0 0 0 0 0 $31.69 Designer 2 S. Ferianc 2 2 0 0 0 0 0 0 0 0 $25.04 Tech Publications Specialist 3 H. Vining 3 3 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

Total Hours 40 3 37 0 0 0 0 0 0 0 0

Direct Labor $1,905.39 $211.71 $1,693.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 119.00% $2,267.41 $251.93 $2,015.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 20.90% $398.23 $44.25 $353.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 32.60% $621.16 $69.02 $552.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $5,192.19 $576.91 $4,615.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $95.27 $10.59 $84.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Materials $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Bob's Barricades $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $396.00 $396.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $63.00 $63.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $459.00 $459.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $131.15 $131.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $163.65 $163.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Page 2 of 9 Copy of DC004F TACO #1

Date: 9/15/2021

Task #: HW554-DC004F TACO #1 ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Subtotal $6,007.11 $587.50 $5,419.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $519.22 $57.69 $461.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $6,526.33 $645.19 $5,881.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Page 3 of 9 Copy of DC004F TACO #1

LEVEL OF EFFORT / EXPENSE WORKSHEET

SITE : Altamonte Springs Dry Cleaner

SUBTASK:

DATE: May 24, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. Howard

Designer 2 S. Feriac 2 Tech Pub. Specialist 3 H. Vining 3

TOTAL LABOR 37

EQUIPMENT ITEM RATE UNIT USAGE

Expendables $32.50 Day 1 $32.50 Shallow GW Sampling Kit $208.55 day 0 $0.00 Deep Groundwater Sampling Kit $349.20 Day 0 $0.00 Water Level Indicator $19.40 Day 1 $19.40 Diffusion Sampler (2" well) $22.35 each 5 $111.75 Diffusion Sampler Kit $28.15 each 0 $0.00 Diffusion Sampler Well Cap $12.65 each 0 $0.00 Well Cap, 2" $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 HDPE Tubing $0.25 foot 0 $0.00 55-gallon Drum $58.20 each 1 $58.20

TOTAL EQUIPMENT: $221.85

VEHICLE TYPE RATE UNIT USAGE

Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 1 $97.00

TOTAL VEHICLE: $97.00

PER DIEM STAFF RATE UNIT USAGE

Hotel $99.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00

TOTAL PER DIEM: $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (Halos Only) $66.00 5 1 $396.00 EPA Method 8260 (Halos Only) $66.00 1 0 $66.00 Sample Shipping (Small cooler) $63.00 1 $63.00 Sample Shipping (large cooler) $104.00 0 $0.00

TOTAL LAB: $525.00

SUBCONTRACTOR COSTS

NAME PURPOSE Rate UNIT USAGE TOTALS

Erwin Remediation IDW Transporation and Disposal $100.00 Drum 1 $100.00 Columbia Analytical Protective Mesh Covers $2.00 each 0 $0.00

TOTAL SUB: $100.00

Report Document Production Drafting GW Flow and Analytical Results Maps

Notes: Proposed GW Samples and PDB Deployment into Monitoring Wells MW002, MW009, MW016R, MW017 and MW019.

2-Biennial Sampling

Technical Review of Biennial Report, Update Recommendations (2 hrs) Ordering Replacement Passive Sampling Bags (1 hr), Preparation of Upper and Lower GW Flow Maps and GW Analytical Results Maps (2 hrs). Update of GW Elevation, Analytical Summary Tables gradient Calulations (3 hrs) Letter Report Text and Preparation of Recommendations and conclusions (9 hrs). CD/Database Tables Update, Data Check and Upload, ADaPT Laboratory Data Check (1 hr).

Travel Preparation and Mobilization (1 hr). Round trip travel to site (2 hrs). Open Wells and Collect Depth to Groundwater Measurements from All Wells (2 hrs). Harvest PDB's and collection of Groundwater Samples from PDBs located within Monitoring Wells MW002, MW009, MW016R, MW017 and MW019 for VOHs by EPA Method 8260 (5 hrs). IDW Sample Collection and IDW Handling (1 hr) Sample preparation, Chain of custody preparation, Sample Packaging (1 hr). Site Restoration and Cleanup (1 hr), Sample Delivery (1 hr).

2-BiennialGW Page 1 of 9 Copy of DC004F TACO #1

SUBTASK:

DATE: September 15, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. Howard

Designer 2 S. Feriac 2 Tech Pub. Specialist 3 H. Vining 3

TOTAL LABOR 37

EQUIPMENT ITEM RATE UNIT USAGE

Expendables $32.50 Day 1 $32.50 Shallow GW Sampling Kit $208.55 day 0 $0.00 Deep Groundwater Sampling Kit $349.20 Day 0 $0.00 Water Level Indicator $19.40 Day 1 $19.40 Diffusion Sampler (2" well) $22.35 each 5 $111.75 Diffusion Sampler Kit $28.15 each 0 $0.00 Diffusion Sampler Well Cap $12.65 each 0 $0.00 Well Cap, 2" $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 HDPE Tubing $0.25 foot 0 $0.00 55-gallon Drum $58.20 each 0 $0.00

TOTAL EQUIPMENT: $163.65

VEHICLE TYPE RATE UNIT USAGE

Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 1 $97.00

TOTAL VEHICLE: $97.00

PER DIEM STAFF RATE UNIT USAGE

Hotel $99.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00

TOTAL PER DIEM: $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (Halos Only) $66.00 5 1 $396.00 EPA Method 8260 (Halos Only) $66.00 0 0 $0.00 Sample Shipping (Small cooler) $63.00 1 $63.00 Sample Shipping (large cooler) $104.00 0 $0.00

TOTAL LAB: $459.00

SUBCONTRACTOR COSTS

NAME PURPOSE Rate UNIT USAGE TOTALS

Erwin Remediation IDW Transporation and Disposal $100.00 Drum 0 $0.00 Columbia Analytical Protective Mesh Covers $2.00 each 0 $0.00

TOTAL SUB: $0.00

Notes: Proposed GW Samples and PDB Deployment into Monitoring Wells MW002, MW009, MW016R, MW017 and MW019.

Drafting GW Flow and Analytical Results Maps Report Document Production

2-Biennial Sampling

Technical Review of Biennial Report, Update Recommendations (2 hrs) Ordering Replacement Passive Sampling Bags (1 hr), Preparation of Upper and Lower GW Flow Maps and GW Analytical Results Maps (2 hrs). Update of GW Elevation, Analytical Summary Tables gradient Calulations (3 hrs) Letter Report Text and Preparation of Recommendations and conclusions (9 hrs). CD/Database Tables Update, Data Check and Upload, ADaPT Laboratory Data Check (1 hr).

Travel Preparation and Mobilization (1 hr). Round trip travel to site (2 hrs). Open Wells and Collect Depth to Groundwater Measurements from All Wells (2 hrs). Harvest PDB's and collection of Groundwater Samples from PDBs located within Monitoring Wells MW002, MW009, MW016R, MW017 and MW019 for VOHs by EPA Method 8260 (5 hrs). IDW Sample Collection and IDW Handling (1 hr) Sample preparation, Chain of custody preparation, Sample Packaging (1 hr). Site Restoration and Cleanup (1 hr), Sample Delivery (1 hr).

2-Total Page 4 of 9 Copy of DC004F TACO #1

Date: 9/15/2021

Task #: HW554-DC004F TACO #1 ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$63.32 Client Program Manager 1 E. Kramer 0 0.0 $63.32 Engineer/Scientist 5 E. Kramer 0 0 0 0 0 0 0 0 0 0 $60.61 Engineer/Scientist 5 G. Roberts 0 0 0 0 0 0 0 0 0 0 $32.77 Engineer/Scientist 2 K. Howard 0 0 0 0 0 0 0 0 0 0 $31.69 Designer 2 S. Ferianc 0 0 0 0 0 0 0 0 0 0 $25.04 Tech Publications Specialist 3 H. Vining 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

Total Hours 0 0 0 0 0 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 119.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 20.90% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 32.60% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW ($100.00) ($100.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Materials $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Bob's Barricades $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal ($100.00) ($100.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee ($10.00) ($10.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($110.00) ($110.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs ($66.00) ($66.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($66.00) ($66.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) ($58.20) ($58.20) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses ($58.20) ($58.20) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($234.20) $0.00 ($234.20) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Delta Page 5 of 9 Copy of DC004F TACO #1

Date: 9/15/2021

Task #: HW554-DC004F TACO #1 ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($234.20) $0.00 ($234.20) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Delta Page 6 of 9 Copy of DC004F TACO #1

SUBTASK:

DATE: September 15, 2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard Designer 2 S. Feriac Tech Pub. Specialist 3 H. Vining

TOTAL LABOR 0

EQUIPMENT ITEM RATE UNIT USAGE

Expendables $32.50 Day 0 $0.00 Shallow GW Sampling Kit $208.55 day 0 $0.00 Deep Groundwater Sampling Kit $349.20 Day 0 $0.00 Water Level Indicator $19.40 Day 0 $0.00 Diffusion Sampler (2" well) $22.35 each 0 $0.00 Diffusion Sampler Kit $28.15 each 0 $0.00 Diffusion Sampler Well Cap $12.65 each 0 $0.00 Well Cap, 2" $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 HDPE Tubing $0.25 foot 0 $0.00 55-gallon Drum $58.20 each -1 ($58.20)

TOTAL EQUIPMENT: ($58.20)

VEHICLE TYPE RATE UNIT USAGE

Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 0 $0.00

TOTAL VEHICLE: $0.00

PER DIEM STAFF RATE UNIT USAGE

Hotel $99.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00

TOTAL PER DIEM: $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (Halos Only) $66.00 0 0 $0.00 EPA Method 8260 (Halos Only) $66.00 -1 0 ($66.00) Sample Shipping (Small cooler) $63.00 0 $0.00 Sample Shipping (large cooler) $104.00 0 $0.00

TOTAL LAB: ($66.00)

SUBCONTRACTOR COSTS

NAME PURPOSE Rate UNIT USAGE TOTALS

Erwin Remediation IDW Transporation and Disposal $100.00 Drum -1 ($100.00) Columbia Analytical Protective Mesh Covers $2.00 each 0 $0.00

TOTAL SUB: ($100.00)

2-Biennial Sampling

2-Delta Page 7 of 9 Copy of DC004F TACO #1

Contractor: APTIM Environmental & Infrastructure, In

Date: 5/24/2021

Task #: HW554-DC004F ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$63.32 Client Program Manager E. Kramer 3 3.3 $63.32 Engineer/Scientist 5 E. Kramer 2 2 0 0 0 0 0 0 0 0 $60.61 Engineer/Scientist 5 G. Roberts 16 16 0 0 0 0 0 0 0 0 $32.77 Engineer/Scientist 2 K. Howard 14 14 0 0 0 0 0 0 0 0 $31.69 Designer 2 S. Ferianc 2 2 0 0 0 0 0 0 0 0 $25.04 Tech Publications Speciali H. Vining 3 3 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 Total Hours 40 3 37 0 0 0 0 0 0 0 0

Direct Labor $1,905.39 $211.71 $1,693.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 119.00% $2,267.41 $251.93 $2,015.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 20.90% $398.23 $44.25 $353.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 32.60% $621.16 $69.02 $552.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $5,192.19 $576.91 $4,615.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $95.27 $10.59 $84.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Equipment Procurement)

Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Services Procurement)

Subcontractor Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $462.00 $462.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $63.00 $63.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $525.00 $525.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 8 of 9 Copy of DC004F TACO #1

Contractor: APTIM Environmental & Infrastructure, In

Date: 5/24/2021

Task #: HW554-DC004F ERIC_5459 SubTask 1 Project Management SubTask 6

Site: Altamonte Springs Dry Cleaner SubTask 2 2-Biennial Sampling SubTask 7

Activity/Phase: Biennial Sampling SubTask 3 SubTask 8

Project Manager: Eric Kramer SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $131.15 $131.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $58.20 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $221.85 $221.85 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$6,241.31 $587.50 $5,653.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subtotal $519.22 $57.69 $461.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee

Total Estimated Cost $6,760.53 $645.19 $6,115.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate Page 9 of 9 Copy of DC004F TACO #1

Proposed Scope of Work Biennial Sampling Altamonte Springs Dry Cleaners Task Assignment DC004F TACO #1 ERIC_5459 (Former Fac ID No. 599500541) APTIM Environmental and Infrastructure, LLC 09/15/21

The former Altamonte Springs Dry Cleaner (DC004F) facility is sampled on a biennial basis.

The following proposed scope of work for DC004F Task Assignment Change Order (TACO) #1 has been prepared to reconcile the Task Assignment (TA).

Subtask 2 – Biennial Sampling:

Because the need for pumping and purging the wells is eliminated by using Passive Diffusion Bag (PDB) samplers and the PDBs contain limited water for the collection of each sample, no water remained for storage or disposal after the sampling event. Therefore, Subtask 2 has been updated to removes the cost of the drum, the cost of the drum characterization analytical and the associated pickup and disposal.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed between APTIM Environmental & Infrastructure, LLC and Florida Department of Environmental Protection No. HW554.

If you have any questions, please do not hesitate to call.

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

(Street, Name:

CO HW554

D000 N/ADC004F

APTIM

Eric Kramer, P.E.

(850)-245-8960Melissa A Walsh

ERIC_5459

Altamonte Springs Dry Cleaners 478 East Altamonte Avenue, Suite 112, Altamonte Springs, Seminole Monitoring

APTIM will conduct biennial groundwater sampling and submit a Biennial Groundwater Monitoring Report as the final deliverable. Work will be done according to the attached scope of work dated May 24, 2021.

Biennial Groundwater Monitoring Report

09/30/2021

01/13/2022

$ 6,760.53 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.08.05 12:17:25 -04'00'

Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.08.05 12:17:33 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.08.05 13:11:20 -04'00'

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2021.08.05 14:50:13 -04'00'

$ 6,760.53

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Biennial Groundwater Monitoring Report 09/30/2021

Submittal and FDEP approval of Biennial Groundwater Monitoring Report $ 6,760.53

$ 6,760.53

HW554

DC004F

2-BiennialGW
Total
2-Total
Delta
2-Delta
Cost Estimate