This document constitutes a Task Assignment Notification Form and supporting deliverables for Contract No. HW554 between the Florida Department of Environmental Protection (FDEP) and APTIM Environmental & Infrastructure, LLC. The task assignment (DC003L) is managed by FDEP Contract Manager Melissa A Walsh and APTIM representative Eric Kramer, P.E., and pertains to environmental monitoring and remediation activities at the Former Brantley Cleaners facility located at 924 West State Road 436, Suite 1250, Altamonte Springs, Seminole County, Florida (FDEP Site No. ERIC_5454).
Task Assignment DC003L authorizes APTIM to perform annual groundwater sampling and soil vapor sampling at the site according to the October 4, 2021 scope of work. The work is divided into three subtasks: Subtask 1 (Project Management), Subtask 2 (Annual Groundwater Sampling involving 7 passive diffusion bag samples and 4 conventional well samples), and Subtask 3 (Vapor Sampling from 7 SVE wells). Final deliverables include a Groundwater and Soil Vapor Sampling Letter Report, GIS tables, ADaPT EDDs, and project management documentation, due April 14, 2022, with task completion by June 25, 2022. The total task assignment value is $17,893.84 on a fixed-price basis, with no retainage. Invoice payments are structured in two installments: $9,331.97 upon FDEP approval of field documentation and lab reports for Subtask 2, and $8,561.87 upon approval of the final letter report and database updates for Subtasks 1 and 3. IDW (Investigative Derived Waste) disposal services were procured through competitive bidding, with Erwin Remediation selected as the lowest responsive and responsible bidder at $100.00 per drum.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW554
D000 N/ADC003L
APTIM
Eric Kramer, P.E.
(850)-245-8960Melissa A Walsh
ERIC_5454
Former Brantley Cleaners
924 West State Rd. 436, Suite 1250; Altamonte Springs; Seminole County
Monitoring
This Task Assignment is for annual groundwater sampling and soil vapor sampling. APTIM will collect groundwater samples using a combination of passive diffusion bags and conventional sampling. APTIM will document all results. in a letter report Work will be performed according to the October 4, 2021 scope of work.
Groundwater and Soil Vapor Sampling Letter Report, GIS tables, ADaPT EDDs, and Project Management
04/14/2022
06/25/2022
$ 17,893.84 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Melissa Walsh Digitally signed by Melissa Walsh Date: 2022.01.04 13:45:43 -05'00'
Melissa Walsh Digitally signed by Melissa Walsh Date: 2022.01.04 13:45:58 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.01.04 17:17:46 -05'00'
Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2022.01.05 09:46:57 -05'00'
$ 17,893.84
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Field documentation, Lab reports, and IDW documentation 03/14/2022
Groundwater and Soil Vapor Sampling Letter Report, GIS tables, ADaPT EDDs, and Project Management 04/14/2022
FDEP Approval of Field documentation, Lab reports, and IDW documentation:
Subtask 2 $ 9,331.97
FDEP approval of Groundwater and Soil Vapor Sampling Report, GIS tables, ADaPT EDDs, and Project Management ; Subtasks 1 & 3 $ 8,561.87
$ 17,893.84
HW554
DC003L
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum TO: APTIM Contract File
Contract No. HW554
FROM: Melissa A Walsh, Project Manager
SUBJECT:
FAC # ERIC_ 5454
Task Assignment # DC003L Monitoring
DATE: December 14, 2021
Under this Task Assignment, APTIM will collect groundwater samples using a combination of passive diffusion bags and conventional sampling. APTIM will also collect soil vapor samples from select SVE wells. . Work will be done according to the October 4, 2021 scope of work. .
Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate.
Subtasks 2 and 3 Groundwater and Vapor Sampling Activities:
APTIM and DEP agree to the proposed scope of work and level of effort. This subtask allows for the collection of groundwater and vapor samples using, passive diffusion bags, conventional sampling techniques, and Tedlar bags. Replacement bags will be deployed after samples have been collected.
APTIM received IDW treatment and disposal bids from Clark, Erwin, and Capital Environmental.
Erwin was selected as the lowest responsive and responsible bidder.
Reporting:
APTIM will prepare a letter report summarizing the results of the vapor and groundwater sampling field event. The report will summarize the analytical results in Tables, Figures and Text and provide conclusions and recommendations.
Documentation of costs is included in the attached CEF, Level-of-Effort sheets, and the APTIM proposal. The final deliverable due date is April 14, 2022, and the Task Assignment Completion Date is June 25, 2022.
The final cost total for DC003L is $ 17,893.84
FDEP COST ESTIMATE
Contractor: APTIM Environmental & Infrastructure, LLC
Date: 10/4/2021
Task #: HW554-DC003L ERIC_5454 SubTask 1 Project Management SubTask 6
Site: Brantley Cleaners (former) SubTask 2 2-Annual Sampling SubTask 7
Activity/Phase: Annual Sampling SubTask 3 3-Vapor Sampling SubTask 8
Project Manager: Eric Kramer SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$63.32 Client Program Manager 1 E. Kramer 8 8.1 $63.32 Engineer/Scientist 5 E. Kramer 6 2 4 0 0 0 0 0 0 0 $60.61 Engineer/Scientist 5 G. Roberts 30 26 4 0 0 0 0 0 0 0 $32.77 Engineer/Scientist 2 K. Howard 40 16 24 0 0 0 0 0 0 0 $27.18 Engineering Technician 2 B. Skipper 12 0 12 0 0 0 0 0 0 0 $31.69 Designer 2 S. Ferianc 5 3 2 0 0 0 0 0 0 0 $25.04 Tech Pub. Specialist 3 H. Vining 4 2 2 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Hours 105 8 49 48 0 0 0 0 0 0 0
Direct Labor $4,605.51 $511.72 $2,371.97 $1,721.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 119.00% $5,480.56 $608.95 $2,822.64 $2,048.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 20.90% $962.55 $106.95 $495.74 $359.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 32.60% $1,501.39 $166.82 $773.26 $561.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $12,550.01 $1,394.44 $6,463.61 $4,691.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $230.28 $25.59 $118.60 $86.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $291.00 $194.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $291.00 $194.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Equipment Procurement)
Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Services Procurement)
Subcontractor Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $2,258.00 $858.00 $1,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,362.00 $962.00 $1,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 4 Copy of DC003L est
FDEP COST ESTIMATE
Contractor: APTIM Environmental & Infrastructure, LLC
Date: 10/4/2021
Task #: HW554-DC003L ERIC_5454 SubTask 1 Project Management SubTask 6
Site: Brantley Cleaners (former) SubTask 2 2-Annual Sampling SubTask 7
Activity/Phase: Annual Sampling SubTask 3 3-Vapor Sampling SubTask 8
Project Manager: Eric Kramer SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $97.50 $65.00 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $939.85 $714.20 $225.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $58.20 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,095.55 $837.40 $258.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$16,638.84 $1,420.03 $8,685.61 $6,533.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subtotal $1,255.00 $139.44 $646.36 $469.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee
Total Estimated Cost $17,893.84 $1,559.47 $9,331.97 $7,002.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 2 of 4 Copy of DC003L est
LEVEL OF EFFORT / EXPENSE WORKSHEET
SITE : Brantley Cleaners (former)
SUBTASK:
DATE: October 04, 2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
TITLE STAFF WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 2
Engineer/Scientist 5 G. Roberts
Engineer/Scientist 2 K. Howard
Designer 2 S. Feriac 3 Tech Pub. Specialist 3 H. Vining 2
TOTAL LABOR 49
EQUIPMENT ITEM RATE UNIT USAGE
Expendables $32.50 Day 2 $65.00 Shallow GW Sampling Kit $208.55 day 1 $208.55 Deep Groundwater Sampling Kit $349.20 Day 1 $349.20 Diffusion Sampler (2" well) $22.35 Day 7 $156.45 Well Cap, 2" $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 HDPE Tubing $0.25 foot 0 $0.00 55-gallon Drum $58.20 each 1 $58.20
TOTAL EQUIPMENT: $837.40
VEHICLE TYPE RATE UNIT USAGE
Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 2 $194.00
TOTAL VEHICLE: $194.00
PER DIEM STAFF RATE UNIT USAGE
Hotel $70.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00
TOTAL PER DIEM: $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA Method 8260 (Halos Only) $66.00 11 1 $792.00 EPA Method 8260 (Halos Only/IDW) $66.00 1 $66.00 Sample Shipping (Small cooler) $63.00 0 $0.00 Sample Shipping (large cooler) $104.00 1 $104.00
TOTAL LAB: $962.00
SUBCONTRACTOR COSTS
NAME PURPOSE Rate UNIT USAGE Tax TOTALS
Misc. Supplies Home Depot/Lowes/Equivilent $50.00 Lump 0 $0.00 $0.00 Erwin Remediation IDW Transporation and Disposal 100 Drum 1 $100.00
TOTAL SUB: $100.00
Notes: Proposed PDB Deployment into Monitoring Wells MW001, MW004, MW006, MW009, MW012, MW013 & MW016 and conventional sampling of MW005, MW007, MW010 and MW011.
Gauge 16 MW's.
2-Annual Sampling
Technical Review of Annual Report, Update Recommendations (2 hrs) Ordering Replacement Passive Sampling Bags and Laboratory Sampling Kits (2 hrs), Preparation of shallow and intermediate GW Flow Maps, Analytical Summry and Result Plume Maps (3 hrs).
Update of GW Elevation, Analytical Summary Tables (3 hrs), Letter Report Text and Preparation of Recommendations and conclusions (15 hrs). CD/Database Tables Update and Upload, ADaPT Laboratory Data Submittal (2 hrs).
Travel Preparation and Mobilization (1 hr), Round trip travel to site (3 hrs). Collect Depth to Groundwater Measurements from all wells (3 hrs). Retrieve PDB's and collect 7 samples (5 hrs).
Deploy new PDBs in each of the seven wells (2 hrs). Convention sample four wells using down hole pump (6 hrs.) Prepare chain of custody preparation, sample packaging (1 hr), sample delivery (1 hr).
Report Document Production Drafting GW Flow and Analytical Results Maps
2-AnnualGW Page 3 of 4 Copy of DC003L est
LEVEL OF EFFORT / EXPENSE WORKSHEET
SITE : Brantley Cleaners (former)
SUBTASK:
DATE: October 04, 2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
TITLE STAFF WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 4
Engineer/Scientist 5 G. Roberts
Engineer/Scientist 2 K. McDonald
Engineering Technician 2 B. Skipper
Designer 2 S. Feriac 2 Tech Pub. Specialist 3 H. Vining 2
TOTAL LABOR 48
EQUIPMENT ITEM RATE UNIT USAGE
Expendables $32.50 Day 1 $32.50 Air Flow Meter $17.50 day 1 $17.50 Regenerative Blower $92.15 Day 1 $92.15 Portable Generator (15-25 kw) $116.00 Day 1 $116.00 Well Cap, 2" $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 HDPE Tubing $0.25 foot 0 $0.00 55-gallon Drum $58.20 each 0 $0.00
TOTAL EQUIPMENT: $258.15
VEHICLE TYPE RATE UNIT USAGE
Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 1 $97.00
TOTAL VEHICLE: $97.00
PER DIEM STAFF RATE UNIT USAGE
Hotel $70.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00
TOTAL PER DIEM: $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA Method TO-15 (VOC Soil Vapor) $200.00 7 0 $1,400.00 EPA Method 8260 (Halos Only) $66.00 0 0 $0.00 Sample Shipping (Small cooler) $63.00 0 $0.00 Sample Shipping (large cooler) $104.00 0 $0.00
TOTAL LAB: $1,400.00
SUBCONTRACTOR COSTS
NAME PURPOSE Rate UNIT USAGE Tax TOTALS
Misc. Supplies Home Depot/Lowes/Equivilent $50.00 Lump 0 $0.00 $0.00 Erwin Remediation IDW Transporation and Disposal 100 Drum 0 $0.00
TOTAL SUB: $0.00
Vapor samples for laboratory analysis from SVE wells VE01B, VE02B, VE04B, VE05B, VE06B, VE02A and VE05C.
Preparation and loadout of MAGS test apparatus (2), Mobilization and Travel round trip (2 hrs), Reconfigure existing piping to perform vapor sampling at 7 existing wells for analysis (8 hrs.)
Drafting vapor analytical maps Vapor Report Document Production
3-Vapor Sampling
Technical Review of Vapor Report, Update Recommendations (4 hrs) Oversight of Field Activities and Review of MAGS Analytical Data and Field Notes (2 hrs), CD/Database Tables Update for Air Samples and Upload, (2 hrs).
Preparation and loadout of MAGS test apparatus (2), Mobilization and Travel round trip (2 hrs), Reconfigure existing piping to perform vapor sampling at 7 existing wells for analysis (8 hrs.), Chain of custody preparation, Sample Packaging, Sample Drop-off for Delivery (2 hrs). Upload data and preparation of vapor sample analytical results Maps, Data Tables (4 hrs), Preparation of Vapor Report Text summarizing results (6 hrs).
3-Vapor Sampling Page 4 of 4 Copy of DC003L est
Item Description Units Unit Price Total
Amount Units Unit Price Total
Amount Units Unit Price Total
Amount Transporation Disposal (soil) 0 $0.00 0 $0.00 0 $0.00 Disposal (liquid) 1 $90.00 $90.00 1 $380.00 $380.00 1 $100.00 $100.00 Additional Costs/Fees 1 $50.00 $50.00 1 $100.00 $100.00
Total $140.00 $480.00 $100.00
Clark Environmental Safety-Kleen
Included in Disposal
None
Erwin Remediation
Included in Disposal
IDW Pickup and Disposal Bid Summary Former Brantley Dry Cleaners.
924 West State Road 436, Ste 1250 Altamonte Springs, Florida 32714
FDEP Site No. ERIC_5454 (Former FAC ID #599500158)
Included in Disposal
Roberts, Gregg
From: Bright, Thomas Gary <Thomas.Bright@safety-kleen.com> Sent: Wednesday, May 19, 2021 7:38 AM To: Roberts, Gregg Subject: RE: Request for Quotation for Non-Hazardous IDW T&D – Altamonte Springs Dry Cleaner
EXTERNAL SENDER
Good morning Greg. All of the locations you sent me would be handled out of the Sanford branch except the Jupiter location. But in all the cases this will cover them. This quote is just an estimate pending analysis and profile approval.
Profile fee ‐ $100.00 Per location Non haz disposal‐ $380.00 per drum
Again this is just an estimate pending analysis.
Thanks Thomas
Please visit our online store: www.store.safety‐kleen.com
Thomas Bright / Account Manager | Safety‐Kleen | Sanford Florida| A Clean Harbors Company| thomas.bright@safety‐kleen.com Direct Cell‐ 407‐212‐5152 |(f) 407‐321‐0065
Safety Starts with Me: Live It 3‐6‐5
From: Roberts, Gregg <Gregg.Roberts@aptim.com> Sent: Tuesday, May 18, 2021 7:29 PM To: Bright, Thomas Gary <Thomas.Bright@safety‐kleen.com> Subject: FW: Request for Quotation for Non‐Hazardous IDW T&D – Altamonte Springs Dry Cleaner
Hello Thomas, the below email is being forwarded to you based on Nicole’s email response.
GREGG ROBERTS, PG
Project Manager
APTIM | ENVIRONMENT & SUSTAINABILITY
O 813 612 3687 M 863 670 0215 E gregg.roberts@aptim.com
From: Roberts, Gregg Sent: Monday, May 17, 2021 7:13 PM To: Vitale, Nicole M <Nicole.Vitale@safety‐kleen.com> Subject: Request for Quotation for Non‐Hazardous IDW T&D – Altamonte Springs Dry Cleaner
Roberts, Gregg
From: Erwin Remediation <erwinremediation@gmail.com> Sent: Tuesday, May 18, 2021 8:03 AM To: Roberts, Gregg Subject: Re: Request for Quotation for Non-Hazardous IDW T&D – Altamonte Springs Dry Cleaner
EXTERNAL SENDER
Gregg, This will be $100.00 per drum.
If possible, please take a composite sample of the entire drum.
Thank you, Jonathan Erwin Erwin Remediation, Inc.
Office: (850) 292‐6511|Email: ErwinRemediation@Gmail.com Erwin Remediation, Inc.|408 Ditmar Street Pensacola, FL 32503
On Mon, May 17, 2021 at 6:13 PM Roberts, Gregg <Gregg.Roberts@aptim.com> wrote:
Hello Jonathan:
I need an estimate to include in a proposal to pick‐up and dispose of non‐hazardous liquid which will be generated during upcoming groundwater sampling activities at the following site:
Here are the site specifics:
Altamonte Springs Dry Cleaners (Former)
478 East Altamonte Drive
Altamonte Springs, Florida 32701
ERIC_5459 (Former FAC ID# 599500541)
Proposed Scope of Work Annual Groundwater Sampling & Vapor Sampling Former Brantley Cleaners Task Assignment DC003L ERIC_5454 (Former Facility ID No. 599500158) Aptim Environmental & Infrastructure, Inc. (APTIM) 10/4/21
The former Brantley Cleaners facility, located in Altamonte Springs, has an installed SVE remedial system that was turned off because the drycleaning facility continued to use a solvent based cleaning process. Recently, the facility switched to a petroleum-based cleaning process and FDEP is considering re-activating the SVE remedial system. Groundwater sampling has continued on an annual basis after the remedial system was turned off. This Task Assignment (DC003L) provides for collecting vapor samples at five Zone B, one Zone A and one Zone C SVE wells and the collection and sampling of seven (7) Passive Diffusion Bags (PDB’s) (currently installed in wells) and four wells to be conventionally sampled. APTIM proposes to document the results of vapor and groundwater sampling in one report.
Subtask 2 Annual Groundwater Sampling: The proposed scope of work includes the collection of depth to groundwater measurements from the 16 monitor wells (MW001 through MW016). Groundwater samples will be collected from the 7 existing monitoring wells containing the PDB bags (MW001, MW004, MW009, MW013, and MW016; and intermediate wells MW006 and MW012) for analysis by EPA Method 8260 for volatile organic halocarbons (VOHs). The current PDBs were deployed in these seven wells on November 18, 2020. In addition, four monitoring wells (MW005, MW007, MW010 and MW-011) are to be conventionally sampled using downhole pumps with disposable tubing. Groundwater intrinsic values will not be collected from the monitoring wells using PDB’s; however, intrinsic measurements from the four conventionally sampled wells will be collected on this sampling event.
Seven replacement PDB samplers will be obtained from ALS Environmental (ALS), a licensed manufacturer of passive diffusion samplers and will be placed within the wells at similar depths as the existing samplers. The PDB samplers deployed into 2-inch diameter monitoring wells MW004, MW006, MW009, MW012, and MW013 are 24 inches long and 1 ¼ inches in diameter.
The PDB samplers deployed into the smaller 1-inch diameter monitoring wells MW001 and MW016 are 48 inches long and ¾ inches in diameter. The samplers will be ordered pre-filled with approximately 220 milliliters of certified, laboratory-grade, analyte-free, deionized water.
The PDB’s will be deployed similar to the current bags to the following total depths:
1) MW001, (1” well), total depth of 35 ft bls (placement from 31 to 35 ft bls)
2) MW004, (2” well) total depth of 34 ft bls (placement from 32 to 34 ft bls)
3) MW006, (2” well) total depth of 71 ft bls (placement from 69 to 71 ft bls)
4) MW009, (2” well) total depth of 51 ft bls (placement from 49 to 51 ft bls)
5) MW012, (2” well) total depth of 71 ft bls (placement from 69 to 71 ft bls)
6) MW013, (2” well) total depth of 51 ft bls (placement from 49 to 51 ft bls)
7) MW016, (1” well), total depth of 34 ft bls (placement from 30 to 34 ft bls).
Subtask 3 Vapor Sampling: During system operation no discrete vapor sample analysis was performed; therefore, the selection of sampling SVE wells is somewhat subjective. However, based on discussions with FDEP, Zone B SVE wells were selected as these wells should capture contaminant vapors at the base of Zone A and top of Zone C. Zone A consists of nonconsolidated fine grained sands which are more readily remediated using vapor extraction, whereas deeper lithologies exhibit interbedded clayey fine sands. This subtask authorizes collection of vapor samples for laboratory analysis from five SVE wells (VE01B, VE02B, VE04B, VE05B and VE06B) constructed in Depth Interval B (8-18 feet below land surface). In addition, review of the Site Assessment Report (SAR) identified specific locations where addition vapor sampling should be performed. APTIM recommends collection of vapor samples from VE02A and VE05C. Each of the SVE wells are routed back to the remedial compound in dedicated piping runs. Since the well heads are difficult to access and attach a vacuum hose, APTIM will disconnect the vacuum piping at the remedial trailer and connect to a vacuum blower. After connecting the vacuum blower to the dedicated piping for the specific SVE well a vacuum pressure of 45 inches water column vacuum will be induced for five minutes. This should be sufficient time to fully evacuate the pipe and extract subsurface vapors. The vapor samples will be collected in Tedlar® bags and shipped to a NELAC accredited laboratory for analysis using modified EPA Method TO 15.
Vapor & Groundwater Sampling Summary
Sample I.D. Parameters Method Rationale
MW001 VOH EPA Method 8620 Existing PDB sample location
MW004 VOH EPA Method 8620 Existing PDB sample location
MW006 VOH EPA Method 8620 Existing PDB sample location
MW009 VOH EPA Method 8620 Existing PDB sample location
MW012 VOH EPA Method 8620 Existing PDB sample location
MW013 VOH EPA Method 8620 Existing PDB sample location
MW016 VOH EPA Method 8620 Existing PDB sample location
MW005 VOH EPA Method 8620 Shallow well downgradient of source, last sampled 8/31/12
MW007 VOH EPA Method 8620 Shallow well downgradient of source, last sampled 8/31/12
MW010 VOH EPA Method 8620 Shallow well downgradient of source, last sampled 1/31/07
MW011 VOH EPA Method 8620 Shallow well downgradient of source, last sampled 1/31/07
VE01B VOH Modified TO15 Location near floor crack potential migration conduit
VE02B VOH Modified TO15 Near DC machine
VE04B VOH Modified TO15 SAR reported high concentrations this location DP016
VE05B VOH Modified TO15 SAR reported high concentrations this location DP018
VE06B VOH Modified TO15 SAR reported high concentrations this location DP016
VE02A VOH Modified TO15 SAR reported high concentrations this location and depth
VE05C VOH Modified TO15 Near DC machine, SAR reported high concentrations DP004
Reporting and Schedule: APTIM will prepare a report summarizing the results of the vapor and groundwater sample collection analysis. The report will summarize the analytical results in Tables, Figures and Text and provide conclusions and recommendations. APTIM recommends the following project schedule:
Description Due Date
Collection of GW Samples and Deployment of PDBs 12/10/21
Collection of vapor sampling 12/10/21
Submit Letter Report 1/14/22
Submit GIS/Data Base Update 1/14/22
Task Expiration Date 3/25/22
APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed between APTIM Environmental & Infrastructure, LLC and Florida Department of Environmental Protection No. HW554. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.
If you have any questions, please contact us for clarification.